A Closed-Loop Collaborative Management Method for the Entire Procurement and Logistics Process of Steel Mills

By constructing a closed-loop collaborative management system for the entire procurement and logistics process of steel mills, the problems of opaque loading information and dynamic adjustment of production scheduling have been solved. This has enabled automated management of the entire process from loading to quality inspection, improving management efficiency and accuracy, and ensuring the integrity and safety of cargo transportation.

CN123117944APending Publication Date: 2026-11-17YUKUAI CHUANGLING INTELLIGENT TECH (NANJING) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202610847239.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-06-12
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Steel companies lack means to verify the authenticity of loading information in their procurement and logistics management, which leads to the inability to detect loading anomalies in a timely manner, the inability to dynamically adjust production scheduling plans, the inability to automatically link quality inspection anomalies, and the disconnect between the performance evaluation of suppliers and carriers, making it impossible to achieve full-process automated management.

Method used

Construct a closed-loop collaborative management system for the entire procurement and logistics process of steel mills. Through supplier data integration, vehicle data collection, in-transit inventory calculation, production scheduling collaboration, and quality inspection assessment units, it can achieve cross-validation of loading information, real-time monitoring, dynamic production scheduling decisions, and automated handling of quality inspection anomalies.

Benefits of technology

It has achieved fully automated management of the entire process from loading to quality inspection, improved the verification of the authenticity of loading information, dynamically adjusted production scheduling, reduced manual intervention and settlement disputes, improved management efficiency and accuracy, and ensured the integrity and safety of cargo transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123117944A_ABST
    Figure CN123117944A_ABST
Patent Text Reader

Abstract

This invention proposes a closed-loop collaborative management method for the entire procurement and logistics process of steel mills. The method connects suppliers and steel mills through a cloud-based collaborative management platform. It receives loading performance information through a supplier data connection unit and verifies loading authenticity by calling on-board load data. It collects real-time data on in-transit location, real-time load, and driving behavior safety events to monitor cargo integrity and assess transportation safety risks. It also calculates estimated arrival time at the mill and generates in-transit inventory data to drive production scheduling adjustments. When quality inspection anomalies occur, the anomaly is determined according to the contractually agreed-upon inspection items, automatically linking the responsible party and generating deduction documents. This invention achieves end-to-end data connectivity and business closure from supplier loading to quality inspection deductions, effectively solving problems in existing technologies such as opaque loading information, inability to guarantee the safety of goods in transit, disconnect between logistics and production, and lack of a closed-loop quality inspection and settlement system. This significantly reduces the risk of production line downtime and inventory costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical fields of supply chain management for iron and steel enterprises and industrial Internet, and in particular to a whole-process closed-loop collaborative management method for procurement logistics oriented to steel mills. Background Art

[0002] With the development of industrial Internet technology, iron and steel enterprises have made certain progress in the digitalization of procurement logistics. In the in-plant logistics link, unattended weighing systems, intelligent unloading guidance systems, and automatic vehicle identification systems have been widely applied, realizing unattended management of the whole process of vehicle entering the factory, weighing, unloading, and leaving the factory; in the transportation monitoring link, by interfacing with platforms such as GPS / Beidou positioning systems, China Railway 95306 freight system, and Shipxy, real-time position tracking and abnormal state warning of vehicles and ships can be realized; in the quality inspection management link, the application of intelligent sampling systems, automatic testing equipment and Laboratory Information Management System (LIMS) has significantly improved the efficiency and accuracy of raw material and fuel quality inspection; in the procurement management link, some enterprises have launched e-procurement platforms to realize online release and tracking of procurement orders. However, the prior art still has many deep-seated technical defects in practical applications, and cannot meet the demands for high-quality development of iron and steel enterprises, which is specifically reflected in the following aspects: First, at present, key information such as loading time, loading quantity, and loading quality obtained by iron and steel enterprises completely relies on unilateral declaration by suppliers, and there is no independent technical means for cross-verification. Although some enterprises require suppliers to upload loading photos or videos, such information is extremely easy to be tampered with, and its authenticity and timeliness cannot be guaranteed. Once the loading quantity does not match or there is a quality deviation, the steel mill can often only discover the problem after the goods arrive at the factory, resulting in production scheduling delays and resource waste.

[0003] Second, although solutions for acquiring real-time information such as vehicle position and speed are also adopted at present, such information is only used for monitoring and abnormal warning during the transportation process, and has not been converted into a decision-making basis valuable for production scheduling. The existing production scheduling system still performs scheduling based on static procurement orders and agreed delivery dates, and cannot dynamically adjust the production plan according to the actual transportation progress of materials. When unforeseen factors such as weather changes, road congestion, and vehicle failures occur during transportation and cause materials to arrive late, the scheduling plan cannot respond in a timely manner, and can only be coped with by temporarily adjusting the production rhythm or consuming safety stock, which not only increases inventory costs, but may also lead to disorder of production order.

[0004] Finally, the in-transit material information cannot be effectively transmitted to the production scheduling system, resulting in a lack of support for scheduling decisions based on in-transit inventory data. Simultaneously, the inspection and testing data after materials arrive at the factory are disconnected from the performance evaluation systems of suppliers and carriers. Abnormal quality inspection results lack automated linkage with supplier deduction mechanisms, making it impossible to automatically adjust supplier ratings and procurement shares based on historical quality inspection data, thus hindering the implementation of a merit-based supplier selection process. Summary of the Invention

[0005] To address the aforementioned technical problems, this application proposes a closed-loop collaborative management method for the entire procurement and logistics process of steel mills. This method is applied to a closed-loop collaborative management system for the entire procurement and logistics process of steel mills, which includes a supplier data integration unit, a vehicle-mounted data acquisition unit, an in-transit inventory calculation unit, a production scheduling coordination unit, and a quality inspection and assessment unit. The method is characterized by the following steps: S1: The supplier data docking unit receives and verifies the loading performance information sent by the supplier after loading is completed; The loading performance information shall include at least the contract number, material information, declared loading quantity, and carrier vehicle identification.

[0006] S2: After the vehicle is loaded, the on-board data acquisition unit collects the factory load reference value through the pre-installed load sensor, and cross-compares the factory load reference value with the declared load quantity in the loading performance information to verify the authenticity of the loading. During the cross-comparison process, if the deviation exceeds a preset threshold, an abnormal loading warning will be triggered and the steel mill and supplier will be notified.

[0007] Using vehicle load data for pre-verification of the authenticity of supplier loading extends the control boundary from the steel plant gate to the supplier loading site, breaking the information blind spot on the supplier side. It can promptly detect problems such as short loading, omissions, and false reporting of quantities before the vehicle leaves the supplier's plant area, avoiding production scheduling delays and production line shutdowns due to waiting for materials caused by discovering abnormalities only after the goods arrive at the plant.

[0008] S3: During transportation, the vehicle-mounted data acquisition unit collects vehicle positioning, real-time load data, and driving behavior safety event data in real time at a preset time frequency, and uploads them to the cloud platform.

[0009] In-transit monitoring can not only track vehicle location, but also link cargo information, providing comprehensive and traceable data support for subsequent in-transit inventory data calculation, cargo integrity monitoring, and transportation safety risk assessment.

[0010] S4: The in-transit inventory calculation unit dynamically calculates the estimated arrival time (ETA) of each batch of materials based on the real-time uploaded vehicle location, transportation starting point, preset transportation route, and estimated dwell time at the transit warehouse, and generates structured in-transit inventory data based on the ETA.

[0011] S5: The production scheduling coordination unit pushes the in-transit inventory data to the steel mill's production scheduling system to support the advance preparation or adjustment of the production scheduling plan and realize in-transit production scheduling decisions.

[0012] S6: After the materials arrive at the factory, the quality inspection and assessment unit receives and tests the test results data from the steel plant's quality inspection system; The test results data correspond one-to-one with the contract number, material information, and carrier vehicle identification.

[0013] Quality issues in each batch of materials can be accurately attributed to specific suppliers and carriers, providing objective and irrefutable evidence for subsequent liability determination and performance evaluation.

[0014] S7: When an abnormality is detected in the test results data, the quality inspection assessment unit automatically matches the corresponding supplier and carrier information, and generates and pushes the assessment deduction document according to the preset assessment rules.

[0015] Through the above technical solutions, a complete business closed loop is constructed from anomaly detection to responsibility matching and deduction assessment, realizing full-process automation of quality management, greatly improving settlement efficiency, reducing manual intervention and settlement disputes, and forcing upstream and downstream of the supply chain to continuously improve service quality.

[0016] Furthermore, in step S2, the load sensor acquires the total weight data of the vehicle through the CAN bus interface according to the preset CAN ID; the initial load reference value is the stable weight value collected when the vehicle is loaded and started for the first time.

[0017] Furthermore, in step S4, the specific method for dynamically calculating the estimated arrival time is as follows: ETA = T_current + T_remaining + T_transfer; Wherein, T_current is the current time, T_remaining is the remaining road transport time calculated based on the historical transport timeliness statistical model and real-time road conditions, and T_transfer is the expected stay time at the transit depot; the historical transport timeliness statistical model is a database of average travel time by road segment established based on historical transport data of the same transport route, the same time period, and the same season within a preset period in the past.

[0018] Furthermore, the driving behavior safety event data includes driver fatigue driving, distracted driving, forward collision warning, lane departure warning, and sudden acceleration / deceleration events monitored by the vehicle-mounted data acquisition unit; the in-transit inventory data includes at least the type and quantity of materials, supplier information, carrier information, vehicle location, estimated arrival time, and transit warehouse status; the performance evaluation deduction document includes at least the abnormal detection items, standard values, measured values, deviation range, deduction amount, and deduction basis.

[0019] Furthermore, step S4 also includes: monitoring the transportation route based on the real-time uploaded vehicle location, monitoring the integrity of the goods based on the load data, and assessing the transportation safety risks based on the driving behavior safety event data. When it is detected that the driving route deviates from the preset path or the dwell time exceeds the limit, the vehicle load changes abnormally, or the driver's driving behavior is risky, an on-the-road anomaly warning is immediately triggered and relevant management personnel are notified.

[0020] By transforming discrete in-transit logistics data into structured and quantifiable in-transit inventory data, asset management of in-transit materials can be realized; through real-time continuous comparison of load, abnormal behaviors such as unloading, changing goods, and spillage can be detected in a timely manner, ensuring the integrity of cargo transportation; through driving behavior safety risk assessment, early warnings can be given for safety hazards such as driver fatigue and distracted driving, significantly reducing the incidence of transportation accidents.

[0021] Furthermore, step S5 specifically includes: S51: The production scheduling coordination unit will compare and analyze the in-transit inventory data with the steel mill's existing physical inventory data and the already scheduled production plan; S52: For materials whose estimated arrival time (ETA) is earlier than the material demand time for production scheduling, mark them as available inventory in transit and include them in available resources for production scheduling. S53: For materials whose estimated arrival time (ETA) lags behind the material requirements for production scheduling, automatically generate production scheduling adjustment suggestions, including postponing the corresponding production orders, initiating alternative material solutions, or adjusting the production rhythm.

[0022] Furthermore, step S53 also includes: When multiple batches of materials have estimated arrival times that lag behind production schedule requirements, calculate the production urgency coefficient E for each delayed batch using the formula: E = ; in, Based on the preset material importance weights, the main raw materials Greater than auxiliary raw materials ; This refers to the number of days the existing physical inventory of the material is available. To correspond to the urgency weight of the production process, the core process Larger than non-core processes ; , All satisfy the condition that they are greater than 0 and less than or equal to 1; Finally, the lagging batches of materials are sorted from high to low according to the production urgency coefficient E, and the production orders corresponding to the lagging batches of materials with high production urgency coefficient E are adjusted first.

[0023] By using a production urgency coefficient, the scheduling priority can be automatically optimized when multiple batches of materials are delayed simultaneously. This ensures the supply of main raw materials such as iron ore and coke, as well as core processes such as blast furnaces and converters, avoiding unplanned production stoppages caused by scheduling conflicts and helping to improve the resilience of the production system.

[0024] Furthermore, in step S7, the abnormal test results data include deviations in chemical composition, physical properties, and appearance quality defects; the quality inspection and assessment unit has a built-in abnormal judgment rule engine, which is used to determine an abnormality when the measured value of any test item pre-agreed in the purchase contract exceeds the preset allowable error range, and automatically associates the supplier and carrier according to the contract number, matching the preset tiered or fixed amount deduction standard.

[0025] Furthermore, step S7 also includes: integrating historical loading verification data, transportation timeliness data, driving behavior safety event data, and quality inspection result data to generate a full lifecycle credit evaluation report for suppliers and carriers, providing data support for adjusting procurement share.

[0026] Preferably, in step S1, the loading performance data also includes photos or videos of the loading site, and the platform identifies the photos or videos to help verify the authenticity of the loading process.

[0027] Preferably, the vehicle-mounted data acquisition unit integrates a Beidou / GPS dual-mode positioning module and a 4G / 5G communication module, supporting local caching during network outages and automatic retransmission after network recovery.

[0028] Preferably, when an on-the-go anomaly warning is triggered, the system automatically captures the in-vehicle video clips and sensor data for the corresponding time period, generates an anomaly event evidence report with a timestamp, and stores it in encrypted form.

[0029] Preferably, in step S4, when it is detected that a vehicle has been staying at a non-designated location for more than 2.5 hours, the system automatically sends a dispatch reminder to the carrier and provides the optimal detour route suggestion based on real-time road conditions and traffic control information.

[0030] The beneficial effects of the proposed method for closed-loop collaborative management of the entire procurement logistics process for steel mills are as follows: (1) By establishing a cross-verification mechanism for data from suppliers, steel mills, and carriers, the load data of vehicles is used for pre-verification of the authenticity of supplier loading, extending the control boundary from the steel mill gate to the supplier loading site, solving the problem of opaque loading information, enabling early detection of loading anomalies, and avoiding production line stoppages due to raw material shortages; (2) By dynamically calculating the estimated arrival time and quantifying it into in-transit inventory data, the in-transit logistics data is transformed into decision data that can directly drive production scheduling, realizing deep collaboration between logistics and production, enabling steel mills to make production scheduling decisions based on physical inventory and in-transit inventory, and improving inventory turnover rate; (3) A system is constructed from quality inspection anomaly detection to... The complete business loop of responsibility matching, automatic deduction and assessment linkage realizes full-process automation of quality management, greatly improves settlement efficiency and accuracy and reduces manual intervention and settlement disputes; (4) Real-time collection of on-the-way load data and continuous comparison with the factory load benchmark value, as well as collection of driver driving behavior safety event data and risk assessment, realizes automatic monitoring of the integrity of on-the-way goods and early warning of safety risks in the transportation process, can promptly detect abnormal behaviors such as unloading and changing goods in the middle of the way and driving safety hazards, ensure the safety and integrity of goods transportation, and reduce the incidence of transportation accidents; (5) Adopting modular design and standardized interface, no need to make large-scale modifications to the existing system, low implementation cost and quick results, especially suitable for the digital transformation needs of steel enterprises. Attached Figure Description

[0031] Figure 1 This is a schematic diagram of a closed-loop collaborative management system for the entire procurement and logistics process of steel mills, as described in this invention. Figure 2 This is a schematic diagram of the overall workflow of a closed-loop collaborative management method for the entire procurement and logistics process of steel mills according to the present invention. Figure 3 This is a flowchart illustrating steps S6 and S7 of a closed-loop collaborative management method for the entire procurement and logistics process of steel mills according to the present invention. Detailed Implementation

[0032] To provide a further understanding of the purpose, structure, features, and functions of the present invention, detailed descriptions are provided below with reference to specific embodiments.

[0033] This invention proposes a closed-loop collaborative management method for the entire process of bulk raw material procurement and logistics in steel enterprises. The method is implemented based on a cloud-based closed-loop collaborative management system for the entire procurement and logistics process of steel mills. Figure 1 As shown, the system includes a supplier data docking unit, a vehicle data acquisition unit, an in-transit inventory calculation unit, a production scheduling coordination unit, and a quality inspection and assessment unit. The supplier data integration unit connects to the supplier's delivery system via an API interface. The vehicle-mounted data acquisition unit is deployed on each of the carrier vehicles at the carrier end, and acts as an edge computing node to realize the local acquisition and preprocessing of vehicle-mounted data; The in-transit inventory calculation unit and the production scheduling coordination unit are deployed sequentially at the steel mill end to jointly realize the transformation of logistics data into production decisions; The quality inspection and assessment unit is deployed at the steel plant, serving as a hub connecting the steel plant's internal quality inspection system with the external supplier / carrier management system; The cloud platform uniformly receives upstream data from suppliers and carriers, and after calculation and analysis, distributes the structured data to the steel mill.

[0034] like Figure 2 As shown, the method includes the following steps: S1: The supplier data docking unit receives and verifies the loading performance information sent by the supplier after loading is completed; S2: The vehicle-mounted data acquisition unit calls the pre-loaded weight sensor of the corresponding carrier vehicle according to the carrier vehicle identification, collects the factory load reference value after the vehicle is loaded, and cross-compares the factory load reference value with the declared loading quantity in the loading performance information to verify the loading authenticity. S3: During transportation, the vehicle-mounted data acquisition unit collects vehicle positioning, real-time load data, and driving behavior safety event data in real time at a preset time frequency, and uploads them to the cloud platform. S4: The in-transit inventory calculation unit dynamically calculates the estimated arrival time (ETA) of each batch of materials based on the real-time uploaded vehicle location, transportation starting point, preset transportation route, and estimated dwell time at the transit warehouse, and generates structured in-transit inventory data based on the ETA. S5: The production scheduling coordination unit pushes the in-transit inventory data to the steel mill's production scheduling system to support the advance preparation or adjustment of the production scheduling plan and realize in-transit production scheduling decisions. S6: After the materials arrive at the factory, the quality inspection and assessment unit receives and tests the test results data from the steel plant's quality inspection system; S7: When an abnormality is detected in the test results data, the quality inspection assessment unit automatically matches the corresponding supplier and carrier information, and generates and pushes the assessment deduction document according to the preset assessment rules.

[0035] Example 1: This example illustrates the closed-loop management process of the entire procurement logistics of iron ore.

[0036] A steel mill has signed a procurement contract for 1000 tons of iron ore with 62% grade with Supplier A (Contract No. HT20260601). The contract stipulates that the delivery date is June 10, 2026, the carrier is Carrier B Transportation Company, and the license plate number of the carrying vehicle is Lu A12345. The inspection and testing items specified in the contract include iron content, sulfur content, phosphorus content, silicon dioxide content and moisture content.

[0037] In step S1, after Supplier A completes loading, its supplier shipment system automatically sends loading performance information to the full-process closed-loop collaborative management system for procurement logistics oriented to steel mills, including: Contract No. "HT20260601", material information "62% grade iron ore", declared loading quantity 1000 tons, carrying vehicle identifier "Lu A12345", and loading completion time 14:30 on June 8, 2026. The supplier data docking unit verifies the loading performance information, and confirms that the contract is valid, the material information is consistent with the order, the declared loading quantity is within the allowable range of the order, and the carrying vehicle is in the qualified carrier list.

[0038] In step S2, the vehicle-mounted data acquisition unit calls the pre-installed load sensor mounted at the leaf spring support of the corresponding vehicle's rear suspension system according to the carrying vehicle identifier "Lu A12345", and broadcasts the total vehicle weight data in real time through the CAN bus interface according to the CAN ID (compliant with the SAE J1939 protocol). When the vehicle completes loading and starts for the first time, the sensor continuously collects stable weight values for 5 seconds, and calculates the average value to obtain the factory load reference value of 992 tons. The factory load reference value is cross-compared with the declared loading quantity of 1000 tons, and the calculated deviation is (1000-992) / 1000=0.8%, which is less than the preset threshold of ±3%, the verification is passed, and the vehicle is allowed to depart.

[0039] In step S3, during the transportation process, the vehicle-mounted data acquisition unit collects vehicle positioning, real-time load data and driving behavior safety event data in real time at a frequency of once every 10 seconds, associates them with the material information "62% grade iron ore" and the contract number HT20260601, and uploads them to the cloud platform.

[0040] In step S4, the in-transit inventory calculation unit performs the following operations: Dynamically calculate the estimated time of arrival (ETA) at the factory based on the real-time vehicle positioning, the preset transportation route (a-b-transit warehouse-steel mill), the historical transportation time efficiency statistical model and the real-time data of the transit warehouse, specifically: The historical transportation time efficiency statistical model is based on the historical transportation data of the route from a to b, in June, during the period from 8:00 to 20:00 in the past 12 months, and the average driving time of this road section is statistically obtained as 12 hours per 500 kilometers; Current time T_current = 8:00 AM on June 9, 2026. Based on the vehicle's current location, the remaining mileage is 350 kilometers. The historical average remaining driving time T_hist = 12 hours × (350 / 500) = 8.4 hours; The third-party real-time traffic interface shows that the current road segment is clear and the real-time remaining driving time T_real=8 hours; The remaining road transport time T_remaining is calculated using the following weighted formula: T_remaining = T_hist×w1 + T_real×w2; Where w1 and w2 are weighting coefficients, and w1+w2=1; in this embodiment, w1=0.4 and w2=0.6 are taken.

[0041] The remaining road transport time T_remaining = 8.4 × 0.4 + 8 × 0.6 = 8.16 hours; Next, we connect to the transfer warehouse and find that the current number of vehicles in the queue is 3. Based on the estimated waiting time, we obtain the estimated stay time in the transfer warehouse, T_transfer = 1.24 hours. The final calculation yields ETA = T_current + T_remaining + T_transfer = 8:00 AM on June 9, 2026 + 8.16 hours + 1.24 hours = 5:24 PM on June 9, 2026.

[0042] In addition, the real-time load data was continuously compared with the factory load benchmark value of 992 tons. The load variation during transportation was always within ±2%, and no abnormalities were found. The vehicle data acquisition unit did not detect serious safety events such as driver fatigue or distracted driving, and no safety warnings were triggered.

[0043] Finally, structured in-transit inventory data is generated based on ETA, including: material information "62% grade iron ore", quantity 992 tons, supplier A, carrier vehicle identification "Lu A12345", current location, estimated arrival time at the factory on June 9, 2026 at 17:24, and transit warehouse status "not arrived".

[0044] In step S5, the production scheduling coordination unit pushes the in-transit inventory data to the steel mill's production scheduling system. The steel mill's production scheduling system matches the corresponding blast furnace production process based on the material information "62% grade iron ore". It compares this batch of materials with the existing physical inventory of 300 tons and the already scheduled production plan. It confirms that the estimated arrival time at the plant on June 9, 2026 at 18:07 is earlier than the scheduled material demand time on June 10, 2026 at 8:00. It marks this as available in-transit inventory and includes it in the available production resource pool, confirming that the original production plan is feasible.

[0045] Execute step S6, such as Figure 3 As shown, at 17:21 on June 9, 2026, the vehicle arrived at the steel mill, and the materials were unloaded and sent to the quality inspection stage. The steel mill's quality inspection system conducted tests according to the five testing items stipulated in the contract. The results showed that the iron content was 61.8%, the sulfur content was 0.03%, the phosphorus content was 0.02%, the silicon dioxide content was 4.2%, and the moisture content was 8.5%, all within the allowable tolerance range. The quality inspection assessment unit received the test results data, which corresponded one-to-one with the contract number HT20260601, the material information "62% grade iron ore", and the vehicle identification "Lu A·12345", and was therefore deemed qualified.

[0046] In step S7, since the test results were normal, the system automatically generated a normal settlement statement and pushed it to the financial system for settlement. Simultaneously, data on loading accuracy, on-time delivery rate, quality inspection pass rate, load anomaly rate, and safety incident occurrence rate were recorded in the credit files of supplier A and carrier B.

[0047] This embodiment achieves fully automated closed-loop management of the iron ore procurement logistics process, from loading to settlement, without the need for manual intervention, thus significantly improving management efficiency.

[0048] Example 2: The difference between this example and Example 1 is that a real-time load anomaly is detected in step S4, which is used to illustrate the process of monitoring the integrity of goods in transit and handling anomalies.

[0049] A steel mill signed a purchase contract (contract number HT20260602) for 500 tons of coke with supplier C. The license plate number of the transport vehicle is Ji B67890.

[0050] In step S4, the in-transit inventory calculation unit detected a sudden drop in the vehicle's real-time load from 498 tons to 450 tons during transportation, a change of 9.6%, lasting for more than 30 seconds. The system immediately identified this as a cargo anomaly, triggering an in-transit anomaly alert and simultaneously notifying the steel mill's logistics department and carrier B via SMS, app push notifications, and system pop-ups.

[0051] After receiving the alert, the steel mill's logistics department immediately contacted carrier B to verify the situation. They discovered that some coke had spilled during transport due to a damaged tarpaulin on the vehicle. Carrier B immediately arranged for personnel to clean up and reload the vehicle at the nearest service area. After reloading, the vehicle's load capacity was restored to 497 tons. Once the system detected that the load capacity had returned to normal, the alert was lifted and the estimated arrival time at the mill was updated.

[0052] Execute subsequent steps S5 to S7 to complete the remaining transportation, scheduling coordination, and quality inspection and settlement processes. Simultaneously, the platform automatically generates a responsibility allocation report. Based on the time, location, and vehicle data of the anomaly, it determines that the anomaly was entirely caused by improper vehicle maintenance by Carrier B, with a responsibility ratio of 100%. This load anomaly event is recorded in Carrier B's credit file.

[0053] This embodiment enables automatic monitoring and early warning of the integrity of goods in transit, and can automatically assign responsibilities based on objective data, reducing disputes between upstream and downstream parties.

[0054] The present invention has been described in the above-described embodiments; however, these embodiments are merely examples for implementing the present invention. It must be noted that the disclosed embodiments do not limit the scope of the present invention. Conversely, any modifications and refinements made without departing from the spirit and scope of the present invention are within the scope of patent protection of the present invention.

[0055] The contents of this invention not described in detail are existing technologies known to those skilled in the art.

Claims

1. A steel plant-oriented procurement logistics whole-process closed-loop collaborative management method applied to a steel plant-oriented procurement logistics whole-process closed-loop collaborative management system comprising a supplier data docking unit, a vehicle-mounted data acquisition unit, an in-transit inventory calculation unit, a production scheduling collaboration unit, and a quality inspection assessment unit, characterized in that, Includes the following steps: S1: The supplier data docking unit receives and verifies the loading performance information sent by the supplier after loading is completed; The loading performance information shall include at least the contract number, material information, declared loading quantity, and carrier vehicle identification. S2: After the vehicle is loaded, the on-board data acquisition unit collects the factory load reference value through the pre-installed load sensor, and cross-compares the factory load reference value with the declared load quantity in the loading performance information to verify the authenticity of the loading. During the cross-comparison process, if the deviation exceeds the preset threshold, an abnormal loading warning will be triggered and the steel mill and supplier will be notified. S3: During transportation, the vehicle-mounted data acquisition unit collects vehicle positioning, real-time load data, and driving behavior safety event data in real time at a preset time frequency, and uploads them to the cloud platform. S4: The in-transit inventory calculation unit dynamically calculates the estimated arrival time (ETA) of each batch of materials based on the real-time uploaded vehicle location, transportation starting point, preset transportation route, and estimated dwell time at the transit warehouse, and generates structured in-transit inventory data based on the ETA. S5: The production scheduling coordination unit pushes the in-transit inventory data to the steel mill's production scheduling system to support the advance preparation or adjustment of the production scheduling plan and realize in-transit production scheduling decisions. S6: After the materials arrive at the factory, the quality inspection and assessment unit receives and tests the test results data from the steel plant's quality inspection system; The test results data correspond one-to-one with the contract number, material information and carrier vehicle identification; S7: When an abnormality is detected in the test results data, the quality inspection assessment unit automatically matches the corresponding supplier and carrier information, and generates and pushes the assessment deduction document according to the preset assessment rules.

2. The method of claim 1, wherein, In step S2, the load sensor acquires the total weight data of the vehicle through the CAN bus interface according to the preset CAN ID; the initial load reference value is the stable weight value collected when the vehicle is loaded and started for the first time.

3. The method of claim 1, wherein, In step S4, the specific method for dynamically calculating the estimated arrival time is as follows: ETA = T_current + T_remaining + T_transfer; Wherein, T_current is the current time, T_remaining is the remaining road transport time calculated based on the historical transport timeliness statistical model and real-time road conditions, and T_transfer is the expected stay time at the transit depot; the historical transport timeliness statistical model is a database of average travel time by road segment established based on historical transport data of the same transport route, the same time period, and the same season within a preset period in the past.

4. The method of claim 1, wherein, The driving behavior safety event data includes driver fatigue driving, distracted driving, forward collision warning, lane departure warning and sudden acceleration and deceleration events monitored by the vehicle data acquisition unit; The in-transit inventory data shall include at least the type and quantity of materials, supplier information, carrier information, vehicle location, estimated arrival time at the factory, and the status of transit warehouse stay; the assessment deduction document shall include at least the abnormal detection items, standard values, measured values, deviation range, deduction amount, and deduction basis.

5. The method of claim 4, wherein, Step S4 also includes: monitoring the transportation route based on the real-time uploaded vehicle location, monitoring the integrity of the goods based on the load data, and assessing the transportation safety risks based on the driving behavior safety event data. When the driving route deviates from the preset path or the dwell time exceeds the limit, the vehicle load changes abnormally, or the driver's driving behavior is risky, an on-the-road anomaly warning is immediately triggered and relevant management personnel are notified.

6. The method of claim 1, wherein, Step S5 specifically includes: S51: The production scheduling coordination unit will compare and analyze the in-transit inventory data with the steel mill's existing physical inventory data and the already scheduled production plan; S52: For materials whose estimated arrival time (ETA) is earlier than the material demand time for production scheduling, mark them as available inventory in transit and include them in available resources for production scheduling. S53: For materials whose estimated arrival time (ETA) lags behind the material requirements for production scheduling, automatically generate production scheduling adjustment suggestions, including postponing the corresponding production orders, initiating alternative material solutions, or adjusting the production rhythm.

7. The method of claim 6, wherein, Step S53 also includes: When there are multiple batches of materials whose estimated arrival time at the factory lags behind the production demand, the production urgency coefficient E of each lagging batch of materials is calculated, with the formula being: E = (T - T0) / T0 ; wherein, is a preset material importance weight, the of the main raw material is greater than the of the auxiliary raw material; is the available days of the existing physical inventory of the material, is a preset emergency weight corresponding to the production process, the of the core process is greater than the of the non-core process; , both satisfy greater than 0 and less than or equal to 1; Finally, the lagging batches of materials are sorted from high to low according to the production urgency coefficient E, and the production orders corresponding to the lagging batches of materials with high production urgency coefficient E are adjusted first.

8. The method of claim 1, wherein, In step S7, the abnormal test results include deviations in chemical composition, physical properties, and appearance quality defects. The quality inspection and assessment unit has a built-in abnormal judgment rule engine, which is used to determine an abnormality when the measured value of any test item pre-agreed in the purchase contract exceeds the preset allowable error range, and automatically associates the supplier and carrier according to the contract number, matching the preset tiered or fixed amount deduction standard.

9. The method of claim 1, wherein, Step S7 also includes: integrating historical loading verification data, transportation timeliness data, driving behavior safety event data, and quality inspection result data to generate a full lifecycle credit evaluation report for suppliers and carriers, providing data support for adjusting procurement share.