A pre-construction curtain grouting technology for bridge pile foundations in karst areas
By using curtain grouting technology to form a closed curtain structure before bridge pile foundation construction, the problem of high construction difficulty in complex karst areas has been solved, achieving efficient and safe pile foundation construction, reducing costs and improving the quality of finished products.
Patent Information
- Application Number
- CN202611219756.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-12
- Publication Date
- 2026-11-17
AI Technical Summary
In the construction of bridge pile foundations in complex karst areas, existing technologies lack a systematic solution to the problem of ground reinforcement, resulting in high construction difficulty, high cost, significant safety hazards, and low construction efficiency.
The pre-construction curtain grouting technology for bridge pile foundations is adopted. By forming a closed curtain structure before drilling the pile foundation, and using methods such as curtain grouting hole distribution map, skip-hole interval drilling, and segmented grouting, a stable curtain structure is formed to ensure the dense sealing of karst areas and construction safety.
It improves the one-time hole formation rate of bridge pile foundations, reduces the hole collapse rate and grout leakage rate, saves construction costs and construction time, and improves the quality of finished pile foundations and construction safety.
Smart Images

Figure CN123109196A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of geotechnical engineering technology, and in particular to a pre-construction curtain grouting technology for bridge pile foundations in karst areas. Background Technology
[0002] In the construction of highway projects, it is inevitable to build in complex karst areas, especially in karst basins. These karst areas are characterized by towering peaks, numerous depressions, and complex and diverse geological conditions, which increases the difficulty of constructing highway projects in this type of geological environment. In particular, the construction of bridge foundations in complex karst areas often faces problems such as water leakage and borehole collapse, mud loss, and poor pile quality. There are also potential seepage pressures from karst fissures in the bearing stratum and hidden safety hazards. Therefore, it is essential to treat the karst mass during construction.
[0003] Currently, the following methods are commonly used when constructing bridge pile foundations in karst areas: One approach is a passive solution during the drilling process: if karst caves leak or the borehole collapses during pile foundation drilling, temporary sealing methods such as backfilling with rubble, clay, C20 concrete, or cement are used. This approach is cumbersome, the backfill materials are difficult to effectively consolidate with the karst, the reinforcement effect is uncontrollable, and repeated treatments lead to uncontrollable construction periods; moreover, this approach is a passive emergency measure, implemented only when problems occur, and has a certain degree of lag.
[0004] The second option is the steel casing follow-up scheme: when encountering karst caves, long steel casings are buried to penetrate the karst cave layer, protecting the pile foundation holes and preventing the impact of karst seepage on the pile foundation holes. However, this scheme is difficult to implement under large karst cave conditions, and requires a large amount of steel casings, resulting in high material costs.
[0005] In summary, the existing technology lacks a systematic solution to the problem of ground reinforcement during bridge pile foundation construction in complex karst areas. Ideally, there should be an underground soil and rock treatment technology that can improve the stability and bearing capacity of the site environment before bridge pile foundation construction, while simultaneously increasing construction efficiency, reducing project costs, and enhancing construction safety. Summary of the Invention
[0006] To address the problems in the existing technologies mentioned above, and based on a comprehensive analysis of the complex karst distribution at the construction site and its impact on bridge pile foundations, this invention researches a pre-construction curtain grouting construction method for bridge pile foundations in complex karst areas. This is of great significance for reducing quality risks and safety hazards during highway bridge pile foundation construction. Based on this, the present invention proposes a pre-construction curtain grouting technology for bridge pile foundations in karst areas, the specific implementation process of which includes the following steps: Step S1, Construction Preparation: Clear and level the construction site, conduct geological surveys, obtain engineering geological exploration data and advanced drilling columnar section, and formulate curtain grouting technology plan and curtain grouting hole distribution map in conjunction with the pile foundation construction plan. Step S2, determining the hole position: The pile foundation is measured and laid out at the construction site to determine the hole position and center. A steel casing is installed at the pile foundation hole opening, and then a trench is excavated outside the steel casing as the hole opening area for curtain drilling. Step S3, Drilling: According to the distribution map of curtain grouting holes, a skip-hole interval method is adopted in the trench, that is, two consecutive constructions do not select two adjacent curtain grouting holes for drilling. Step S4, Hole cleaning and fracture flushing: The borehole is cleaned twice, once during the drilling process and once after the hole is completed, to clean the fractures inside the hole. Step S5, Hole Inspection: The quality of the drilled hole is inspected using a special hole inspection tool and a water pressure test is conducted according to the design requirements. Step S6, Install grouting pipe and mix grout: After the hole is accepted, install the grouting pipe and mix the curtain grouting grout. Add a preset proportion of quick-setting agent to the grout according to the required initial setting time. Step S7, Segmented grouting: Use a high-pressure pump to perform segmented intermittent grouting from bottom to top. The grouting sequence follows the drilling sequence in step S3. Adopt an immediate grouting strategy of grouting one hole immediately after drilling. During the grouting process, the grouting volume is controlled by both pressure gauge and grout volume. Grouting ends when the grouting pressure of the corresponding grouting section remains stable and the grouting volume is lower than the minimum grouting volume. Step S8, orifice sealing: Select quick-setting cement or increase the content of quick-setting agent in the grouting slurry to seal the orifice of the curtain grouting according to the size and shape of the orifice. Then remove the grouting pipeline, clean the orifice and ensure that its surface is flat. Step S9, Grouting effect check: After completing the grouting by repeating the above steps, check and evaluate the quality of the curtain. For curtain positions where the quality does not meet the design requirements, add grout. After passing the test, carry out pile foundation drilling construction.
[0007] Furthermore, in step S2, the steel casing is made of rolled steel plate with an inner diameter larger than the designed pile diameter. After installation, the top surface is 0.3m above the ground. A reinforcing rib is welded to the upper and lower sections and the outer side of the middle section of the casing to increase rigidity. Then, the bottom and outer perimeter of the casing are backfilled with clay soil and compacted in layers. After the trench excavation is completed, a drainage channel is excavated and set up on the side of the trench.
[0008] Furthermore, in the drilling and grouting construction of steps S3 and S7, for cases where multiple curtain grouting holes are set, the drilling and grouting of the larger karst fissures on the outer curtain are constructed first, and the construction is carried out inward ring by ring after the outer ring construction is completed; the size of the fissures is determined based on the geological exploration data and the advanced drilling columnar section in step S1.
[0009] Furthermore, in step S6, the grouting material is a cement slurry with 42.5 silicate cement as the main raw material, and a certain amount of water glass solution is added as a quick-setting agent for mixing. The initial setting time of the mixed slurry is controlled within the range of 30 to 60 seconds.
[0010] Furthermore, the water-cement ratio of the cement slurry is controlled within the range of 0.8:1 to 2:1, and the volume ratio of the cement slurry to the water glass solution is within the range of 1:0.8 to 1:1.5.
[0011] Furthermore, in step S7, the length of each grouting section is controlled to be 2 to 3 meters, and the grouting volume each time does not exceed 50 m³.
[0012] Furthermore, in step S9, a combination of core sampling and water pressure testing is used to comprehensively evaluate the curtain forming quality: the area between two adjacent curtain grouting holes is selected as a measuring point, and drilling is performed at the measuring point to extract complete rock core samples for on-site recording and description evaluation, including the length, diameter, integrity, fracture development, filling degree and distribution characteristics of the cement stone body. The rock core samples are then sent for testing to conduct unconfined compressive strength tests. The strength of the cement stone body is not lower than the strength of the bedrock surrounding the measuring point, which is considered qualified. For the measuring point boreholes remaining after on-site core sampling, the Lurong test method is used to conduct water pressure tests, and the Lurong value after the test is calculated and converted into the permeability coefficient. A permeability coefficient less than 1×10-6 cm / s indicates that the curtain has reliable water-stopping performance.
[0013] Furthermore, in step S1, the distribution location of the curtain grouting holes in the curtain grouting hole location distribution diagram is determined by the following method: the design thickness of the curtain is determined according to the design diameter of the pile foundation and the geological survey. The curtain grouting holes are arranged in a concentric circle manner, with the center of the pile foundation hole as the center and the edge of the steel casing as the inner boundary. There are three circles arranged within the curtain thickness range, namely the outer circle, the middle circle and the inner circle; the radius of the outer circle R1=r+T; the radius of the middle circle R2=r+2 / 3T; the radius of the inner circle R3=r+T / 3; where r is the radius of the steel casing and T is the design thickness of the curtain.
[0014] Furthermore, the number of grouting holes in each ring should ensure effective grout diffusion and overlap between adjacent boreholes to guarantee the continuity of the curtain. The specific number is determined based on the designed thickness of the curtain and the scale of karst cave development in the karst geology: when the karst cave is large or the fissures are well-developed, more holes are used to enhance the curtain's density; when the karst cave is small and concentrated, fewer holes are used to improve construction efficiency. The grouting holes in different rings are staggered, and the central angles between adjacent boreholes in the same ring are equal.
[0015] Furthermore, during drilling in step S3, the borehole deviation should be controlled within 1%, and the deviation between the borehole trajectory and the designed position should not exceed 0.2m. In the drilling and grouting steps of steps S3 and S7, the outer ring curtain grouting holes are constructed first, and the grouting pressure of the outer ring is controlled within the range of 0.3 to 0.5 MPa. Then, the middle ring grouting is constructed, and the grouting pressure of the middle ring is increased to the range of 0.5 to 0.8 MPa. Finally, the inner ring grouting is constructed, and its grouting pressure is increased to the range of 0.8 to 1.2 MPa.
[0016] Compared with the prior art, the present invention has the following beneficial effects: 1. This invention moves the curtain grouting process to before the pile foundation drilling, and forms a closed curtain structure around the perimeter of the pile foundation borehole in advance. This fundamentally changes the passive response mode of traditional pile foundation construction, which involves dealing with karst caves encountered during drilling. It transforms karst treatment from an uncontrollable emergency rescue to a controllable proactive prevention.
[0017] 2. This invention employs a skip-hole interval drilling method, combined with a three-dimensional orderly drilling and grouting sequence: outer ring first, then inner ring; large ring first, then small ring; lower layer first, then upper layer. The skip-hole interval reduces disturbance to the strata during drilling. During construction, a closed boundary is first formed around the pile foundation hole to prevent grout overflow. Large fissures are grouted first to ensure gradual and dense sealing of the karst area. Grouting from lower to upper layers avoids upper-layer grout blocking the grouting channels of lower layers. In the sequential grouting process, each grouting sequence is performed after the formation of the previous sequence's curtain, effectively inspecting and reinforcing the preceding construction. The overall construction deployment allows the grout to diffuse orderly and solidify layer by layer in the karst fissures, forming a complete curtain structure, resulting in better uniformity and reliability of the entire curtain structure.
[0018] 3. Through engineering practice, it has been verified that after adopting the method of this invention: the one-time hole formation rate of bridge pile foundations is increased to 100%; the hole collapse rate and void rate during drilling construction are reduced to 3%; the grout leakage and grout runoff rate are reduced to 5%; the pile foundation hole formation period is reduced by 27.5%; the material cost of karst treatment is reduced by 24.8%; the total cost of karst treatment is reduced by 56%; and the quality of finished pile foundations is improved by 10%. Attached Figure Description
[0019] Figure 1 This is a schematic diagram illustrating the implementation process of the pre-construction curtain grouting technology for bridge pile foundations in karst areas according to the present invention. Figure 2 This is a schematic diagram of the on-site construction of curtain grouting at the bridge pile foundation orifice in this invention.
[0020] In the attached diagram: 1. Pile foundation hole; 2. Steel casing; 3. Trench; 4. Drainage and diversion channel; 5. Curtain grouting hole; 6. Drilling machine. Detailed Implementation
[0021] The technical solution of the present invention will now be described with reference to the accompanying drawings. However, the described embodiments are only some embodiments of the present invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0022] It should be noted that in the description of this invention, terms such as "upper," "lower," "front," and "rear" indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. This is merely for ease of description and does not indicate or imply that the device or element must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, it should not be construed as a limitation of this invention.
[0023] The accompanying drawings show various structural schematic diagrams according to embodiments disclosed in the present invention. These drawings are not drawn to scale, and some details may be enlarged or omitted for illustrative purposes.
[0024] One implementation scenario of this invention is a highway project in southwestern my country. This project involves 85 bridges and 3441 pile foundations. The bridge sections are mostly located in karst basin areas where karst water is shallow and primarily moves horizontally, exhibiting distinct horizontal zonation. Karst is characterized by significant uncertainty and concealment; when soil cavities or sinkholes exist beneath the loose overburden, the groundwater level fluctuates frequently near the bedrock surface, easily leading to karst ground subsidence. To ensure the quality and safety of bridge pile foundation construction, this project employs the pre-construction curtain grouting technology for bridge pile foundations in karst areas, as described in this invention. This technology consolidates the karst mass before pile drilling, ensuring the geological stability and bearing capacity of the pile foundation construction. Figure 1 As shown, the specific construction process of this invention is as follows: Step S1, Construction Preparation: The site for the upcoming pile foundation construction was cleared and leveled. A geological survey was conducted at the bridge pile foundation construction site to determine the distribution, scale, and filling conditions of the underground karst area. Based on engineering geological exploration data and advanced drilling columnar section, the distribution of curtain grouting boreholes on the site was determined. Then, in conjunction with the pile foundation construction plan, a curtain grouting technical scheme was developed. The thickness of the curtain was calculated according to relevant geotechnical mechanics specifications to ensure sufficient bearing capacity and water-stopping effect. Subsequently, with the center of the pile foundation borehole as the center, the distribution, number, depth, and diameter of the curtain grouting boreholes within the curtain thickness range were determined, thus creating a curtain grouting borehole distribution map.
[0025] In this example, the engineering geological exploration data was obtained by scanning a large area of the pile foundation construction area using the high-density resistivity method to preliminarily determine the planar distribution and main orientation of the karst caves. Specifically, the high-density resistivity method uses a Wenner device for electrode arrangement. During measurement, the power supply electrode and the measuring electrode are moved sequentially to form a two-dimensional resistivity profile covering the entire pile foundation construction area. On the resistivity profile, intact limestone exhibits high resistivity characteristics, while the karst cave filling material exhibits medium to low resistivity characteristics depending on the filling condition. Karst caves filled with soft plastic clay show even lower apparent resistivity values. By delineating and interpreting the resistivity anomaly areas, the approximate range of karst cave development can be determined. Further detailed exploration is then conducted using advanced drilling and core sampling methods, recording in detail the rock name, weathering degree, fracture development, dissolution phenomena, and filling material characteristics of the core samples. The vertical distribution of the karst caves is determined by observing abnormal mud consumption, sudden drill bit drops, and abrupt changes in drilling speed during the drilling process. The number of caves revealed by a single borehole, the elevation of the top and bottom plates of the caves, the height of the caves, and the filling conditions should be recorded in detail and drawn into a borehole columnar diagram.
[0026] After the preliminary exploration is completed, appropriate drilling rigs and grouting equipment will be selected based on the geological topography and grouting technology plan, and preparations will be made. Specifically, this project selects the XY-200-T-SJ-3 integrated drilling rig tower crane, which combines core drilling, water pump, and hydraulic functions.
[0027] Step S2, determine the hole position: According to the pile foundation positioning in the pile foundation construction plan, the hole positions are measured and laid out on the construction site, and the center of the pile hole is determined. A steel casing is then installed at the pile hole opening. For example... Figure 2 As shown, specifically, the steel casing is made of 13mm steel plate. A reinforcing rib is welded to the upper, lower, and middle outer sides of the steel casing to increase rigidity. Then, the bottom and outer sides of the steel casing are backfilled with clay soil and compacted in layers to enhance the rigid protection of the pile hole by the steel casing. In terms of specific parameters, the inner diameter of the steel casing is 20cm larger than the designed pile diameter, the burial depth of the steel casing is 2m, and the top of the steel casing is 0.3m above the ground to prevent subsequent grouting slurry and surface water from entering the pile hole.
[0028] After the steel casing is installed, a cross line is drawn on the top surface of the steel casing according to the pile location markings. The reinforcing steel bars are then installed along these cross lines to mark the center line of the steel casing. The steel casing is inspected and accepted according to the following requirements: the deviation between the center of the steel casing and the center of the pile hole should not exceed 50mm, and the vertical inclination of the steel casing should not exceed 1%. A trench is then excavated outside the steel casing to serve as the borehole area for curtain grouting drilling, providing a starting working face for the drill bit and preventing it from slipping or deviating on the loose surface soil. A drainage channel is excavated along the edge of the trench to drain backwater and silt carried out by karst during drilling, preventing water accumulation at the construction site from affecting construction stability.
[0029] Step S3, Drilling: According to the curtain grouting hole location distribution map, the curtain grouting holes are drilled in the trench using a skip-hole interval method. Specifically, this means that two consecutive drilling operations do not select two adjacent curtain grouting holes. The skip-hole interval method involves drilling the curtain grouting holes according to their numbers on the distribution map; for example, drilling the odd-numbered holes first, followed by the even-numbered holes. This skip-hole interval method avoids cross-drilling between adjacent holes, reduces disturbance to the formation during drilling, and improves the project's impermeability and stability.
[0030] For cases involving multiple rings of curtain grouting holes, the drilling of these holes needs to be carried out sequentially, following the order of outer rings followed by inner rings and larger holes before smaller ones. Specifically, the holes in the outer ring with larger karst fissures are drilled first. Then, after completing the drilling of all curtain grouting holes in the outer ring with skip-hole intervals, drilling proceeds ring by ring inwards, with each ring following the skip-hole intervals and the order of larger holes before smaller ones. The size of the fissures is determined based on the geological exploration data and the advanced drilling columnar section from step S1, thus adjusting the drilling sequence accordingly.
[0031] In practice, the drilling equipment and work platform are placed on the holes to be drilled in sequence according to the skip-hole interval method and drilling sequence. After the drilling equipment is debugged, the pipeline is connected and protected and fixed, the drilling work is started.
[0032] It should be noted that, to avoid borehole collapse during drilling, this embodiment adopts an immediate grouting strategy of grouting one borehole immediately after drilling. Grouting is performed immediately after drilling is completed at a single pile foundation borehole, and the subsequent steps are described based on this strategy. When site conditions and equipment permit, simultaneous drilling at multiple locations can also be carried out. When drilling multiple locations simultaneously, the above-mentioned skip-hole interval method, drilling sequence, and immediate grouting strategy are also followed.
[0033] Step S4, hole cleaning and fissure flushing: The first cleaning is performed during the drilling process, and the second cleaning is performed after drilling is completed. High-pressure water pressure from bottom to top is used to remove rock samples, mud, and sediment from the borehole, flushing out any remaining clay residue and improving the adhesion between the subsequent grouting material and the soil. The water pressure in the second cleaning is higher than that in the first cleaning to ensure that the fractures are thoroughly cleaned after drilling is complete.
[0034] Step S5, Hole inspection: During and after the drilling process, the drilling quality must be inspected. A specialized borehole inspector is used to conduct phased quality checks, and a water pressure test is performed according to design requirements. Only after ensuring the borehole quality meets the design specifications can the next step be carried out. If the borehole is unqualified, it needs to be re-cleaned and cleaned. If the requirements are still not met after cleaning, the cause of the borehole deviation must be analyzed, the drilling rig parameters adjusted, and a new borehole drilled around the original location. The re-drilled borehole is then inspected again according to requirements.
[0035] Step S6: Install grouting and mix grout: After the pile foundation boreholes pass inspection and the borehole formation meets the requirements, the grouting pipes are installed, and the curtain grouting material is mixed. High-quality curtain grouting material should possess good fluidity, adhesion, and durability, enhancing the structure's load-bearing capacity and seismic performance while filling gaps. High-quality materials improve project quality and safety. To achieve better crack flow and setting effects, this embodiment uses 42.5 silicate cement as the main raw material and adds a certain amount of water glass solution as a quick-setting agent during mixing. This allows for maximum control of the grout's initial setting time according to project requirements, achieving the best consolidation effect.
[0036] In a further technical solution, the water-cement ratio of the cement slurry is controlled within the range of 0.8:1 to 2:1. When there are many fissures in the karst area and the slurry needs strong diffusion ability to quickly fill the karst area, a larger water-cement ratio is used to ensure the fluidity of the slurry; when the karst area has poor stability and the slurry needs to solidify quickly to solidify the karst area, a smaller water-cement ratio is used. The volume ratio of the water glass solution to the cement slurry is determined based on field tests. In this example, the initial setting time of the slurry needs to be controlled within the range of 30 to 60 seconds. Therefore, the volume ratio of cement slurry to water glass solution is within the range of 1:0.8 to 1:1.5. When the grouting pressure is high or the formation permeability is strong, a shorter initial setting time is required to prevent excessive diffusion of the slurry, and a higher proportion of water glass solution can be added; when the grouting pressure is low or the formation permeability is weak, a lower proportion of water glass solution is added to control a longer initial setting time to ensure sufficient penetration of the slurry.
[0037] Step S7, segmented grouting: A high-pressure pump is used to perform intermittent grouting in the pile foundation holes from bottom to top. The grouting operation is carried out based on the drilling sequence in step S3, specifically as follows: First, construct the outer ring curtain grouting holes to form a closed boundary, and then construct the inner ring curtain grouting holes. This allows the outer ring curtain to be formed first, which in turn constrains the subsequent inner ring grouting, ensuring that the grout spreads and overlaps within a specified range and does not flow outward, thus preventing insufficient curtain thickness. First, grouting is performed to seal large fissures to prevent the slurry from flowing away into karst caves at large fissure positions, then grouting is carried out to seal small fissures, so that the slurry is more efficiently used to form a curtain around the pile, significantly improving the effective utilization rate of the slurry; Segmented grouting is carried out from bottom to top, the upper layer grouting is performed after the lower layer slurry is consolidated, the length of each grouting section is controlled to 2 to 3 meters, and the grouting amount each time does not exceed 50m³, which avoids slurry channeling along the borehole wall caused by excessively long one-time grouting length or excessive grouting amount that leads to failure to effectively fill the fissures, and also facilitates the control of grouting pressure and grouting amount of each section to ensure the grouting quality of each section. During the grouting process, the grouting amount is controlled by both the pressure gauge and the slurry amount, so as to reduce the slurry leakage and slurry channeling phenomena caused by sudden changes in grouting pressure and grouting amount. The initial setting time of the slurry is controlled to no more than 1 minute based on the grouting material ratio in step S6. When the grouting pressure of the corresponding grouting section remains stable and the grouting amount is lower than the minimum grouting amount, it indicates that the fissures or karst caves in this grouting section have been effectively filled, and the grouting is ended.
[0038] Step S8, borehole orifice sealing: Appropriate materials are selected to seal the curtain grouting borehole orifice according to the size and shape of the orifice to prevent the slurry from leaking out of the orifice. For example, for large-diameter orifices, fast-hardening cement can be poured for rapid sealing, or the content of water glass in the grouting material can be directly increased to seal the orifice by greatly shortening the initial setting time of the slurry. After the grouting of the last section is completed and the orifice is sealed, the grouting pipeline can be dismantled, the orifice is cleaned and its surface is ensured to be flat.
[0039] Step S9, grouting effect inspection: Repeat the above steps until the grouting of each curtain grouting borehole on the pile foundation hole position is completed, then the quality of the formed curtain is detected and evaluated, and supplementary grouting is immediately carried out for the positions where the curtain quality fails to meet the specification and design requirements. Further, the method combining core drilling sampling and water pressure test can be adopted to comprehensively evaluate the forming quality of the curtain, which is specifically as follows: The area between two adjacent curtain grouting boreholes is selected as the measuring point, which is the area where the slurry diffusion overlaps, and the compactness and integrity of the curtain can be best reflected in this area. Drill at the measuring point, take out the complete rock core sample for on-site recording, description and evaluation, including the length, diameter, integrity degree, fissure development situation, filling degree and distribution characteristics of the cement stone of the core sample. The ideal rock core sample should present a complete columnar or short columnar shape, with cement stone filled in fissures and holes, well cemented with the surrounding rock mass, and no obvious voids or loose areas. Then the rock core sample is sent for inspection to carry out the unconfined compressive strength test, and it is qualified when the strength of the cement stone body is not lower than the strength of the bedrock around the measuring point.
[0040] For the boreholes remaining after core sampling, a water pressure test is conducted using the Lurong test method. Water pressure is applied to the borehole and maintained at 0.3 MPa for at least 10 minutes. The test pressure is monitored in real time using a pressure gauge installed at the borehole opening, and the flow rate is measured using a flow meter installed on the pipeline. Under stable test pressure conditions, the stable flow rate value is read, and the Lurong value is calculated. The Lurong value calculation formula is: q = Q / (P × L), where q is the Lurong value, Q is the injected flow rate, P is the test pressure, and L is the test section length. Based on the Lurong value, the permeability coefficient K is converted to K = Q / (2πL) × ln(L / r), where r is the borehole radius. The permeability coefficient K of the curtain should be less than 1 × 10⁻⁶. -6 The cm / s indicates that the curtain has reliable water-stopping performance and can effectively isolate the impact of groundwater on pile foundation construction.
[0041] According to the above standards, if any index of the core sampling or water pressure test fails to meet the requirements, supplementary grouting should be carried out in the unqualified area. After supplementary grouting, quality testing should be carried out again until all indexes meet the requirements. When the curtain quality is determined to be qualified, the pre-construction curtain grouting technology of the bridge pile foundation of the present invention is completed, and pile foundation drilling construction can be carried out under the protection of the formed curtain structure.
[0042] To illustrate the distribution and construction of the multi-ring curtain grouting holes described in this invention, a further detailed description of steps S1, S3, and S7 in the grouting construction scenario of a certain pile foundation hole in the above-mentioned project is provided below: In the preliminary construction preparation process of step S1, it is necessary to formulate a distribution map of curtain grouting hole locations: the design thickness T of the curtain is determined according to the design diameter of the pile foundation and the geological survey. The curtain grouting holes are arranged in a concentric circle manner, with the center of the pile foundation hole as the center and the edge of the steel casing as the inner boundary. There are three circles arranged within the thickness range of the curtain, namely the outer circle, the middle circle and the inner circle. The curtain grouting holes are arranged on the edge line of each circle.
[0043] For this implementation scenario, the pile foundation design diameter is 1.9m (corresponding to a steel casing radius r=1.0m), and the karst cave development depth is relatively large. The curtain thickness is designed to provide sufficient bearing capacity and water-stopping effect under these geological conditions, and the curtain design thickness is determined to be T=1.5m. The number of the three-ring curtain grouting holes is determined as follows: The outer circle has a radius of R1 = r + T = 2.5m and 10 holes are arranged. The core objective of this curtain grouting hole is to form a preliminary water-stop barrier in the outer area of the pile, providing boundary constraints for subsequent inner circle grouting.
[0044] The radius of the middle circle is R2=r+2 / 3T=2m, and 12 holes are arranged. The core objective of the grouting holes in this circle is to fill the overlapping gaps between the grouting holes of the outer circle curtain and to enhance the overall thickness and density of the curtain.
[0045] The inner circle has a radius of R3 = r + T / 3 = 1.5m and 8 holes are arranged. The core objective of this curtain grouting hole is to form a tight water-stopping and sealing structure in the core area around the pile, so as to ensure that the pile foundation construction area is completely isolated from the surrounding karst strata.
[0046] The number of boreholes in each ring must be determined to ensure effective grout diffusion and overlap between adjacent boreholes, guaranteeing the continuity of the curtain. The specific number is determined based on the designed curtain thickness and the scale of karst cave development in the karst geology: when the karst caves are large or the fissures are well-developed, a larger number of boreholes is used to enhance the curtain's density; when the karst caves are small and concentrated, a smaller number of boreholes is used to improve construction efficiency. The grouting holes in different rings are staggered, and the central angles between adjacent boreholes in the same ring are equal.
[0047] The diameter of each curtain grouting hole is designed to be 125mm according to conventional selection. The designed hole depth is determined based on the results of karst cave distribution exploration. In principle, it should penetrate the bottom of the deepest karst cave and enter the intact bedrock for no less than 1m. For areas with thick overburden, the drilling depth should also include the thickness of the overburden.
[0048] During drilling in step S3, the borehole deviation should be controlled within 1%, and the deviation between the borehole trajectory and the designed position should not exceed 0.2m. In the drilling and grouting steps of steps S3 and S7, based on the skip-hole interval method and following the order of constructing the curtain grouting holes in the large fracture area first, the outer ring curtain grouting holes are constructed first to form the first line of defense of the curtain. The grouting pressure of the outer ring is controlled within the range of 0.3 to 0.5 MPa. Then, the middle ring grouting construction is carried out, and the grouting pressure of the middle ring is increased to the range of 0.5 to 0.8 MPa. The increase in grouting pressure is based on the following technical principle: outer... The outer ring grouting hole curtain has been formed, providing boundary constraints for subsequent grouting. This ensures that the grout mainly diffuses within the area between the outer and middle ring grouting holes, preventing outward leakage. The higher grouting pressure overcomes the constraint resistance of the outer ring grouting hole curtain, allowing the grout to fully fill the overlapping area between the outer ring grouting holes, forming a uniformly thick intermediate annular curtain band. Finally, the inner ring grouting is carried out, with the grouting pressure increased to the range of 0.8 to 1.2 MPa. This allows the grout to achieve a high filling density within a smaller diffusion radius, forming a dense core curtain around the pile.
[0049] During grouting, the grouting pressure and volume are monitored in real time. When the grouting pressure remains at a stable value and the grouting volume continues to increase, it indicates that the grout is spreading to a distance. When the grouting pressure suddenly rises or the grouting volume suddenly decreases, it indicates that the ground fissures or karst caves have been filled, and grouting can be terminated. After the inner curtain grouting holes are grouted, the pile perimeter curtain system forms a three-layer nested structure: the outer curtain forms the outer boundary, the middle curtain forms the intermediate reinforcement layer, and the inner curtain forms the core water-stopping core. The three curtains overlap and interlock to form a complete pile perimeter water-stopping system.
[0050] In this embodiment, a highway project in Southwest my country, actual construction verification showed that, compared to the traditional method of sealing during pile foundation drilling without pre-construction curtain grouting, the pre-construction curtain grouting method implemented through the above-mentioned technical solution reduced the collapse rate and void rate of bridge pile foundation drilling to 3% after forming a curtain structure in complex karst areas, ensuring steady construction progress. Through the implementation of pre-construction curtain grouting technology for bridge pile foundations in complex karst areas, the one-time hole formation rate of bridge pile foundations in this type of terrain increased to 100%, and the quality of finished pile foundations improved by 10%, effectively guaranteeing construction quality. Furthermore, as shown in Appendix Table 1, cost budgeting and schedule calculations for a certain pile foundation show that the implementation of this technology significantly reduced the use of backfill materials, reducing the cost of a single pile foundation by about half. The curtain grouting treatment before pile foundation construction also avoided the need for frequent intervention in karst conditions during pile foundation construction, shortening the pile formation period by 27.5% compared to traditional pile foundation construction methods. The implementation of the above technologies has saved construction costs and time to a certain extent, and has universal application value.
[0051] Table 1 Comparison of Pile Foundation Construction Costs and Duration
[0052] Finally, it should be noted that the above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A pre-construction curtain grouting technology for bridge pile foundations in karst areas, characterized in that, The implementation process includes the following steps: Step S1, Construction Preparation: Clear and level the construction site, conduct geological surveys, obtain engineering geological exploration data and advanced drilling columnar section, and formulate curtain grouting technology plan and curtain grouting hole distribution map in conjunction with the pile foundation construction plan. Step S2, determining the hole position: Measure and mark the pile foundation hole position at the construction site, determine the center of the hole position, install a steel casing at the pile foundation hole opening, and then excavate a trench outside the steel casing as the hole opening area for curtain drilling. Step S3, Drilling: According to the distribution map of curtain grouting holes, a skip-hole interval method is adopted in the trench, that is, two consecutive constructions do not select two adjacent curtain grouting holes for drilling; Step S4, Hole cleaning and fracture flushing: The borehole is cleaned twice, once during the drilling process and once after the hole is completed, to clean the fractures inside the hole. Step S5, Hole Inspection: The quality of the drilled hole is inspected using a special hole inspection tool and a water pressure test is conducted according to the design requirements. Step S6, Install grouting pipe and mix grout: After the hole is accepted, install the grouting pipe and mix the curtain grouting grout. Add a preset proportion of quick-setting agent to the grout according to the required initial setting time. Step S7, Segmented grouting: Use a high-pressure pump to perform segmented intermittent grouting from bottom to top. The grouting sequence follows the drilling sequence in step S3. Adopt an immediate grouting strategy of grouting one hole immediately after drilling. During the grouting process, the grouting volume is controlled by both pressure gauge and grout volume. Grouting ends when the grouting pressure of the corresponding grouting segment remains stable and the grouting volume is lower than the minimum grouting volume. Step S8, orifice sealing: Select quick-setting cement or increase the content of quick-setting agent in the grouting slurry to seal the orifice of the curtain grouting according to the size and shape of the orifice. Then remove the grouting pipeline, clean the orifice and ensure that its surface is flat. Step S9, Grouting effect check: After completing the grouting by repeating the above steps, check and evaluate the quality of the curtain. For curtain positions where the quality does not meet the design requirements, add grout. After passing the test, carry out pile foundation drilling construction.
2. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In step S2, the steel casing is made of rolled steel plate with an inner diameter larger than the designed pile diameter. After installation, the top surface is 0.3m above the ground. A reinforcing rib is welded to the upper and lower sections and the outer side of the middle section of the casing to increase rigidity. Then, the bottom and outer sides of the casing are backfilled with clay soil and compacted in layers. After the trench excavation is completed, a drainage channel is excavated and set up on the side of the trench.
3. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In the drilling and grouting construction of steps S3 and S7, for cases where multiple curtain grouting holes are set, the drilling and grouting of the larger karst fissures on the outer curtain are constructed first, and the construction is carried out inward ring by ring after the outer ring construction is completed; the size of the fissures is determined based on the geological exploration data and the advanced drilling columnar section in step S1.
4. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In step S6, the grouting material is a cement slurry with 42.5 silicate cement as the main raw material, and a certain amount of water glass solution is added as a quick-setting agent for mixing. The initial setting time of the mixed slurry is controlled within the range of 30 to 60 seconds.
5. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 4, characterized in that, The water-cement ratio of the cement slurry is controlled within the range of 0.8:1 to 2:1, and the volume ratio of the cement slurry to the water glass solution is within the range of 1:0.8 to 1:1.
5.
6. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In step S7, the length of each grouting section is controlled to be 2 to 3 meters, and the grouting volume each time does not exceed 50m³.
7. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In step S9, the method combining core drilling sampling and water pressure test is adopted to comprehensively evaluate the forming quality of the curtain: the area between two adjacent curtain grouting holes is selected as the measuring point, drilling is carried out at the measuring point, and complete core samples are taken out for on-site recording, description and evaluation, including the length, diameter, integrity degree, fracture development of the core sample, as well as the filling degree and distribution characteristics of the cement stone body. Then the core samples are sent for inspection to carry out the unconfined compressive strength test, and it is qualified if the strength of the cement stone body is not lower than the strength of the bedrock around the measuring point; for the measuring point borehole retained after on-site core drilling sampling, the water pressure test is carried out by the Lugeon test method, the Lugeon value after the test is calculated and converted into the permeability coefficient, and the permeability coefficient is less than 1×10 -6 cm / s, which indicates that the curtain has reliable water stopping performance.
8. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 1, characterized in that, In step S1, the distribution location of the curtain grouting holes in the curtain grouting hole location distribution diagram is determined by the following method: the design thickness of the curtain is determined according to the design diameter of the pile foundation and the geological survey. The curtain grouting holes are arranged in a concentric circle manner, with the center of the pile foundation hole as the center and the edge of the steel casing as the inner boundary. There are three circles arranged within the curtain thickness range, namely the outer circle, the middle circle and the inner circle; the radius of the outer circle R1=r+T; the radius of the middle circle R2=r+2 / 3T; the radius of the inner circle R3=r+T / 3; where r is the radius of the steel casing and T is the design thickness of the curtain.
9. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 8, characterized in that, The number of grouting holes in each ring should be sufficient to ensure effective grout diffusion and overlap between adjacent boreholes, thus ensuring the continuity of the curtain. The specific number should be determined based on the designed thickness of the curtain and the scale of karst cave development in the karst geology: when the karst cave is large or the fissures are well developed, more holes should be used to enhance the curtain's density; when the karst cave is small and concentrated, fewer holes should be used to improve construction efficiency. The grouting holes in different rings should be staggered, and the central angles between adjacent boreholes in the same ring should be equal.
10. The pre-construction curtain grouting technology for bridge pile foundations in karst areas according to claim 8, characterized in that, When drilling in step S3, the borehole deviation should be controlled within 1%, and the deviation between the borehole trajectory and the design position should not exceed 0.2m. In the drilling and grouting steps of steps S3 and S7, the outer ring curtain grouting holes are constructed first, and the grouting pressure of the outer ring is controlled within the range of 0.3 to 0.5MPa. Then, the middle ring grouting is constructed, and the grouting pressure of the middle ring is increased to the range of 0.5 to 0.8MPa. Finally, the inner ring grouting is constructed, and its grouting pressure is increased to the range of 0.8 to 1.2MPa.