Connection nodes and construction methods between hollow steel tube concrete arch ribs and arch columns
By using the coordinated force transmission path of the column anchoring components, the inner and outer steel pipe connection components, and the arch internal force transmission components, the problem of load concentration at the top of the outer steel pipe in the connection node between the hollow sandwich steel pipe concrete arch rib and the arch column is solved, thus achieving efficient load distribution and improved construction efficiency.
Patent Information
- Application Number
- CN202611596001.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-15
- Publication Date
- 2026-11-17
AI Technical Summary
In the existing connection nodes between hollow steel tube concrete arch ribs and arch columns, the force transmission paths of the inner and outer steel tubes are discontinuous, resulting in the load being concentrated in a local area at the top of the outer steel tube. Furthermore, the construction is complex, making it difficult to achieve an efficient connection between factory prefabrication and on-site assembly.
The system employs a coordinated force transmission path consisting of column anchoring components, inner and outer steel pipe connection components, and arch internal force transmission components. Through the connection of the outer steel pipe, sandwich concrete, and inner steel pipe, a mechanical link is established between the inner and outer steel pipes, forming a continuous force transmission path that efficiently transfers the load to the lower part and both sides of the arch rib section.
It effectively disperses the load at the base of the arch column, reduces localized stress concentration at the top of the outer steel pipe, improves construction efficiency, and achieves an efficient connection between factory prefabrication and on-site assembly.
Smart Images

Figure CN123109047A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of bridge engineering technology, and in particular to a connection node and construction method for a hollow sandwich steel tube concrete arch rib and an arch column. Background Technology
[0002] Hollow-core steel-concrete composite arch ribs are a novel type of composite structure, typically composed of an outer steel tube, an inner steel tube, and a layer of concrete poured between them, with the inner steel tube forming a hollow cavity. This type of structure combines lightweight, high strength, and excellent seismic performance, making it promising for use in long-span arch bridges. The superstructure columns, as key vertical support members transferring bridge deck loads to the arch ribs, bear axial forces, shear forces, and bending moments from the superstructure at their roots, which are then concentrated and transferred to the arch ribs through connection nodes.
[0003] Currently, existing arch-supported column connection nodes typically employ a structure where the column is welded to the outer steel pipe and reinforced with longitudinal and transverse stiffening plates, primarily strengthening the base of the column and the top area of the outer steel pipe. For hollow sandwich sections, this type of localized reinforcement has limited force transmission to the inner steel pipe and the lower part of the section, and the problem of localized stress concentration at the node still needs improvement. Conventional shear studs connect the corresponding steel pipes to the sandwich concrete separately, and cannot directly connect the inner and outer steel pipes. When the node lacks a through-mechanical connection, there is insufficient direct constraint on the relative slippage and local separation tendency of the inner and outer steel pipes. Furthermore, if the longitudinal force transmission plate is broken at the column position, the load needs to be transferred through the column wall and local welds, affecting the continuity of longitudinal force transmission; if the hollow cavity lacks a force transmission structure corresponding to the column position, the force transmitted to the top of the inner steel pipe is difficult to effectively diffuse to its lower sides. In addition, the connection between the arch rib and the arch-supported column involves the installation of multiple stiffening plates and connecting components. If the positioning and welding are mainly completed on-site, it will increase the amount of on-site work and the difficulty of quality control.
[0004] Therefore, it is urgent to develop a node and construction method suitable for connecting hollow steel tube concrete arch ribs and arch columns, establish a collaborative force transmission path involving the inner and outer steel tubes and the interlayer concrete, so that the load transmitted from the column base can be diffused longitudinally along the arch rib and further transferred from the top connection area to the lower sides of the inner steel tube, enhance the mechanical connection and cross-sectional collaborative stress between the inner and outer steel tubes, and adapt to the requirements of factory prefabrication and on-site assembly construction. Summary of the Invention
[0005] The purpose of this invention is to solve the above-mentioned technical problems and provide a connection node and construction method for a hollow sandwich steel tube concrete arch rib and an arch column. A new connection node is proposed, in which there is no direct rigid connection between the inner and outer steel tube connection components, the column anchoring components, and the arch internal force transmission components. Instead, the outer steel tube, sandwich concrete, and inner steel tube of the arch rib segment are connected. The collaborative force transmission path of the above components efficiently and with a short path transmits the force from the root of the arch column to the lower part and both sides of the arch rib section, so that the force on the arch column is no longer mainly limited to the local area at the top of the outer steel tube.
[0006] To achieve the above objectives, the present invention provides the following solution: The present invention discloses a connection node between a hollow sandwich steel tube concrete arch rib and an arch column, comprising: The arch rib segment has a column corresponding area that corresponds to the column on the arch. The arch rib segment includes an inner steel pipe, a sandwiched concrete layer and an outer steel pipe arranged sequentially from the inside to the outside. A column anchoring assembly is used to anchor the arch column to the outer steel pipe of the corresponding area of the column, and the extension line of the central axis of the arch column anchored in the corresponding area of the column passes through the central axis of the arch rib segment. Inner and outer steel pipe connecting components, which are used to anchor the outer and inner steel pipes in the corresponding area of the column and are distributed in the corresponding area of the column; The arch internal force transmission component includes a first connecting end, a second connecting end, and a third connecting end; the first connecting end is fixedly connected to the inner steel pipe of the corresponding area of the column and is located on the extension line of the central axis of the column on the arch; the second connecting end and the third connecting end are both connected to the inner wall of the inner steel pipe of the arch rib segment located on the opposite side of the corresponding area of the column and are arranged on both sides of the extension line of the central axis of the column on the arch.
[0007] In one embodiment, the column anchoring assembly includes an arch-mounted column reserved section, which is fixedly connected to the outer steel pipe of the corresponding area of the column. The arch-mounted column reserved section is a tubular structure whose outer contour matches that of the arch-mounted column, and is used for coaxial fixed connection with the arch-mounted column.
[0008] In one embodiment, the column anchoring assembly further includes a longitudinal through plate and a transverse stiffening plate; the longitudinal through plate passes through the reserved section of the arch column along the central axis of the arch rib segment, and the longitudinal through plate is fixedly connected to the reserved section of the arch column and the outer steel pipe of the corresponding area of the column; the transverse stiffening plate is arranged perpendicular to the reserved section of the column, and the transverse stiffening plate is fixedly connected to the reserved section of the arch column and the outer steel pipe of the arch rib segment.
[0009] In one embodiment, the inner and outer steel pipe connecting assembly is a through-ring groove rivet, and the through-ring groove rivets are provided on both sides of the longitudinal through plate and the transverse stiffening plate.
[0010] In one embodiment, the arch-inner force transmission assembly includes an upper connecting plate, oblique force transmission members, and a lower connecting plate. The upper connecting plate serves as the first connecting end and is fixedly connected to the inner steel pipe. One end of each of the two oblique force transmission members is anchored to the upper connecting plate via connecting ring groove rivets, and the other end of each of the two oblique force transmission members is anchored to the lower connecting plate via connecting ring groove rivets. The lower connecting plates on the two oblique force transmission members serve as the second and third connecting ends, respectively, and are fixedly connected to the inner steel pipe.
[0011] In one embodiment, the arch-in-the-arch force transmission assembly includes a set of upper connecting plates and two sets of lower connecting plates. Each set of upper connecting plates includes two upper connecting plates spaced apart along the central axis of the steel-concrete composite arch. One end of the oblique force transmission member is located between the two upper connecting plates in the set. An upper stiffening plate is fixedly connected between the two upper connecting plates in the set. Each set of lower connecting plates includes two lower connecting plates spaced apart along the central axis of the steel-concrete composite arch. The other end of each oblique force transmission member is located between the two lower connecting plates in the corresponding set. A lower stiffening plate is fixedly connected between the two lower connecting plates in the set.
[0012] In one embodiment, shear studs are provided on both the outer wall of the inner steel pipe and the inner wall of the outer steel pipe, and the shear studs are used to embed into the sandwich concrete.
[0013] This invention also discloses a construction method for the connection node between the hollow sandwich steel tube concrete arch rib and the arch column, including the following steps: S1. Factory-processed components: In the factory, the outer and inner steel pipes of the arch rib segment are manufactured, and corresponding through rivet mounting holes are machined in the corresponding areas of the outer and inner steel pipes and the corresponding columns of the arch. The reserved section of the arch column, longitudinal through plate, transverse stiffening plate, upper connecting plate, lower connecting plate and oblique force transmission component are manufactured. S2. Install the column anchoring components and the inner arch connecting plate: The arch-support column pre-reserved section, the longitudinal through plate, and the transverse stiffening plate are assembled and welded to the corresponding column area of the outer steel pipe to form a column anchoring assembly; the longitudinal through plate passes continuously along the axial direction of the arch rib segment through the arch-support column pre-reserved section and is welded to the arch-support column pre-reserved section and the outer steel pipe respectively; the transverse stiffening plate is welded to the arch-support column pre-reserved section and the outer steel pipe respectively. The upper connecting plate is welded to the top inner wall corresponding to the reserved section of the arch column of the inner steel pipe, and the lower connecting plate is welded to the inner wall of both sides of the lower part of the inner steel pipe respectively. S3. Assemble the inner and outer steel pipes and install mechanical connectors: The inner steel pipe is positioned inside the outer steel pipe to form an annular sandwich space between them, and the through rivet mounting holes on the inner steel pipe and the outer steel pipe correspond to each other. After completing the required welding at the node, install the two inclined force transmission components, the through-ring groove rivets, and the connecting ring groove rivets; the upper ends of the two inclined force transmission components are connected to the upper connecting plate through the connecting ring groove rivets, and the lower ends are connected to the corresponding lower connecting plates located on both sides of the lower part of the inner steel pipe through the connecting ring groove rivets, so that the two inclined force transmission components extend from the top connection area to the lower sides, forming an inverted V-shaped arch internal force transmission assembly together with the upper connecting plate and the lower connecting plate; The through-ring groove rivets are arranged near both sides of the longitudinal through plate and the transverse stiffening plate, and pass through the outer steel pipe, the annular interlayer space and the inner steel pipe through corresponding through-ring rivet mounting holes, and are riveted to connect the outer steel pipe and the inner steel pipe. S4. Filling of interlayer concrete: After the through-ring groove rivet and the connecting ring groove rivet are installed, concrete is poured into the annular interlayer space between the outer steel pipe and the inner steel pipe to form interlayer concrete, so that the rod segment of the through-ring groove rivet located in the annular interlayer space is embedded in the interlayer concrete. S5, Arch Rib Segment Transportation: The prefabricated arch rib segments are transported to the construction site, and the upper end of the reserved section of the arch column is used as the on-site connection end. S6. On-site connection of the arch-mounted columns: The arch-mounted column is hoisted and its lower end is connected to the upper end of the reserved section of the arch-mounted column.
[0014] In one implementation, In step S1, an upper stiffening plate and a lower stiffening plate are also fabricated, and connecting rivet holes are machined at the corresponding connection positions of the upper connecting plate, the lower connecting plate, and the inclined force transmission member; shear studs are welded on the inner wall of the outer steel pipe and the outer wall of the inner steel pipe. In step S2, a through-plate opening adapted to the longitudinal through-plate is machined on the pipe wall of the reserved section of the arch column, the longitudinal through-plate is passed through the through-plate opening, and connected to the reserved section of the arch column by a double-sided continuous fillet weld along the through-plate opening. The upper connecting plate is configured as two plates spaced apart along the axial direction of the arch rib segment, and the lower connecting plate is configured as two sets of plates located on both sides of the lower part of the inner steel pipe, each set including two lower connecting plates spaced apart along the axial direction of the arch rib segment. The arc-shaped edges of each of the upper connecting plates and each of the lower connecting plates are continuously welded to the inner wall of the inner steel pipe; an upper stiffening plate is provided between two upper connecting plates, and the upper stiffening plate is welded to the two upper connecting plates and the inner steel pipe; a lower stiffening plate is provided between two lower connecting plates in each group, and the lower stiffening plate is welded to the corresponding two lower connecting plates and the inner steel pipe; In step S3, the upper end of each inclined force transmission member is located between two upper connecting plates, and the lower end is located between two lower connecting plates of a corresponding group. At the upper connection portion of each inclined force transmission member, the two upper connecting plates are respectively connected to the corresponding connection surface of the inclined force transmission member by connecting ring groove rivets. At its lower connection portion, the two lower connecting plates of a corresponding group are respectively connected to the corresponding connection surface of the inclined force transmission member by connecting ring groove rivets. The through-ring groove rivet's insertion path avoids the longitudinal through plate, the transverse stiffening plate, the upper connecting plate, and the lower connecting plate.
[0015] In one embodiment, in step S6, the upper section of the reserved section of the arch column matches the lower section of the arch column; the arch column is hoisted so that the lower end of the arch column is coaxially aligned with the upper end of the reserved section of the arch column, and a butt weld with the same strength as the base material of the arch column is used for connection, and the weld is inspected and repaired for corrosion protection.
[0016] The force mechanism of this invention is as follows: Axial force, shear force, and bending moment transmitted from the arch column are input to the node through the reserved section of the arch column. The longitudinal through plate continuously passes through the reserved section and, through welding connection with the reserved section and the outer steel pipe, diffuses the column force along the arch rib axis, reducing the link of local transfer through the column pipe wall after the longitudinal plate is broken; the transverse stiffening plate provides transverse and oblique force transmission and support, dispersing the concentrated force at the column root to a larger area of the outer steel pipe. The sandwich concrete participates in the load transfer between the inner and outer steel pipes through contact pressure bearing with the inner and outer steel pipes and interface force transmission of the shear studs. The through-ring groove rivets establish a direct mechanical connection between the two layers of steel pipes. When the outer steel pipe is locally tensile and tends to separate radially, the rivets participate in the force bearing through the tension of the rod body and the anchor pressure at both ends, limiting the relative separation deformation of the inner and outer steel pipes, and together with the sandwich concrete and shear studs, maintaining the force transmission connection of the node. The force transmitted to the top area of the inner steel pipe is transferred to the two oblique force-transmitting members via the upper connecting plate and connecting ring groove rivets. The inverted V-shaped arrangement utilizes the axial stiffness of the oblique members to establish a force transmission channel spanning the hollow cavity between the top connecting area and the lower two sides, and then transmits the force to the lower two side pipe walls via the lower connecting plate. The upper and lower connecting plates and corresponding stiffening plates strengthen the connection area between the end of the member and the pipe wall, dispersing the end force. Thus, the load diffusion of the external plates, the mechanical connection between the inner and outer steel pipes, and the oblique force transmission within the arch work together to allow more areas of the arch rib section to share the column load.
[0017] The present invention achieves the following technical effects compared to the prior art: In this invention, the connecting nodes include arch rib segments, column anchoring components, inner and outer steel pipe connecting components, and arch internal force transmission components. The column anchoring components are located on the outside of the outer steel pipe and are used to receive and diffuse the force of the column on the arch over a large area of the outer steel pipe. The inner and outer steel pipe connecting components are used to establish a mechanical connection between the inner and outer steel pipes. The arch internal force transmission components are located in the hollow cavity enclosed by the inner steel pipe and are used to transmit and diffuse the force of the top of the inner steel pipe corresponding to the column area to both sides of the lower part of the inner steel pipe. There is no direct rigid connection between the inner and outer steel pipe connecting components, column anchoring components, and arch internal force transmission components. Instead, they are connected through the outer steel pipe, the interlayer concrete, and the inner steel pipe. The collaborative force transmission path of the above components efficiently and with a short path transmits the force from the root of the column on the arch to the lower part and both sides of the arch rib section, so that the force of the column on the arch is no longer mainly limited to the local area at the top of the outer steel pipe. Attached Figure Description
[0018] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained by analyzing these drawings without creative effort.
[0019] Figure 1 This is a schematic diagram of the cross-sectional structure perpendicular to the central axis of the connection node between the hollow sandwich steel tube concrete arch rib and the column on the arch in an embodiment of the present invention (the dotted line in the figure is the central axis). Figure 2 This is a schematic diagram of the longitudinal section structure of the connection node between the hollow sandwich steel tube concrete arch rib and the arch column in an embodiment of the present invention, arranged along the central axis (the dotted line in the figure is the central axis). Figure 3 for Figure 1 A magnified schematic diagram of the local structure at point A; Figure 4 This is a three-dimensional structural diagram illustrating the connection relationship between the column anchoring assembly and the outer steel pipe in an embodiment of the present invention. Figure 5 This is a three-dimensional structural schematic diagram from another perspective showing the connection relationship between the column anchoring component and the outer steel pipe in an embodiment of the present invention. Figure 6 This is a top view schematic diagram of the connection relationship between the column anchoring component and the outer steel pipe in an embodiment of the present invention; Figure 7 This is an exploded structural diagram of the column anchoring assembly in an embodiment of the present invention; Figure 8 This is an exploded structural diagram of the force transmission component inside the arch in an embodiment of the present invention; Figure 9 This is a schematic diagram of the arch-inner force transmission component from a frontal view in an embodiment of the present invention; Figure 10 This is a side view structural diagram of the force transmission component inside the arch in an embodiment of the present invention; Figure 11 This is a schematic diagram of the arch-in-the-arch force transmission component from a bottom-view perspective in an embodiment of the present invention; Figure 12 This is a schematic diagram of the through-ring groove rivet in an embodiment of the present invention.
[0020] Explanation of reference numerals in the attached figures: 1. Arch rib segment; 11. Inner steel pipe; 12. Concrete sandwich layer; 13. Outer steel pipe; 14. Shear studs; 2. Columns supporting the arch; 3. Column anchoring assembly; 31. Arch-mounted column reserved section; 32. Longitudinal through plate; 33. Transverse stiffening plate; 311. Through plate opening; 322. Rounded transition edge; 4. Inner and outer steel pipe connecting components; 41. Through-ring groove rivet; 411. Rod body; 412. Outer bearing pad; 413. Inner bearing pad; 414. Nail head; 415. Collar; 5. Force transmission components inside the arch; 51. Upper connecting plate; 52. Inclined force transmission component; 53. Lower connecting plate; 54. Upper stiffening plate; 55. Lower stiffening plate; 56. Connecting ring groove rivet; 57. Connecting rivet hole; 541. V-shaped notch of upper stiffening plate; 551. V-shaped notch of lower stiffening plate. Detailed Implementation
[0021] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments analyzed and obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0022] The purpose of this invention is to provide a connection node and construction method for a hollow sandwich steel tube concrete arch rib and an arch column, in order to solve the problems existing in the prior art. A new connection node is proposed, in which there is no direct rigid connection between the inner and outer steel tube connection components, the column anchoring components and the arch force transmission components. Instead, the outer steel tube, the sandwich concrete and the inner steel tube of the arch rib segment are connected. The collaborative force transmission path of the above components efficiently and with a short path transmits the force from the root of the arch column to the lower part and the two sides of the arch rib section, so that the force of the arch column is no longer mainly limited to the local area at the top of the outer steel tube.
[0023] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0024] Example 1 like Figures 1 to 12 As shown, this embodiment provides a connection node between a hollow-core steel-concrete composite arch rib and an upper column. This force transmission node is located at the connection position between the upper column 2 and the arch rib segment 1.
[0025] This connection node includes an arch rib segment 1, a column anchoring assembly 3, an inner and outer steel pipe connection assembly 4, and an arch internal force transmission assembly 5. The arch rib segment 1 has a column corresponding area corresponding to the arch column 2. The arch rib segment 1 includes an inner steel pipe 11, a sandwiched concrete layer 12, and an outer steel pipe 13 arranged sequentially from the inside to the outside. The inner steel pipe 11 forms a hollow cavity extending along the arch rib axis. The column anchoring assembly 3 anchors the arch column 2 to the outer steel pipe 13 in the column corresponding area. The extension line of the central axis of the arch column 2 anchored in the column corresponding area passes perpendicularly through the central axis of the arch rib segment 1. The inner and outer steel pipe connection assembly 4 anchors the outer steel pipe 13 and the inner steel pipe 11 in the column corresponding area and surrounds the extension line of the central axis of the arch column 2. The arch internal force transmission assembly 5 includes a first connecting end, a second connecting end, and a third connecting end. The first connecting end is fixedly connected to the inner steel pipe 11 in the corresponding area of the column and is located on the extension line of the central axis of the arch column 2. The second and third connecting ends are both connected to the inner wall of the inner steel pipe 11 on the opposite side of the column in the arch rib segment 1. The second and third connecting ends are located on both sides of the extension line of the central axis of the arch column 2. That is, the first connecting end, the second connecting end and the third connecting end form the three endpoints of an isosceles triangle, with the first connecting end as the vertex. The median of the isosceles triangle coincides with the extension line of the central axis of the arch column 2, so as to effectively transfer the force transmitted from the root of the arch column 2 to the lower part and the two sides of the arch rib section.
[0026] The function of the column anchoring assembly 3 is to receive and diffuse the force of the arch column 2 over a large area of the outer steel pipe 13. The function of the inner and outer steel pipe connecting assembly 4 is to establish a mechanical connection between the inner steel pipe 11 and the outer steel pipe 13.
[0027] The function of the arch-inner force transmission component 5 is to transmit and diffuse the force from the top of the inner steel pipe 11 to the lower sides of the inner steel pipe 11 corresponding to the column area (where the top refers to the pipe wall side corresponding to the column 2 on the arch, and the bottom refers to the pipe wall side away from the column 2 on the arch). Although the column anchoring component 3 and the arch-inner force transmission component 5 are not directly rigidly connected, they form a continuous force transmission system through the outer steel pipe 13, the interlayer concrete 12, the inner and outer steel pipe connecting component 4, and the inner steel pipe 11. This system can meet the requirements of the coordinated force transmission path of the above components, while efficiently and with a short path transmitting the force from the root of the column 2 on the arch to the lower and lateral areas of the arch rib section.
[0028] In one embodiment of this invention, the column anchoring assembly 3 includes an arch-mounted column pre-reserved section 31, which is fixedly connected (preferably welded) to the outer steel pipe 13 of the corresponding area of the column. The arch-mounted column pre-reserved section 31 is a tubular structure whose outer contour matches that of the arch-mounted column 2. The arch-mounted column pre-reserved section 31 is used for coaxial fixed connection with the arch-mounted column 2.
[0029] In one embodiment of this invention, the arch support column pre-fabricated section 31 is prefabricated in the factory along with the arch rib segment 1, rather than being a separate transition sleeve between the arch support column 2 and the arch rib. The cross-sectional shape and dimensions of the arch support column pre-fabricated section 31 are the same as those of the arch support column 2. The lower end profile of the arch support column pre-fabricated section 31 is adapted to the outer surface of the outer steel pipe 13 and welded to the outer steel pipe 13. The upper end of the arch support column pre-fabricated section 31 is connected to the arch support column 2 at the construction site using an equal-strength butt weld.
[0030] In one embodiment of this invention, the column anchoring assembly 3 further includes a longitudinal through plate 32 and a transverse stiffening plate 33. The longitudinal through plate 32 is arranged along the central axis of the arch rib segment 1 and penetrates the reserved section 31 of the arch column. The longitudinal through plate 32 is fixedly connected (preferably welded) to the reserved section 31 of the arch column and the outer steel pipe 13 of the corresponding area of the column. The transverse stiffening plate 33 is arranged parallel to or inclined to the cross-section of the central axis of the arch rib segment 1. The transverse stiffening plate 33 is fixedly connected (preferably welded) to the reserved section 31 of the arch column and the outer steel pipe 13 of the arch rib segment 1. The longitudinal through plate 32 mainly diffuses the force of the arch column 2 along the axial direction of the arch rib, while the transverse stiffening plate 33 mainly diffuses the force of the arch column 2 along the axial direction of the cross-section of the arch rib segment 1 in a parallel and oblique direction, reducing the concentration of force at the root of the arch column 2 and the local area of the outer steel pipe 13.
[0031] In one embodiment of this invention, the longitudinal through plate 32 is a continuous, integral plate, not a series of separate plates on either side of the arch column pre-reserved section 31. Therefore, a through-plate opening 311 needs to be pre-drilled in the pipe wall of the arch column pre-reserved section 31 for the longitudinal through plate 32 to pass through. During welding, the arch column pre-reserved section 31 and the longitudinal through plate 32 are connected by double-sided fillet welds, which are continuously arranged along the through-plate opening 311. The lower edge of the longitudinal through plate 32 is welded to the outer steel pipe 13.
[0032] In one embodiment of this example, a pre-reserved section 31 of an arched column is provided with two longitudinal through plates 32.
[0033] In one embodiment of this example, the longitudinal through plate 32 is trapezoidal in shape, and the side of the longitudinal through plate 32 near the bottom corner is rounded to form a rounded transition edge 322, which makes the plate rigidity transition smoothly while reducing stress concentration at the end of the through plate.
[0034] In one embodiment of this invention, a plurality of transverse stiffening plates 33 are arranged around the arch column reserved section 31. The side of the transverse stiffening plate 33 closest to the arch column reserved section 31 is welded to the arch column reserved section 31, and its lower edge contour is adapted to the curved surface of the outer steel pipe 13 and welded to the outer steel pipe 13.
[0035] In one embodiment of this example, four transverse stiffening plates 33 are provided.
[0036] In one embodiment of this invention, the inner and outer steel pipe connecting assembly 4 is a through-groove rivet 41, with through-groove rivets 41 provided on both sides of the longitudinal through plate 32 and the transverse stiffening plate 33. The through-groove rivet 41 includes a rod 411, an outer bearing pad 412, an inner bearing pad 413, a rivet head 414, and a collar 415. The rod 411 is radially arranged along the arch rib and, during installation, passes sequentially through the outer steel pipe 13 and the inner steel pipe 11. The outer bearing pad 412 on the rod 411 is located on the outside of the outer steel pipe 13, and the inner bearing pad 413 is located on the inside of the inner steel pipe 11. The collar 415 is fitted onto the annular groove section of the rod 411 and formed by riveting with a riveting tool, so that the collar 415 locks into the annular groove of the rod 411; the nail head 414 and the collar 415 are respectively anchored at the end by the outer bearing pad 412 and the inner bearing pad 413. After the interlayer concrete 12 is poured, the middle section of the rod 411 with the through-groove rivet 41 is embedded in the interlayer concrete 12. The through-groove rivet 41 only penetrates the outer steel pipe 13 and the inner steel pipe 11, and does not penetrate the longitudinal through plate 32, the transverse stiffening plate 33, the upper connecting plate 51 or the lower connecting plate 53. Multiple through-groove rivets 41 are arranged in groups near both sides of the longitudinal through plate 32 and the transverse stiffening plate 33, so that their arrangement range corresponds to the load diffusion area of the column anchoring assembly 3. Through-groove rivets 41 establish a through-mechanical connection between the outer steel pipe 13 and the inner steel pipe 11, supplementing the force transmission path that previously relied solely on the interlayer concrete 12 and shear studs 14 on one side. The through-groove rivets 41 are installed using a rivet gun.
[0037] In one embodiment of this example, the through-groove rivet 41 passively participates in the stress during service: when the outer steel pipe 13, the sandwich concrete 12, and the inner steel pipe 11 in the corresponding area of the column exhibit relative deformation tendencies, the through-groove rivet 41 restricts the relative displacement through mechanical anchoring at both ends and the force applied to the rod body 411; this node does not require the through-groove rivet 41 to apply a design preload or to form a preload on the sandwich concrete 12 as a necessary condition.
[0038] In one embodiment of this example, the arch-inner force transmission component 5 includes an upper connecting plate 51, oblique force transmission members 52, and a lower connecting plate 53. The upper connecting plate 51 is fixedly connected (preferably welded) to the inner steel pipe 11 as a first connecting end. One end of the two oblique force transmission members 52 is anchored to the upper connecting plate 51 by connecting ring groove rivets 56, and the other end of the two oblique force transmission members 52 is anchored to the lower connecting plate 53 by connecting ring groove rivets 56. The lower connecting plates 53 on the two oblique force transmission members 52 are respectively fixedly connected (preferably welded) to the inner steel pipe 11 as a second connecting end and a third connecting end.
[0039] In one embodiment of this invention, the arch-in-the-arch force transmission component 5 includes a set of upper connecting plates 51 and two sets of lower connecting plates 53. Each set of upper connecting plates 51 comprises two upper connecting plates 51 spaced along the central axis of the steel-concrete composite arch. One end of the oblique force transmission member 52 is located between the two upper connecting plates 51 in the set. An upper stiffening plate 54 is fixedly connected (preferably welded) between the two upper connecting plates 51 in the set. Each set of lower connecting plates 53 comprises two lower connecting plates 53 spaced along the central axis of the steel-concrete composite arch; the other end of each oblique force transmission member 52 is located between the two lower connecting plates 53 in the corresponding set. A lower stiffening plate 55 is fixedly connected (preferably welded) between the two lower connecting plates 53 in the set. The arrangement of the upper stiffening plate 54 and the lower stiffening plate 55 can improve the local stiffness and force diffusion capacity of the arch-in-the-arch connection area, reducing the degree to which the force is concentrated on a single connecting plate or a local pipe wall.
[0040] In one embodiment of this invention, the arc-shaped edges of the upper connecting plate 51 and the lower connecting plate 53 are continuously welded to the inner wall of the inner steel pipe 11.
[0041] In one embodiment of this invention, the upper stiffening plate 54 is provided with an upper stiffening plate V-shaped notch 541, and the lower stiffening plate 55 is provided with a lower stiffening plate V-shaped notch 551. The lower stiffening plate V-shaped notch 551 is arranged facing upwards, and the upper stiffening plate V-shaped notch 541 is arranged facing downwards. The lower stiffening plate V-shaped notch 551 and the upper stiffening plate V-shaped notch 541 facilitate the welding of the plates without affecting the stress distribution.
[0042] In one embodiment of this invention, the oblique force transmission member 52 is made of steel profile. The out-of-plane stiffness of the H-shaped cross-section maintains the stability of the internal force transmission assembly 5 and transmits the force from the top connection area to the lower sides of the inner steel pipe 11. At each connection point, the top and bottom flanges of the steel profile correspond to two opposing upper connecting plates 51 and two lower connecting plates 53, and are connected by connecting ring groove rivets 56. The two oblique force transmission members 52 form an inverted V-shaped force transmission path. The upper connecting plate 51 receives the force from the area corresponding to the top column of the inner steel pipe 11, and the lower connecting plate 53 and lower stiffening plate 55 transmit and diffuse it to the lower sides of the inner steel pipe 11, which facilitates the participation of more parts of the arch rib section in the nodal stress.
[0043] In one embodiment of this invention, shear studs 14 are provided on the outer wall of the inner steel pipe 11 and the inner wall of the outer steel pipe 13. The shear studs 14 are used to embed into the sandwich concrete 12. The shear studs 14 are used for shear force transfer between the corresponding steel pipes (inner steel pipe 11 and outer steel pipe 13) and the sandwich concrete 12.
[0044] The collaborative force transmission mechanism of this connection node: The axial force, shear force, and bending moment transmitted from the arch column 2 first enter the arch column pre-reserved section 31. Part of the force directly enters the outer steel pipe 13 through the connection between the arch column pre-reserved section 31 and the outer steel pipe 13; another part of the force diffuses along the arch rib axis to both sides of the node through the longitudinal through plate 32, and diffuses to a larger area of the outer steel pipe 13 through the transverse stiffening plate 33 along a direction parallel to the cross section or obliquely.
[0045] The force diffused to the outer steel pipe 13 is transmitted to the inner steel pipe 11 through the shear studs 14 of the outer steel pipe 13, the interlayer concrete 12, the shear studs 14 of the inner steel pipe 11, and the through-ring groove rivets 41. The force corresponding to the top column area of the inner steel pipe 11 is transmitted to the two oblique force transmission members 52 through the upper connecting plate 51, and then to the lower connecting plates 53 on both sides, and diffused to the lower sides of the inner steel pipe 11 through the lower stiffening plate 55; the upper stiffening plate 54 is used to strengthen the top input area. In this way, the column force that was originally mainly concentrated on the outer side of the top of the arch rib can be transmitted to other parts of the arch rib section, promoting the coordinated force bearing of the outer steel pipe 13, the interlayer concrete 12, and the inner steel pipe 11.
[0046] A central space is maintained between the two oblique force-transmitting components 52. This central space is not specifically designed to form a maintenance passage, but it can be used for personnel passage when the component size and operating conditions permit. However, it should be noted that personnel passage is not a necessary condition for realizing the coordinated force transmission function of this node.
[0047] In one embodiment of this example, The length of the reserved section 31 of the arch support column is 1.2m, and the cross-sectional dimensions are the same as those of the arch support column 2.
[0048] The oblique force transmission member 52 is made of HW 250×250 steel. There are two oblique force transmission members 52, arranged in an inverted V shape along the cross-section of the arch rib; The connecting ring groove rivets 56 adopt the LMDY-T24-36G type, with a total of 24 sets.
[0049] The inner and outer steel pipe connection assembly 4 uses LMDTF-T25G type through-ring groove rivets 41, with a total of 72 sets.
[0050] The specifications and quantities mentioned above are engineering parameters for this embodiment and can be adjusted according to the size of the arch rib, the function of the column, and the arrangement of the nodes without changing the basic structural relationship of the nodes coordinating force transmission.
[0051] The interlayer concrete 12 uses C80 high-strength concrete, which can form a high-strength filling and force-transfer medium in a limited interlayer space; depending on the specific bridge's stress, durability and construction performance requirements, high-strength or ultra-high-performance cement-based materials such as ultra-high performance concrete (UHPC) can also be used.
[0052] Example 2 like Figures 1 to 12 As shown, this embodiment provides a construction method for the connection node between the hollow sandwich steel tube concrete arch rib and the arch column, which can be used for the construction of the connection node between the arch rib and the arch column in Embodiment 1, including the following steps: S1. Factory-processed components: In the factory, the outer steel pipe 13 and inner steel pipe 11 of the arch rib segment 1 are manufactured. Corresponding through rivet mounting holes are processed in the corresponding areas of the outer steel pipe 13 and inner steel pipe 11 and the corresponding columns of the arch column 2. The arch column reserved section 31, longitudinal through plate 32, transverse stiffening plate 33, upper connecting plate 51, lower connecting plate 53 and oblique force transmission component 52 are manufactured. S2. Install the column anchoring components and the inner arch connecting plate: The arch column reserved section 31, longitudinal through plate 32 and transverse stiffening plate 33 are assembled and welded to the corresponding column area of the outer steel pipe 13 to form column anchoring assembly 3; the longitudinal through plate 32 passes through the arch column reserved section 31 continuously along the axial direction of the arch rib segment 1, and is welded to the arch column reserved section 31 and the outer steel pipe 13 respectively; the transverse stiffening plate 33 is welded to the arch column reserved section 31 and the outer steel pipe 13 respectively. A connecting plate 51 is welded to the top inner wall corresponding to the reserved section 31 of the arch column, and a lower connecting plate 53 is welded to the inner wall on both sides of the lower part of the inner steel pipe 11. S3. Assemble the inner and outer steel pipes and install mechanical connectors: The inner steel pipe 11 is positioned inside the outer steel pipe 13, so that an annular sandwich space is formed between the two, and the through rivet mounting holes on the inner steel pipe 11 and the outer steel pipe 13 correspond to each other. After completing the required welding at the node, install two oblique force transmission components 52, through-ring groove rivets 41, and connecting ring groove rivets 56; the upper ends of the two oblique force transmission components 52 are connected to the upper connecting plate 51 through the connecting ring groove rivets 56, and the lower ends are connected to the corresponding lower connecting plates 53 located on both sides of the lower part of the inner steel pipe 11 through the connecting ring groove rivets 56, so that the two oblique force transmission components 52 extend from the top connection area to the lower sides, and together with the upper connecting plate 51 and the lower connecting plate 53, they form an inverted V-shaped arch internal force transmission assembly 5; Through-ring groove rivets 41 are arranged near both sides of the longitudinal through plate 32 and the transverse stiffening plate 33. They pass through the outer steel pipe 13, the annular interlayer space and the inner steel pipe 11 through corresponding through-ring rivet mounting holes, and are riveted to connect the outer steel pipe 13 and the inner steel pipe 11. S4. Filling of interlayer concrete: After the through-ring groove rivet 41 and the connecting ring groove rivet 56 are installed, concrete is poured into the annular interlayer space between the outer steel pipe 13 and the inner steel pipe 11 to form an interlayer concrete 12, so that the rod segment of the through-ring groove rivet 41 located in the annular interlayer space is embedded in the interlayer concrete 12. S5, Arch Rib Segment Transportation: The prefabricated arch rib segment 1 is transported to the construction site, and the upper end of the reserved section 31 of the arch column is used as the on-site connection end. S6. On-site connection of the arch-mounted columns: Hoist the arch support column 2 and connect the lower end of the arch support column 2 to the upper end of the reserved section 31 of the arch support column.
[0053] In one embodiment of this example, In step S1, an upper stiffening plate 54 and a lower stiffening plate 55 are also fabricated, and connecting rivet holes 57 are machined at the corresponding connection positions of the upper connecting plate 51, the lower connecting plate 53 and the oblique force transmission member 52; shear studs 14 are welded on the inner wall of the outer steel pipe 13 and the outer wall of the inner steel pipe 11. In step S2, a through-plate opening 311 adapted to the longitudinal through-plate 32 is machined on the pipe wall of the reserved section 31 of the arch column. The longitudinal through-plate 32 is passed through the through-plate opening 311 and connected to the reserved section 31 of the arch column by a double-sided continuous fillet weld along the through-plate opening 311. The upper connecting plate 51 is configured as two plates spaced apart along the axial direction of the arch rib segment 1, and the lower connecting plate 53 is configured as two sets of plates located on both sides of the lower part of the inner steel pipe 11, each set including two lower connecting plates 53 spaced apart along the axial direction of the arch rib segment 1. The arc-shaped edges of each upper connecting plate 51 and each lower connecting plate 53 are continuously welded to the inner wall of the inner steel pipe 11; an upper stiffening plate 54 is set between two upper connecting plates 51, and the upper stiffening plate 54 is welded to the two upper connecting plates 51 and the inner steel pipe 11; a lower stiffening plate 55 is set between two lower connecting plates 53 in each group, and the lower stiffening plate 55 is welded to the corresponding two lower connecting plates 53 and the inner steel pipe 11. In step S3, the upper end of each inclined force transmission member 52 is located between two upper connecting plates 51, and the lower end is located between two lower connecting plates 53 of the corresponding group; at the upper connection part of each inclined force transmission member 52, the two upper connecting plates 51 are respectively connected to the corresponding connection surface of the inclined force transmission member 52 through connecting ring groove rivets 56; at its lower connection part, the two lower connecting plates 53 of the corresponding group are respectively connected to the corresponding connection surface of the inclined force transmission member 52 through connecting ring groove rivets 56. The through-ring groove rivet 41 is installed in a way that avoids the longitudinal through plate 32, the transverse stiffening plate 33, the upper connecting plate 51 and the lower connecting plate 53.
[0054] In one embodiment of this example, in step S6, the upper section of the reserved section 31 of the arch column matches the lower section of the arch column 2; the arch column 2 is hoisted so that the lower end of the arch column 2 is coaxially aligned with the upper end of the reserved section 31 of the arch column, and a butt weld with the same strength as the base material of the arch column 2 is used for connection, and the weld is inspected and repaired for corrosion protection.
[0055] In one embodiment of this example, the interlayer concrete 12 is C80 high-strength concrete.
[0056] In one embodiment of this example, the lower end of the arch column 2 is connected to the arch column reserved section 31 of the connecting node by a butt weld of equal strength to the base material of the arch column 2, and the weld is inspected and repaired for corrosion protection.
[0057] In one embodiment of this invention, the through rivet mounting holes are arranged in groups near both sides of the longitudinal through plate 32 and the transverse stiffening plate 33, with the hole positions avoiding the locations of the longitudinal through plate 32, the transverse stiffening plate 33, the upper connecting plate 51, and the lower connecting plate 53. The arch-mounted column pre-reserved section 31, the longitudinal through plate 32, the transverse stiffening plate 33, the upper connecting plate 51, the lower connecting plate 53, the oblique force transmission member 52, the upper stiffening plate 54, and the lower stiffening plate 55 are manufactured according to the design dimensions, and connecting rivet mounting holes are machined at the corresponding positions of the upper connecting plate 51, the lower connecting plate 53, and the oblique force transmission member 52.
[0058] In one embodiment of this invention, the diameter, wall thickness, and spacing of the outer steel pipe 13 and the inner steel pipe 11 of the hollow sandwich steel tube concrete arch rib, as well as the strength grade of the sandwich concrete 12, can be adjusted according to the specific bridge design.
[0059] In one embodiment of this invention, the interlayer concrete 12 is made of C80 high-strength concrete; however, depending on the specific stress, durability, and construction performance requirements of the bridge, high-strength or ultra-high-performance cement-based materials such as ultra-high performance concrete (UHPC) may also be used. The shear studs 14 on the outer steel pipe 13 and the inner steel pipe 11 may also be other shear connectors that meet the shear force transfer requirements between the steel pipe and the interlayer concrete 12.
[0060] In one embodiment of this example, the length of the arch support column reserved section 31 is 1.2m; of course, the arch support column reserved section 31 can be adjusted according to the division of the arch rib segment 1, transportation conditions and on-site welding position, and is not limited to 1.2m; its cross-section can be adapted to different forms of arch support columns 2, but it should be kept as a reserved section at the bottom of the arch support column 2, prefabricated in the factory along with the arch rib segment 1, and connected to the upper arch support column on site.
[0061] In one embodiment of this invention, the number, thickness, spacing, and axial extension length of the longitudinal through plates 32 can be adjusted; the through-plate openings 311 on the arch column reserved section 31 can be through-plate holes or through-plate grooves extending from the edge of the pipe wall. Regardless of the form, the longitudinal through plates 32 maintain a continuous overall passage through the arch column reserved section 31 and form a continuous welded connection with it.
[0062] In one embodiment of this example, the number, inclination angle, outer contour, and circumferential arrangement of the transverse stiffening plates 33 along the reserved section 31 of the arch column can be adjusted according to the function of the column; the transverse stiffening plates 33 can be orthogonal or oblique to the axis of the arch rib, and different plate thicknesses or local reinforcements can be used.
[0063] In one embodiment of this example, the type, diameter, length, quantity, and grouping of the through-groove rivets 41 can be adjusted according to the spacing between the inner steel pipe 11 and the outer steel pipe 13 and the range of node reinforcement. Rectangular, fan-shaped, or other regular arrays can be used on both sides of the longitudinal through plate 32 and the transverse stiffening plate 33. However, the through-groove rivets 41 still penetrate the inner steel pipe 11 and the outer steel pipe 13, but do not penetrate the external plates or the force transmission components 5 inside the arch.
[0064] In one embodiment of this example, the through-ring groove rivet 41 is of type LMDTF-T25G, and 72 sets are provided.
[0065] In one embodiment of this invention, the oblique force transmission member 52 is preferably made of HW 250×250 steel. Channel steel or other members with greater out-of-plane stiffness can also be used; its cross-sectional specifications and inclination angle can be adjusted according to the diameter of the inner steel pipe 11 and the force transmission requirements, but the two oblique force transmission members 52 still extend from the upper connection area to the lower sides of the inner steel pipe 11, forming an inverted V-shaped force transmission path.
[0066] In one embodiment of this example, the outer contours, plate thicknesses, and local openings of the upper connecting plate 51, lower connecting plate 53, upper stiffening plate 54, and lower stiffening plate 55 can be adjusted according to the curvature of the inner steel pipe 11 and the cross section of the oblique force transmission member 52; each connecting plate maintains a welded connection with the contact edge of the inner steel pipe 11, and each stiffening plate strengthens the connection area between the corresponding connecting plate and the inner steel pipe 11.
[0067] In one embodiment of this invention, the type and quantity of the connecting groove rivets 56 can be adjusted according to the plate thickness of the oblique force transmission member 52 and the connecting plate, as well as the connection load-bearing requirements. The connecting groove rivets 56 can be of type LMDY-T24-36G, with a total of 24 sets; after adjustment, the connecting groove rivets 56 still connect the two oppositely arranged connecting plates to the corresponding flanges or connecting surfaces of the oblique force transmission member 52.
[0068] In one embodiment of this example, the specific weld forms of the arch column reserved section 31, the outer steel pipe 13, the longitudinal through plate 32, the transverse stiffening plate 33, and the upper connecting plate 51, the lower connecting plate 53, the upper stiffening plate 54, and the lower stiffening plate 55 can be fillet welds, bevel welds, or combinations thereof, provided that the requirements of equal strength connection, continuous force transmission, and manufacturing are met.
[0069] The construction method in this embodiment focuses on the connection node between the arch rib segment 1 and the upper column 2 of the hollow steel-concrete composite arch rib. The welded plates in the column anchoring assembly 3 and the welded plates in the arch internal force transmission assembly 5 are all installed in the factory. After each welding operation is completed, through-groove rivets 41 and connecting groove rivets 56 are installed, and then the interlayer concrete 12 is poured, thus forming an integrated arch rib node segment, improving factory prefabrication and quality control. The welding-then-riveting process reduces interference from the groove rivets on the welding operation; both types of groove rivets are installed before the interlayer concrete 12 is poured, allowing the hollow cavity to be used for the installation, riveting, and quality inspection of the inner bearing pad 413, avoiding long-distance through drilling after the interlayer concrete 12 has hardened. This improves the level of prefabricated construction and reduces on-site construction disturbance. The arch column reserved section 31 is prefabricated as a whole in the factory along with the arch rib section 1. After the interlayer concrete 12 reaches the specified strength, the node section is transported to the site. The main task on site is to perform equal-strength butt welding between the arch column 2 and the arch column reserved section 31. This helps to reduce the workload of high-altitude positioning, welding and adjustment of complex plates, and correspondingly reduces on-site welding fumes, construction energy consumption and disturbance to the surrounding environment.
[0070] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.
Claims
1. A connection node between a hollow sandwich steel tube concrete arch rib and an arch column, characterized in that, include: The arch rib segment (1) is provided with a column corresponding area corresponding to the arch column (2). The arch rib segment (1) includes an inner steel pipe (11), a sandwich concrete (12) and an outer steel pipe (13) arranged sequentially from the inside to the outside. The column anchoring assembly (3) is used to anchor the arch column (2) on the outer steel pipe (13) of the corresponding area of the column. The extension line of the central axis of the arch column (2) anchored on the corresponding area of the column passes through the central axis of the arch rib segment (1). Inner and outer steel pipe connecting components (4), which are used to anchor the outer steel pipe (13) and inner steel pipe (11) in the corresponding area of the column, and are distributed in the corresponding area of the column; And an arch-inner force transmission component (5), the arch-inner force transmission component (5) includes a first connecting end, a second connecting end and a third connecting end; the first connecting end is fixedly connected to the inner steel pipe (11) of the corresponding area of the column and is located on the extension line of the central axis of the upper column (2); the second connecting end and the third connecting end are both connected to the inner wall of the inner steel pipe (11) of the arch rib segment (1) located on the opposite side of the corresponding area of the column and are set on both sides of the extension line of the central axis of the upper column (2).
2. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column as described in claim 1, characterized in that, The column anchoring assembly (3) includes an arch-mounted column reserved section (31), which is fixedly connected to the outer steel pipe (13) of the corresponding area of the column. The arch-mounted column reserved section (31) is a tubular structure whose outer contour matches that of the arch-mounted column (2). The arch-mounted column reserved section (31) is used to be coaxially fixedly connected with the arch-mounted column (2).
3. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column as described in claim 2, characterized in that, The column anchoring assembly (3) further includes a longitudinal through plate (32) and a transverse stiffening plate (33); the longitudinal through plate (32) passes through the arch column reserved section (31) along the central axis of the arch rib segment (1), and the longitudinal through plate (32) is fixedly connected to the arch column reserved section (31) and the outer steel pipe (13) of the corresponding area of the column; the transverse stiffening plate (33) is set perpendicular to the arch rib segment (1), and the transverse stiffening plate (33) is fixedly connected to the arch column reserved section (31) and the outer steel pipe (13) of the arch rib segment (1).
4. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column according to claim 3, characterized in that, The inner and outer steel pipe connecting assembly (4) is a through-ring groove rivet (41), and the through-ring groove rivet (41) is provided on both sides of the longitudinal through plate (32) and the transverse stiffening plate (33).
5. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column according to claim 1, characterized in that, The arch-inner force transmission assembly (5) includes an upper connecting plate (51), an inclined force transmission member (52), and a lower connecting plate (53). The upper connecting plate (51) serves as the first connecting end and is fixedly connected to the inner steel pipe (11). One end of each of the two inclined force transmission members (52) is anchored to the upper connecting plate (51) via a connecting ring groove rivet (56). The other end of each of the two inclined force transmission members (52) is anchored to the lower connecting plate (53) via a connecting ring groove rivet (56). The lower connecting plates (53) on the two inclined force transmission members (52) serve as the second connecting end and the third connecting end, respectively, and are fixedly connected to the inner steel pipe (11).
6. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column according to claim 5, characterized in that, The arch-in-the-arch force transmission component (5) includes a set of upper connecting plates (51) and two sets of lower connecting plates (53). The set of upper connecting plates (51) includes two upper connecting plates (51) arranged at intervals along the central axis of the steel-concrete composite arch. One end of the oblique force transmission member (52) is located between the two upper connecting plates (51) of the set. An upper stiffening plate (54) is fixedly connected between the two upper connecting plates (51) of the set. Each set of lower connecting plates (53) includes two lower connecting plates (53) arranged at intervals along the central axis of the steel-concrete composite arch. The other end of each oblique force transmission member (52) is located between the two lower connecting plates (53) of the corresponding set. A lower stiffening plate (55) is fixedly connected between the two lower connecting plates (53) of the set.
7. The connection node between the hollow sandwich steel tube concrete arch rib and the arch column according to claim 1, characterized in that, Shear studs (14) are provided on the outer wall of the inner steel pipe (11) and the inner wall of the outer steel pipe (13), and the shear studs (14) are used to embed into the sandwich concrete (12).
8. A construction method for the connection node between a hollow sandwich steel tube concrete arch rib and an arch column, characterized in that, Includes the following steps: S1. Factory-processed components: In the factory, the outer steel pipe (13) and inner steel pipe (11) of the arch rib segment (1) are manufactured. Corresponding through rivet mounting holes are machined in the corresponding areas of the outer steel pipe (13) and the inner steel pipe (11) and the corresponding column of the arch column (2). The arch column reserved section (31), longitudinal through plate (32), transverse stiffening plate (33), upper connecting plate (51), lower connecting plate (53) and oblique force transmission component (52) are manufactured. S2. Install the column anchoring components and the inner arch connecting plate: The arch-support column reserved section (31), the longitudinal through plate (32) and the transverse stiffening plate (33) are assembled and welded to the column corresponding area of the outer steel pipe (13) to form a column anchoring assembly (3); the longitudinal through plate (32) passes through the arch-support column reserved section (31) continuously along the axial direction of the arch rib segment (1), and is welded to the arch-support column reserved section (31) and the outer steel pipe (13) respectively; the transverse stiffening plate (33) is welded to the arch-support column reserved section (31) and the outer steel pipe (13) respectively. The upper connecting plate (51) is welded to the top inner wall corresponding to the reserved section (31) of the arch column, and the lower connecting plate (53) is welded to the inner walls on both sides of the lower part of the inner steel pipe (11). S3. Assemble the inner and outer steel pipes and install mechanical connectors: The inner steel pipe (11) is positioned inside the outer steel pipe (13) to form an annular sandwich space between them, and the through rivet mounting holes on the inner steel pipe (11) and the outer steel pipe (13) correspond to each other. After completing the required welding at the node, install two inclined force transmission components (52), through-ring groove rivets (41), and connecting ring groove rivets (56); the upper ends of the two inclined force transmission components (52) are connected to the upper connecting plate (51) through the connecting ring groove rivets (56), and the lower ends are connected to the corresponding lower connecting plates (53) located on both sides of the lower part of the inner steel pipe (11) through the connecting ring groove rivets (56), so that the two inclined force transmission components (52) extend from the top connecting area to the lower sides, and together with the upper connecting plate (51) and the lower connecting plate (53), they form an inverted V-shaped arch internal force transmission assembly (5); The through-ring groove rivets (41) are arranged near both sides of the longitudinal through plate (32) and the transverse stiffening plate (33), and pass through the outer steel pipe (13), the annular interlayer space and the inner steel pipe (11) through the corresponding through rivet mounting holes, and are riveted to connect the outer steel pipe (13) and the inner steel pipe (11); S4. Filling of interlayer concrete: After the through-groove rivet (41) and the connecting groove rivet (56) are installed, concrete is poured into the annular interlayer space between the outer steel pipe (13) and the inner steel pipe (11) to form an interlayer concrete (12), so that the rod segment of the through-groove rivet (41) located in the annular interlayer space is embedded in the interlayer concrete (12). S5, Arch Rib Segment Transportation: The prefabricated arch rib segment (1) is transported to the construction site, and the upper end of the reserved section (31) of the arch column is used as the on-site connection end. S6. On-site connection of the arch-mounted columns: The arch support column (2) is hoisted and the lower end of the arch support column (2) is connected to the upper end of the reserved section (31) of the arch support column.
9. The construction method according to claim 8, characterized in that, In step S1, an upper stiffening plate (54) and a lower stiffening plate (55) are also made, and connecting rivet holes (57) are machined at the corresponding connection positions of the upper connecting plate (51), the lower connecting plate (53) and the oblique force transmission member (52); shear studs (14) are welded on the inner wall of the outer steel pipe (13) and the outer wall of the inner steel pipe (11); In step S2, a through-plate opening (311) adapted to the longitudinal through-plate (32) is processed on the pipe wall of the reserved section (31) of the arch column. The longitudinal through-plate (32) is passed through the through-plate opening (311) and connected to the reserved section (31) of the arch column by a double-sided continuous fillet weld along the through-plate opening (311). The upper connecting plate (51) is configured as two plates spaced apart along the axial direction of the arch rib segment (1), and the lower connecting plate (53) is configured as two sets of plates located on both sides of the lower part of the inner steel pipe (11), each set including two lower connecting plates (53) spaced apart along the axial direction of the arch rib segment (1). The arc-shaped edges of each of the upper connecting plates (51) and each of the lower connecting plates (53) are continuously welded to the inner wall of the inner steel pipe (11); an upper stiffening plate (54) is provided between two upper connecting plates (51), and the upper stiffening plate (54) is welded to the two upper connecting plates (51) and the inner steel pipe (11); a lower stiffening plate (55) is provided between two lower connecting plates (53) in each group, and the lower stiffening plate (55) is welded to the corresponding two lower connecting plates (53) and the inner steel pipe (11); In step S3, the upper end of each inclined force transmission member (52) is located between two upper connecting plates (51), and the lower end is located between two lower connecting plates (53) of a corresponding group; at the upper connection part of each inclined force transmission member (52), the two upper connecting plates (51) are respectively connected to the corresponding connection surface of the inclined force transmission member (52) through connecting ring groove rivets (56); at its lower connection part, the two lower connecting plates (53) of a corresponding group are respectively connected to the corresponding connection surface of the inclined force transmission member (52) through connecting ring groove rivets (56); The through-ring groove rivet (41) is installed in a path that avoids the longitudinal through plate (32), the transverse stiffening plate (33), the upper connecting plate (51) and the lower connecting plate (53).
10. The construction method according to claim 9, characterized in that, In step S6, the upper section of the reserved section (31) of the arch column matches the lower section of the arch column (2); the arch column (2) is hoisted so that the lower end of the arch column (2) is coaxially aligned with the upper end of the reserved section (31) of the arch column, and a butt weld with the same strength as the base material of the arch column (2) is used for connection, and the weld is inspected and repaired for corrosion.