Digital twin-based photovoltaic project management and control methods, systems, devices and equipment
By integrating digital twin models with on-site sensing and monitoring data, the problem of low management efficiency caused by the independent deployment of photovoltaic project monitoring systems has been solved, and accurate anomaly identification and efficient management and control throughout the entire life cycle have been achieved.
Patent Information
- Application Number
- CN202611291570.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-24
- Publication Date
- 2026-11-17
AI Technical Summary
Photovoltaic projects use different monitoring systems deployed independently at different monitoring stages, such as construction, quality acceptance, and operation. The information collected on-site cannot be correlated with the relevant components and business information in the digital twin model of the photovoltaic project, resulting in low management efficiency.
The photovoltaic project management and control method based on digital twins obtains the target digital twin model of the photovoltaic project, combines the spatial range information of component units and compliance judgment rule data, realizes the accurate distribution of monitoring tasks and automatic identification of anomalies, and establishes the data link between the digital twin model and the on-site perception and monitoring data to uniformly complete the automatic identification of anomalies.
It has significantly improved the efficiency of quality, safety, progress and equipment fault identification throughout the entire life cycle of photovoltaic projects, gotten rid of the inefficient mode of manual comparison, and achieved precise control over construction, acceptance and operation.
Smart Images

Figure CN123117533A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of electronic technology, and more specifically to a method, system, device, and equipment for managing photovoltaic projects based on digital twins. Background Technology
[0002] Large-scale desert photovoltaic projects cover a wide area, involve a large amount of equipment, and have a tight construction schedule. They also involve the collaborative work of multiple professional and international teams. There are a large number of photovoltaic arrays, cables, inverters and other equipment on site. The control of on-site construction quality, operation safety, construction progress and material cost is extremely difficult. It is necessary to rely on digital means to achieve refined management and control of the whole process.
[0003] In related technologies, photovoltaic projects use different monitoring systems to be deployed and operated independently at different monitoring stages such as construction, quality acceptance and operation. The information collected on site cannot be correlated with the relevant components and business information in the digital twin model of the photovoltaic project. Impact analysis such as construction progress identification, quality defect identification, safety violation identification and equipment commissioning fault diagnosis mainly rely on manual comparison, resulting in low management efficiency. Summary of the Invention
[0004] This invention provides a method, system, device, and equipment for photovoltaic project management based on digital twins, in order to solve the problem that in related technologies, different monitoring systems are deployed and operated independently at different monitoring stages, the information collected on site cannot be correlated with relevant components and business information in the digital twin model of the photovoltaic project, and the impact analysis mainly relies on manual comparison, resulting in low management efficiency.
[0005] In a first aspect, the present invention provides a photovoltaic project management and control method based on digital twins. The method includes: acquiring a target digital twin model of the photovoltaic project, the target digital twin model including multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. Each component unit corresponds one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include construction monitoring, quality acceptance monitoring, and operation monitoring. Based on preset photovoltaic project management and control requirement information, at least one monitoring task corresponding to each component unit is determined. The preset photovoltaic project management and control requirement information is used to characterize any one of the management and control requirement information for the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. The monitoring tasks of each component unit are distributed to a monitoring module, so that the monitoring module executes the monitoring tasks and obtains monitoring data corresponding to each component unit. The monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information are input into a pre-constructed quality and safety identification module, so that the quality and safety identification module outputs the anomaly identification result of the corresponding component unit.
[0006] The photovoltaic project management and control method based on digital twins provided by this invention addresses the shortcomings of related technologies, such as the independent deployment of monitoring systems at each stage of photovoltaic projects, the inability to link monitoring data with digital twin components and business information, and the reliance on manual comparison for various anomaly identifications, which leads to inefficient management and control. Based on a photovoltaic digital twin model that integrates full-cycle compliance judgment rules, it uses component units corresponding to physical facilities as carriers to match phased monitoring tasks. This enables the accurate distribution of monitoring tasks to the monitoring modules to collect corresponding component data. Then, by combining component spatial information with phased compliance rules, it unifies and automatically identifies anomalies. This establishes a data link between the digital twin model and on-site perception and monitoring data, eliminating the inefficient mode of manual comparison. It can simultaneously cover the full-cycle management and control needs of construction, acceptance, and operation, significantly improving the identification efficiency and control accuracy of photovoltaic project quality, safety, progress, and equipment failures.
[0007] In an optional implementation, the method further includes associating the anomaly identification results of each component unit with the target digital twin model.
[0008] The method provided by this optional implementation directly maps the component anomaly identification results to the corresponding spatial location of the digital twin model, intuitively presenting the area where the fault or defect is located and the physical facility, breaking down the information barrier between monitoring data and three-dimensional models, and facilitating managers to quickly locate problematic components.
[0009] In one optional implementation, the step of obtaining the target digital twin model of a photovoltaic project includes: obtaining a full lifecycle business dataset and photovoltaic project design data; constructing an initial digital twin model of the photovoltaic project based on the photovoltaic project design data, the initial digital twin model including multiple component units and the coding information of each component unit; decomposing the full lifecycle business dataset according to the multiple component units to obtain the business data corresponding to each component unit; and mapping the business data of the multiple component units to the digital twin model based on the coding information of each component unit to obtain the target digital twin model.
[0010] The method provided by this optional implementation method builds an initial digital twin model with a unique code based on design data, splits the full life cycle business data by component unit and completes the data mapping through coding, so that each component unit in the model is bound to the corresponding full life cycle business information, opens up the data channels of design, construction, acceptance and operation, solves the problem of traditional technology business data and three-dimensional model being mutually isolated and unable to accurately match components, and provides a complete and unified data foundation for subsequent phased monitoring and component-level anomaly identification.
[0011] In one optional implementation, an initial digital twin model of the photovoltaic project is constructed based on the photovoltaic project design data, including: constructing a three-dimensional design model of the photovoltaic project based on the photovoltaic project design data, wherein the three-dimensional design model is used to characterize the full-dimensional design element information and engineering quantity information of the engineering spatial entity facilities in the photovoltaic project; structurally decomposing the three-dimensional design model to obtain multiple component units; encoding each component unit to obtain the corresponding component unit encoding information; and writing the encoding information of multiple component units into the three-dimensional design model to obtain the initial digital twin model of the photovoltaic project.
[0012] The method provided by this optional implementation method is to build a three-dimensional model by carrying complete spatial and engineering quantity information in the design data, and then to decompose the model into components by structure and assign independent codes to write into the model, so as to realize the one-to-one binding of physical facilities, three-dimensional model components and unique codes, and to establish a standardized component index system from the source. This provides a unified data benchmark for the accurate mounting of subsequent full life cycle business data, the automatic association of monitoring data with components, and the phased anomaly location, and solves the problems of traditional BIM models lacking unique component identifiers and various business data not being able to accurately correspond to physical facilities.
[0013] In an optional implementation, when the preset photovoltaic project management and control requirements information is the management and control requirements information for the operation monitoring stage, the above method further includes: if it is determined that the operation monitoring data of the target component is abnormal based on the anomaly identification result, obtaining the inspection image data of the physical facility corresponding to the target component; performing appearance anomaly identification on the inspection image data to obtain the image recognition result; if it is determined that the appearance of the target component is abnormal based on the image recognition result, then pushing the defect elimination work order of the target component to the first target terminal; if it is determined that the appearance of the target component is not abnormal based on the image recognition result, then pushing the manual electrical inspection task to the second target terminal.
[0014] The method provided by this optional implementation method enables hierarchical diagnosis of component data anomalies during photovoltaic operation. It first retrieves inspection images to perform appearance recognition to distinguish fault types. Appearance defects are directly assigned to eliminate work orders, while no appearance problems are pushed to push electrical testing tasks. This avoids maintenance personnel blindly going to the site to investigate, accurately distinguishes fault handling paths, shortens the fault location and elimination cycle of photovoltaic equipment, and improves the efficiency of power plant operation and maintenance.
[0015] Secondly, the present invention provides a photovoltaic project management and control system based on digital twins. The system includes: a monitoring module and a photovoltaic project management and control platform; the monitoring module includes multiple monitoring devices, including at least one drone, at least one robot, at least one camera, at least one smart safety helmet, and at least one photovoltaic operation monitoring device; the photovoltaic project management and control platform is communicatively connected to the multiple monitoring devices and is used to execute the photovoltaic project management and control method based on digital twins of the first aspect or any corresponding embodiment described above.
[0016] The photovoltaic project management and control system based on digital twin provided by this invention integrates multiple sensing terminals such as drones, inspection robots, cameras, smart safety helmets, and photovoltaic operation monitoring equipment to form an air-ground collaborative monitoring module. It uniformly connects to the management and control platform to implement the full-cycle digital twin management and control logic. Various types of on-site collected data can be synchronously associated with model components to achieve automated anomaly identification without the need for manual cross-system comparison. It takes into account the monitoring capabilities of the entire construction, acceptance, and operation stages, and realizes the integration of multi-dimensional perception, intelligent judgment, and closed-loop management and control of photovoltaic projects, significantly reducing the manual management and control costs of large-scale photovoltaic projects.
[0017] Thirdly, the present invention provides a photovoltaic project management and control device based on digital twins. The device includes: a first acquisition module, used to acquire a target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. Each component unit corresponds one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include construction monitoring, quality acceptance monitoring, and operation monitoring. A first determination module, used to determine at least one monitoring task corresponding to each component unit based on preset photovoltaic project management and control requirement information. The preset photovoltaic project management and control requirement information represents any one of the management and control requirement information for the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. A second determination module, used to distribute the monitoring tasks of each component unit to a monitoring module, so that the monitoring module executes the monitoring tasks and obtains monitoring data corresponding to each component unit. A third determination module, used to input the monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information into a pre-constructed quality and safety identification module, so that the quality and safety identification module outputs the anomaly identification result of the corresponding component unit.
[0018] Fourthly, the present invention provides an electronic device, comprising: a memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the computer instructions to perform the photovoltaic project management method based on digital twin described in the first aspect or any corresponding embodiment.
[0019] Fifthly, the present invention provides a computer-readable storage medium storing computer instructions for causing a computer to execute the digital twin-based photovoltaic project management method described in the first aspect or any corresponding embodiment thereof.
[0020] In a sixth aspect, the present invention provides a computer program product, including computer instructions for causing a computer to execute the photovoltaic project management and control method based on digital twins as described in the first aspect or any corresponding embodiment thereof. Attached Figure Description
[0021] To more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.
[0022] Figure 1 This is a schematic diagram of an application scenario according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the first process of a photovoltaic project management and control method based on digital twins according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the second process of the photovoltaic project management and control method based on digital twin according to an embodiment of the present invention; Figure 4 This is a schematic diagram of the third process of the photovoltaic project management and control method based on digital twin according to an embodiment of the present invention; Figure 5 This is a schematic diagram of a photovoltaic project management and control system based on digital twins according to an embodiment of the present invention; Figure 6 This is a flowchart illustrating the BIM+smart construction site full-process management method in the embodiments of this application; Figure 7 This is a schematic diagram of the system architecture of the Smart Construction Site Digital System in the embodiments of this application; Figure 8 This is a structural block diagram of a photovoltaic project management and control device based on digital twin according to an embodiment of the present invention; Figure 9 This is a schematic diagram of the hardware structure of an electronic device according to an embodiment of the present invention. Detailed Implementation
[0023] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0024] It is understood that before using the technical solutions disclosed in the various embodiments of the present invention, users should be informed of the types, scope of use, and usage scenarios of the personal information involved in the present invention and their authorization should be obtained in accordance with relevant laws and regulations through appropriate means.
[0025] The terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this invention, "a plurality of" means two or more, unless otherwise explicitly specified.
[0026] As an optional application scenario of this invention, such as Figure 1 As shown, the architecture system may include at least one terminal device and at least one server. Figure 1 The system is illustrated in the example, which includes a computer 101, a mobile terminal 102, and a server 103, and the terminal devices such as the computer 101 and the mobile terminal 102 are connected to the server 103 through a network 110.
[0027] Specifically, the terminal device can be a smartphone, tablet, laptop, PDA, desktop computer, game console, smart TV, smart wearable device, in-vehicle terminal, VR (Virtual Reality) device, AR (Augmented Reality) device, etc. Server 103 can be a standalone physical server, a server cluster, a distributed system, or a cloud server providing cloud services. Network 110 can be a wired or wireless network, examples of which include, but are not limited to, the Internet, corporate intranet, local area network, wide area network, mobile communication network, and combinations thereof.
[0028] In related technologies, photovoltaic projects use different monitoring systems to be deployed and operated independently at different monitoring stages such as construction, quality acceptance and operation. The information collected on site cannot be correlated with the relevant components and business information in the digital twin model of the photovoltaic project. Impact analysis such as construction progress identification, quality defect identification, safety violation identification and equipment commissioning fault diagnosis mainly rely on manual comparison, resulting in low management efficiency.
[0029] In view of this, this application provides a photovoltaic project management and control method based on digital twins, which can be applied to a single server to achieve photovoltaic project management and control. The method provided in this application addresses the shortcomings of related technologies, such as independent deployment of monitoring systems at each monitoring stage of a photovoltaic project, inability to link monitoring data with digital twin components and business information, and inefficiency caused by reliance on manual comparison for anomaly identification. Based on a photovoltaic digital twin model integrating full-cycle compliance judgment rules, it matches phased monitoring tasks with component units corresponding to physical facilities as carriers. This enables the accurate distribution of monitoring tasks to the monitoring module to collect corresponding component data. Then, by combining component spatial information with phased compliance rules, automatic anomaly identification is completed uniformly. This establishes a data link between the digital twin model and on-site sensing and monitoring data, eliminating the inefficient manual comparison mode. It can simultaneously cover the full-cycle management and control needs of construction, acceptance, and operation, significantly improving the identification efficiency and control accuracy of photovoltaic project quality, safety, progress, and equipment failure.
[0030] According to an embodiment of the present invention, a method for managing and controlling photovoltaic projects based on digital twins is provided. It should be noted that the steps shown in the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer-executable instructions. Furthermore, although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in a different order than that shown here.
[0031] This embodiment provides a photovoltaic project management and control method based on digital twins, which can be used in the aforementioned server. Figure 2 This is a flowchart of a photovoltaic project management and control method based on digital twins according to an embodiment of the present invention, such as... Figure 2 As shown, the process includes the following steps: Step S201: Obtain the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. The multiple component units correspond one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage.
[0032] For example, the target digital twin model is a three-dimensional digital mirror constructed based on the physical engineering of a photovoltaic project. It fully maps all physical facilities of the power station and serves as an integrated data carrier carrying spatial, component, and phased management rules. It is used to connect the entire lifecycle management and control business of design, construction, acceptance, and operation and maintenance. The component unit is the smallest digital management unit broken down according to the photovoltaic design information, corresponding to each physical facility such as photovoltaic panels, inverters, combiner boxes, cables, and brackets, realizing one-to-one binding between digital objects and on-site physical objects. The spatial range information of the component unit is stored in the three-dimensional coordinates, area boundaries, and location distribution data within the digital twin model for precise positioning. The monitoring system identifies the actual spatial location of each component within the photovoltaic field; it also divides the photovoltaic project's lifecycle into three control periods: the construction monitoring phase, which corresponds to the entire construction process including on-site civil engineering and component installation; the quality acceptance monitoring phase, which corresponds to the quality verification of sub-items and sub-projects; and the operation monitoring phase, which corresponds to the daily operation and maintenance monitoring after the power station is built and put into operation. The compliance judgment rule data consists of pre-set standard thresholds, specification requirements, and qualification judgment logic for each phase. The construction phase includes installation deviation standards, the acceptance phase includes quality acceptance specifications, and the operation phase includes power generation, equipment temperature rise, and normal ranges for current and voltage, used to automatically determine whether the monitoring data exceeds the standard or is abnormal.
[0033] Step S202: Based on the preset photovoltaic project management and control requirements information, determine at least one monitoring task corresponding to each different component unit. The preset photovoltaic project management and control requirements information is used to characterize any one of the management and control requirements information in the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage.
[0034] For example, the preset photovoltaic project management and control requirements information consists of standardized management and control requirements pre-entered into the system, corresponding to three management and control scenarios throughout the photovoltaic lifecycle. Management and control standards for any stage—construction, quality acceptance, or operation—can be selected individually, including the indicators to be verified, inspection frequency, and key management points for each stage. Monitoring tasks refer to targeted data collection and inspection instructions generated for individual component units, including specific operations such as image capture, electrical parameter collection, on-site safety inspection, and dimensional deviation detection. In this embodiment, the management and control requirements information for the stage to be monitored is read, and all management and control indicators to be verified for that stage are extracted. Then, the system matches the equipment type and spatial attributes of each component unit, automatically assigning suitable monitoring tasks to each type of component. Multiple monitoring tasks can be generated for the same component according to management and control requirements. Subsequently, the system will target and distribute these tasks to monitoring devices such as drones, inspection robots, and smart safety helmets to complete data collection.
[0035] Step S203: The monitoring tasks of each component unit are sent to the monitoring module so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to each component unit.
[0036] For example, in this embodiment of the application, standardized acquisition instructions are generated according to the spatial location and task type of the component unit and sent to each terminal acquisition device in the monitoring module through the communication link; each type of terminal device performs image, electrical and environmental parameter acquisition on the corresponding component area according to the instructions, and after the acquisition is completed, the original monitoring data with component location identifier is sent back to the server to form a dedicated monitoring dataset for each component.
[0037] Step S204: Input the monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information into the pre-built quality and safety identification module so that the quality and safety identification module outputs the abnormal identification result of the corresponding component unit.
[0038] For example, in this embodiment of the application, the server simultaneously sends the monitoring data with component identification, the current stage compliance threshold, and the three-dimensional spatial coordinates of the component into the quality and safety identification module. The module first matches the corresponding stage judgment standard, compares the monitoring value with the compliance range, identifies appearance defects by combining image AI algorithm, comprehensively judges problems such as installation deviation, power generation abnormality, and safety violation, and finally outputs the abnormal judgment result bound to the component number and spatial location.
[0039] The photovoltaic project management and control method based on digital twins provided in this embodiment addresses the shortcomings of related technologies, such as the independent deployment of monitoring systems at each monitoring stage of photovoltaic projects, the inability to link monitoring data with digital twin components and business information, and the reliance on manual comparison for various anomaly identifications, which leads to inefficient management and control. Based on a photovoltaic digital twin model that integrates full-cycle compliance judgment rules, it uses component units corresponding to physical facilities as carriers to match phased monitoring tasks. This enables the accurate distribution of monitoring tasks to the monitoring modules to collect corresponding component data. Then, by combining component spatial information with phased compliance rules, it unifies and automatically identifies anomalies. This establishes a data link between the digital twin model and on-site perception and monitoring data, eliminating the inefficient mode of manual comparison. It can simultaneously cover the full-cycle management and control needs of construction, acceptance, and operation, significantly improving the identification efficiency and control accuracy of photovoltaic project quality, safety, progress, and equipment failures.
[0040] This embodiment provides a photovoltaic project management and control method based on digital twins, which can be used in the aforementioned server. Figure 3 This is a flowchart of a photovoltaic project management and control method based on digital twins according to an embodiment of the present invention, such as... Figure 3 As shown, the process includes the following steps: Step S301: Obtain the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. The multiple component units correspond one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage.
[0041] Specifically, step S301 includes: Step S3011: Obtain the full lifecycle business dataset and photovoltaic project design data.
[0042] For example, photovoltaic project design data is a complete set of digital data generated in the early stage of photovoltaic project forward design, including site layout, support structure, components, inverters, cables and other equipment parameters, 3D modeling geometric information, engineering quantities, drawings, equipment specifications, spatial coordinates, etc.; the full life cycle business dataset covers all business data of photovoltaic project from construction, quality acceptance to commissioning and operation and maintenance: process records, material ledgers, and quality inspection records in the construction stage; sub-item acceptance data and rectification records in the acceptance stage; power generation and electrical data, inspection records, defect work orders, equipment maintenance ledgers, etc. in the operation stage.
[0043] Step S3012: Construct an initial digital twin model of the photovoltaic project based on the photovoltaic project design data. The initial digital twin model includes multiple component units and the coding information of each component unit.
[0044] In some optional implementations, step S3012 above includes: Step a1: Construct a three-dimensional design model of the photovoltaic project based on the photovoltaic project design data. The three-dimensional design model is used to represent the full-dimensional design element information and engineering quantity information of the engineering space physical facilities in the photovoltaic project.
[0045] For example, the physical facilities of the engineering space refer to all physical objects on the photovoltaic project site, encompassing all engineering equipment and structures such as photovoltaic modules, brackets, combiner boxes, inverters, cables, transformer substations, and site roads; the full-dimensional design element information includes multi-dimensional design parameters such as equipment dimensions, installation angles, layout spacing, wiring methods, material specifications, coordinate positions, and construction process standards; the engineering quantity information is the measurement statistics such as the quantity, length, area, and weight of various equipment, cables, and brackets extracted from the design data. In this embodiment, the complete set of design drawings, equipment parameters, overall layout, cable laying list, and other design data of the photovoltaic project are read, and the overall layout of the site and the three-dimensional structure of each piece of equipment are restored according to the real space scale using a 3D modeling tool; the design elements such as equipment model, installation process, and coordinate position are entered simultaneously, and the quantity of various components and the volume of consumables are automatically counted to form engineering quantity information, ultimately generating a complete photovoltaic 3D design model.
[0046] Step a2: Decompose the three-dimensional design model into multiple component units.
[0047] For example, in this embodiment of the application, the area is first divided into layers according to the site area, sub-array, and branch road. Then, the complete engineering entity in the model is split into the smallest independent management objects such as photovoltaic modules, brackets, inverters, combiner boxes, cables, and transformer boxes. During the splitting, the original spatial coordinates, equipment type, design parameters, and engineering quantity association information of each component are retained simultaneously. After the splitting is completed, a set of standardized component units that do not overlap and correspond one-to-one with the actual objects on site are formed.
[0048] Step a3: Encode each component unit to obtain the corresponding component unit's encoding information.
[0049] For example, in this embodiment of the application, a unique code is generated for each component unit according to a preset coding rule. The code integrates fields such as field area number, subarray number, component type, and equipment serial number, which can distinguish the region to which the component belongs and the equipment category. The code is bound to the component unit one by one to ensure that each component unit has independent and non-repeating coding information. The coding information is associated with the spatial location of the component and the equipment attributes, providing a unique index identifier for subsequent business data and monitoring data mounting and matching.
[0050] Step a4: Write the coding information of multiple component units into the three-dimensional design model to obtain the initial digital twin model of the photovoltaic project.
[0051] For example, in this embodiment of the application, all component units are processed, and the unique coding information corresponding to each component is written as an attribute field into the attribute parameters of the component object inside the three-dimensional design model. The coding is bound to the component unit, and the model retains the original geometric shape, spatial coordinates, design elements and engineering quantity information without changing the three-dimensional geometric data of the model. After the coding attribute is written, an initial digital twin model of the photovoltaic project with unique component identification is formed.
[0052] Step S3013: Decompose the full lifecycle business dataset according to multiple component units to obtain the business data corresponding to each component unit.
[0053] For example, in this embodiment of the application, various business records in the full lifecycle business dataset are processed, and the associated information such as equipment location, equipment type, and equipment number contained in each business record is extracted. The batch business data across regions and processes are split and classified according to the component unit dimension. Business content such as construction records, acceptance data, operation and maintenance defects, and material ledgers that are strongly related to a single component unit are selected, and irrelevant data is eliminated so that each piece of business data belongs to the corresponding component unit. The independent business data subset of each component unit is output.
[0054] Step S3014: Based on the coding information of each component unit, the business data of multiple component units are mapped into the digital twin model to obtain the target digital twin model.
[0055] For example, in this embodiment of the application, the unique code of the component unit is used as the matching index to read the business data subset corresponding to each component unit, and the component object matching the code is retrieved in the digital twin model; various business data such as construction, acceptance, and operation are mounted and bound to the corresponding model component as extended attributes of the component without modifying the original geometric, spatial and coding information of the model. After completing the association writing of all component business data, the initial digital twin model that originally only had design information is upgraded to the target digital twin model that integrates the business data of the entire life cycle.
[0056] Step S302: Based on the preset photovoltaic project management and control requirements information, determine at least one monitoring task corresponding to each different component unit. The preset photovoltaic project management and control requirements information is used to characterize any one of the management and control requirements information for the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. For details, please refer to... Figure 2 Step S202 of the illustrated embodiment will not be described again here.
[0057] Step S303: The monitoring tasks for each component unit are sent to the monitoring module, so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to different component units. For details, please refer to [link to relevant documentation]. Figure 2Step S203 of the illustrated embodiment will not be described again here.
[0058] Step S304 involves inputting the monitoring data of each component unit, the compliance judgment rule data for the corresponding monitoring stage, and the spatial range information into the pre-built quality and safety identification module, so that the quality and safety identification module outputs the anomaly identification result for the corresponding component unit. For details, please refer to [link to relevant documentation]. Figure 2 Step S204 of the illustrated embodiment will not be described again here.
[0059] Step S305: Associate the anomaly identification results of each component unit with the target digital twin model.
[0060] For example, the unique component unit code and information such as anomaly type, anomaly level, and occurrence time carried by the anomaly identification result are extracted. The component code is used as a matching index to retrieve and locate the corresponding component object in the target digital twin model. The anomaly identification result is written into the model as a new attribute of the component object, and the spatial range information of the component is bound at the same time. The corresponding component can be highlighted in the 3D scene to complete the association and binding between the anomaly result and the component of the digital twin model.
[0061] This embodiment provides a photovoltaic project management and control method based on digital twins, which can be used in the aforementioned server. Figure 4 This is a flowchart of a photovoltaic project management and control method based on digital twins according to an embodiment of the present invention, such as... Figure 4 As shown, the process includes the following steps: Step S401: Obtain the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. Each component unit corresponds one-to-one with multiple physical facilities in the photovoltaic project. These component units are determined based on the design information of the photovoltaic project. The different monitoring stages include construction monitoring, quality acceptance monitoring, and operation monitoring. For details, please refer to [link to relevant documentation]. Figure 3 Step S301 of the illustrated embodiment will not be described again here.
[0062] Step S402: Obtain the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial extent information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. Each component unit corresponds one-to-one with multiple physical facilities in the photovoltaic project. These component units are determined based on the design information of the photovoltaic project. The different monitoring stages include construction monitoring, quality acceptance monitoring, and operation monitoring. For details, please refer to [link to relevant documentation]. Figure 3 Step S302 of the illustrated embodiment will not be described again here.
[0063] Step S403: The monitoring tasks for each component unit are sent to the monitoring module, so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to different component units. For details, please refer to [link to relevant documentation]. Figure 3 Step S303 of the illustrated embodiment will not be described again here.
[0064] Step S404 involves inputting the monitoring data of each component unit, the compliance judgment rule data for the corresponding monitoring stage, and the spatial range information into the pre-built quality and safety identification module, so that the quality and safety identification module outputs the anomaly identification result for the corresponding component unit. For details, please refer to [link to relevant documentation]. Figure 3 Step S304 of the illustrated embodiment will not be described again here.
[0065] In some optional implementations, when the preset photovoltaic project management and control requirements information is the management and control requirements information for the operation monitoring phase, the above method further includes: Step S405: If it is determined from the anomaly identification result that there is an anomaly in the operation monitoring data of the target component, obtain the inspection image data of the physical facility corresponding to the target component.
[0066] For example, in this embodiment of the application, the unique code and spatial location information of the target component are located based on the anomaly identification result. The platform sends an image acquisition request to the monitoring module based on the spatial coordinates of the component, and dispatches monitoring devices such as drones and inspection robots to the area where the target component is located to collect on-site inspection images. After the monitoring device completes the acquisition, it sends the inspection image data carrying the component identification back to the management and control platform to complete the image data acquisition.
[0067] Step S406: Perform appearance anomaly identification on the inspection image data to obtain image recognition results.
[0068] For example, in this embodiment of the application, the inspection image data obtained from the return is input into the pre-trained photovoltaic appearance recognition AI model. The model performs target detection and feature extraction on the image, identifies various appearance defects such as photovoltaic module breakage, backsheet burning, bracket deformation, and cable damage, and filters irrelevant interference targets by combining component spatial information, and outputs image recognition results including whether there is an appearance abnormality, defect type, and defect location.
[0069] Step S407: If, based on the image recognition results, it is determined that the appearance of the target component is abnormal, then a defect elimination work order for the target component is pushed to the first target terminal.
[0070] For example, a defect elimination work order is a business work order generated for maintenance personnel. It records information such as the target component code, spatial location, defect type, defect image, and handling requirements to guide on-site personnel in carrying out fault and defect repair work. The first target terminal is the business terminal held by the maintenance personnel, such as a mobile phone or on-site tablet, used to receive defect repair work tasks. In this embodiment, after determining that the target component has an appearance abnormality based on the image recognition result, the component code, spatial location, defect type, inspection image, and other information are extracted and automatically assembled to generate a defect elimination work order. The defect elimination work order is pushed to the first target terminal through the platform communication interface, and the personnel can then view the component defect information and carry out on-site defect elimination work.
[0071] Step S408: If, based on the image recognition results, it is determined that there is no abnormality in the appearance of the target component, then the manual electrical inspection task is pushed to the second target terminal.
[0072] For example, a manual electrical inspection task is an on-site inspection instruction generated for photovoltaic equipment without external damage. It requires personnel to be present to conduct electrical parameter tests and troubleshoot internal electrical faults in the components and circuits. The task includes component codes, equipment locations, inspection items, and inspection standards. The second target terminal is a business terminal such as a mobile phone or tablet used by electrical inspection professionals, specifically for receiving electrical on-site inspection tasks, distinct from the work terminal that receives defect elimination work orders. In this embodiment, based on the image recognition results, it is confirmed that the target component has no external defects. The component code, spatial location, electrical anomalies, and corresponding inspection specifications are extracted, and a manual electrical inspection task is automatically generated. The task is then sent to the second target terminal via a communication link, reminding professionals to bring inspection tools to the site to verify electrical parameters.
[0073] This embodiment also provides a photovoltaic project management and control system based on digital twins, such as... Figure 5 As shown, the system includes: a monitoring module 501 and a photovoltaic project management and control platform 502; The monitoring module 501 includes multiple monitoring devices, including at least one drone, at least one robot, at least one camera, at least one smart safety helmet, and at least one photovoltaic operation monitoring device. The photovoltaic project management platform 501 is communicatively connected to the multiple monitoring devices in the monitoring module 501 and is used to execute the photovoltaic project management method based on digital twins described in the above embodiments.
[0074] For example, drones are used to conduct large-scale high-altitude inspections of photovoltaic (PV) fields, remotely checking for defects in PV panel arrays, supports, and transformer substations. They quickly identify potential hazards such as shading, component damage, loose cables, and equipment overheating, covering large areas difficult for manual access and improving inspection efficiency. Inspection robots are used to autonomously move along PV field roads and equipment access routes, continuously monitoring inverters, combiner boxes, and switchgear operating parameters at close range, collecting data on equipment temperature, abnormal noises, and wiring status. This enables 24 / 7 automated point-to-point monitoring, reducing the need for manual on-site supervision. Cameras are used to collect real-time video footage of PV areas and power distribution rooms, monitoring on-site personnel operations and equipment operating status, identifying abnormalities such as violations, foreign object intrusion, and fires, and simultaneously storing video evidence for traceability. Smart safety helmets are provided for on-site maintenance personnel, integrating positioning, video transmission, gas sensing, and alarm functions. They upload personnel location and on-site conditions in real time, promptly alerting in case of danger to ensure the personal safety of workers. Photovoltaic operation monitoring equipment is used to collect core operating data such as output power, voltage, current, irradiance, and temperature of photovoltaic modules and inverters, analyze power generation efficiency in real time, identify power generation faults such as attenuation and power anomalies, and support quantitative assessment of power generation status.
[0075] The following specific embodiment illustrates the photovoltaic project management method based on digital twins provided in this application.
[0076] Example 1: This application provides a BIM+smart construction site full-process management and control method and a smart construction site digital system. A flowchart of the BIM+smart construction site full-process management and control method is shown below. Figure 6 As shown, based on the photovoltaic 3D forward design model, an engineering object coding system covering the design, procurement, construction, commissioning, and handover stages is established; multi-source data from the site is acquired through drones, quadruped robots, AI cameras, smart safety helmets, mobile apps, law enforcement recorders, environmental monitoring equipment, and equipment operation data interfaces; multi-source data is associated with BIM models, construction plans, material ledgers, quality standards, safety rules, commissioning fault model libraries, and cloud collaborative file libraries; and events are generated through AI image recognition, progress comparison, fault diagnosis, and rule engine to drive responsibility assignment, rectification, review, archiving, and collaborative approval.
[0077] The system architecture diagram of the smart construction site digital system is shown below. Figure 7As shown, the overall architecture adopts a five-layer structure: perception layer, communication and data layer, platform layer, application layer, and access layer. The perception layer includes interfaces for collecting operational data from drones, quadruped robots, AI cameras, smart safety helmets, law enforcement recorders, mobile terminals, environmental monitoring equipment, and photovoltaic equipment. The communication and data layer includes gigabit fiber optics, dedicated networks, local carrier networks, wireless networks, and signal enhancement equipment. The platform layer includes account management, login authentication, role-based access control, model engine, process engine, map engine, data access and conversion services, database, and rule engine. The application layer includes a panoramic cockpit, safety management, construction management, design management, quality management, schedule management, cost management, commissioning management, environmental management, material and equipment management, emergency management, and smart device management. The access layer includes a smart screen, a web client, and a mobile app.
[0078] The specific implementation steps of the above method are shown in Table 1 below.
[0079] Table 1. BIM+Smart Construction Site Full-Process Management Method and Flow
[0080] The functional modules of the smart construction site digital system are as follows: (1) 3D forward design and engineering quantity statistics module: Based on PVStation or similar 3D forward design tools, it supports automatic component layout, flexible arrangement of 4 strings / 3 strings / 2 strings, generation of standard subarray and non-standard subarray schemes, automatic cable convergence, engineering quantity statistics and drawing output in flat and narrow fields.
[0081] (2) BIM model coding module: Write the engineering decomposition structure code into the BIM object attribute. The coding should include at least the fields of project, region, system, profession, component type, component number, construction task, material batch and acceptance status.
[0082] (3) Air-ground collaborative data acquisition module: Automatically generate inspection tasks for drones and quadruped robots based on construction area, planned tasks and risk level, and collect images, videos, location information and inspection reports; AI camera and smart safety helmet continuously collect personnel, equipment and safety status.
[0083] (4) AI Quality and Safety Recognition Module: This module identifies photovoltaic modules, supports, bolts, cables, personnel, vehicles, hazardous areas, and work activities. It first performs distortion correction, illumination equalization, dust interference suppression, and sharpness scoring on the on-site images. Then, it performs gridded slicing of the images based on the array boundaries, support layout, and construction area coding in the BIM model. Subsequently, it identifies modules, personnel, vehicles, and safety helmets through a target detection model, extracts module edges, road boundaries, and hazardous areas through a semantic segmentation model, and calculates the module installation angle, spacing, and offset through key point or edge fitting algorithms. The recognition results are matched with BIM object coding, construction tasks, quality acceptance rules, and safety rules, outputting defect type, violation type, confidence level, location, corresponding BIM object coding, screenshot evidence, and suggested rectification measures.
[0084] (5) BIM4D progress comparison module: bind the planned tasks with the BIM component codes, update the actual progress through AI recognition results, mobile terminal inspection data and on-site collected data, and display the progress status in different colors in the three-dimensional model.
[0085] (6) AI Diagnosis and Debugging Module: Access photovoltaic equipment operation data, call the fault model library to judge abnormalities such as zero current in the string, low current, and low power generation of the inverter, and perform fusion verification in combination with UAV inspection images. During fusion verification, the system first maps the abnormal string, inverter or box transformer to the specific array, row and column number and spatial coordinates in the BIM model according to the equipment code; then retrieves UAV images obtained in the same time window or after triggering a re-inspection, and performs spatial and temporal matching between the image recognition results and the abnormal operation results; if the abnormal location of the operation data is consistent with the location of the shading, dust accumulation, component damage, cable abnormality, joint detachment or installation deviation identified in the image, the fault confidence is increased and a troubleshooting work order is generated; if the operation data is abnormal but no appearance abnormality is found in the image, the fault type is adjusted to internal equipment fault, communication abnormality or electrical connection abnormality, and a manual electrical inspection task is pushed; if the image is abnormal but the operation data has not exceeded the limit, an early warning event is generated and included in the subsequent trend tracking.
[0086] (7) Cloud Collaborative Document Linkage Module: Links with cloud platforms such as Think Project. When design documents, procurement documents or construction problem reports are changed, the module automatically matches the affected BIM objects, construction tasks, material batches, cost items and responsible persons, triggering approval or reminders.
[0087] (8) Closed-loop rectification and mobile terminal module: The mobile terminal APP receives alarms and tasks, and supports on-site photography, voice, location, rectification instructions and review opinions; the platform retains the whole process record for the cockpit to perform statistical analysis.
[0088] The system provided in this application, through 3D forward design and automatic quantity surveying, transforms the design of large-scale photovoltaic (PV) sites from manual layout and statistics to model-driven design. PDF project data shows that previously, designing a PV site manually took approximately 15 days; with PVStation, it can be completed in about 3 days, improving design efficiency by approximately 80% and ensuring the accuracy of quantities. By encoding engineering objects, BIM models, construction plans, materials, quality, safety, costs, and commissioning data are integrated, enabling precise tracking of objects such as piles, supports, components, inverters, and transformer substations, avoiding the problem of having only 3D displays without a closed-loop business process. Through drones, quadruped robots, and AI cameras, aerial-ground collaborative inspections are formed, allowing online, non-destructive, and batch screening of PV module installation quality, bolt loosening, and angular deviations. It also supports construction progress, safety helmet wearing, and personnel intrusion detection. Project data shows that construction progress recognition accuracy exceeds 90%, safety violations are reduced by approximately 40%, and site inspection costs are reduced by approximately 50%. By comparing BIM4D progress simulation with actual progress, managers can view the differences between the plan and the actual progress along a timeline, quickly locate delayed areas and responsibilities in the 3D model, and project data shows that the overall construction progress has been improved by approximately 15%. Through dual-model verification using equipment operation data and drone images, the time for locating commissioning issues such as string zero current, low current, and low inverter power generation can be shortened; project data shows that fault location time can be reduced to 1-2 days, and the overall commissioning cycle can be shortened by approximately 20%. Through integration with the Think Project cloud platform, full-process sharing, version control, and remote approval by multinational teams of design, procurement, and construction documents are achieved; project data shows that the document processing cycle can be shortened by approximately 50%, reducing the risk of construction using old documents and information lag across teams. Through a closed-loop process of "identification—location—assignment—rectification—review—archiving—linkage," safety, quality, schedule, cost, materials, commissioning, and emergency modules are uniformly driven, significantly shortening the time for hazard rectification. This is suitable for replication and application in large-scale overseas new energy projects with short construction periods, high collaboration, and extreme natural conditions.
[0089] In summary, this application takes engineering object coding and BIM digital twins as its core, and links multi-source perception data, AI identification and diagnosis results, schedule plans, quality and safety rules and cross-border collaborative documents into a unified closed loop. This technically solves the problems of data fragmentation, slow problem location, difficulty in rectification and tracking, and low efficiency of remote collaboration in the construction process of large-scale desert photovoltaic projects.
[0090] Example 2: In the photovoltaic project in location A, given the long and narrow site and limited land availability, flexible layout schemes of 4-string, 3-string, and 2-string arrays can be generated using 3D forward design software. This software automatically outputs data on subarrays, modules, cables, and quantities. Subsequently, objects such as piles, supports, modules, inverters, transformer substations, roads, and fences are entered into a unified code, and their correspondence with the construction plan and procurement documents is established.
[0091] During the construction phase, AI recognition does not directly judge the original images in isolation. Instead, it first matches the shooting position, attitude, and timestamp of the drone or camera with the coordinates of the BIM model, projecting the site image onto the corresponding photovoltaic array, construction area, and project object code. After the system performs distortion correction, illumination equalization, dust interference suppression, and blur removal on the image, it divides the image into several component units and support units according to the component layout rules. Then, it identifies the component edges, bolt positions, key points of the support, personnel, safety helmets, and boundaries of dangerous areas. For the same object, the system calculates the comprehensive confidence score by combining multiple consecutive frames of images, adjacent flight path images, and fixed camera images. Only when the recognition result reaches a preset threshold and is consistent with the BIM object position is a quality or safety event generated, thereby reducing false alarms caused by strong desert light, shadows, and repetitive arrays.
[0092] During the commissioning phase, the platform first maps the inverter, combiner box, and string operation data to specific array locations in the BIM model according to equipment codes. Using irradiance, component temperature, output of healthy strings in the same area, and historical operation curves as benchmarks, it calculates the normalized power generation efficiency and deviation value for each string or inverter. When string zero current, low current, or low inverter power generation occur, the system calls upon the fault model library based on the duration of the anomaly, the magnitude of the deviation, and spatial clustering characteristics to rank suspected fault causes. Subsequently, the system automatically retrieves drone images of the corresponding area or generates re-inspection tasks, comparing and verifying the image-identified obstructions, dust accumulation, component damage, cable anomalies, loose connectors, or installation deviations with the location of the operational anomaly. When operational data anomalies and image anomalies match on the same BIM object or adjacent objects, the system determines it as a high-confidence fault and generates a troubleshooting work order; when they do not match, the system marks it as requiring manual review or electrical testing, thus achieving dual-model verification of the operational data model and the image model.
[0093] For identified quality, safety, schedule, or commissioning issues, the process engine automatically generates rectification tasks based on object codes, construction areas, specialties, and responsible units, and pushes them to mobile devices. After rectification, the responsible person uploads on-site photos or videos, and the system then triggers drone, robot, camera, or manual review. Once the review is approved, the event is closed, and the results are archived in the quality management, safety management, schedule management, cost management, material management, and cloud collaborative file modules, achieving paperless and digital performance.
[0094] This embodiment also provides a photovoltaic project management and control device based on digital twins, which is used to implement the above embodiments and preferred embodiments; details already described will not be repeated. As used below, the term "module" can refer to a combination of software and / or hardware that performs a predetermined function. Although the device described in the following embodiments is preferably implemented in software, hardware implementation, or a combination of software and hardware, is also possible and contemplated.
[0095] This embodiment provides a photovoltaic project management and control device based on digital twins, such as... Figure 8 As shown, it includes: The first acquisition module 801 is used to acquire the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. The multiple component units correspond one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. The first determining module 802 is used to determine at least one monitoring task corresponding to different component units based on the preset photovoltaic project management and control requirements information. The preset photovoltaic project management and control requirements information is used to characterize any one of the management and control requirements information for the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. The second determining module 803 is used to send the monitoring tasks of each component unit to the monitoring module so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to different component units. The third determining module 804 is used to input the monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information into the pre-built quality and safety identification module, so that the quality and safety identification module outputs the abnormal identification result of the corresponding component unit.
[0096] In some alternative embodiments, the above-described apparatus further includes: The association module is used to associate the anomaly identification results of each component unit with the target digital twin model.
[0097] In some optional implementations, the first acquisition module 801 includes: The acquisition submodule is used to acquire full lifecycle business datasets and photovoltaic project design data; The construction submodule is used to build an initial digital twin model of the photovoltaic project based on the photovoltaic project design data. The initial digital twin model includes multiple component units and the coding information of each component unit. The decomposition submodule is used to decompose the full lifecycle business dataset into multiple component units to obtain the business data corresponding to each component unit. The mapping submodule is used to map the business data of multiple component units to the digital twin model based on the coding information of each component unit, so as to obtain the target digital twin model.
[0098] In some alternative implementations, the construction submodule includes: The building unit is used to construct a three-dimensional design model of a photovoltaic project based on the photovoltaic project design data. The three-dimensional design model is used to represent the full-dimensional design element information and engineering quantity information of the engineering space entity facilities in the photovoltaic project. Decomposition unit is used to structurally decompose a 3D design model to obtain multiple component units; The encoding unit is used to encode each component unit to obtain the encoding information of the corresponding component unit; The writing unit is used to write the encoded information of multiple component units into the three-dimensional design model to obtain the initial digital twin model of the photovoltaic project.
[0099] In some optional implementations, when the preset photovoltaic project management and control requirements information is the management and control requirements information for the operation monitoring phase, the above method further includes: The second acquisition module is used to acquire inspection image data of the physical facility corresponding to the target component if it is determined from the anomaly identification result that there is an anomaly in the operation monitoring data of the target component. The recognition module is used to identify appearance anomalies in inspection image data and obtain image recognition results. The fourth determination module is used to push a defect elimination work order for the target component to the first target terminal if it is determined that the appearance of the target component is abnormal based on the image recognition result. The fifth determination module is used to push the manual electrical inspection task to the second target terminal if the appearance of the target component is determined to be normal based on the image recognition results.
[0100] The photovoltaic project management and control device based on digital twins provided in this invention can execute the photovoltaic project management and control method based on digital twins provided in any embodiment of this invention, and has the corresponding functional modules and beneficial effects for executing the method. Further functional descriptions of the above modules and units are the same as those in the corresponding embodiments described above, and will not be repeated here.
[0101] Figure 9 This is a schematic diagram of the structure of an electronic device provided in an embodiment of the present invention.
[0102] The following is a detailed reference. Figure 9This diagram illustrates a structural schematic suitable for implementing an electronic device according to embodiments of the present invention. The electronic device may include a processor (e.g., a central processing unit, graphics processor, etc.) 901, which can perform various appropriate actions and processes according to a program stored in read-only memory (ROM) 902 or a program loaded from memory 908 into random access memory (RAM) 903. The RAM 903 also stores various programs and data required for the operation of the electronic device. The processor 901, ROM 902, and RAM 903 are interconnected via a bus 904. An input / output (I / O) interface 905 is also connected to the bus 904.
[0103] Typically, the following devices can be connected to I / O interface 905: input devices 906 including, for example, touchscreens, touchpads, keyboards, mice, cameras, microphones, accelerometers, gyroscopes, etc.; output devices 907 including, for example, liquid crystal displays (LCDs), speakers, vibrators, etc.; memory devices 908 including, for example, magnetic tapes, hard disks, etc.; and communication devices 909. Communication device 909 allows electronic devices to exchange data via wireless or wired communication with other devices. Although Figure 9 Electronic devices with various devices are shown, but it should be understood that it is not required to implement or have all of the devices shown, and more or fewer devices may be implemented or have instead.
[0104] In particular, according to embodiments of the present invention, the processes described above with reference to the flowcharts can be implemented as computer software programs. For example, embodiments of the present invention include a computer program product comprising a computer program carried on a non-transitory computer-readable medium, the computer program containing program code for performing the methods shown in the flowcharts. In such embodiments, the computer program can be downloaded and installed from a network via a communication device 909, or installed from a memory 908, or installed from a ROM 902. When the computer program is executed by the processor 901, it performs the functions defined in the digital twin-based photovoltaic project management method of the embodiments of the present invention.
[0105] Figure 9 The electronic device shown is merely an example and should not be construed as limiting the functionality and scope of the embodiments of the present invention.
[0106] This invention also provides a computer-readable storage medium. The methods described above according to embodiments of the invention can be implemented in hardware or firmware, or implemented as computer code that can be recorded on a storage medium, or implemented as computer code downloaded via a network and originally stored on a remote storage medium or a non-transitory machine-readable storage medium and then stored on a local storage medium. Thus, the methods described herein can be processed by software stored on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. The storage medium can be a magnetic disk, optical disk, read-only memory, random access memory, flash memory, hard disk, or solid-state drive, etc.; further, the storage medium can also include combinations of the above types of memory. It is understood that computers, processors, microprocessor controllers, or programmable hardware include storage components capable of storing or receiving software or computer code. When the software or computer code is accessed and executed by the computer, processor, or hardware, the photovoltaic project management method based on digital twins shown in the above embodiments is implemented.
[0107] A portion of this invention can be applied as a computer program product, such as computer program instructions, which, when executed by a computer, can invoke or provide the methods and / or technical solutions according to the invention through the operation of the computer. Those skilled in the art will understand that the forms in which computer program instructions exist in a computer-readable medium include, but are not limited to, source files, executable files, installation package files, etc. Correspondingly, the ways in which computer program instructions are executed by a computer include, but are not limited to: the computer directly executing the instructions, or the computer compiling the instructions and then executing the corresponding compiled program, or the computer reading and executing the instructions, or the computer reading and installing the instructions and then executing the corresponding installed program. Here, the computer-readable medium can be any available computer-readable storage medium or communication medium accessible to a computer.
[0108] Although embodiments of the invention have been described in conjunction with the accompanying drawings, those skilled in the art can make various modifications and variations without departing from the spirit and scope of the invention, and such modifications and variations all fall within the scope defined by the appended claims.
Claims
1. A photovoltaic project management and control method based on digital twins, characterized in that, The method includes: Obtain a target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. The multiple component units correspond one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. Based on the preset photovoltaic project management and control requirements information, at least one monitoring task is determined for each different component unit. The preset photovoltaic project management and control requirements information is used to characterize any one of the management and control requirements information for the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. The monitoring tasks of each component unit are sent to the monitoring module so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to each component unit. The monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information are input into the pre-built quality and safety identification module so that the quality and safety identification module outputs the abnormal identification result of the corresponding component unit.
2. The method according to claim 1, characterized in that, The method further includes: The anomaly identification results of each component unit are associated with the target digital twin model.
3. The method according to claim 1 or 2, characterized in that, The steps for obtaining the target digital twin model of the photovoltaic project include: Acquire full lifecycle business datasets and photovoltaic project design data; An initial digital twin model of the photovoltaic project is constructed based on the photovoltaic project design data. The initial digital twin model includes multiple component units and the coding information of each component unit. The full lifecycle business dataset is decomposed according to the multiple component units to obtain business data corresponding to different component units; Based on the encoding information of each component unit, the business data of multiple component units are mapped into the digital twin model to obtain the target digital twin model.
4. The method according to claim 3, characterized in that, Based on the photovoltaic project design data, an initial digital twin model of the photovoltaic project is constructed, including: Based on the photovoltaic project design data, a three-dimensional design model of the photovoltaic project is constructed. The three-dimensional design model is used to represent the full-dimensional design element information and engineering quantity information of the engineering space entity facilities in the photovoltaic project. The three-dimensional design model is structurally decomposed to obtain multiple component units; Each component unit is encoded to obtain the corresponding component unit's encoding information; The encoded information of multiple component units is written into the three-dimensional design model to obtain the initial digital twin model of the photovoltaic project.
5. The method according to claim 1, characterized in that, When the preset photovoltaic project management and control requirements information is management and control requirements information for the operation monitoring phase, the method further includes: If it is determined based on the anomaly identification result that there is an anomaly in the operation monitoring data of the target component, obtain the inspection image data of the physical facility corresponding to the target component; The inspection image data is subjected to appearance anomaly identification to obtain image recognition results; If, based on the image recognition results, it is determined that the appearance of the target component is abnormal, a defect elimination work order for the target component is pushed to the first target terminal. If, based on the image recognition results, it is determined that the appearance of the target component is not abnormal, then a manual electrical inspection task is pushed to the second target terminal.
6. A photovoltaic project management and control system based on digital twins, characterized in that, The system includes: a monitoring module and a photovoltaic project management and control platform; The monitoring module includes multiple monitoring devices, including at least one drone, at least one robot, at least one camera, at least one smart safety helmet, and at least one photovoltaic operation monitoring device. The photovoltaic project management and control platform is communicatively connected to multiple monitoring devices and is used to execute the photovoltaic project management and control method based on digital twins as described in any one of claims 1 to 5.
7. A photovoltaic project management and control device based on digital twins, characterized in that, The device includes: The first acquisition module is used to acquire the target digital twin model of the photovoltaic project. The target digital twin model includes multiple component units of the photovoltaic project, spatial range information of each component unit, and compliance judgment rule data corresponding to different monitoring stages. The multiple component units correspond one-to-one with multiple physical facilities in the photovoltaic project. The multiple component units are determined based on the design information of the photovoltaic project. The different monitoring stages include the construction monitoring stage, the quality acceptance monitoring stage, and the operation monitoring stage. The first determining module is used to determine at least one monitoring task corresponding to different component units based on preset photovoltaic project management and control requirements information. The preset photovoltaic project management and control requirements information is used to characterize any one of the management and control requirements information for the construction monitoring stage, the management and control requirements information for the quality acceptance monitoring stage, and the management and control requirements information for the operation monitoring stage. The second determining module is used to send the monitoring tasks of each component unit to the monitoring module, so that the monitoring module can execute the monitoring tasks and obtain the monitoring data corresponding to different component units respectively; The third determining module is used to input the monitoring data of each component unit, the compliance judgment rule data of the corresponding monitoring stage, and the spatial range information into the pre-built quality and safety identification module, so that the quality and safety identification module outputs the abnormal identification result of the corresponding component unit.
8. An electronic device, characterized in that, include: A memory and a processor are interconnected, the memory stores computer instructions, and the processor executes the computer instructions to perform the photovoltaic project management method based on digital twins as described in any one of claims 1 to 5.
9. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores computer instructions for causing the computer to execute the photovoltaic project management method based on digital twins as described in any one of claims 1 to 5.
10. A computer program product, characterized in that, It includes computer instructions for causing a computer to execute the photovoltaic project management method based on digital twins as described in any one of claims 1 to 5.