Construction method for non-pressure drainage pipeline elevation conflict and non-pressure drainage pipeline system
By constructing a well structure at the intersection of unpressurized drainage pipes and disconnecting and connecting the pipes, a second unpressurized drainage pipe was laid, which solved the problem of the elevation conflict between the existing pipes and the second-phase pipes, and achieved a low-cost and rapid construction solution.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- MCC CAPITAL ENGINEERING & RESEARCH INC LTD
- Filing Date
- 2026-03-19
- Publication Date
- 2026-06-02
AI Technical Summary
During the second phase of construction of the industrial project, the existing unpressurized drainage pipeline conflicts with the second phase pipeline plan, resulting in high construction difficulty, high cost and high risk. Existing solutions affect the operation of the original pipeline or increase the amount of excavation, and cannot effectively resolve the elevation conflict.
A well structure is constructed at the intersection of the first and second unpressurized drainage pipes. The first unpressurized drainage pipe is disconnected and connected within the well structure. The second unpressurized drainage pipe is laid through the opening in the well structure to ensure that the two do not interfere with each other. The water flow path is optimized by utilizing the inner cavity and groove design of the well structure.
Without disrupting the existing pipeline operation, reduce construction costs and time, ensure smooth drainage for both pipelines, minimize impact on the existing pipelines, and shorten the construction period.