An optimization method and application for power grid power source maintenance planning in a new type of power system
By designing maintenance plans in advance in the new power system, and combining them with overall system control and boundary conditions, the power output configuration is optimized. This solves the problem of the disconnect between maintenance plans and power balance in traditional methods, improves the efficiency and accuracy of maintenance plans, and ensures the safe and stable operation of the power grid.
Patent Information
- Application Number
- CN202611269024.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-20
- Publication Date
- 2026-11-10
AI Technical Summary
In new power systems, traditional maintenance planning methods cannot adapt to the uncertainty and volatility of new energy power generation, resulting in a disconnect between maintenance plans and power balance calculations, leading to problems such as decreased power supply reliability or wasted power redundancy.
The maintenance plan is calculated in advance, and the units are ranked according to their installed capacity. Combined with the overall system control principles, maintenance time constraints and boundary conditions, the output coordination configuration of various power sources is optimized. The optimal maintenance scheme is selected through evaluation indicators, reducing iterative calculation steps and achieving a scientific connection between the maintenance plan and the power balance.
It significantly improves the efficiency and accuracy of maintenance planning, optimizes power output coordination, ensures safe and stable power supply to the power grid, avoids insufficient reserves or waste of redundancy, and adapts to the operating characteristics of new power systems.
Smart Images

Figure CN123070929A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the fields of power systems and energy storage technology, specifically to an optimization method and application of a new type of power grid power source maintenance plan. Background Technology
[0002] During the operation of the power system, regular maintenance of generator units is an important part of ensuring the safe, stable and reliable power supply of the power grid. Its core objective is to ensure the healthy operation of the generator units while meeting the power load demand and reserve capacity requirements of the system and maintaining the supply and demand balance of the power system through scientific and reasonable maintenance planning.
[0003] In principle, generator unit maintenance should be scheduled during low-load seasons when there is surplus power capacity (except for nuclear power units). After the unit maintenance plan is finalized, if the output of the remaining available units cannot meet the system load or system reserve requirements, the additional installed capacity needed to fill this supply-demand gap is defined as maintenance reserve capacity. The determination of maintenance reserve capacity must be finalized after the initial maintenance plan is drafted, taking into account the system's annual load curve, through detailed power balance calculations. This is a key parameter for ensuring the reliability of system power supply during maintenance.
[0004] In traditional power systems, the power source types are relatively homogeneous, mainly hydropower and thermal power. The operating characteristics and load patterns of the power system are relatively stable. Maintenance plan calculations are generally carried out after the operating positions and output processes of each power source are determined (power balance) and after the working and load reserve balance calculations are performed, thus determining whether the installed capacity needs to be changed. With the deepening of energy transition, the power system is rapidly evolving into a new type of power system dominated by new energy sources, and the limitations of traditional maintenance planning methods are becoming increasingly apparent. The proportion of installed capacity of new energy power generation such as wind power and photovoltaic power in the new power system continues to increase. Its uncertainty, volatility, and randomness lead to increasingly complex operating characteristics of the power system, reducing the representativeness of traditional typical scenarios and failing to accurately reflect the supply and demand changes of the power system over long periods. There is an urgent need to adopt long-sequence continuous power production simulation methods for system analysis.
[0005] If the traditional maintenance planning process is followed, where maintenance plans are formulated only after power balance calculations are completed, numerous problems arise. In long-sequence continuous power production simulations, adjustments to subsequent maintenance plans will negatively impact the working positions and output allocation of each power source in the earlier power balance calculations, leading to repeated iterative calculations that are extremely cumbersome and significantly reduce work efficiency. Furthermore, the disconnect between maintenance plans and power balance calculations can easily result in a mismatch between maintenance arrangements and the actual supply and demand of the system. This may lead to insufficient system reserves during maintenance, decreased power supply reliability, or unreasonable maintenance arrangements resulting in wasted power redundancy, making it difficult to adapt to the operation and management requirements of new power systems.
[0006] Therefore, given the characteristics of the new power system, there is an urgent need for an optimized method for power grid maintenance planning under the new power system, to break through the limitations of the traditional process, to achieve a scientific connection between maintenance planning and power balance calculation, to improve the rationality and accuracy of maintenance planning, and to ensure the safe, stable and efficient operation of the new power system. Summary of the Invention
[0007] To address the existing problems, this invention provides an optimization method and application for power grid power source maintenance planning under a new type of power system. This method solves the problems of system complexity caused by the characteristics of new energy power generation and insufficient representativeness of traditional typical scenarios in the new power system. By designing the maintenance plan calculation in advance, it effectively avoids interference from maintenance plan adjustments on the previous power source output configuration, reduces iterative calculation steps, and significantly improves the efficiency and accuracy of maintenance plan formulation. Simultaneously, it optimizes the coordinated configuration of output from various power sources, accurately adapting to the operating characteristics of the new power system, and providing reliable technical support for efficient power grid operation and maintenance and the rational utilization of energy resources.
[0008] To achieve the above objectives, the present invention provides a novel method for optimizing power grid power supply maintenance plans under a new power system, characterized by comprising the following steps: Step 1: Sort all types of power plant units, excluding wind power and photovoltaic power plants, according to their single-unit installed capacity from largest to smallest, to form a maintenance optimization sorting sequence K for all units in the power system. The various types of power plant units include at least one of hydropower, thermal power, energy storage and gas power plant units. Step 2: For each unit k in the cyclic maintenance optimization sorting sequence K, based on the overall system control principle, maintenance time constraint principle and maintenance period executable boundary conditions, determine all feasible maintenance plans for unit k, forming a plan set N; Step 3: For each maintenance plan i in the scheme set N of unit k, calculate the absolute value of the remaining system capacity after deducting the maintenance capacity of the unit, and use it as the evaluation index Z of the maintenance plan. Step 4: After completing the index calculation of all maintenance plans for the unit, select the plan with the smallest evaluation index Z value as the optimal maintenance plan and determine it as the final maintenance plan for unit k. Step 5: Repeat steps 2 to 4 until all units in sequence K have been processed.
[0009] Furthermore, in step 2, the overall system control principles include: The available system capacity after deducting maintenance capacity shall not be less than the sum of system load and system standby capacity, except in cases where the total installed capacity of the system is less than the sum of system load and system standby capacity.
[0010]
[0011]
[0012] In the formula, The system's available capacity during time period t. The actual system load during time period t. The system reserve capacity for time period t. This represents the total installed capacity of the system. This refers to the set of generating units undergoing maintenance during time period t. For set The single unit capacity of the mth unit in the middle.
[0013] Furthermore, the system's backup capacity The calculation formula is:
[0014] In the formula, This represents the reserve capacity factor.
[0015] Furthermore, in step 2, the boundary conditions that can be executed during the maintenance period include the following constraints: (1) The maintenance period of the thermal power unit does not overlap with the heating season: In the formula, Let represent the maintenance period for the i-th option of unit k. It is the heating season; (2) The maintenance period for hydropower units is included in the dry season: In the formula It is the dry season; (3) The maintenance period of the solar thermal power plant meets the conditions of sufficient system capacity and limited solar resources: and In the formula, Let be the capacity adequacy coefficient for time period t. η min This is the lower limit of the capacity adequacy factor. ( t () represents the light resource coefficient for time period t. max This represents the upper limit of the light resource coefficient. (4) The maintenance periods for pumped storage units do not overlap with the periods when peak shaving is difficult: In the formula, This is a period when peak-shaving is difficult.
[0016] Furthermore, the capacity adequacy factor η ( t The formula for calculating ) is:
[0017] In the formula, The system's available capacity during time period t. L ( t () represents the actual system load during time period t. The system's standby capacity is t.
[0018] Furthermore, in step 2, the executable boundary conditions for the maintenance period also include: only one unit of the same power plant is scheduled for maintenance at the same time, that is, for any two different units within the same power plant... , ,satisfy: ,
[0019] In the formula, [ For the unit The maintenance period for the i-th option is [ For the unit Maintenance period for option j.
[0020] Furthermore, in step 3, the evaluation index Z is calculated as follows:
[0021] And it satisfies:
[0022] In the formula, Z represents the absolute value of the system's remaining capacity after deducting the unit's maintenance capacity. Z z ( t Let be the system installed capacity at time t. Z j ( t Let be the single unit capacity of the j-th maintenance unit. Z b ( t Let be the electrical load at time t. Z l ( t Let be the load reserve capacity at time t. Z s ( t Let be the emergency reserve capacity at time t. J for t The number of generating units that are constantly undergoing maintenance. T The calculation period is specified.
[0023] Furthermore, in step 3, it is also determined whether the current maintenance plan meets the maximum maintenance rate requirement of the power station to which the unit belongs. If it exceeds the maximum maintenance rate, the plan is set as infeasible and a penalty function is introduced. The calculation formula for the penalty function is:
[0024] In the formula, The target value for evaluating infeasible solutions. K represents the maximum evaluation target value of the preset feasible solution, and K is the penalty coefficient. This represents the actual maintenance rate of the power station during time period t. This represents the maximum permissible maintenance rate for the power station.
[0025] An information data processing terminal for implementing an optimized method for power grid power supply maintenance planning under the aforementioned novel power system.
[0026] A computer-readable storage medium includes instructions that, when executed on a computer, cause the computer to perform the aforementioned optimization method for power grid power supply maintenance planning in a novel power system.
[0027] The beneficial effects of this invention are as follows: Addressing the system complexity caused by the characteristics of new energy power generation and the insufficient representativeness of traditional typical scenarios, this invention advances the calculation of annual maintenance plans, adapting to the needs of long-sequence continuous power production simulation. This avoids the impact of maintenance plan adjustments on previous power output configurations, reduces iterative calculations, and significantly improves the efficiency and accuracy of maintenance plan formulation. Simultaneously, by achieving a scientific connection between maintenance plans and power balance, and combining the system's annual load curve and the characteristics of new energy sources, it coordinates unit maintenance, load supply, and reserve requirements. This not only ensures the safe and stable power supply of the grid and avoids problems of insufficient reserves or redundant waste, but also optimizes the coordinated configuration of power output, accurately adapting to the characteristics of new power systems. It provides technical support for efficient grid operation and maintenance and rational energy utilization, and has significant engineering application value. Attached Figure Description
[0028] Figure 1 This is a flowchart of an optimization method for power grid power supply maintenance planning under a novel power system, as described in an embodiment of the present invention. Figure 2 This is a schematic diagram of the balance calculation principle of the optimization method for power grid power supply maintenance plan in an embodiment of the present invention; Figure 3 This is a schematic diagram illustrating the principle of the balance calculation for the optimization method of the power grid power supply maintenance plan within a calculation cycle in an embodiment of the present invention. Figure 4 This is a diagram showing the results of the annual maintenance plan for power system units in an embodiment of the present invention. Detailed Implementation
[0029] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. The specific embodiments described herein are merely illustrative and are not intended to limit the invention.
[0030] like Figure 1 As shown, the optimization method for provincial power grid power supply maintenance plan using the present invention specifically includes the following steps: Step 1: For all types of power station units other than wind power and photovoltaic power stations, sort them from largest to smallest based on their single unit installed capacity to form the maintenance optimization sorting sequence K for all units in the power system; In this embodiment, power system data for a certain province is collected, including power source data such as wind power, photovoltaic, hydropower, pumped storage, thermal power, and gas power. Among them, by 2030, the installed capacity of wind power will be 18,000 MW, the installed capacity of photovoltaic power will be 26,000 MW, the installed capacity of pumped storage will be 10,000 MW, the installed capacity of hydropower in the province will be 15,000 MW, the installed capacity of thermal power will be 40,000 MW, and the installed capacity of gas power will be 950 MW.
[0031] Step 2: For each unit k in the cyclic maintenance optimization sorting sequence K, based on the overall system control principle, maintenance time constraint principle and maintenance period executable boundary conditions, determine all feasible maintenance plans for unit k, forming a plan set N; In this embodiment, the overall system control principles, maintenance time constraints, and the limitations on executable boundary conditions during maintenance periods are as follows: 2.1 System Overall Control Principles 2.1.1 The available system capacity after deducting maintenance capacity shall not be less than the sum of system load and system reserve capacity (except where the total installed capacity of the system is less than the sum of system load and system reserve capacity).
[0032]
[0033]
[0034] 2.1.2 Power supply maintenance should be planned and arranged in accordance with load demand (except for nuclear power units).
[0035]
[0036] In the formula, The system's available capacity during time period t. The actual system load during time period t. The system reserve capacity for time period t. This represents the total installed capacity of the system. This refers to the set of generating units undergoing maintenance during time period t. For set The single unit capacity of the m-th unit in the middle, This represents the reserve capacity factor.
[0037] 2.2 Maintenance Time Constraint Principle The maintenance period for coal-fired power units and combined heat and power units is 6 weeks; the maintenance period for gas-fired power units is 4 weeks; and the maintenance period for hydroelectric power units and pumped storage units is 4 weeks.
[0038] Maintenance is not considered for wind turbines and photovoltaic units.
[0039] Run-of-river hydropower stations can meet their expected output by operating some units at full or near full capacity while shutting down the rest, thus enabling flexible maintenance arrangements. In this embodiment, maintenance of the run-of-river hydropower station units is not considered.
[0040] 2.3 Boundary conditions that can be applied during maintenance periods 2.3.1 Thermal power units should not be scheduled for maintenance during the heating season, while hydropower units are generally scheduled for maintenance during the dry season;
[0041]
[0042] In the formula, This is a maintenance period. For the heating season, It is the dry season.
[0043] 2.3.2 Solar thermal power plants are generally scheduled for maintenance during periods when system capacity is ample and solar resources are scarce;
[0044]
[0045]
[0046] In the formula, This is the capacity adequacy factor. Let be the light resource coefficient for time period t.
[0047] 2.3.3 Pumped storage units will not be scheduled for maintenance during periods of peak-shaving difficulty;
[0048] In the formula, This is a period when peak-shaving is difficult.
[0049] 2.3.4 In principle, only one unit of a power plant should be scheduled for maintenance at any given time.
[0050]
[0051]
[0052]
[0053] In the formula,k , l These are different generating units within the same power plant.
[0054] Step 3: For each maintenance plan i in the scheme set N of unit k, calculate the absolute value of the remaining system capacity after deducting the maintenance capacity of the unit, and use it as the evaluation index Z of the maintenance plan. like Figure 2 , 3 As shown, in this embodiment, combining the power load process of the receiving-end area and the maintenance characteristics of various power sources, the system's available capacity after deducting the maintenance capacity is greater than or equal to the sum of the system load and the system reserve, is used as the boundary condition. The absolute value of the system's remaining capacity after deducting the unit's maintenance capacity is calculated and used as the evaluation index Z of the maintenance plan. The calculation method is as follows: 3.1 Calculate the absolute value Z of the remaining system capacity after deducting the maintenance capacity of the unit.
[0055]
[0056] In the formula, Z represents the absolute value of the system's remaining capacity after deducting the unit's maintenance capacity. Z z ( t )for t The installed capacity at any given time Z j ( t ) for generator unit j single-machine capacity, Z b ( t () represents the electrical load. Z l ( t ) is for load standby. Z s ( t This is the emergency reserve capacity. J for t The number of generating units that are constantly undergoing maintenance. T To calculate the calculation period, this method performs calculations on a weekly basis. 3.2 Determine whether the proposed scheme meets the maximum maintenance rate requirement of the power station to which the unit belongs. If it exceeds the maximum maintenance rate, the scheme is deemed infeasible, and a penalty function is set. The formula for the penalty function is as follows:
[0057] In the formula, The target value for evaluating infeasible solutions. K represents the maximum evaluation target value of the preset feasible solution, and K is the penalty coefficient. This represents the actual maintenance rate of the power station during time period t. This represents the maximum permissible maintenance rate for the power station.
[0058] 3.3 If the maximum maintenance rate requirement is met, the scheme is considered feasible and the objective function value is calculated.
[0059] Step 4: After completing the calculation of all schemes, select the scheme with the minimum evaluation objective function as the optimal scheme, which will be used as the maintenance plan scheme for the unit. Step 5: Repeat steps 2, 3, and 4 to calculate the maintenance schedule for unit k+1 until all unit maintenance calculations and arrangements are completed.
[0060] In this embodiment, different maintenance schedule plans are shown in the table below. Figure 4 In order to utilize the provincial power grid power source maintenance arrangement method proposed in this invention, the annual maintenance plan of the power system on a weekly scale is obtained in this embodiment.
[0061]
[0062] This embodiment provides a method for scheduling maintenance of provincial power grid sources under a new type of power system. It addresses the system complexity caused by the characteristics of new energy power generation in the new power system and the lack of representativeness of traditional typical scenarios. By prioritizing the calculation of maintenance plans, it effectively avoids interference from adjustments to maintenance plans on the previous power output configuration, reduces iterative calculation steps, and significantly improves the efficiency and accuracy of maintenance plan formulation. At the same time, it optimizes the coordinated configuration of output from various power sources, accurately adapts to the operating characteristics of the new power system, and provides reliable technical support for efficient operation and maintenance of the power grid and rational utilization of energy resources.
[0063] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for optimizing power grid power source maintenance plans under a novel power system, characterized in that, Includes the following steps: Step 1: Sort all types of power plant units, excluding wind power and photovoltaic power plants, according to their single-unit installed capacity from largest to smallest, to form a maintenance optimization sorting sequence K for all units in the power system. The various types of power plant units include at least one of hydropower, thermal power, energy storage and gas power plant units. Step 2: For each unit k in the cyclic maintenance optimization sorting sequence K, based on the overall system control principle, maintenance time constraint principle and maintenance period executable boundary conditions, determine all feasible maintenance plans for unit k, forming a plan set N; Step 3: For each maintenance plan i in the scheme set N of unit k, calculate the absolute value of the remaining system capacity after deducting the maintenance capacity of the unit, and use it as the evaluation index Z of the maintenance plan. Step 4: After completing the index calculation of all maintenance plans for the unit, select the plan with the smallest evaluation index Z value as the optimal maintenance plan and determine it as the final maintenance plan for unit k. Step 5: Repeat steps 2 to 4 until all units in sequence K have been processed.
2. The optimization method for power grid power supply maintenance planning under the new power system according to claim 1, characterized in that, In step 2, the overall system control principles include: The available system capacity after deducting maintenance capacity shall not be less than the sum of system load and system standby capacity, except in cases where the total installed capacity of the system is less than the sum of system load and system standby capacity. In the formula, The system's available capacity during time period t. The actual system load during time period t. The system reserve capacity for time period t. This represents the total installed capacity of the system. This refers to the set of generating units undergoing maintenance during time period t. For set The single unit capacity of the mth unit in the middle.
3. The optimization method for power grid power supply maintenance planning under the new power system according to claim 2, characterized in that, The system's backup capacity The calculation formula is: In the formula, This represents the reserve capacity factor.
4. The optimization method for power grid power supply maintenance planning under the new power system according to claim 1, characterized in that, In step 2, the boundary conditions that can be executed during the maintenance period include the following constraints: (1) The maintenance period of the thermal power unit does not overlap with the heating season: In the formula, Let represent the maintenance period for the i-th option of unit k. It is the heating season; (2) The maintenance period for hydropower units is included in the dry season: In the formula It is the dry season; (3) The maintenance period of the solar thermal power plant meets the conditions of sufficient system capacity and limited solar resources: and In the formula, Let be the capacity adequacy coefficient for time period t. η min This is the lower limit of the capacity adequacy factor. ( t () represents the light resource coefficient for time period t. max This represents the upper limit of the light resource coefficient. (4) The maintenance periods for pumped storage units do not overlap with the periods when peak shaving is difficult: In the formula, This is a period when peak-shaving is difficult.
5. The optimization method for power grid power supply maintenance planning under the new power system according to claim 4, characterized in that, The capacity adequacy coefficient η ( t The formula for calculating ) is: In the formula, The system's available capacity during time period t. L ( t () represents the actual system load during time period t. The system's standby capacity is t.
6. The optimization method for power grid power supply maintenance planning under the new power system according to claim 1, characterized in that, In step 2, the boundary conditions for the maintenance period also include: only one unit in the same power plant is scheduled for maintenance at the same time, that is, for any two different units in the same power plant. , ,satisfy: , In the formula, [ For the unit The maintenance period for the i-th option is [ For the unit Maintenance period for option j.
7. The optimization method for power grid power supply maintenance planning under the new power system according to claim 1, characterized in that, In step 3, the evaluation index Z is calculated as follows: And it satisfies: In the formula, Z represents the absolute value of the system's remaining capacity after deducting the unit's maintenance capacity. Z z ( t Let be the system installed capacity at time t. Z j ( t Let be the single unit capacity of the j-th maintenance unit. Z b ( t Let be the electrical load at time t. Z l ( t Let be the load reserve capacity at time t. Z s ( t Let be the emergency reserve capacity at time t. J for t The number of generating units that are constantly undergoing maintenance. T The calculation period is specified.
8. The optimization method for power grid power supply maintenance planning under the new power system according to claim 1, characterized in that, In step 3, it is also determined whether the current maintenance plan meets the maximum maintenance rate requirement of the power station to which the unit belongs. If it exceeds the maximum maintenance rate, the plan is set as infeasible and a penalty function is introduced. The calculation formula of the penalty function is: In the formula, The target value for evaluating infeasible solutions. K represents the maximum evaluation target value of the preset feasible solution, and K is the penalty coefficient. This represents the actual maintenance rate of the power station during time period t. This represents the maximum permissible maintenance rate for the power station.