A composite pre-support method for segmented splitting curtain grouting and horizontal jet grouting in water-rich, extremely soft rock tunnels

By combining segmented split curtain grouting with horizontal jet grouting as a composite pre-support method, the risks of instability and water inrush faced by tunnel excavation in water-rich and extremely soft rock strata were solved, forming a seepage-proof and load-bearing composite pre-support body, thus achieving safe and stable tunnel excavation.

CN123109707APending Publication Date: 2026-11-17THE FIFTH ENG OF CCCC FOURTH ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611068537.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-17
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In water-rich, extremely soft rock formations, tunnel excavation faces the risks of easy instability at the tunnel face and high rates of mudslides and water inrushes. Conventional single-support methods are insufficient to form an effective anti-seepage and load-bearing structure, making it difficult to constrain unloading displacement during excavation.

Method used

The composite pre-support method of segmented split curtain grouting and horizontal jet grouting is adopted. Through the construction of grout-stopping walls, the layout of multi-ring grouting holes, and the coordinated construction of segmented split grouting and jet grouting, a composite pre-support body with dual properties of seepage prevention and load bearing is formed. This includes the construction of grout-stopping walls, the coordinated construction of multi-ring horizontal jet grouting piles and pipe roofs.

Benefits of technology

It effectively constrains unloading displacement during the excavation process, improves the overall mechanical properties of extremely soft rock formations, ensures the smooth progress of tunnel excavation, prevents grout leakage, forms a closed jet grouting curtain, and provides mechanical support and seepage prevention.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109707A_ABST
    Figure CN123109707A_ABST
Patent Text Reader

Abstract

This invention provides a method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support for water-rich, extremely soft rock tunnels, relating to the field of tunnel and underground engineering construction technology. The method includes: constructing a grout-stopping wall at the tunnel face and arranging grouting holes radially; segmenting the grouting holes, with the near-end segment using segmented forward grouting for low-pressure filling, and the far-end segment using a sleeve valve bundle of long and short pipes for high-pressure splitting grouting; implementing grouting in the order of first the waterless area and then the water-bearing area, and first the inner ring and then the outer ring; after the grouting holes have solidified, constructing interlocking multi-ring horizontal jet grouting piles around the tunnel outline to form a closed curtain body, and constructing a pipe roof at the outer ring axis. This invention forms a composite pre-support body with both seepage prevention and load-bearing physical properties around the tunnel excavation outline, improving the self-stabilizing capacity of the surrounding rock.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel and underground engineering construction technology, and in particular to a method for pre-support of water-rich, extremely soft rock tunnels using a combination of segmented splitting curtain grouting and horizontal jet grouting. Background Technology

[0002] With the continuous advancement of transportation infrastructure construction, tunnel projects often need to traverse complex geological environments. When encountering water-rich, extremely soft rock strata, the surrounding rock is mainly composed of fault gouge and mylonite. These rock masses have physical properties such as softening and disintegration upon contact with water, and generally low permeability and porosity. Simultaneously, due to the cavity structure and penetrating fractures formed by repeated groundwater activity, the strata have poor self-stabilizing capacity. Tunnel excavation under these geological conditions easily induces geological risks such as mudslides and water inrushes. Conventional single grouting reinforcement methods are insufficient when facing rock masses with varying degrees of looseness ahead of the tunnel face. This makes it difficult to simultaneously address the low-pressure filling of shallow cavities and the high-pressure fracturing and seepage of deep micro-fractures, easily leading to grout backflow and leakage to the tunnel face or inadequate seepage prevention. Single pre-support measures are difficult to drill in water-rich, fluid-plastic strata, making it difficult to independently form a closed shell that can both block water and provide mechanical support. This results in the inability to effectively constrain unloading displacement during excavation, failing to fully meet the safe construction requirements of extra-long tunnels crossing fault zones. Summary of the Invention

[0003] This invention aims to provide a composite pre-support method for segmented split curtain grouting and horizontal jet grouting in water-rich, extremely soft rock tunnels, in order to solve the technical problems faced by tunnel excavation in water-rich, extremely soft rock strata, such as easy instability of the tunnel face, high risk of mud and water inrush, and the difficulty of forming an effective anti-seepage and bearing structure by conventional single support methods.

[0004] This invention provides a method for pre-support of water-rich, extremely soft rock tunnels using segmented splitting curtain grouting and horizontal jet grouting, comprising the following steps:

[0005] S1. Construction and layout of grouting wall: A grouting wall is constructed at the tunnel face, and multiple grouting holes are arranged radially along the grouting wall in the excavation direction.

[0006] S2. Segmented split curtain grouting: The grouting hole is divided into a proximal segment close to the working face and a distal segment away from the working face along the depth direction; the proximal segment is filled and reinforced with low pressure using segmented forward grouting; after the grouting of the proximal segment is completed, a sleeve valve tube bundle including a combination of long and short tubes is inserted into the grouting hole, and the sleeve valve tube bundle is used to perform high-pressure split grouting on the distal segment;

[0007] S3. Grouting sequence control: Following the principle of first the dry area and then the wet area, and first the inner ring and then the outer ring, the segmented split curtain grouting is carried out on each of the grouting holes in sequence.

[0008] S4. Jet grouting combined construction: After the grouting of the injection holes is completed and reaches the consolidation state, interlocking multi-ring horizontal jet grouting piles are constructed around the outline of the tunnel to form a closed jet grouting curtain, and pipe roof is constructed at the axial position of the horizontal jet grouting piles on the outer ring.

[0009] Optionally, in step S1, the plurality of grouting holes are arranged in inner and outer rings, and the grouting holes in each ring are arranged in a staggered quincunx pattern.

[0010] Optionally, in step S2, the grouting pressure when filling and reinforcing the proximal segment is less than the grouting pressure when performing high-pressure fracturing grouting on the distal segment.

[0011] Optionally, in step S2, the sleeve valve tube bundle of the long and short tube combination includes at least one short tube and at least one long tube;

[0012] The length of the short pipe matches the depth of the proximal section, and is used to perform a grout-stopping seal on the proximal section;

[0013] The long pipe extends to the full length of the grouting hole, and the long pipe is provided with multiple rows of sleeve valve holes in the effective grouting section corresponding to the distal section.

[0014] The sleeve valve tube bundle, as a rigid skeleton, is retained in the grouting hole and together with the surrounding strata forms an anchoring structure.

[0015] Optionally, in step S3, the grouting sequence control also includes a sequential principle: the grouting holes in the same ring are constructed sequentially in an intermittent skipping manner; after the grouting holes in the inner ring form a preliminary solidified body, the grouting holes in the outer ring are then grouted, so as to provide lateral constraint for the grouting of the outer ring through the preliminary solidified body.

[0016] Optionally, in step S4, the multi-ring horizontal jet grouting pile includes an outer ring jet grouting pile and an inner ring jet grouting pile; the sequence of the jet grouting collaborative construction is as follows: first construct the outer ring jet grouting pile, after the outer ring jet grouting pile is constructed, construct the pipe roof at the axial position of the outer ring jet grouting pile, and finally construct the inner ring jet grouting pile.

[0017] Optionally, if the drill gets stuck at a predetermined depth during the construction of the horizontal jet grouting pile, a segmented jet grouting strategy is adopted: first, the front section of the jet grouting pile, which is closer to the working face, is constructed; after draining the accumulated water and fine particles from the duct, the rear section of the jet grouting pile is constructed up to the designed pile length.

[0018] Optionally, the grouting termination criteria for the grouting holes adopt a dual-control principle: the first sequence hole is controlled according to the grouting volume; the second sequence hole is controlled according to the grouting pressure. Grouting ends when the grouting pressure of the second sequence hole reaches the design value and the grout injection volume per unit time drops below the preset threshold and is maintained for a set time.

[0019] Optionally, after the segmented split curtain grouting is completed, water-rich and weak areas in the formation are identified by combining grouting and probing, and auxiliary grouting holes are added in the water-rich and weak areas to carry out reinforcement grouting.

[0020] Optionally, the grouting material used in the segmented split curtain grouting is a two-component grout made of cement and water glass. During the grouting process, the ratio of cement slurry to water glass in the two-component grout and the gelation time of the two-component grout are dynamically adjusted according to the water-richness and porosity of the formation. The gelation time is shortened in areas with high water outflow.

[0021] The present invention has achieved the following beneficial effects:

[0022] This invention employs segmented and differentiated treatment of the grout-stopping wall construction and grouting holes. In the near-end section, low-pressure filling reinforcement is used to expel internal air and free water, forming a pressure-resistant grout-stopping body. In the far-end section, high-pressure fracturing grouting is performed using sleeve valve bundles, forcing the grout into the fractured surface of the surrounding rock to form a network-like grout vein structure. Combined with the controlled grouting sequence of first the waterless area and then the water-bearing area, and first the inner ring and then the outer ring, radial contraction flow of the grout towards the tunnel axis is restricted. Based on this, multi-ring horizontal jet grouting piles and pipe roofs are constructed in synergy to form a closed jet grouting curtain. The sleeve valve bundles, as a rigid skeleton, remain within the holes, forming an anchoring structure with the surrounding strata. This combined implementation of the steps of the invention constructs a composite pre-support structure with both seepage prevention and load-bearing properties around the tunnel excavation outline, constraining unloading displacement during stratum excavation, improving the overall mechanical properties of extremely soft rock strata, and ensuring the smooth progress of subsequent excavation operations.

[0023] Other features and advantages of the invention will be set forth in the following description, and will be apparent in part from the description, or may be learned by practicing the invention. The objects and other advantages of the invention may be realized and obtained by means of the structures particularly pointed out in the written description and the accompanying drawings.

[0024] The technical solution of the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Attached Figure Description

[0025] The accompanying drawings are provided to further illustrate the invention and form part of the specification. They are used in conjunction with embodiments of the invention to explain the invention and do not constitute a limitation thereof. In the drawings:

[0026] Figure 1 This is an overall flowchart of the method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support for water-rich, extremely soft rock tunnels according to an embodiment of the present invention.

[0027] Figure 2 This is a block diagram of the segmented structure and sleeve valve bundle structure of a single grouting hole along the depth direction in an embodiment of the present invention;

[0028] Figure 3 This is a flowchart illustrating the control logic for dynamically adjusting the parameters of the dual-liquid slurry material based on the effluent flow rate, as described in an embodiment of the present invention.

[0029] Figure 4 This is a flowchart illustrating the control logic of the dual-control principle for grouting completion standards in an embodiment of the present invention.

[0030] Figure 5 This is a flowchart illustrating the construction sequence of multi-ring horizontal jet grouting piles and pipe roofs in an embodiment of the present invention.

[0031] Figure 6 This is a flowchart illustrating the triggering and execution process of the segmented rotary jetting strategy for preventing stuck drill pipe in an embodiment of the present invention. Detailed Implementation

[0032] The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are for illustration and explanation only and are not intended to limit the present invention.

[0033] For water-rich, extremely soft rock tunnels, specifically, the surrounding rock in such strata is mainly composed of fault gouge and mylonite. Its physical properties include softening and disintegration upon contact with water, low permeability, low porosity, and localized cavities and interconnected fractures formed by repeated groundwater activity. The implementation of the segmented split curtain grouting and horizontal jet grouting composite pre-support method for water-rich, extremely soft rock tunnels relies on the combined configuration of grouting pressure range, grouting hole spatial layout, grouting sequence control, and horizontal jet grouting spatial structure to form a composite pre-support body with both seepage prevention and load-bearing properties outside the tunnel excavation outline.

[0034] like Figure 1 As shown, the first step in implementing this composite pre-support method is to construct the grout stop wall and lay out the boreholes. The grout stop wall is constructed at the tunnel face. Specifically, the grout stop wall is located behind the tunnel face, with a thickness of no less than 1 meter. The grout stop wall is cast in concrete, covering the entire excavated section of the tunnel, and its edge area is rigidly connected to the existing initial support structure via anchoring or welding. The grout stop wall serves as a spatial water-retaining structure and a reaction structure against subsequent grouting pressure, resisting the normal thrust generated by the grout in the tunnel face direction during the grouting stage.

[0035] After the grout stop wall is constructed and reaches its design strength, the grouting hole layout is carried out. Multiple grouting holes are radially arranged along the backwater side of the grout stop wall (i.e., the side facing the excavation direction). The spatial layout of the grouting holes is defined as follows: along the upper half of the tunnel face, within a central angle of not less than 180°, the holes are arranged in multiple inner and outer rings. The grouting holes within each ring are arranged in a staggered, quincunx pattern. This staggered, quincunx arrangement means that the angular positions of the grouting holes in adjacent rings are staggered in polar coordinates, so that after the grout diffuses in a columnar shape, the diffusing cylinders form overlapping and converging geometric boundaries in three-dimensional space.

[0036] In terms of drilling equipment configuration and operation, the borehole diameter for grouting holes is set at 110mm. Based on the formation permeability determined through theoretical calculations and on-site pumping tests, the design grout diffusion radius for each grouting hole is calibrated to be between 1.0m and 1.5m. Based on this diffusion radius value, the straight-line spacing of the hole bottoms in the circumferential direction is configured to be no greater than 3.0m to meet the overlap requirements of the grout diffusion areas of adjacent grouting holes. The radial range of the grouting reinforcement is configured to extend 6m beyond the tunnel excavation outline, and the hole depth is set according to the advance support cycle length.

[0037] After the grouting holes are drilled, the segmented splitting curtain grouting process is executed. For example... Figure 2 As shown, based on the physical law of the change in the looseness of the rock mass surrounding the borehole wall with the depth from the working face, a single grouting hole is divided into two grouting process sections along the depth direction: a proximal section close to the working face and a distal section far from the working face. Specifically, the depth range of the proximal section is defined as 0 to 10m from the grout stop wall; the depth range of the distal section is defined as more than 10m from the grout stop wall up to the end position of the grouting hole (i.e., the front end of the designed grout stop plate).

[0038] For the near-end section, segmented forward grouting was used for low-pressure filling and reinforcement. The surrounding rock in this area, disturbed by previous excavation and geological activity, is highly loose with large pore volumes. The specific execution logic of segmented forward grouting is as follows: after drilling a certain distance, the drill is withdrawn for grouting; once the grout reaches its initial setting state, the next segment is drilled. The length of each grouting segment is controlled within the range of 5m to 6m. During this stage, the grouting pump is operated, and the grouting pressure parameters are strictly limited to the range of 0 to 6MPa. Under this pressure gradient, the grout is mainly driven by its own gravity and low pressure difference, permeating and filling the gaps between loose particles and macroscopic cavities. By controlling the matching of pump flow rate and pressure, the grout occupies the cavity volume, displacing internal air and free water. After the near-end section is grouted and consolidated, the loose rock mass within 10m of the front section of the duct is cemented, forming a pressure-resistant grout-stopping body in space, which is used to block the physical channel for grout to flow back and leak towards the working face during subsequent high-pressure grouting.

[0039] After the near-end section is filled and reinforced and reaches a consolidated state, high-pressure fracturing grouting is performed on the far-end section. The surrounding rock corresponding to the far-end section is relatively dense with fewer macroscopic pores, mainly existing in the form of micro-fractures. Before grouting the far-end section, a sleeve valve tube bundle consisting of a combination of long and short tubes is inserted into the grouting hole. Specifically, the sleeve valve tube bundle is composed of at least one short tube and at least one long tube, with 2 to 3 tubes inserted into each grouting hole. The geometric length of the short tube matches the depth of the near-end section (i.e., 10m). After insertion, the short tube is connected to the near-end section hole wall through a hole sealing device and a casing material to seal the near-end section. The geometric length of the long tube extends to the full length of the grouting hole, and the section of the long tube corresponding to the far-end section in space is defined as the effective grouting section. Multiple rows of sleeve valve holes are opened at certain intervals on the tube wall of the effective grouting section. The diameter of the sleeve valve orifice is configured to be 8mm to 12mm, and the longitudinal center-to-center distance between adjacent sleeve valve orifices is configured to be no more than 30cm. A grouting core tube with a bidirectional sealing plug is inserted into the long tube, and the grouting outlet of the grouting core tube is positioned at the specific sleeve valve orifice position.

[0040] The grouting pump is activated, raising the grouting pressure to between 6 MPa and 12 MPa. Under this high-pressure environment, the grout pushes open the rubber sleeve outside the sleeve valve orifice, breaking through the casing material and entering the surrounding rock. When the tangential tensile stress generated by hydraulic pressure exceeds the sum of the tensile strength and minimum principal stress of the extremely soft rock in its original state, tensile or shear fractures occur inside the surrounding rock. The grout is forcibly squeezed in along these fracture surfaces, forming a network-like grout vein structure; this process is known as high-pressure fracturing grouting. Furthermore, the sleeve valve tube bundle, composed of long and short tubes inserted into the hole, possesses rigid support characteristics and remains as a rigid framework within the grouting hole after the grouting process is completed. The cement-aggregate body, the sleeve valve tube bundle, and the surrounding strata mechanically combine to form an anchoring structure, providing resistance to shear and pull-out forces, thereby constraining the unloading displacement during the excavation process.

[0041] Throughout the segmented split curtain grouting process, a two-component grout made of cement and water glass was used as the grouting material. Specifically, P.O42.5 ordinary Portland cement was used, and the modulus parameter of the water glass was defined as 2.8 to 3.1, and the concentration parameter was configured as 35 Bé. In the grouting system, the water-cement ratio of the cement grout was set to 0.8:1. In the two-component grout mixing device, the volume ratio of cement grout to water glass was configured within the range of 1:0.3 to 1:0.8. The material parameters were dynamically adjusted based on the physical feedback of the formation: according to the formation water abundance and outflow velocity measured by the water exploration borehole or pilot borehole, the mixing ratio was adjusted in real time to control the gelation time of the two-component grout between 12s and 60s. When a large outflow of water and a high groundwater velocity are detected in the target area, the system increases the proportion of water glass injection and shortens the gelation time of the two-liquid slurry. This promotes the rapid formation of calcium silicate hydration gel reaction in the slurry after it comes into contact with water, preventing the slurry from being diluted and lost by passive water. In areas with well-developed pores but stagnant water flow, the proportion of water glass is reduced and the gelation time is extended to ensure the diffusion radius.

[0042] like Figure 3 As shown, specifically, the dynamic adjustment of the ratio of cement slurry to water glass in the two-liquid slurry based on the formation's water-richness and porosity characteristics employs a graded control threshold strategy based on the outflow velocity.

[0043] Calibration values ​​of groundwater outflow velocity measured from the pilot borehole (Unit: m / min), establish the following exact correspondence:

[0044] when When the flow rate is m / min (determined to be a still or slightly wet area), the scouring effect of the water flow on the slurry is minimal. The volume ratio of the two-component slurry is set between 1:0.3 and 1:0.4 to maintain the gelation time at 50s to 60s, thereby maximizing the effective diffusion radius of the slurry.

[0045] when When the flow rate is m / min (determined to be in the medium dynamic water zone), a medium anti-scouring strategy is activated, the volume ratio is increased and set between 1:0.5 and 1:0.6, and the gelation time is controlled between 30s and 40s.

[0046] when When the flow rate is m / min (in areas with strong turbulent water flow and large outflow), the water flow can easily cause the slurry to be lost. By forcibly setting the volume ratio between 1:0.7 and 1:0.8, the gelation time is shortened to 12s to 20s, achieving immediate gelation and erosion resistance upon contact with water.

[0047] The grouting operation timeline is strictly arranged according to the grouting sequence control principle. The overall principle is to proceed from the waterless area to the water-bearing area, and from the inner ring to the outer ring. The spatial distribution coordinates of the aquifer ahead of the tunnel face are obtained through preliminary geophysical exploration or core drilling data. Grouting equipment is prioritized for execution at holes in the waterless area, followed by advancement towards the water-bearing area. In the circumferential sequence, grouting is prioritized for the inner ring holes. Once the grout in the inner ring has solidified and formed a preliminary solidified body with a certain compressive strength, grouting is then transferred to the outer ring holes. The presence of the preliminary solidified body in the inner ring provides lateral physical constraint boundary conditions for the high-pressure fracturing of the grout in the outer ring, limiting ineffective radial contraction flow of the grout in the outer ring towards the tunnel axis.

[0048] Furthermore, for grouting holes within the same ring, a sequential principle is applied. The grouting holes are numbered as first-sequence holes, second-sequence holes (and even third-sequence holes), and constructed sequentially using an alternating skip-hole method. Specifically, drilling and grouting operations are performed every one or two holes along the ring, avoiding concentrated stress release in the surrounding rock and cross-grouting between holes caused by continuous drilling. During the grouting process, the system generates a three-dimensional mapping model of the reinforced body based on the grouting pressure-flow data of each hole. Through a combination of exploration and grouting verification, water-rich and weak areas in the strata that fail to meet the design seepage prevention standards are identified (primarily distributed in the 10 o'clock to 2 o'clock direction of the arch crown in the fault core area).

[0049] To avoid over-reliance on complex digital models, this method uses clear engineering quantification criteria to determine water-rich, weak areas that fail to meet design seepage prevention standards:

[0050] During the grouting process at each grouting hole, the grouting pressure at the final pressure state is collected in real time. (Unit: MPa) and stable grouting flow rate (Unit: L / min), and calculate the length of the grouting section in a single hole. (Unit: m) Permeability index per unit .

[0051] The baseline permeability threshold for achieving the design seepage prevention standard in extremely soft rock formations is obtained in advance through pressure water tests at pilot boreholes. During the grouting process, if the system identifies two or more adjacent grouting holes within a certain spatial coordinate range... The values ​​are all greater than And under constant grouting pressure, the flow rate If the divergence trend shows no convergence over time, the area where the spatial coordinates are located is directly defined as the water-rich and weak area through logical judgment, thereby triggering the instruction to add auxiliary grouting holes.

[0052] For water-rich and weak areas identified by the system, a densification hole layout command is output to add auxiliary grouting holes in the existing hole mesh gaps. Reinforcement grouting is then performed on these auxiliary grouting holes. The pressure and material parameters of the reinforcement grouting are consistent with those of the far end section until the grouting end standard of this area meets the set threshold.

[0053] like Figure 4 As shown, the determination of the grouting termination standard introduces a dual-control principle logic. The monitoring system collects the cumulative grouting volume, real-time grouting pressure, and instantaneous flow rate data for each grouting hole. For the first sequence hole, the system mainly performs logical control based on the grouting volume. When the cumulative grouting volume of a single hole, as counted by the flow meter, reaches the theoretically estimated volume value, the system issues a stop pumping command, ending the grouting of that hole.

[0054] Among them, the theoretical estimated volume value of the single hole The determination method is based on the derivation of volume filling theory, and its specific physical and mathematical calculation formula is as follows:

[0055] ;

[0056] In the formula, The theoretically estimated slurry diffusion radius (set to 1.0m to 1.5m based on the aforementioned formation permeability). This is the effective grouting section length of the hole (10m for the near end section, and the length of the far end section is determined based on the actual hole depth). The effective porosity of the extremely soft rock formation was determined through previous core drilling. The slurry filling coefficient is set to a range of 0.75 to 0.90 due to varying degrees of formation looseness. The value is the slurry loss and depletion coefficient during construction, ranging from 0.1 to 0.2.

[0057] For the second-order borehole (and the additional auxiliary grouting boreholes), the system performs logical control based on the grouting pressure. The specific judgment condition is as follows: when the real-time grouting pressure collected by the borehole pressure sensor reaches the design upper limit (6MPa or 12MPa), and the grout injection volume per unit time monitored by the flow meter drops to less than the preset threshold (1L / (min·m)), and this high-pressure, low-flow physical state is maintained for no less than 10 minutes on the time axis, the system determines that the formation pores have been compacted and filled, and outputs a grouting end signal for that borehole.

[0058] After grouting in the aforementioned injection holes is completed and reaches a solidified state (the two-liquid grout has completed its hardening period), the physical and mechanical properties of the stratum change, transforming from an extremely soft, fluid-plastic state to a solidified body with a certain bearing capacity. At this point, jet grouting is implemented in conjunction with other construction, constructing interlocking multi-ring horizontal jet grouting piles around the tunnel's outline. The spatial distribution of these multi-ring horizontal jet grouting piles covers a fan-shaped area of ​​at least 220° around the tunnel arch and sidewalls. In terms of parameter configuration, the borehole diameter of the horizontal jet grouting drill is 110mm, and after high-pressure water / grout flow cutting and mixing, the designed pile diameter reaches 600mm. Through coordinate system control, the ends of adjacent jet grouting piles are geometrically tangent or intersecting in the circumferential direction.

[0059] When operating the horizontal jet grouting equipment, set the jet grouting pressure of the high-pressure generator to the range of 35MPa to 40MPa. Maintain the cement slurry cutting flow rate output through the nozzle at 50L / min to 90L / min. Configure the rotation speed of the drill rod driven by the drill rig's power head to 10r / min to 20r / min, and the linear retraction speed of the drill rod to 15cm / min to 30cm / min. Set the water-cement ratio of the jet grouting cement slurry to 1:1, and control the minimum cement usage per meter of single pile to be no less than 300kg / m through the batching system.

[0060] like Figure 5 As shown, the jet grouting construction proceeds in a specific spatial sequence. The multi-ring horizontal jet grouting piles consist of two layers: an outer ring and an inner ring. During operation, the control equipment first constructs the outer ring jet grouting piles on the outer contour coordinates, advancing symmetrically from the central hole at the arch top to the left and right sides. After the outer ring jet grouting pile group is completed and the first hard shell is formed on the periphery, the pipe roof drilling rig is started to drill holes at the geometric axis of each outer ring jet grouting pile, and the pipe roof is driven in. The pipe roof is made of steel pipe with an outer diameter of 108mm, a wall thickness of 6mm, and a drilling diameter of 110mm. After the steel pipe is inserted, grout is injected into the pipe, so that the steel pipe roof and the surrounding cement-soil jet grouting piles form a combined bending-resistant structure. After the pipe roof is completed, the jet grouting equipment is controlled to return to the inner ring coordinates to construct the inner ring jet grouting piles, ultimately forming a closed jet grouting curtain.

[0061] Due to the nonlinear increase in friction and slurry discharge resistance in deep strata, if the drilling tool experiences a surge in torque at a predetermined depth (e.g., more than 14m from the face) due to blockage of strata interlayers or slag discharge channels during the construction of horizontal jet grouting piles, resulting in a stuck drill, the segmented jet grouting strategy will be triggered.

[0062] like Figure 6 As shown, specifically, the torque surge that triggers the segmented rotary injection strategy has a clear system control logic:

[0063] A torque sensor is installed at the power head of the rotary jet grouting machine to record the benchmark operating torque in normal homogeneous extremely soft rock formations at the front section of drill pipe advance (e.g., within 0 to 5 meters of the working face). During subsequent advancements, the system collects dynamic torque data in real time. .

[0064] The system determines that a stuck drill warning has occurred and automatically triggers the segmented rotary jetting strategy when one of the following two conditions is met:

[0065] Instantaneous torque absolute value exceeding the limit: Real-time dynamic torque Exceeding the benchmark operating torque for 3 to 5 consecutive seconds 150%;

[0066] Torque change rate exceeding limit: Torque increase rate per unit time Exceeding the preset safety gradient threshold (indicating a sudden encounter with a hard interlayer or a large area of ​​seizure within the hole).

[0067] The introduction of this quantitative triggering mechanism avoids the drill pipe being forcibly twisted off under the diameter reduction effect of extremely soft rock, thus ensuring the continuity of construction of extra-long hole horizontal jet grouting.

[0068] The system instructs the drilling rig to stop feeding, dividing the construction of a single horizontal jet grouting pile into two phases. First, the initial section of the jet grouting pile (e.g., the 0-14m section) closer to the working face is constructed. After the cutting and mixing of this initial section is completed, a high-flow-rate cleaning pump is started to replace and discharge the accumulated waste mud, water, and fine particles generated during cutting from the borehole. Once the pressure inside the borehole is released and the slag discharge channel is clear, the drilling tool is advanced again beyond the 14m limit to construct the subsequent section of the jet grouting pile to the designed pile length.

[0069] To quantitatively evaluate the effectiveness of the composite pre-support, after the completion of each ring of jet grouting and curtain grouting, an in-hole television camera was used to conduct optical imaging scans of the pile quality inside the borehole, and core samples were extracted in the field using a core drilling rig. The extracted core samples had to meet the integrity requirements, and their unconfined compressive strength and permeability coefficient were tested.

[0070] To ensure that the composite pre-support structure can effectively block water and provide mechanical support, the quantitative assessment has the following specific engineering judgment thresholds as standards for acceptance and review:

[0071] Core integrity standard: The core recovery rate of the extracted core sample must be no less than 85%, and the rock mass quality index (RQD, i.e., the percentage of the cumulative length of the core with a length greater than 10cm to the total length of the borehole) must reach more than 60%, which indicates that the grout and fault gouge have been fully compacted and cemented.

[0072] Mechanical and seepage prevention standards: After 28 days of curing, the unconfined compressive strength of the core sample must reach 1.5 MPa to 3.0 MPa, and the permeability coefficient must decrease to [missing value]. Below cm / s;

[0073] Geometric standards for pile formation: If the three-dimensional point cloud data extracted by the in-hole television camera is used to identify a section with a continuous length of more than 0.5m where the actual diameter of the jet grouting pile is less than 90% of the designed pile diameter (600mm) (i.e. less than 540mm), or if a through-hole water bladder interlayer is found between the grouting solidified body and the jet grouting pile, then a non-compliance judgment signal is triggered.

[0074] If the imaging screen shows that the pile diameter does not meet the standard or the core sampling reveals a local discontinuity, the area is deemed unqualified. A jet grouting drill is then operated at the unqualified coordinates to carry out re-jetting reinforcement until all physical test indicators meet the design specifications before subsequent tunnel earthwork excavation operations are permitted.

[0075] The above process is illustrated numerically using a treatment example of a particularly long tunnel exit section. This tunnel exit section traverses a compressive-shear active fault, with a fault fracture zone core area approximately 280m wide. The surrounding rock material is mylonite and fault gouge, exhibiting a soft plastic to fluid plastic state, and is classified as Class V surrounding rock in the engineering assessment. The daily inflow of confined fissure water is monitored at 1100 to 2300 cubic meters, and the tunnel depth is approximately 400m. Historical data retrieved from the system show that mudslides and water inrushes have occurred in this work area, forming a mixed zone of deposits and cavities ahead of the tunnel face.

[0076] First, the construction equipment was positioned approximately 3 meters behind the working face, and C30 grade concrete was poured to form a 1-meter-thick grout stop wall. The grout stop wall was then welded and locked to the installed initial support steel arch. Next, grouting holes were arranged in an umbrella-shaped radial pattern, with a total of 97 main holes in 6 rings. Drilling was performed using a 110mm drill bit, with the grouting hole depth set at 17 meters, including a 7-meter reserve at the end for the next cycle's grout stop rock mass. The circumferential spacing at the bottom of the holes was set to no more than 3.0 meters, with an estimated grout diffusion radius of 1.0 to 1.5 meters.

[0077] Construction proceeds to the near-end section (0 to 10m). A segmented grouting method is employed, with the drilling rig stopping every 5m and the grouting pump starting for low-pressure filling. The pressure sensor is set to a threshold of 0 to 6 MPa. The grouting station outputs a two-component grout with a water-cement ratio of 0.8:1, with a setting time controlled between 42 and 60 seconds. This stage fills the macroscopic cavities formed by previous disasters.

[0078] After filling to a depth of 10m, insert 2 to 3 sleeve valve tube bundles into each 17m deep hole. The tube bundle structure includes short tubes for grouting the 0-10m section, and long tubes extending into the 10m-17m distal section. The last 7m of the long tube has sleeve valve holes spaced longitudinally at intervals of less than 30cm along its wall. Start the high-pressure pump, increasing the pressure output to 6MPa-12MPa, and perform high-pressure fracturing grouting on the distal section.

[0079] In terms of the construction sequence scheduling of the grouting holes, the process proceeded from the inner circle to the outer circle, and from the waterless exploration area to the water-bearing area. After the grouting of all main holes reached the completion standard, 35 auxiliary holes were added to the residual water-rich area in the direction of 10 o'clock to 2 o'clock on the arch crown, and pressure grouting was carried out by pipe laying. According to records, this circulating curtain grouting operation took 59 days to complete, and the total volume of double-liquid grout injected by the flow meter was approximately 1902 cubic meters (1688 cubic meters from the main holes plus 214 cubic meters from the auxiliary holes).

[0080] After the grout solidified, the jet grouting rig was positioned. A total of 122 horizontal jet grouting piles were designed for the outer and inner rings. The designed pile diameter was 600mm and the length was 17m. The jet grouting pressure was set between 35MPa and 40MPa, and the retraction speed was set between 20 and 40cm / min. During the outer ring construction process, when the hole depth reached 15-17m, excessive torque was detected, causing the drill to jam. A segmented jet grouting strategy was immediately triggered. The first 0-14m section was grouted to drain high-pressure water and sediment from the hole, followed by re-pushing the drill rod to complete the remaining 14-17m section. After the outer ring was completed, a down-the-hole drill was used to drill a 110mm hole at the outer ring pile axis, and a 108mm steel pipe was inserted to form a pipe roof. Finally, the inner ring piles were constructed. This jet grouting process took 17 days.

[0081] In-hole imaging confirmed the continuous integration of the jet grouting piles and the grouting consolidation body. Excavation data revealed that the core soil jet grouting pile diameter reached 700 mm. During tunneling, the tunnel face remained dry and stable, achieving an effective advance of 12 m per cycle, with a total construction period of 71 days. This data confirms the safety and effectiveness of the physical load-bearing structure constructed based on this synergistic grouting and jet grouting process.

[0082] Obviously, those skilled in the art can make various modifications and variations to this invention without departing from its spirit and scope. Therefore, if these modifications and variations fall within the scope of the claims of this invention and their equivalents, this invention also intends to include these modifications and variations.

Claims

1. A method for pre-supporting water-rich, extremely soft rock tunnels using segmented splitting curtain grouting and horizontal jet grouting, characterized in that... Includes the following steps: S1. Construction and layout of grouting wall: A grouting wall is constructed at the tunnel face, and multiple grouting holes are arranged radially along the grouting wall in the excavation direction. S2. Segmented split curtain grouting: The grouting hole is divided into a proximal segment close to the working face and a distal segment away from the working face along the depth direction; the proximal segment is filled and reinforced with low pressure using segmented forward grouting; after the grouting of the proximal segment is completed, a sleeve valve tube bundle including a combination of long and short tubes is inserted into the grouting hole, and the sleeve valve tube bundle is used to perform high-pressure split grouting on the distal segment; S3. Grouting sequence control: Following the principle of first the dry area and then the wet area, and first the inner ring and then the outer ring, the segmented split curtain grouting is carried out on each of the grouting holes in sequence. S4. Jet grouting combined construction: After the grouting of the injection holes is completed and reaches the consolidation state, interlocking multi-ring horizontal jet grouting piles are constructed around the outline of the tunnel to form a closed jet grouting curtain, and pipe roof is constructed at the axial position of the horizontal jet grouting piles on the outer ring.

2. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, In step S1, the plurality of grouting holes are arranged in inner and outer rings, and the grouting holes in each ring are arranged in a staggered quincunx pattern.

3. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, In step S2, the grouting pressure when filling and reinforcing the proximal segment is less than the grouting pressure when performing high-pressure fracturing grouting on the distal segment.

4. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, In step S2, the sleeve valve tube bundle of the long and short tube combination includes at least one short tube and at least one long tube; The length of the short pipe matches the depth of the proximal section, and is used to perform a grout-stopping seal on the proximal section; The long pipe extends to the full length of the grouting hole, and the long pipe is provided with multiple rows of sleeve valve holes in the effective grouting section corresponding to the distal section. The sleeve valve tube bundle, as a rigid skeleton, is retained in the grouting hole and together with the surrounding strata forms an anchoring structure.

5. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, In step S3, the grouting sequence control also includes a sequence principle: The grouting holes within the same ring are constructed sequentially using an intermittent skipping method; After grouting is performed in the grouting holes of the inner ring to form a preliminary solidified body, grouting is then performed in the grouting holes of the outer ring to provide lateral constraint for the grouting of the outer ring through the preliminary solidified body.

6. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, In step S4, the multi-ring horizontal jet grouting pile includes an outer ring jet grouting pile and an inner ring jet grouting pile; The sequence of the jet grouting construction is as follows: first, the outer ring jet grouting piles are constructed; after the outer ring jet grouting piles are completed, the pipe roof is constructed at the axial position of the outer ring jet grouting piles; and finally, the inner ring jet grouting piles are constructed.

7. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 6, is characterized in that, If stuck drill occurs at the predetermined depth during the construction of the horizontal jet grouting piles, a segmented jet grouting strategy will be adopted: First, construct the front section of jet grouting piles that are closer to the working face. After draining the accumulated water and fine particles from the ducts, proceed with the construction of the rear section of jet grouting piles up to the designed pile length.

8. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, The grouting termination criteria for the grouting holes adopt a dual-control principle: the first sequence hole is controlled by the grouting volume; the second sequence hole is controlled by the grouting pressure. Grouting ends when the grouting pressure of the second sequence hole reaches the design value and the grout injection volume per unit time drops below the preset threshold and is maintained for a set time.

9. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, After the segmented split curtain grouting is completed, water-rich and weak areas in the formation are identified by combining exploration and injection, and auxiliary grouting holes are added in the water-rich and weak areas to carry out reinforcement grouting.

10. The method for segmented splitting curtain grouting and horizontal jet grouting composite pre-support of water-rich, extremely soft rock tunnels according to claim 1, characterized in that, The grouting material used in the segmented split curtain grouting is a two-component grout made of cement and water glass. During the grouting process, the ratio of cement slurry to water glass in the two-component grout and the gelation time of the two-component grout are dynamically adjusted according to the water-richness and porosity of the formation. The gelation time is shortened in areas with high water flow.