Construction methods for underground spaces of municipal roads without interrupting pipeline operation

By setting up temporary pipe corridors and cast-in-place piles in the foundation pit, the existing pipelines were relocated to the pipe corridors, solving the problem of pipeline relocation in narrow urban environments. This enabled the pipelines to be shut down for short periods and operate normally during construction, improving construction safety and management convenience, and reducing costs.

CN123109206APending Publication Date: 2026-11-17CHINA CONSTR EIGHTH ENG BUREAU TECH CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611447897.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-17
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In the narrow urban environment, existing pipelines cannot be relocated to the outside of the foundation pit, resulting in a conflict between underground structure construction and pipeline relocation, and the long-term shutdown affects the use of the surrounding area.

Method used

A temporary utility tunnel was set up in the foundation pit as a pipeline relocation area. Cast-in-place piles were used as the supporting foundation to temporarily relocate the existing pipelines to the utility tunnel. The pipelines were relocated back in sections during the construction period to ensure that the pipelines were shut down for a short period of time. The temporary facilities were removed after the underground structure construction was completed.

Benefits of technology

It enabled the shutdown of existing pipelines during short-term relocation and return, while maintaining normal operation during underground structure construction. This solved the problem of pipeline relocation in narrow urban environments, improved construction safety and management convenience, and reduced costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109206A_ABST
    Figure CN123109206A_ABST
Patent Text Reader

Abstract

This invention discloses a construction method for underground spaces in municipal roads that allows for uninterrupted pipeline operation. The method includes the following steps: determining a pipeline relocation area near the sidewall within the foundation pit and constructing cast-in-place piles; excavating to the design elevation of the top of the underground structure and cutting off the portion of the cast-in-place piles above ground; constructing a temporary utility tunnel supported on top of the cut-off piles; relocating existing pipelines to the temporary utility tunnel; excavating the foundation pit, constructing internal supports, and backfilling the underground structure to the top slab; backfilling the top slab (excluding the utility tunnel area) and relocating the pipelines; dismantling the temporary utility tunnel and cast-in-place piles, and performing secondary backfilling. This invention utilizes the space between the diaphragm wall and the main structure to temporarily house existing pipelines, ensuring that the pipelines only temporarily stop operating during relocation and backfilling, thus solving the problem of pipelines in narrow urban areas being unable to be relocated to the outside of the foundation pit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction technology, and in particular to a construction method for underground spaces in municipal roads that allow for uninterrupted pipeline operation. Background Technology

[0002] With the continuous advancement of urban underground space development and construction, more and more underground structures need to be constructed within existing roads and urban built-up areas. Due to the limitations of the urban construction environment, which is usually restricted by surrounding existing buildings, existing construction sites, and urban infrastructure, construction sites are relatively narrow, and the temporary construction areas available during underground space construction are limited.

[0003] When constructing underground spaces beneath existing roads, existing municipal pipelines such as water supply lines, gas lines, power lines, and stormwater and sewage pipelines may run through the construction area of ​​the proposed underground structure. To avoid impacting existing pipelines during underground structure construction, current construction methods typically require the temporary relocation of affected existing pipelines to avoid the underground structure construction area.

[0004] However, in urban environments with dense surrounding buildings and existing construction sites, there is often a lack of space outside the underground structure's foundation pit for the temporary relocation of existing pipelines. This makes it difficult to implement the traditional construction method of relocating pipelines to the outside of the foundation pit, creating a conflict between the relocation of existing pipelines and the construction of underground space. In addition, although some municipal pipelines can be shut down for a short period during the switching process, if the pipelines are shut down for a long time due to underground space construction, it will affect the normal use of the surrounding area.

[0005] Therefore, it is necessary to provide an underground space construction method suitable for narrow urban construction environments, which can meet the construction needs of underground structures while providing temporary relocation space for existing pipelines, so that existing pipelines are only out of service for a short time during relocation and return, and can be restored to operation during the construction of underground structures. Summary of the Invention

[0006] The purpose of this invention is to overcome the shortcomings of the prior art and provide a construction method for underground spaces of municipal roads that allows pipelines to operate without interruption. By delineating a pipeline relocation area within the excavation range of the foundation pit and setting up cast-in-place piles as the supporting foundation for a temporary utility tunnel, existing pipelines are temporarily placed within the tunnel. After the completion of the underground structure's top slab construction, backfilling is carried out in sections and the pipelines are relocated back. Finally, the temporary utility tunnel and cast-in-place piles are dismantled and secondary backfilling is completed. This method ensures that existing pipelines only stop operating during short-term relocation and relocation, while maintaining normal operation for the majority of the underground structure construction time. It solves the construction problem of pipelines being unable to be relocated outside the foundation pit in narrow urban environments.

[0007] To achieve the above objectives, the technical solution adopted by this invention is a construction method for underground spaces of municipal roads without interrupting pipeline operation, comprising the following steps: Step 1: Determine the pipeline relocation area near the diaphragm wall within the excavation range of the foundation pit, and construct cast-in-place piles within the pipeline relocation area; Step 2: Excavate the earthwork in the pipeline relocation area until the top design elevation of the underground structure is reached, and cut off the pile body of the cast-in-place pile above the excavation surface; Step 3: Construct a temporary utility tunnel within the pipeline relocation area, with the temporary utility tunnel supported on top of the cut-off cast-in-place piles; Step 4: Relocate the existing pipelines within the excavation area of ​​the foundation pit to the temporary utility tunnel; Step 5: Excavate the foundation pit and construct internal supports, and backfill the underground structure until the top slab of the underground structure is completed. Step 6: Backfill the top of the underground structure except for the area occupied by the temporary utility tunnel, and relocate the existing pipelines in the temporary utility tunnel. Step 7: Remove the temporary utility tunnel and the cast-in-place piles supporting the temporary utility tunnel, and carry out secondary backfilling in the remaining area at the top of the underground structure.

[0008] A further improvement of the construction method for underground spaces of municipal roads without interrupting pipeline operation in this invention is that, when performing step 1 above, a diaphragm wall that is relatively close to the existing pipeline and relatively parallel to the direction of the existing pipeline is selected as the arrangement side of the pipeline relocation area.

[0009] A further improvement of the construction method for underground spaces of municipal roads without interrupting pipeline operation in this invention is that the existing pipelines include electrical pipelines, rainwater pipelines and gas pipelines. When performing step 3 above, multiple partitions are set in the temporary pipeline corridor to divide the temporary pipeline corridor into multiple independent spaces. When performing step 4 above, different types of existing pipelines are respectively housed in the corresponding independent spaces.

[0010] A further improvement of the construction method for underground spaces of municipal roads without interrupting pipeline operation in this invention is that, when performing step 4 above, the operation of the existing pipeline is first suspended, and the existing pipeline is cut off at both ends respectively. The cut-off existing pipeline is then moved to the temporary utility tunnel, and the two ends of the existing pipeline are reconnected before the operation of the existing pipeline is resumed.

[0011] A further improvement of the construction method for underground spaces of municipal roads without interrupting pipeline operation in this invention is that, when performing step 5 above, during the construction of the uppermost foundation pit support, one end of the foundation pit support is connected to the temporary pipe gallery, and the other end is connected to the diaphragm wall on the side relatively far away from the temporary pipe gallery.

[0012] A further improvement of the construction method for underground spaces of municipal roads without interrupting pipeline operation in this invention is that, before performing step 6 above and after performing step 5 above, a first waterproofing and insulation construction is carried out on the top of the roof slab, excluding the area occupied by the temporary pipe gallery; and when performing step 7 above, after removing the temporary pipe gallery, a second waterproofing and insulation construction is carried out on the remaining area on the top of the roof slab.

[0013] Compared with the prior art, the advantages of the present invention are: 1. By setting up a temporary pipe gallery near the side wall within the excavation area of ​​the foundation pit, the existing pipelines can be temporarily relocated to the pipe gallery inside the foundation pit and close to the ground wall, thus avoiding the occupation of the main structure construction area inside the foundation pit. The temporary relocation of pipelines can be achieved without occupying additional space outside the foundation pit, solving the problem of no spare space outside the foundation pit for pipeline relocation in a narrow urban environment. 2. By setting up partitions in the temporary utility tunnel, different types of existing pipelines are housed in separate spaces, which avoids mutual interference between different pipelines and improves the safety and management convenience during pipeline relocation. 3. By connecting the uppermost internal support of the foundation pit to the side wall of the temporary pipe gallery, and using the temporary pipe gallery as the fulcrum of the internal support, the overall stability during the excavation and backfilling of the foundation pit is enhanced, while the setting of additional support structures is reduced, thus lowering construction costs. Attached Figure Description

[0014] To more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0015] Figure 1 This is a schematic diagram of the construction of cast-in-place piles within the pipeline relocation area of ​​the present invention.

[0016] Figure 2 This is a schematic diagram of the earthwork excavation in the pipeline relocation area according to the present invention.

[0017] Figure 3 This is a schematic diagram of the construction of the temporary utility tunnel according to the present invention.

[0018] Figure 4This is a schematic diagram of the relocation of existing pipelines according to the present invention.

[0019] Figure 5 This is a schematic diagram of the pile foundation construction for the foundation pit of the present invention.

[0020] Figure 6 This is a schematic diagram of the excavation of the foundation pit and the construction of the internal support for the present invention.

[0021] Figure 7 This is a schematic diagram of the underground structure construction of the present invention.

[0022] Figure 8 This is a schematic diagram of the first waterproof and thermal insulation construction of the present invention.

[0023] Figure 9 This is a schematic diagram of the existing pipeline relocation according to the present invention.

[0024] Figure 10 This is a schematic diagram of the temporary pipe gallery demolition and the second waterproofing and insulation construction of the present invention.

[0025] Figure 11 This is a schematic diagram of the underground structure of the present invention.

[0026] 1. Existing pipelines; 2. Pipeline relocation area; 3. Cast-in-place piles; 4. Diaphragm wall; 5. Temporary utility tunnel; 6. Internal support; 7. Underground structure. Detailed Implementation

[0027] The following specific examples illustrate the implementation of the present invention. Those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and various details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of the present invention.

[0028] The construction method of the underground space of municipal roads with uninterrupted pipeline operation according to the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0029] Please see Figures 1-11 The construction method for underground spaces of municipal roads without interrupting pipeline operation, as shown, includes the following steps: Step 1: Determine the pipeline relocation area 2 near the diaphragm wall 4 within the excavation area of ​​the foundation pit, and construct cast-in-place piles 3 within the pipeline relocation area 2; Step 2: Excavate the earthwork in the pipeline relocation area 2 until the top design elevation of the underground structure 7, and cut off the pile body of the cast-in-place pile 3 above the excavation surface; Step 3: Construct a temporary pipe gallery 5 within the pipeline relocation area 2, so that the temporary pipe gallery 5 is supported on the top of the cut-off cast-in-place pile 3; Step 4: Relocate the existing pipeline 1 within the excavation area of ​​the foundation pit to the temporary utility tunnel 5; Step 5: Excavate the foundation pit and construct the internal support 6, and backfill the underground structure 7 until the top slab of the underground structure 7 is completed. Step 6: Backfill the top of the underground structure 7 except for the area occupied by the temporary utility tunnel 5, and relocate the existing pipeline 1 in the temporary utility tunnel 5. Step 7: Remove the temporary utility tunnel 5 and the cast-in-place piles 3 supporting the temporary utility tunnel 5, and carry out secondary backfilling of the remaining area at the top of the underground structure 7.

[0030] Specifically, the underground structure 7 was constructed in sections, such as... Figure 11 As shown, after completing step 7 above, the ground connecting wall 4 is removed and the underground structure 7 of the adjacent zone is connected to form an overall underground structure.

[0031] By adopting a zoned construction approach for the underground structure 7, the construction conditions of the corresponding areas are preserved during the existence of the temporary utility tunnel 5, allowing the relocation of the existing pipeline 1, the installation of the temporary utility tunnel 5, and the construction of the underground structure 7 to avoid each other. After the pipeline is relocated and the temporary utility tunnel 5 is dismantled, the diaphragm wall 4 at the corresponding location is dismantled and connected to the adjacent zone of the underground structure 7, thereby ensuring that the underground structure 7 ultimately forms a continuous whole.

[0032] Specifically, when performing step 5 above, pile foundation construction is first carried out at the designed location within the excavation area of ​​the foundation pit, followed by earthwork excavation and construction of internal support 6. The pile foundation and the cast-in-place piles 3 at the bottom of the temporary pipe gallery 5 together serve as the connecting foundation of the internal support 6.

[0033] By incorporating the cast-in-place piles 3 at the bottom of the temporary utility tunnel 5 into the connection of the internal support 6, the cast-in-place piles 3 can fulfill the support requirements of the temporary utility tunnel 5 while also serving as a support connection during the foundation pit construction phase. This improves the utilization efficiency of the temporary structure and reduces the adverse effects of the temporary utility tunnel 5 on the internal support 6 system of the foundation pit.

[0034] Preferably, when performing step 1 above, a diaphragm wall 4 that is relatively close to the existing pipeline 1 and relatively parallel to the direction of the existing pipeline 1 is selected as the arrangement side of the pipeline relocation area 2.

[0035] By setting the pipeline relocation area 2 on the side of the diaphragm wall 4 that is close to the existing pipeline 1 and relatively parallel to the direction of the existing pipeline 1, the temporary pipe gallery 5 can be arranged in the edge space of the foundation pit, and the temporary relocation of the existing pipeline 1 can be realized in the limited construction space, reducing the occupation of the temporary pipe gallery 5 on the construction area of ​​the underground structure 7.

[0036] Preferably, the existing pipeline 1 includes electrical pipelines, rainwater pipelines and gas pipelines. When performing step 3 above, multiple partitions are set up in the temporary pipeline corridor to divide the temporary pipeline corridor 5 into multiple independent spaces. When performing step 4 above, different types of existing pipelines 1 are respectively housed in the corresponding independent spaces.

[0037] By setting up multiple partitions within the temporary utility tunnel 5, the temporary utility tunnel 5 is divided into multiple independent spaces, and different types of existing pipelines 1 are housed in their respective independent spaces. This allows different types of existing pipelines 1 to be arranged in separate zones, avoiding mutual interference between different pipelines and improving the safety and orderliness of the pipeline arrangement within the temporary utility tunnel 5. At the same time, it facilitates subsequent inspection, maintenance, and relocation operations for various types of existing pipelines 1.

[0038] Specifically, when performing step 1 above, at least two rows of cast-in-place piles 3 are constructed along the extension direction of the ground diaphragm wall 4. When performing step 3 above, the temporary pipe gallery 5 is constructed on top of the at least two rows of cast-in-place piles 3, so that it is set up along the extension direction of the ground diaphragm wall 4.

[0039] By setting at least two rows of cast-in-place piles 3 arranged along the extension direction of the diaphragm wall 4, a stable support system is formed at the bottom of the temporary utility tunnel 5, preventing the temporary utility tunnel 5 from tilting or becoming unstable during the process of bearing the existing pipeline 1; at the same time, the temporary utility tunnel 5 can be continuously extended along the direction of the diaphragm wall 4, forming a temporary accommodation space within the limited internal space of the foundation pit to meet the relocation needs of the existing pipeline 1.

[0040] Specifically, such as Figure 3 As shown: The temporary utility tunnel 5 is a tube with a rectangular cross-section. The partition consists of multiple vertical baffles connected at intervals within the temporary utility tunnel 5, which have divided the interior of the temporary utility tunnel 5 into multiple independent spaces.

[0041] Specifically, before performing step 4 above and after performing step 3 above, earthwork excavation is carried out within the excavation area of ​​the foundation pit until the existing pipeline 1 is exposed.

[0042] Preferably, when performing step 4 above, the operation of the existing pipeline 1 is first suspended, and the existing pipeline 1 is cut off at both ends. The cut-off existing pipeline 1 is then moved to the temporary utility tunnel 5, and the two ends of the existing pipeline 1 are reconnected before the operation of the existing pipeline 1 is resumed.

[0043] By suspending the operation of existing pipeline 1 during the relocation process, cutting off both ends of existing pipeline 1, and then relocating the cut-off existing pipeline 1 as a whole to the temporary utility tunnel 5 and reconnecting it, existing pipeline 1 can be quickly restored to operation after the relocation is completed, shortening the downtime of existing pipeline 1 and reducing the impact of underground space construction on the normal use of the surrounding area.

[0044] Preferably, when performing step 5 above, when constructing the uppermost foundation pit support 6, one end of the foundation pit support 6 is connected to the temporary pipe gallery 5, and the other end is connected to the diaphragm wall 4 on the side relatively far away from the temporary pipe gallery 5.

[0045] By connecting one end of the inner support 6 at the top of the foundation pit to the temporary pipe gallery 5 and the other end to the diaphragm wall 4 on the side relatively far from the temporary pipe gallery 5 during the construction, the temporary pipe gallery 5 participates in the connection of the inner support 6 system. This solves the problem that the inner support 6 at this location cannot be connected to the diaphragm walls 4 on both sides in the traditional way because the temporary pipe gallery 5 is set inside the foundation pit, thus ensuring the stability of the support during the foundation pit excavation process.

[0046] Preferably, before performing step 6 above and after performing step 5 above, the first waterproofing and insulation work is carried out on the top of the roof slab, excluding the area occupied by the temporary pipe gallery 5. When performing step 7 above, after removing the temporary pipe gallery 5, the second waterproofing and insulation work is carried out on the remaining area on the top of the roof slab.

[0047] Specifically, during the first waterproofing and insulation construction, the extension is made to extend to the temporary pipe gallery 5 and form an extension section. During step 6, when the first backfilling of the top slab is carried out, the extension section is exposed. During step 7, when the second waterproofing and insulation construction is carried out, the extension section is overlapped with the extension section.

[0048] By reserving an extension section, the two waterproofing and insulation constructions before and after the demolition of temporary utility tunnel 5 can be connected sequentially without requiring extensive damage to the completed area, thus reducing the difficulty of subsequent construction.

[0049] like Figure 8 As shown: The red dashed line in the diagram represents the first waterproofing and insulation construction; as... Figure 10 As shown: The red dashed lines in the figure represent the first and second waterproofing and insulation construction.

[0050] It should be noted that the structures, proportions, sizes, etc., illustrated in the accompanying drawings are merely for illustrative purposes to aid those skilled in the art and to facilitate understanding and reading. They are not intended to limit the scope of the invention and therefore have no substantial technical significance. Any modifications to the structure, changes in proportions, or adjustments to size, without affecting the effectiveness and purpose of the invention, should still fall within the scope of the technical content disclosed herein. Furthermore, the terms "upper," "lower," "left," "right," "middle," and "one" used in this specification are merely for clarity and not intended to limit the scope of the invention. Changes or adjustments to their relative relationships, without substantially altering the technical content, should also be considered within the scope of the invention.

[0051] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes, and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.

Claims

1. A construction method for underground spaces of municipal roads that allows for uninterrupted pipeline operation, characterized in that, Including the following steps: Step 1: Determine the pipeline relocation area near the diaphragm wall within the excavation range of the foundation pit, and construct cast-in-place piles within the pipeline relocation area; Step 2: Excavate the earthwork in the pipeline relocation area until the top design elevation of the underground structure is reached, and cut off the pile body of the cast-in-place pile above the excavation surface; Step 3: Construct a temporary utility tunnel within the pipeline relocation area, with the temporary utility tunnel supported on top of the cut-off cast-in-place piles; Step 4: Relocate the existing pipelines within the excavation area of ​​the foundation pit to the temporary utility tunnel; Step 5: Excavate the foundation pit and construct internal supports, and backfill the underground structure until the top slab of the underground structure is completed. Step 6: Backfill the top of the underground structure, excluding the area occupied by the temporary utility tunnel, and relocate the existing pipelines in the temporary utility tunnel. Step 7: Remove the temporary utility tunnel and the cast-in-place piles supporting the temporary utility tunnel, and carry out secondary backfilling in the remaining area at the top of the underground structure.

2. The construction method for underground spaces of municipal roads without interrupting pipeline operation as described in claim 1, characterized in that, When performing step 1 above, a diaphragm wall that is relatively close to the existing pipeline and relatively parallel to the direction of the existing pipeline is selected as the layout side of the pipeline relocation area.

3. The construction method for underground spaces of municipal roads with uninterrupted pipeline operation as described in claim 1, characterized in that, The existing pipelines include electrical pipelines, rainwater pipelines and gas pipelines. When performing step 3 above, multiple partitions are set up in the temporary pipeline corridor to divide the temporary pipeline corridor into multiple independent spaces. When performing step 4 above, the different types of existing pipelines are respectively housed in the corresponding independent spaces.

4. The construction method for underground spaces of municipal roads without interrupting pipeline operation as described in claim 1, characterized in that, When performing step 4 above, first suspend the operation of the existing pipeline, cut off the existing pipeline at both ends, move the cut-off existing pipeline to the temporary utility tunnel, reconnect the two ends of the existing pipeline, and then resume the operation of the existing pipeline.

5. The construction method for underground spaces of municipal roads without interrupting pipeline operation as described in claim 1, characterized in that, When performing step 5 above, when constructing the uppermost support in the foundation pit, one end of the support in the foundation pit is connected to the temporary pipe gallery, and the other end is connected to the diaphragm wall on the side relatively far away from the temporary pipe gallery.

6. The construction method for underground spaces of municipal roads without interrupting pipeline operation as described in claim 1, characterized in that, Before performing step 6 above, and after performing step 5 above, the first waterproofing and insulation work is carried out on the top of the top slab, excluding the area occupied by the temporary pipe gallery. When performing step 7 above, after removing the temporary pipe gallery, the second waterproofing and insulation work is carried out on the remaining area on the top of the top slab.