Electric aircraft high-voltage power distribution control method and system, medium and product thereof
By integrating a pre-charging circuit and solid-state relays into a high-voltage power distribution control method, the problems of load priority scheduling and rapid fault isolation in electric aircraft under high power density are solved, thereby improving the safety and reliability of the system.
Patent Information
- Application Number
- CN202610253325.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-03-03
- Publication Date
- 2026-05-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing high-voltage power distribution systems for electric aircraft struggle to achieve load priority scheduling and rapid fault isolation at the branch level under high power density conditions, leading to system-level cascading failures and impacting flight safety.
A pre-charge circuit is used to achieve soft start upon power-on. Power is distributed to the load branch through a power distribution stage integrated with multiple solid-state relays or contactors. An independent protection unit is configured at the load output stage to monitor voltage, current and temperature parameters in real time and perform fault isolation operations.
It enables load priority scheduling and branch-level rapid fault isolation under high power density conditions, improves system electromagnetic compatibility and fault handling quality, and ensures flight safety.
Smart Images

Figure CN122035309A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of high-voltage power distribution technology, and in particular to a high-voltage power distribution control method, system, medium and product for electric aircraft. Background Technology
[0002] As electric aircraft develop towards higher power density and longer flight time, their high-voltage power distribution systems face increasingly stringent safety and reliability requirements.
[0003] Current mainstream solutions mostly adopt a two-level power distribution architecture, relying on mechanical contactors or primary solid-state switches to distribute power. Although the structure is simple, it is difficult to complete accurate fault identification and isolation within milliseconds when dealing with sudden load changes or local faults. Especially in scenarios with multiple loads operating in parallel, if differentiated power supply protection for critical loads cannot be implemented and branch-level rapid protection cannot be achieved simultaneously, a single point of failure can easily lead to system-level cascading failures, seriously threatening flight safety.
[0004] Therefore, how to achieve high-voltage power distribution control that combines load priority scheduling and branch-level rapid fault isolation under high power density conditions has become a key technical problem that urgently needs to be solved. Summary of the Invention
[0005] To address the shortcomings of existing technologies and achieve high-voltage power distribution control that combines load priority scheduling and branch-level rapid fault isolation under high power density conditions, this application provides a high-voltage power distribution control method, system, medium, and related products for electric aircraft.
[0006] Firstly, the objective of this invention is achieved through the following technical solution: A high-voltage power distribution control method for an electric aircraft, comprising: It receives DC power from the power battery pack and achieves soft start upon power-on through a pre-charging circuit; According to load priority, electrical energy is distributed to the motor controller, auxiliary power module, air conditioning system and electric heating system through a power distribution stage; the power distribution stage integrates multiple solid-state relays or contactors to form load branches; Each load branch is configured with an independent protection unit at the load output stage. The independent protection unit monitors voltage, current and temperature parameters in real time and performs fault isolation operation when the monitored parameters exceed the corresponding preset threshold.
[0007] By adopting the above technical solutions, the pre-charging circuit enables soft-start upon power-up, suppressing inrush current. Because the electric aircraft's battery pack has high voltage (typically ≥400V DC) and low internal resistance, direct power-up easily generates inrush currents of thousands of amperes, which not only impacts contactor contacts and accelerates aging but may also trigger false protection. The pre-charging circuit, by slowly charging the bus capacitor before the main contactor closes, effectively suppresses dI / dt, limiting the power-up inrush current to within 1.5 times the rated operating current, meeting the power input characteristics requirements of the electric aircraft and improving its system electromagnetic compatibility. Through a load-priority-based power distribution stage, combined with multi-channel solid-state relays / contactors, millisecond-level dynamic power dispatch and high power density integration are achieved. Then, an independent protection unit is configured at the load output stage to monitor voltage / current / temperature in real time and perform fault isolation, constructing a branch-level "plug-and-play" safety barrier. Once the threshold is triggered, the protection unit directly drives the corresponding solid-state relay (SSR) to turn off, with a fault isolation time of ≤500μs, meeting the aviation-grade fault handling quality requirements. This application solves the technical problems of surge suppression, critical load protection and rapid fault containment in high power density power distribution, thereby achieving the technical objective of "realizing high-voltage power distribution control with both load priority scheduling and branch-level rapid fault isolation under high power density conditions".
[0008] In a preferred embodiment of this application: the pre-charge circuit is connected in parallel with the main contactor, and the main contactor is closed after the bus voltage ramp-up rate during the soft start process is controlled to 80%-90% of the rated voltage by adjusting the pre-charge resistance value; the power distribution stage dynamically adjusts the power supply sequence of the motor controller, auxiliary power module, air conditioning system and electric heating system through the load priority scheduling module, wherein the motor controller receives power supply with priority over other loads.
[0009] By adopting the above technical solution, the pre-charger and main contactor are connected in parallel. By adjusting the pre-charger resistor, the bus voltage ramp-up rate is controlled, avoiding overvoltage or insufficient charging and improving power-on consistency. Once the bus voltage reaches 80%–90% of its rated value, i.e., when the bus voltage is close to steady state, the main contactor is closed, significantly reducing the voltage difference between contacts and suppressing arcing.
[0010] In a preferred embodiment, this application further includes: Acquire the real-time line impedance characteristics of each branch in the high-voltage power distribution network of the electric aircraft, the current flight attitude data, and the preset priority information of each load device; Based on the line impedance characteristics and the flight attitude data, the variability of the power distribution network topology is evaluated to obtain the current optimal topology configuration scheme. Based on the optimal topology configuration scheme, the connection relationship of the high-voltage power distribution network is dynamically reconstructed, and the power demand between the propulsion system and auxiliary equipment is predicted and analyzed in combination with the preset priority information to obtain a dynamic power allocation strategy that considers the load power supply priority constraint. According to the dynamic power allocation strategy, power allocation command parameters are sent to the intelligent power distributor so that the intelligent power distributor can perform real-time dynamic power allocation between the propulsion system and auxiliary equipment; and the regional protection unit is synchronized in conjunction with the multi-level protection coordination strategy so as to achieve rapid isolation in the event of a local fault.
[0011] By adopting the above technical solutions, rapid isolation and maintenance of overall system operation are achieved in the event of a local fault. This application selects low-loss paths based on real-time line impedance to improve energy transmission efficiency. Different power modes are mapped through flight attitude (e.g., climb, hover) to pre-allocate resources, enabling adaptive power distribution in flight conditions. Then, topology reconfiguration not only optimizes efficiency but also bypasses potentially high-resistance and overheated branches, improving system health. Regionalized unit state synchronization upgrades fault identification from "local judgment" to "network consensus," shortening isolation time and preventing fault propagation.
[0012] In a preferred embodiment, this application describes the process of evaluating the variability of the power distribution network topology based on the line impedance characteristics and the flight attitude data to obtain the current optimal topology configuration, which includes: Based on the line impedance characteristics, calculate the equivalent transmission loss coefficient of each power distribution path under the current operating conditions; Based on the flight attitude data, the current flight stage of the aircraft is analyzed, and the corresponding typical power load mode is mapped. Combining the equivalent transmission loss coefficient with the typical power load pattern, a multi-objective optimization function is constructed, which aims to minimize transmission loss and maximize load matching. Solving the multi-objective optimization function yields a power distribution network connection matrix that satisfies the constraints, which serves as the current optimal topology configuration.
[0013] By adopting the above technical solutions, the equivalent transmission loss coefficient transforms physical impedance into a comparable efficiency index to quantitatively evaluate the merits of different paths; load mode prediction enhances scheduling foresight, for example, identifying the "landing phase" allows for pre-reduction of air conditioning power to provide margin for motors; multi-objective balancing avoids the defects of single-point optimization, as simply pursuing the lowest loss may lead to insufficient power supply to a certain load, while this solution takes into account both "sufficient supply" and "efficient delivery"; the power distribution network connection matrix provides executable topology instructions: directly outputting switching action combinations to provide a topology decision-making method with high execution efficiency and supply-demand matching.
[0014] In a preferred embodiment of this application: the dynamic reconfiguration of the connection relationship of the high-voltage power distribution network according to the optimal topology configuration scheme, and the prediction and analysis of the power demand between the propulsion system and auxiliary equipment in combination with the preset priority information, to obtain a dynamic power allocation strategy considering load power supply priority constraints, includes: Based on the optimal topology configuration scheme, identify switchable redundant power distribution paths and adjustable point switch states, and generate a topology reconfiguration instruction set; Based on the flight attitude data, pitch angle, roll angle and acceleration change rate are extracted, and the power demand curves of the propulsion system and auxiliary equipment in the next time window are estimated through a pre-trained power demand prediction model. The power demand curve is matched with the current available power capacity to determine the power allocation priority sequence between the propulsion system and auxiliary equipment; The dynamic power allocation strategy is generated by combining the topology reconfiguration instruction set with the power allocation priority sequence.
[0015] By employing the above technical solutions, redundant paths and adjustable switches are extracted from the optimal topology configuration to generate a topology reconfiguration instruction set, thereby improving the availability of the power distribution network. Predictive power management is achieved by predicting the power demand for the next second based on flight attitude data and other flight dynamic parameters. When total power supply is limited, peak shaving and valley filling are dynamically implemented according to priority (e.g., suspending electric heating to protect motors) to avoid overload and achieve a dynamic balance between capacity and power demand.
[0016] In a preferred embodiment of this application, the step of sending power allocation instruction parameters to the intelligent power distributor according to the dynamic power allocation strategy specifically includes: Based on the dynamic power allocation strategy, the minimum sustaining power required by the propulsion system and the interruptibility level of auxiliary equipment in the current flight phase are obtained. Calculate the power margin range corresponding to the minimum sustaining power and the interruptibility level, and determine the real-time power limit of each output port based on the power margin range; Efficiency-load characteristic modeling was performed on the multi-channel DC-DC converter module inside the intelligent power divider to obtain the conversion efficiency curves of each channel under different loads. Based on the conversion efficiency curve and the real-time power limit, the output current distribution ratio of each channel is optimized, and the power allocation command parameters, including channel enable status, output voltage setting value and current limiting threshold, are generated.
[0017] By adopting the above technical solutions, the minimum sustaining power of the propulsion system and the interruptibility level of auxiliary equipment are obtained. The minimum sustaining power of the propulsion system ensures that the electric aircraft always has sufficient power to guarantee the bottom line safety of flight. By setting the real-time power limit of each port, fine-grained interruptibility management is achieved. For example, electric heating can be completely cut off and air conditioning can be frequency reduced to achieve "flexible load shedding" rather than abrupt power outage. Then, based on the characteristic that the efficiency of the DC-DC converter module is different under different loads (such as the highest efficiency at half load), the allocation is optimized to make it work in the high-efficiency zone to maximize the energy utilization efficiency.
[0018] In a preferred embodiment, this application divides the high-voltage power distribution network into regional independent protection units. When any of the regional independent protection units detects an abnormal event that meets the local fault criteria, it immediately triggers an internal circuit breaker operation and broadcasts a fault isolation signal to adjacent protection units. Specifically, this includes the following steps: After detecting a current surge exceeding the first threshold and lasting for a longer than a preset time limit, the local solid-state circuit breaker is activated to perform a disconnection operation. The voltage phase angle and current harmonic content at the moment of fault occurrence are recorded synchronously and encapsulated into a fault feature package; The fault characteristic packet is broadcast to adjacent regional independent protection units via a high-speed fiber optic link; After receiving the fault feature packet, the adjacent regional independent protection unit compares its own monitoring data with the fault feature packet. If they match, it enters an early warning state and shortens its own protection action delay; if they do not match, it maintains normal protection logic.
[0019] By adopting the above technical solution, this application deploys regional independent protection units in the high-voltage power distribution network and introduces a local fault detection mechanism based on current surge and time-limit criteria. Combined with digital encapsulation of voltage phase angle and current harmonic characteristics and high-speed fiber optic broadcasting, it achieves low-latency, high-fidelity sharing of fault information. Adjacent regional independent protection units perform consistency comparisons based on received fault feature packets and dynamically adjust their own protection action strategies—accelerating response only when multi-point data collaboratively verifies the existence of a fault; otherwise, maintaining the original logic. This mechanism effectively avoids the problems of false tripping, failure to tripping, or cascading tripping that easily occur in traditional centralized or isolated protection systems, significantly improving the accuracy of fault identification and the timeliness of isolation. Simultaneously, it accurately defines fault boundaries, maximizing the continuous power supply capability of non-faulty areas, thereby greatly enhancing the operational resilience and reliability of the high-voltage power distribution network for electric aircraft while ensuring system safety.
[0020] Secondly, the objective of this invention is achieved through the following technical solution: A high-voltage power distribution control system for an electric aircraft, used to execute a high-voltage power distribution control method for an electric aircraft as described above, the system comprising: The power battery pack is used to output high-voltage DC power. A pre-charging module, connected to the power battery pack, is configured to perform soft-start charging of the bus capacitor through a pre-charging circuit when the system is powered on. The power distribution stage includes multiple solid-state relays or contactors, which respectively constitute a motor controller branch, an auxiliary power module branch, an air conditioning system branch, and an electric heating system branch. The power distribution stage is configured to distribute electrical energy to each load branch according to a preset load priority. The load output stage, located downstream of the power distribution stage, includes multiple independent protection units. Each independent protection unit corresponds to a load branch and is configured to monitor the voltage, current, and temperature parameters of the corresponding load branch in real time. When any monitored parameter exceeds the corresponding preset threshold, a fault isolation operation is performed on the load branch.
[0021] Thirdly, the objective of this invention is achieved through the following technical solution: A computer-readable storage medium storing a computer program that, when executed by a processor, implements the steps of the above-described high-voltage power distribution control method for an electric aircraft.
[0022] Fourthly, the objective of this invention is achieved through the following technical solution: A computer program product includes a computer program / instructions that, when executed by a processor, implement the steps of a high-voltage power distribution control method for an electric aircraft as described above.
[0023] In summary, this application includes at least one of the following beneficial technical effects: 1. The power battery DC power is received through the pre-charge circuit to avoid the impact of large current at the moment of power-on; the power distribution stage supplies power to the motor controller, auxiliary power supply, air conditioner, electric heating and other loads according to the preset priority; the power distribution stage is composed of multiple solid-state relays or contactors to form each load branch, and each branch is equipped with an independent protection unit at the load output stage to monitor voltage, current and temperature in real time, and isolate when the threshold is exceeded.
[0024] 2. A closed-loop high-voltage power distribution control architecture integrating line impedance sensing, flight status identification, and load priority constraints was constructed. By collecting the impedance characteristics of distribution branches and aircraft attitude data in real time, the system can dynamically evaluate and generate the optimal topology configuration scheme, thereby driving the power distribution network to reconfigure its connection relationships. Simultaneously, combined with preset load priority information, predictive modeling of the future power demands of the propulsion system and auxiliary equipment is performed to form a dynamic power allocation strategy that balances mission criticality and energy efficiency, which is then executed by an intelligent power divider. Furthermore, a multi-level coordinated regional protection mechanism is introduced to achieve state synchronization and rapid isolation of faulty units. This scheme overcomes the limitations of traditional static power distribution modes, enabling the high-voltage power distribution system to possess intelligent capabilities such as environmental adaptability, topology reconfigurability, power dispatchability, and fault coordination. Attached Figure Description
[0025] Figure 1 This is a flowchart of a high-voltage power distribution control method for an electric aircraft according to one embodiment of this application; Figure 2 This is an example diagram of the power distribution architecture in a high-voltage power distribution control method for an electric aircraft according to an embodiment of this application. Detailed Implementation
[0026] The present application will be further described in detail below with reference to the accompanying drawings.
[0027] In one embodiment, such as Figure 1 As shown, this application discloses a high-voltage power distribution control method for an electric aircraft, which specifically includes the following steps: S1: Receives DC power output from the power battery pack and achieves soft start upon power-on through the pre-charge circuit.
[0028] In this embodiment, the implementation scheme is applicable to the high-voltage DC power distribution system of multi-rotor eVTOL or fixed-wing electric aircraft. The system operates at a voltage level of 400V–800V DC, powered by a high-energy-density lithium-ion battery pack. The load includes a propulsion motor controller, an onboard computer auxiliary power supply, a cockpit air conditioning system, and a battery / cabin electric heating device. The battery pack refers to a high-voltage energy storage unit composed of multiple lithium-ion cells connected in series and parallel, with a nominal output voltage of 600V DC and a maximum continuous discharge current of 500A. The pre-charge circuit is a current-limiting circuit used to limit the initial charging current of the bus capacitor before the main power path is closed. It consists of a pre-charge contactor, a pre-charge resistor, and control logic. Power-on soft start refers to controlling the pre-charge process to allow the high-voltage bus voltage to rise gradually to near its steady-state value.
[0029] Specifically, the pre-charge circuit is connected in parallel with the main contactor. By adjusting the pre-charge resistance, the bus voltage ramp-up rate during the soft start process is controlled to reach 80%-90% of the rated voltage before the main contactor is closed. The power distribution stage dynamically adjusts the power supply sequence of the motor controller, auxiliary power module, air conditioning system and electric heating system through the load priority scheduling module, with the motor controller receiving power supply before other loads.
[0030] In this embodiment, the pre-charge circuit includes a pre-charge contactor (Kp) and a pre-charge resistor connected in series. The positive terminal of the power battery pack is sequentially connected to the pre-charge contactor Kp and the pre-charge resistor Rp (resistance value, e.g., 50Ω, power capacity 1kW), then connected in parallel with the main contactor Km and connected to the high-voltage DC bus (HV Bus), with the negative terminal grounded. The main contactor (Km) is connected in parallel with the pre-charge circuit; a supporting capacitor bank with a total capacitance of 2000μF is connected in parallel to ground on the bus. Taking the nominal voltage of the power battery pack as 600V DC, the power distribution stage consists of multiple power electronic switches, including four solid-state relays (SSR1–SSR4): corresponding to the left front, right front, left rear, and right rear motor controllers (MC1–MC4), respectively. Each load branch integrates a current sensor, a voltage sampling point, and a temperature probe.
[0031] When the system is powered on, the pre-charge contactor Kp is closed first. At this time, the current flows through Rp to charge the bus capacitor, and the bus voltage Vbus rises exponentially to the rated value. The central control unit (CCU) monitors Vbus in real time through a high-voltage sensor. When Vbus reaches 85% of the rated voltage and the voltage change rate is less than 5V / ms, it determines that the soft start is complete, and then closes the main contactor Km, and opens Kp after a 100ms delay. During this process, the inrush current is limited to less than 30A, far lower than the peak value of over 1000A that may occur during direct power-on, effectively protecting the mechanical and electrical life of the main contactor Km and preventing the battery management system from interrupting power supply due to overcurrent alarms.
[0032] S2: Based on load priority, power is distributed to the motor controller, auxiliary power module, air conditioning system and electric heating system through the power distribution stage; the power distribution stage integrates multiple solid-state relays or contactors to form load branches.
[0033] In this embodiment, as Figure 2 As shown, Figure 2This is an application example of the power distribution architecture in a high-voltage power distribution control method for an electric aircraft. The motor controller drives the propulsion motor; the auxiliary power module supplies power to the flight control, communication, and navigation systems; the load output stage is configured with filter circuits, surge protectors, power protectors, overvoltage and undervoltage protection circuits, overcurrent protection, and temperature protectors to ensure stable output power quality and adapt to diverse loads such as various load devices on the aircraft. The electric heating system is used for battery insulation or cockpit heating; load priority refers to the power supply sequence level set for each electrical device based on flight safety and mission criticality, with the motor controller being the highest priority (Level 1), the auxiliary power module the second highest priority (Level 2), the air conditioning system the medium priority (Level 3), and the electric heating system the lowest priority (Level 4). The power distribution stage is a power distribution execution layer composed of multiple power electronic switching devices, used to connect or disconnect each load branch according to instructions. Solid-state relays or contactors are used as switching elements; solid-state relays are suitable for high-frequency switching and arc-free operation scenarios, while contactors are suitable for high-current, low-cost applications.
[0034] For example, the power distribution stage uses a 6-way hybrid switch configuration: 4 of them are silicon carbide (SiC) MOSFET solid-state relays (rated voltage 800V, current 200A), corresponding to the left front, right front, left rear, and right rear motor controller branches respectively; 1 is an electromagnetic contactor (rated 600V / 100A) used for the auxiliary power module; and the other is an IGBT module with a drive circuit used for the branch shared by air conditioning and electric heating, which is time-division multiplexed through a local low-voltage relay. The control terminals of all switches are connected to the power distribution management unit (PMU). The PMU has an embedded load priority scheduling module, whose strategy is as follows: after system initialization, all Level 1 branches are enabled first; if the total current is not exceeded (e.g., <400A), Level 2 and Level 3 are enabled sequentially; when power capacity is detected to be insufficient (e.g., battery SOC <20% or total current >450A), Level 4 branches are automatically disconnected, and if still insufficient, Level 3 is deloaded. For example, in emergency return-to-home mode, even if the air conditioning is running, the PMU will immediately cut off its power supply to ensure that all electrical energy is prioritized for the motor controller and flight control system.
[0035] S3: Configure independent protection units for each load branch at the load output stage. The independent protection units monitor voltage, current and temperature parameters in real time and perform fault isolation operations when the monitored parameters exceed the corresponding preset thresholds.
[0036] In this embodiment, the load output stage refers to the power distribution terminal interface area located downstream of the power distribution stage and directly connected to each electrical device. The independent protection unit is a local protection device integrated into each load branch, comprising a current sensor, a voltage sampling circuit, a temperature probe, and a microcontroller. Fault isolation operation refers to the independent protection unit autonomously or under a superior command disconnecting the power supply switch of the corresponding branch when abnormal monitoring parameters occur, thus achieving physical and electrical isolation of the fault point.
[0037] Specifically, each independent protection unit adopts a standardized modular design. For example, the protection unit configuration for the motor controller branch is as follows: current sampling range ±300A, accuracy ±1%; voltage sampling range 0–800V; NTC temperature sensor mounted on the solid-state relay heat sink. Preset thresholds are set differently according to load characteristics—motor branch: overcurrent threshold 250A (lasting 5s) or 350A (instantaneous 100ms), overtemperature threshold 90℃; auxiliary power supply branch: overcurrent 80A, overvoltage 650V; air conditioning / electric heating branch: overcurrent 60A, undervoltage 400V. When any parameter exceeds the limit, the local MCU immediately outputs a shutdown signal to the corresponding switch's drive circuit and simultaneously reports a fault code to the PMU via the CAN bus. For example, if the right rear motor experiences a sudden current surge to 400A for 150ms due to bearing jamming, its independent protection unit will disconnect the solid-state relay in that branch within 20ms, while the other three motors and auxiliary systems continue to operate normally.
[0038] In one embodiment, a high-voltage power distribution control method for an electric aircraft further includes: S10: Obtain the real-time line impedance characteristics of each branch in the high-voltage power distribution network of the electric aircraft, the current flight attitude data, and the preset priority information of each load device.
[0039] In this embodiment, the real-time line impedance characteristics refer to the equivalent resistance and inductance parameters of each power distribution branch under the current temperature, current and connection state, which are used to characterize energy transmission loss; the current flight attitude data is provided by the flight control computer (FCC), including pitch, roll, yaw and three-axis acceleration; the preset priority information follows the four-level classification information in step S2.
[0040] Specifically, the PMU performs data acquisition every 10ms: It measures the end-to-end impedance of each branch using a high-frequency injection method, and compensates for copper resistance temperature drift using temperature sensor data to obtain the real-time impedance value Z_branch = R + jωL. Here, Z_branch describes the impedance characteristics of a distribution branch to AC or (including high-frequency DC) current; R is the equivalent resistance, including conductor copper resistance, contact resistance, and switch conduction resistance; j is an imaginary unit, indicating that the reactance and resistance are orthogonal; ω is the angular frequency; and L is the branch's equivalent inductance, a parasitic inductance determined by the wiring loop area and core material, measured in Henry, affecting the rate of change of current (di / dt). It receives flight attitude data packets from the FCC via the CAN bus, including fields such as Pitch=15°, Roll=-3°, and Ax=0.8m / s². It reads the priority weight table of each load from non-volatile memory and associates it with the current mission mode (e.g., "cruise," "hover," "emergency return"), dynamically adjusting the weights. For example, during an emergency return, the Level... The weight of 2 has been temporarily increased to 0.9.
[0041] S20: Based on the line impedance characteristics and flight attitude data, evaluate the variability of the distribution network topology to obtain the current optimal topology configuration.
[0042] In this embodiment, variability evaluation refers to selecting the connection method that satisfies electrical constraints and has the best overall performance from all legal topology combinations; the optimal topology configuration scheme is output in the form of a binary connection matrix, indicating the on / off state of each switch, such as 1 = closed, 0 = open.
[0043] Specifically, step S20 includes: S201: Calculate the equivalent transmission loss coefficient of each power distribution path under the current operating conditions based on the line impedance characteristics.
[0044] In this embodiment, dynamic evaluation and optimization decisions of the power distribution network topology are implemented in the high-voltage power distribution system of the electric aircraft. The system has two independent high-voltage DC buses (HV Bus A and HV Bus B), and key loads (such as four motor controllers and auxiliary power modules) can be switched between the two buses via solid-state relays to form various legal connection combinations. The PMU periodically executes the topology evaluation process to output an updated optimal topology configuration scheme.
[0045] Specifically, a power distribution path refers to the complete electrical path from a high-voltage bus to a load input terminal, including cables, connectors, switching devices, etc.; the equivalent transmission loss factor is used to quantify the energy loss ratio of the path at the current current level.
[0046] First, the resistance component R, in Ω, is extracted and combined with the current predicted based on the current load from flight condition estimates. Calculate the Joule heat loss power of this path. Subsequently, based on the expected output power of the load... For example, the mechanical power of the motor or the output power of the auxiliary power supply, the equivalent transmission loss factor is defined as: For example, if the predicted current of a certain motor branch is 200A and the measured R = 0.015Ω, then... =200^2 × 0.015 = 600W; If the expected output power of the motor is 80kW, then =600 / (80000+600)≈0.0074.
[0047] S202: Based on flight attitude data, analyze the current flight stage of the aircraft and map the corresponding typical power load mode.
[0048] In this embodiment, the flight phase is a semantic classification of the aircraft's dynamic state, which directly affects the power demand distribution of the propulsion system and auxiliary systems; the typical power load pattern is a standardized power demand template established based on historical flight data or simulation models.
[0049] Specifically, the PMU receives real-time attitude data packets from the flight control computer (FCC), including pitch, roll, yaw rate, and three-axis accelerations (Ax, Ay, Az). Phase identification is performed based on a preset rule engine. If |Pitch| < 5° and |Roll| < 5° and |Az−g| < 0.2m / s², it is determined to be the "hovering phase"; If Pitch > 10° and Ax > 0.6 m / s², it is determined to be the "climbing phase"; If Pitch < −8° and Ax < −0.5 m / s², it is determined to be the "descent phase"; If |Roll|>15° and Ay>1.0m / s², it is determined to be the "turning phase".
[0050] Each phase is associated with a typical power load pattern, which is stored in the PMU's non-volatile memory. For example, the climbing phase corresponds to the following pattern: total power of four motors 320kW (80kW per motor), auxiliary power 10kW, air conditioning off at 0kW, electric heating off at 0kW; while the hovering phase corresponds to: total power of four motors 240kW, auxiliary power 8kW, air conditioning 5kW, and cabin temperature control.
[0051] S203: Combining the equivalent transmission loss coefficient with typical power load patterns, a multi-objective optimization function is constructed. The multi-objective optimization function aims to minimize transmission loss and maximize load matching.
[0052] In this embodiment, load matching reflects the degree of fit between the actual power supply capacity and typical load requirements.
[0053] The expression for constructing the multi-objective optimization function is as follows: Where J is the comprehensive optimization objective value; Enable indicator variables for the path. ∈{0,1} is a binary variable, indicating whether the k-th path is enabled; This represents the total number of power distribution paths. This represents the total number of load devices; As load priority weight; The load matching degree has a value of 0 to 1. This represents the maximum available electrical power that can be allocated to load i under the current topology. Available electrical power from a typical load model derived from step S202. Ensure the match score does not exceed 1. The weights are adjustable, and the sum of the two is 1; LoadMatch represents the degree of matching between the actual power supply capacity and the demand.
[0054] S204: Solve the multi-objective optimization function to obtain the power distribution network connection matrix that satisfies the constraints, which is used as the current optimal topology configuration scheme.
[0055] In this embodiment, the constraints include electrical safety boundaries and system physical limitations; the distribution network connection matrix is a set of switch control commands output in a structured form. The PMU uses an improved genetic algorithm (GA) to search for the optimal topology within the valid solution space. The constraints include: each load must be connected to one and only one bus, the total output current of a single bus is ≤450A, the current of any branch is ≤ its solid-state relay rating, and the voltage drop is ≤5%, with the voltage drop estimated based on path R and I.
[0056] The improved genetic algorithm (GA) initializes 100 individuals with random topology, evolves them through 50 generations, and converges, ultimately outputting a connectivity matrix, for example: This matrix indicates that the left front motor (MC1) and right rear motor (MC4) are connected to Bus A, the right front motor (MC2) and left rear motor (MC3) are connected to Bus B, and the auxiliary power supply is connected to Bus A. This configuration balances the loads on both buses (A: 170A, B: 165A) and avoids the high-resistance branch (R=0.022Ω) caused by connector aging in the MC2→Bus A path, thereby meeting the 320kW propulsion requirement during the climb phase while reducing the total transmission loss by approximately 12%. This connection matrix is then converted into solid-state relay control commands and sent to the power distribution stage for dynamic reconfiguration.
[0057] First, the equivalent transmission loss coefficient of each feasible path is calculated based on real-time impedance. Secondly, the current flight phase is analyzed based on the flight attitude—for example, when |Pitch|>10° and Ax>0.5 m / s², it is determined to be the "climbing phase," mapping a typical load mode: the total power demand of the four motors is approximately 320kW, the auxiliary power supply is 10kW, and the air conditioning is off. Subsequently, based on the constructed multi-objective optimization function, a genetic algorithm is used to solve the problem under constraints such as voltage drop <5% and branch current < rated value, outputting the power distribution network connection matrix.
[0058] S30: Based on the optimal topology configuration scheme, the connection relationship of the high-voltage power distribution network is dynamically reconstructed, and the power demand between the propulsion system and auxiliary equipment is predicted and analyzed in combination with the preset priority information to obtain a dynamic power allocation strategy that takes into account the load power supply priority constraints.
[0059] In this embodiment, dynamic reconfiguration refers to switching load connection points by coordinating switching action sequences without power interruption; power demand prediction analysis uses flight mechanics models to predict power change trends within the next 1–3 seconds; and dynamic power allocation strategy is a set of instructions that allocate specific power quotas to each load after the topology is determined.
[0060] Specifically, the PMU generates a topology reconfiguration instruction set, controlling the solid-state relays according to the principle of "close first, then disconnect": for example, when switching MC2 from Bus A to Bus B, the SSR on the Bus B side is closed first, and the SSR on the Bus A side is disconnected only after confirming continuity, to avoid power interruption. Simultaneously, based on flight attitude data, a pre-trained LSTM neural network model is invoked. The input of the pre-trained LSTM neural network model is the historical sequence of attitude angles and accelerations, and the output is the torque demand of each motor within the next 2 seconds, predicting that the total power of the propulsion system will increase from 280kW to 350kW. Combining the current remaining battery capacity and priority weights, if the remaining capacity of the front battery is SOC=65%, the available power is 400kW; the allocation strategy is determined: ensuring a total of 350kW for all four motors (fully met at Level 1), maintaining the auxiliary power at 10kW (Level 2), and suspending air conditioning and electric heating (reduced at Level 3 / 4). This clarifies the power upper limit for each branch.
[0061] Specifically, step S30 includes: Based on the optimal topology configuration, the connection relationships of the high-voltage power distribution network are dynamically reconstructed. Combined with preset priority information, the power demand between the propulsion system and auxiliary equipment is predicted and analyzed, resulting in a dynamic power allocation strategy that considers load power supply priority constraints, including: S301: Based on the optimal topology configuration scheme, identify switchable redundant power distribution paths and adjustable point switch states, and generate a topology reconfiguration instruction set.
[0062] In this embodiment, redundant power distribution path refers to the existence of two or more legal power supply paths for the same load, such as MC1 being able to connect to Bus A or Bus B; adjustable point switch state refers to a solid-state relay whose on / off state needs to be changed; topology reconfiguration instruction set is a set of switch control commands arranged in a timing sequence.
[0063] Specifically, the PMU analyzes the distribution network connection matrix and compares it with the current actual connection status. If a discrepancy is found, the switch pair requiring operation is identified: SSR_MC2_A is opened, and SSR_MC2_B is closed. To avoid momentary power outages, the PMU generates a "close first, then open" instruction sequence: At time T0: a "pre-conduction" instruction is sent to SSR_MC2_B; at T0+0.5ms: after confirming that SSR_MC2_B is on, a "turn off" instruction is sent to SSR_MC2_A; at T0+2ms: the voltage stability of the MC2 branch is verified, and the switching is completed. The topology reconfiguration instruction set includes the load ID, target bus, switch action type, and execution timing offset.
[0064] S302: Based on flight attitude data, pitch angle, roll angle and acceleration change rate are extracted, and the power demand curves of the propulsion system and auxiliary equipment in the next time window are estimated through a pre-trained power demand prediction model.
[0065] In this embodiment, the next time window refers to the prediction interval within the next 1–3 seconds; the power demand prediction model is a lightweight machine learning model that is trained offline and inferred online; and the power demand curve is a vector of power demand for each load represented by a time series.
[0066] Specifically, the PMU acquires a high-frequency (100Hz) attitude data stream from the flight control computer (FCC) to extract key dynamic features: pitch angle. and its rate of change Roll angle and its rate of change Triaxial acceleration And its first-order difference. These are then used as input features and fed into a pre-trained gated recurrent unit (GRU) neural network model. The model outputs a power demand vector with a sampling point every 100ms over the next 3 seconds. To obtain the power demand curve. For example, under sharp turning conditions ( =−20 =−15° / s), the model predicts that the power of the two motors on the right side will increase from 60kW to 95kW in 0.8 seconds, while the power of the air conditioner will remain unchanged at 5kW.
[0067] S303: Match the power demand curve with the current available power capacity to determine the power allocation priority sequence between the propulsion system and auxiliary equipment.
[0068] In this embodiment, the current available power capacity is provided by the battery management system (BMS), including the maximum continuous discharge power P_max and the remaining power (SOC); the power allocation priority sequence is the decision result of allocating power supply quotas to each load in time slices under resource-constrained conditions.
[0069] Specifically, for the predicted power curve Perform time-window integration to obtain the total power demand value. If the total power demand value > P_max, then initiate the priority pruning logic: retain the full demand of Level 1 (propulsion system): the power of the four motors cannot be reduced; assess whether Level 2 (APS) can be deloaded: if the APS is currently only used for non-critical equipment (such as entertainment systems), it can be reduced to the minimum sustaining power, such as 5kW; reduce Level 3 / 4 in order of priority. Finally, a time-priority-power limit triplet sequence is generated, which is the power allocation priority sequence.
[0070] S304: Combines the topology reconfiguration instruction set with the power allocation priority sequence to generate a dynamic power allocation strategy.
[0071] In this embodiment, the dynamic power allocation strategy is a comprehensive control strategy that integrates physical connection instructions and power limit instructions, and can be directly issued to the underlying execution unit. The topology reconfiguration instruction set generated in S301 and the power allocation priority sequence generated in S303 are spatiotemporally aligned to form a unified scheduling package. The dynamic power allocation strategy includes topology control instructions and power limit instructions.
[0072] S40: Send power allocation command parameters to the intelligent power distributor according to the dynamic power allocation strategy, so that the intelligent power distributor can dynamically allocate the power between the propulsion system and auxiliary equipment in real time; and combine the multi-level protection coordination strategy to synchronize the status of the regional protection unit so as to achieve rapid isolation when a local fault occurs.
[0073] In this embodiment, the intelligent power divider is a power execution terminal that integrates a multi-channel DC-DC converter and a digital control interface; the multi-level protection coordination strategy refers to the regional protection units sharing their status through high-speed communication to achieve coordinated action.
[0074] Specifically, the PMU translates the dynamic power allocation strategy into power dispatching command parameters, including: MC1 channel enable = 1, output voltage = 600V, current limit = 220A; APS channel enable = 1, output voltage = 600V, current limit = 80A; AC / HEAT channel enable = 0. These commands are sent to the intelligent power divider via the EtherCAT bus at 1ms intervals, which adjusts the PWM duty cycle of each DC-DC module accordingly to achieve millisecond-level power response.
[0075] Simultaneously, the PMU broadcasts the current topology status and load priority sequence to all regional protection units (PU1–PU6). If PU3 (corresponding to the MC2 branch) detects a short-circuit fault and performs a local disconnection, it will send a fault characteristic packet to adjacent units such as PU2 and PU4 via the fiber optic link. The fault characteristics include a harmonic content (THD) of 45% and a phase angle change (Δφ) of 120°. After comparing its own current waveform and confirming consistency, PU2 immediately shortens its overcurrent protection delay from 50ms to 10ms and enters a cooperative isolation mode to prevent fault current from backflowing through redundant paths. This mechanism ensures accurate and rapid fault isolation even in complex topologies, maintaining the overall operation of the system.
[0076] Furthermore, power allocation command parameters are sent to the intelligent power divider according to the dynamic power allocation strategy, specifically including: S401: Based on the dynamic power allocation strategy, obtain the minimum sustaining power required by the propulsion system and the interruptibility level of auxiliary equipment during the current flight phase.
[0077] In this embodiment, minimum sustaining power refers to the minimum total power required for the propulsion system to maintain basically controllable flight under the current flight conditions; interruptibility level is a classification identifier for whether auxiliary equipment can be deloaded or disconnected when power is limited. For example, the interruptibility level of the auxiliary power module is "uninterruptible", the interruptibility level of the air conditioning system is "deloadable", and the interruptibility level of the electric heating system is "completely interruptible".
[0078] S402: Calculate the power margin range corresponding to the minimum sustaining power and the interruptible level, and determine the real-time power limit of each output port based on the power margin range.
[0079] In this embodiment, the power margin range refers to the remaining power range that the system can allocate to non-critical loads while ensuring minimum sustaining power; the real-time power limit is the maximum power value that each output channel is allowed to output at the current moment. The power margin range is the difference between the currently available total power and the minimum sustaining power. For example, the allocation of the power margin range is as follows: APS (Uninterruptible Power Supply) allocates its nominal demand (e.g., 10 kW) without occupying the margin; AC (Degradable Power Supply) allocates a maximum of 5 kW, but can be reduced if the margin is insufficient; Heater (Full Cut-off Power Supply) is only activated when the margin is >20 kW.
[0080] S403: Perform efficiency-load characteristic modeling on the multi-channel DC-DC conversion module inside the intelligent power divider to obtain the conversion efficiency curves of each channel under different loads.
[0081] In this embodiment, efficiency-load characteristic modeling refers to establishing a functional relationship between the output power (or current) of a DC-DC converter and its conversion efficiency through offline testing or online identification; the conversion efficiency curve is used to guide how to allocate the load to maximize overall energy efficiency.
[0082] Specifically, before products leave the factory, efficiency tests are conducted on each type of DC-DC module: with an input voltage of 600V and an adjustable output voltage, the input power and output power are recorded at different output power levels from 10% to 100% of the rated power. The conversion efficiency is then calculated based on the output power and input power. The test data is fitted to a quadratic function: ,in For the first Channel output current. As the curve shows, the conversion efficiency reaches a peak of approximately 96.2% at I≈125A, and the efficiency decreases below or above this value. This model allows the system to actively adjust the load to the high-efficiency operating range while meeting the power limit.
[0083] S404: Based on the conversion efficiency curve and real-time power limit, optimize the output current distribution ratio of each channel and generate power allocation command parameters including channel enable status, output voltage setting value and current limiting threshold.
[0084] In this embodiment, the output current allocation ratio refers to how to allocate current among multiple parallel or similar channels to improve overall efficiency when the total power demand is fixed; the power allocation command parameters are the underlying instruction set that can directly drive the DC-DC controller.
[0085] Specifically, the conversion efficiency curves of each channel are fitted as nonlinear functions of the output current to construct an objective function that maximizes the overall system efficiency. Maximizing the overall system efficiency is equivalent to minimizing the total input power. Power balance constraints are introduced, including total output power equaling demand power and single-channel current not exceeding safety limits. The objective function is solved using gradient descent or interior-point methods to obtain the optimal output current allocation ratio for each channel. Based on the optimal output current allocation ratio, the PWM duty cycle and feedback gain parameters of each channel are dynamically adjusted to achieve efficiency-oriented precise power allocation. The PWM duty cycle directly controls the energy transfer of the DC-DC converter. The feedback gain parameter affects the dynamic response of the current loop.
[0086] For example, the PMU performs the following operation based on the efficiency curve and power limit: For the propulsion system (CH1–CH4), if the total demand is 320 kW, the current of each motor should be allocated to the vicinity of its efficiency peak point (e.g., 80 A per channel, corresponding to 80 kW). If a channel is derated due to a fault, the excess power will be transferred to other high-efficiency channels; For CH6, if a 5 kW output is required, select to operate it in the current range with an efficiency >92%.
[0087] The final generated power distribution command includes the channel enable status, output voltage setpoint, and current limiting threshold. Based on the power distribution command parameters, a power distribution command is generated and sent to each DC-DC controller of the intelligent power divider via digital communication at 1ms intervals to achieve high-efficiency power output while meeting task requirements. Specifically, based on the optimal output current distribution ratio and the current input and output voltages, the required PWM duty cycle is inversely calculated using a small-signal model. The proportional gain and integral time in the current loop parameters are then configured, and the PWM duty cycle, proportional gain, and integral time are written to the control unit of the corresponding channel via an internal register or PWM generator module.
[0088] In one embodiment, a high-voltage power distribution control method for an electric aircraft includes: a method for controlling the high-voltage power distribution of an electric aircraft, which divides the high-voltage power distribution network into regional independent protection units. When any regional independent protection unit detects an abnormal event that meets the local fault criteria, it immediately triggers an internal circuit breaking operation and broadcasts a fault isolation signal to adjacent protection units. Specifically, the method includes the following steps: S100: After detecting a sudden change in current exceeding the first threshold and the duration exceeding the preset time limit, the local solid-state circuit breaker is activated to perform a disconnection operation.
[0089] In this embodiment, the system is applied to a high-voltage DC power distribution network for electric aircraft with regionalized collaborative protection capabilities. The system divides the high-voltage bus into multiple Regionalized Independent Protection Units (RIPUs) according to physical zones. Each RIPU is responsible for monitoring a section of the bus and the load branches connected to that section (such as a motor controller or auxiliary power module). Current surge refers to the instantaneous rate of change of current per unit time or the step increment relative to the steady-state value. The "first threshold" and "preset time limit" constitute the core parameters of the local fault criterion.
[0090] Specifically, each RIPU incorporates a high-bandwidth Hall current sensor to acquire the branch current i(t) in real time. The RIPU's local microcontroller calculates the current surge every 10 μs: Δi = |i(t)−i(t−T_window)|, where T_window is 100 μs. If Δi exceeds a first threshold for three consecutive sampling periods and the duration exceeds 200 μs (e.g., 150 A), a short circuit or severe overcurrent fault is identified. In this case, the RIPU immediately drives a local solid-state circuit breaker (e.g., a switching module composed of four parallel SiC MOSFETs) to turn off the gate signal, disconnecting the faulty branch. The entire detection-action delay is controlled within ≤500 μs. The solid-state circuit breaker is used for fault disconnection.
[0091] S200: Synchronously records the voltage phase angle and current harmonic content at the moment of fault occurrence and encapsulates them into a fault feature package.
[0092] In this embodiment, the RIPU synchronously latches, for example, the voltage phase angle, at the same time as triggering step S100. Key data for total harmonic distortion (THD) of current, voltage phase angle The bus voltage ripple is sampled using a high-speed ADC to extract the instantaneous phase of the fundamental frequency, which is the motor PWM carrier frequency, such as 10 kHz. The current spectrum is calculated using a Fast Fourier Transform (FFT, 512 points, 1 ms window). The THD is defined as follows: ,in For fundamental current, For the h-th harmonic. Key data, along with timestamps, RIPU IDs, and fault type tags, are encapsulated into a standard fault feature package.
[0093] S300: Broadcasts fault characteristic packets to adjacent regional independent protection units via high-speed fiber optic links.
[0094] In this embodiment, a high-speed fiber optic link refers to a point-to-point communication channel constructed using plastic optical fiber (POF) or quartz optical fiber in conjunction with an optical transceiver module; an adjacent regional independent protection unit refers to an upstream and downstream protection unit that is physically directly connected.
[0095] Specifically, each RIPU is equipped with a pair of full-duplex fiber optic transceivers, such as the HFBR-1528Z, forming a ring topology. After the S200 step completes encapsulation, the RIPU immediately transmits a fault characteristic packet in broadcast mode via the fiber optic interface. Due to the use of a dedicated physical layer, the protocol overhead is extremely low, and the end-to-end transmission delay is ≤2μs.
[0096] S400: After receiving a fault feature packet, the adjacent regional independent protection unit compares its own monitoring data with the fault feature packet. If they match, it enters the early warning state in advance and shortens its own protection action delay; if they do not match, it maintains normal protection logic.
[0097] In this embodiment, consistency comparison refers to determining whether local observations support the "same fault event"; early warning status refers to improving monitoring sensitivity; and shortening protection action delay refers to reducing the original time limit from milliseconds to microseconds.
[0098] For example, RIPU_3 experiences a fault and generates a corresponding fault feature packet. Upon receiving the fault feature packet from RIPU_3, the adjacent RIPU (such as RIPU_2) executes the following logic: Time alignment: Extract local voltage / current data within a ±5 μs time window based on the timestamp; Feature comparison: If the local THD > 25% and the voltage phase angle difference |Δφ| < 15°, then it is judged as "consistent"; otherwise, it is judged as "inconsistent". Dynamic response: If consistent: RIPU_2 immediately shortens its own overcurrent protection time limit from 50 ms to 5 ms and increases the current sampling rate to 1 MSPS, entering "cooperative isolation mode"; if inconsistent: maintains the original protection parameters and continues to operate independently.
[0099] For example, when RIPU_3 trips due to a short circuit in MC3 and broadcasts THD=45%, At 82°, RIPU_2 detected a local THD of 42%. =80°, consistent judgment, and then shorten the action delay. If subsequent fault current flows back to the RIPU_2 branch through the redundant path, it can be quickly disconnected within 5 ms to prevent fault propagation. Meanwhile, RIPU_5 (THD=5%), which is far from the fault point, =200°) will not be affected, ensuring continuous power supply to non-faulty areas.
[0100] It should be understood that the sequence number of each step in the above embodiments does not imply the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of this application.
[0101] In one embodiment, a high-voltage power distribution control system for an electric aircraft is provided, which corresponds to the high-voltage power distribution control method for an electric aircraft described in the above embodiments.
[0102] A high-voltage power distribution control system for an electric aircraft, comprising: The power battery pack is used to output high-voltage DC power. The pre-charge module is connected to the power battery pack and is configured to perform soft-start charging of the bus capacitor through the pre-charge circuit when the system is powered on. The power distribution stage includes multiple solid-state relays or contactors, which respectively constitute the motor controller branch, the auxiliary power module branch, the air conditioning system branch, and the electric heating system branch. The power distribution stage is configured to distribute power to each load branch according to the preset load priority. The load output stage, located downstream of the power distribution stage, contains multiple independent protection units. Each independent protection unit corresponds to a load branch and is configured to monitor the voltage, current, and temperature parameters of the corresponding load branch in real time. When any monitored parameter exceeds the corresponding preset threshold, it performs a fault isolation operation on the load branch.
[0103] For specific limitations regarding a high-voltage power distribution control system for an electric aircraft, please refer to the limitations of a high-voltage power distribution control method for an electric aircraft mentioned above, which will not be repeated here. Each module in the aforementioned high-voltage power distribution control system for an electric aircraft can be implemented entirely or partially through software, hardware, or a combination thereof. Each module can be embedded in or independent of the processor in a computer device in hardware form, or it can be stored in the memory of a computer device in software form, so that the processor can call and execute the corresponding operations of each module.
[0104] In one embodiment, a computer-readable storage medium is provided having a computer program stored thereon, which, when executed by a processor, implements the steps of a high-voltage power distribution control method for an electric aircraft.
[0105] Those skilled in the art will understand that all or part of the processes in the methods of the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium. When executed, the computer program can include the processes of the embodiments of the above methods. Any references to memory, storage, databases, or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM), or flash memory.
[0106] In one embodiment, particularly according to embodiments of the present invention, the processes described above with reference to the flowchart can be implemented as a computer software program. For example, embodiments of the present invention include a computer program product comprising a computer program / instructions that, when executed by a processor, implement the steps of a high-voltage power distribution control method for an electric aircraft. In such embodiments, the computer program can be downloaded and installed from a network via a communication module, and / or installed from a removable medium. When the computer program is executed by a central processing unit (CPU), it performs the various functions defined in the present invention.
[0107] Those skilled in the art will clearly understand that, for the sake of convenience and brevity, the above-described division of functional units and modules is used as an example. In practical applications, the above functions can be assigned to different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
[0108] The above-described embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this application, and should all be included within the protection scope of this application.
Claims
1. A high-voltage power distribution control method for an electric aircraft, characterized in that, include: It receives DC power from the power battery pack and achieves soft start upon power-on through a pre-charging circuit; According to load priority, electrical energy is distributed to the motor controller, auxiliary power module, air conditioning system and electric heating system through a power distribution stage; the power distribution stage integrates multiple solid-state relays or contactors to form load branches; Each load branch is configured with an independent protection unit at the load output stage. The independent protection unit monitors voltage, current and temperature parameters in real time and performs fault isolation operation when the monitored parameters exceed the corresponding preset threshold.
2. The high-voltage power distribution control method for an electric aircraft according to claim 1, characterized in that, The pre-charging circuit is connected in parallel with the main contactor. By adjusting the pre-charging resistance, the bus voltage ramp-up rate during the soft start process is controlled to reach 80%-90% of the rated voltage before the main contactor is closed. The power distribution stage dynamically adjusts the power supply sequence of the motor controller, auxiliary power module, air conditioning system and electric heating system through the load priority scheduling module, wherein the motor controller receives power supply with priority over other loads.
3. The high-voltage power distribution control method for an electric aircraft according to claim 1, characterized in that, The method also includes: Acquire the real-time line impedance characteristics of each branch in the high-voltage power distribution network of the electric aircraft, the current flight attitude data, and the preset priority information of each load device; Based on the line impedance characteristics and the flight attitude data, the variability of the power distribution network topology is evaluated to obtain the current optimal topology configuration scheme. Based on the optimal topology configuration scheme, the connection relationship of the high-voltage power distribution network is dynamically reconstructed, and the power demand between the propulsion system and auxiliary equipment is predicted and analyzed in combination with the preset priority information to obtain a dynamic power allocation strategy that considers the load power supply priority constraint. According to the dynamic power allocation strategy, power allocation command parameters are sent to the intelligent power distributor so that the intelligent power distributor can perform real-time dynamic power allocation between the propulsion system and auxiliary equipment; and the regional protection unit is synchronized in conjunction with the multi-level protection coordination strategy so as to achieve rapid isolation in the event of a local fault.
4. The high-voltage power distribution control method for an electric aircraft according to claim 3, characterized in that, The step of evaluating the variability of the power distribution network topology based on the line impedance characteristics and the flight attitude data to obtain the current optimal topology configuration includes: Based on the line impedance characteristics, calculate the equivalent transmission loss coefficient of each power distribution path under the current operating conditions; Based on the flight attitude data, the current flight stage of the aircraft is analyzed, and the corresponding typical power load mode is mapped. Combining the equivalent transmission loss coefficient with the typical power load pattern, a multi-objective optimization function is constructed, which aims to minimize transmission loss and maximize load matching. Solving the multi-objective optimization function yields a power distribution network connection matrix that satisfies the constraints, which serves as the current optimal topology configuration.
5. The high-voltage power distribution control method for an electric aircraft according to claim 3, characterized in that, The process involves dynamically reconstructing the connection relationships of the high-voltage power distribution network based on the optimal topology configuration scheme, and predicting and analyzing the power demand between the propulsion system and auxiliary equipment in conjunction with the preset priority information to obtain a dynamic power allocation strategy that considers load power supply priority constraints, including: Based on the optimal topology configuration scheme, identify switchable redundant power distribution paths and adjustable point switch states, and generate a topology reconfiguration instruction set; Based on the flight attitude data, pitch angle, roll angle and acceleration change rate are extracted, and the power demand curves of the propulsion system and auxiliary equipment in the next time window are estimated through a pre-trained power demand prediction model. The power demand curve is matched with the current available power capacity to determine the power allocation priority sequence between the propulsion system and auxiliary equipment; The dynamic power allocation strategy is generated by combining the topology reconfiguration instruction set with the power allocation priority sequence.
6. The high-voltage power distribution control method for an electric aircraft according to claim 3, characterized in that, The step of sending power allocation command parameters to the intelligent power distributor according to the dynamic power allocation strategy specifically includes: Based on the dynamic power allocation strategy, the minimum sustaining power required by the propulsion system and the interruptibility level of auxiliary equipment in the current flight phase are obtained. Calculate the power margin range corresponding to the minimum sustaining power and the interruptibility level, and determine the real-time power limit of each output port based on the power margin range; Efficiency-load characteristic modeling was performed on the multi-channel DC-DC converter module inside the intelligent power divider to obtain the conversion efficiency curves of each channel under different loads. Based on the conversion efficiency curve and the real-time power limit, the output current distribution ratio of each channel is optimized, and the power allocation command parameters, including channel enable status, output voltage setting value and current limiting threshold, are generated.
7. The high-voltage power distribution control method for an electric aircraft according to claim 6, characterized in that, In a high-voltage power distribution network, regional independent protection units are defined. When any of these regional independent protection units detects an abnormal event that meets the local fault criteria, it immediately triggers an internal circuit breaker operation and broadcasts a fault isolation signal to adjacent protection units. The specific steps include the following: After detecting a current surge exceeding the first threshold and lasting for a longer than a preset time limit, the local solid-state circuit breaker is activated to perform a disconnection operation. The voltage phase angle and current harmonic content at the moment of fault occurrence are recorded synchronously and encapsulated into a fault feature package; The fault characteristic packet is broadcast to adjacent regional independent protection units via a high-speed fiber optic link; After receiving the fault feature packet, the adjacent regional independent protection unit compares its own monitoring data with the fault feature packet. If they match, it enters an early warning state and shortens its own protection action delay; if they do not match, it maintains normal protection logic.
8. A high-voltage power distribution control system for an electric aircraft, characterized in that, The system is used to perform a high-voltage power distribution control method for an electric aircraft as described in any one of claims 1 to 7, the system comprising: The power battery pack is used to output high-voltage DC power. A pre-charging module, connected to the power battery pack, is configured to perform soft-start charging of the bus capacitor through a pre-charging circuit when the system is powered on. The power distribution stage includes multiple solid-state relays or contactors, which respectively constitute a motor controller branch, an auxiliary power module branch, an air conditioning system branch, and an electric heating system branch. The power distribution stage is configured to distribute electrical energy to each load branch according to a preset load priority. The load output stage, located downstream of the power distribution stage, includes multiple independent protection units. Each independent protection unit corresponds to a load branch and is configured to monitor the voltage, current, and temperature parameters of the corresponding load branch in real time. When any monitored parameter exceeds the corresponding preset threshold, a fault isolation operation is performed on the load branch.
9. A computer-readable storage medium storing a computer program, characterized in that, When the computer program is executed by the processor, it implements the steps of the high-voltage power distribution control method for an electric aircraft as described in any one of claims 1 to 7.
10. A computer program product comprising a computer program / instructions, characterized in that, When the computer program / instructions are executed by the processor, they implement the steps of the high-voltage power distribution control method for an electric aircraft as described in any one of claims 1 to 7.