Oil production well site electric control cabinet remote monitoring system based on Internet of Things
By deploying the Internet of Things oil production well site electric control cabinet remote monitoring system at the oil production well site, the problem of difficulty in monitoring the real-time working conditions of the well site electric control cabinet equipment has been solved, real-time monitoring of equipment status and rapid fault handling have been achieved, and maintenance has been improved. efficiency and reduced downtime, achieving cost reduction and efficiency increase in oil production operations.
Patent Information
- Application Number
- CN202420265988.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-02
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-02-02
AI Technical Summary
At oil production well sites, it is difficult to monitor the real-time working conditions of well site electrical control cabinet equipment in real time, resulting in maintenance relying on manual inspections, which is inefficient and takes a long time to deal with faults, resulting in downtime losses and impact on the operation process.
Design a remote monitoring system for oil production wellsite electric control cabinets based on the Internet of Things, including a data collection gateway and 4GDTU. It collects equipment data through a variety of interfaces and uploads it to the cloud Web platform to achieve real-time monitoring and management. It supports Modbus RTU/TCP protocol. , using MQTT protocol and Node.js/HTML5 technology, to provide real-time working condition monitoring, fault alarm and remote guidance functions.
It enables equipment maintenance personnel to check the status of well team equipment in real time, reduce the intensity of inspections, detect faults in time, improve maintenance efficiency, reduce downtime, reduce maintenance costs, and achieve cost reduction and efficiency increase in oil production operations.
Smart Images

Figure CN221863005U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to a remote monitoring system for an electric control cabinet in an oil well field based on the Internet of Things, and belongs to the technical field of electronic communications in an oil well field. Background Art
[0002] In drilling and oil production operations, compared with traditional diesel engine mechanical drive and hydraulic drive, electric drive technology has the advantages of high transmission efficiency, high control accuracy, energy saving and environmental protection. Modern oil production well sites are generally equipped with special electric control rooms, which are equipped with winch control cabinets, turntable control cabinets, drilling pump control cabinets, automatic drill feed control cabinets, etc. The frequency conversion speed regulation system with the frequency converter as the core drives the asynchronous motor, and is connected to the winch, turntable and other equipment through the coupling for oil production operations. The electric control cabinet of the oil production well site is a key equipment for oil and gas production operations. If the frequency converter fails and stops, it will directly lead to the cessation of oil production operations. Therefore, the maintenance of the electric control cabinet equipment is very important.
[0003] With the advancement of digital oilfield and smart oilfield construction, many oil production wells have been digitalized and upgraded, and some important oil and gas production parameters (such as drilling and logging information) have been connected to the remote monitoring system of the oil production company. However, for the real-time working conditions of the equipment in the well field electrical control cabinet, due to the variety of equipment models, communication interfaces and protocols, data acquisition is relatively difficult, and remote monitoring systems are rarely connected, and manual maintenance is still the main method. Since the well field is usually located in a remote area and scattered, the equipment maintenance personnel cannot remotely obtain the real-time working conditions of the equipment in the well field electrical control cabinet. They can only take regular inspections or telephone reports from the field staff of the well team, which is labor-intensive and inefficient. When the equipment in the electrical control cabinet fails, only professional equipment maintenance personnel can rush to the site to shut down and troubleshoot. After identifying the cause of the fault, secondary processing such as replacement of accessories is often required. The fault handling time is long, which not only causes downtime losses, but also affects the normal drilling and oil production process. Utility Model Content
[0004] The purpose of this application is to provide an Internet of Things-based remote monitoring system for electrical control cabinets in oil production well sites, to overcome the defects of existing manual maintenance methods, to effectively improve the maintenance efficiency of electrical control cabinet equipment, to reduce maintenance costs, to reduce downtime of oil production operations, and to achieve the goal of reducing costs and increasing efficiency of oil production operations.
[0005] To achieve the above objectives, the first aspect of the present application provides an Internet of Things-based remote monitoring system for electric control cabinets in oil well sites, comprising:
[0006] Data acquisition gateway, 4GDTU and Web platform;
[0007] The data acquisition gateway is installed on site, and includes an RS-232 interface, an RS-485 interface, an Ethernet interface, and a multi-channel digital input interface, for collecting the operating data of the on-site equipment, and uploading the collected operating data to the Web platform through the 4GDTU;
[0008] The Web platform is deployed in the cloud and is used to monitor and manage the real-time working status of the on-site equipment according to the operating data uploaded by the 4GDTU.
[0009] Optionally, the operating data of the on-site equipment includes: inverter operating parameters and motor start and stop information;
[0010] The data acquisition gateway is specifically used for:
[0011] Connecting to the frequency converter in the electric control cabinet through the RS-485 interface and the Ethernet interface, and collecting the frequency converter operating parameters based on the Modbus RTU / TCP protocol;
[0012] Connecting to the contactor in the electric control cabinet through the multi-channel digital input interface and collecting the motor start and stop information;
[0013] The inverter operating parameters and the motor start and stop information are sent to 4GDTU via the RS-232 interface.
[0014] Optionally, the 4GDTU includes: a triple-network LTE 4G network module for data transmission, a TCP / UDP data transparent transmission module and an MQTT standard Internet of Things protocol module.
[0015] Optionally, the 4GDTU includes: a device authentication and authority management module for ensuring the security of the data transmission process.
[0016] Optionally, the Web platform is constructed based on Node.js and HTML5 technologies, and deployed in the cloud based on a public cloud server.
[0017] Optionally, the Web platform includes:
[0018] A TCP / MQTT access module, used for receiving the operation data uploaded by the 4GDTU through TCP transparent transmission or MQTT protocol;
[0019] The time series database module is used to store the received operation data for a long time.
[0020] Optionally, the Web platform further includes:
[0021] A real-time working condition monitoring module, used to monitor the real-time working condition of the on-site equipment based on the operating data uploaded by the 4GDTU;
[0022] A historical curve query module, used to query the historical operating condition curve of the local equipment based on the operation data stored in the time series database module for a long time;
[0023] The health status monitoring module is used to monitor the health status of the on-site equipment based on the operation data stored in the time series database module for a long time.
[0024] Optionally, the Web platform includes:
[0025] The fault alarm / early warning module is used to send out alarm signals and fault code information when a fault occurs in the remote monitoring system of the electric control cabinet of the oil well site or in the on-site equipment.
[0026] Optionally, the Web platform includes:
[0027] The display module is used to provide a front-end display page based on the PC and mobile phone Web browsers, and to receive remote guidance instructions input by the user.
[0028] A second aspect of the present application provides an oil well site electric control cabinet, comprising: the oil well site electric control cabinet is internally provided with an oil well site electric control cabinet remote monitoring system as described in any one of the first aspects of the present application.
[0029] The beneficial effect of the remote monitoring system of the electric control cabinet of the oil well site based on the Internet of Things provided by the present application is that: compared with the prior art, the system provided by the present application is applied to the oil well site, which is convenient for equipment maintenance personnel to view the working status of the on-site equipment of the well team in real time, greatly reducing the intensity of inspection work. In addition, when equipment failures occur, it is also convenient for staff to discover and deal with them in time. It effectively improves the maintenance efficiency of the electric control cabinet equipment, reduces maintenance costs, reduces the downtime of oil production operations, and achieves the purpose of reducing costs and increasing efficiency of oil production operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0031] Figure 1 A schematic diagram of the structure of a remote monitoring system for an electric control cabinet in an oil well site provided in an embodiment of the present application;
[0032] Figure 2 A schematic diagram of a configuration of a local data acquisition gateway for a well team provided in an embodiment of the present application;
[0033] Figure 3 A schematic diagram of a web platform access page for a well crew provided in an embodiment of the present application. DETAILED DESCRIPTION
[0034] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0035] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0036] It should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0037] like Figure 1 As shown, an embodiment of the present application provides an Internet of Things-based remote monitoring system for electric control cabinets in oil well sites, which consists of a data acquisition gateway installed on site, a 4G DTU (data transmission unit) and a Web platform deployed in the cloud.
[0038] The data acquisition gateway includes an RS-232 interface, an RS-485 interface, an Ethernet interface and a multi-channel digital input interface, which are used to collect the operating data of the local equipment, and upload the collected operating data to the Web platform through the 4GDTU; the Web platform is used to monitor and manage the real-time working status of the local equipment according to the operating data uploaded by the 4GDTU.
[0039] As can be seen from the above, the oil well site electric control cabinet remote monitoring system based on the Internet of Things provided by the embodiment of the present application is applied to the oil well site, which is convenient for equipment maintenance personnel to view the working status of the on-site equipment of the well team in real time, greatly reducing the intensity of inspection work. In addition, when equipment failures occur, it is also convenient for staff to discover and handle them in time. It effectively improves the maintenance efficiency of electric control cabinet equipment, reduces maintenance costs, reduces oil production downtime, and achieves the purpose of reducing costs and increasing efficiency in oil production operations.
[0040] In one embodiment, the data acquisition gateway can be installed inside the electric control cabinet (electric control room or electric control room) of the oil well site, so as to collect the operating data of various on-site equipment such as the inverter working parameters, motor start and stop status, ambient temperature and humidity through various interfaces, and upload the collected operating data to the cloud platform through 4G DTU.
[0041] In one embodiment, when the operating data of the on-site equipment includes inverter operating parameters and motor start-stop information, the data acquisition gateway is specifically used to: connect to the inverter in the electric control cabinets such as the winch control cabinet and the turntable control cabinet through the RS-485 interface and / or the Ethernet interface, and collect the inverter operating parameters such as the real-time speed, output current, bus voltage, fault code, etc. of the inverter based on the Modbus RTU / TCP protocol; connect to the auxiliary contacts of the low-voltage contactor and vacuum contactor in the MCC (motor control center) cabinet in the electric control cabinet through the multi-channel digital input interface, and collect motor start-stop information. Among them, the multi-channel digital input interface can be set to a 12-channel digital input interface according to actual needs.
[0042] In one embodiment, when the operating data of the on-site equipment includes data such as ambient temperature and humidity, it can also be connected to equipment such as a temperature and humidity monitor through an RS-485 interface to collect corresponding data.
[0043] In one implementation, the data acquisition gateway sends data such as the inverter operating parameters, motor start and stop information, and ambient temperature and humidity to the 4GDTU via the RS-232 interface.
[0044] In one embodiment, the 4GDTU includes: a three-network LTE 4G network module for data transmission, supporting the three-network LTE 4G networks of China Mobile / China Unicom / China Telecom; a TCP / UDP data transparent transmission module, supporting the TCP / UDP data transparent transmission function; and an MQTT standard Internet of Things protocol module, supporting the MQTT standard Internet of Things protocol.
[0045] The embodiment of the present application provides a data acquisition gateway with multiple different communication interfaces and a 4GDTU that supports multiple communication protocols and data transmission modes to realize real-time collection of operating data of different on-site equipment, solve the problem that the real-time working conditions of the equipment in the well site electrical control cabinet are difficult to obtain data due to the variety of equipment models, communication interfaces and protocols, and has a wide range of applications.
[0046] In one embodiment, the 4GDTU also includes: a device authentication and authority management module for ensuring the security of the data transmission process, supporting a variety of device authentication and authority management functions, and being able to safely and reliably send the electric control cabinet operation data collected by the data acquisition gateway to the cloud Web platform.
[0047] In one embodiment, the backend of the Web platform is developed based on Node.js, and the frontend is developed based on HTML5 technology, and is deployed on a public cloud server (such as Alibaba Cloud, Tencent Cloud, etc.).
[0048] In one embodiment, the Web platform includes: a TCP / MQTT access module, which realizes receiving the operation data uploaded by the 4GDTU through TCP transparent transmission or MQTT protocol; and a time series database module, which realizes long-term storage of the received operation data.
[0049] In one embodiment, the Web platform also includes: multiple functional modules such as real-time working condition monitoring, historical curve query, health status monitoring, fault alarm / warning, etc., and provides a front-end display page for users through a display module.
[0050] In one embodiment, the real-time operating condition monitoring module is used to monitor the real-time operating condition of the on-site equipment based on the operating data uploaded by the 4GDTU; the historical curve query module is used to query the historical operating condition curve of the on-site equipment based on the operating data stored in the time series database module for a long time; the health status monitoring module is used to monitor the health status of the on-site equipment based on the operating data stored in the time series database module for a long time.
[0051] In one embodiment, the fault alarm / early warning module is used to send out an alarm signal and fault code information when a fault occurs in the remote monitoring system of the electric control cabinet or the on-site equipment at the oil well site. For example, when the system exceeds the data limit or the equipment fails, an alarm signal and fault code information can be sent out through a web page prompt or SMS to notify the on-site staff at the well site to handle it in time.
[0052] In one embodiment, the display module is used to provide users with front-end display pages based on PC and mobile phone web browsers, and to receive remote guidance instructions input by users. Equipment maintenance personnel can conveniently view the real-time working status of on-site equipment on PC and mobile phones, greatly reducing the intensity of inspection work. At the same time, in the case of some minor faults, the on-site staff of the well site can be guided by the system to handle them in a timely manner without rushing to the site.
[0053] An embodiment of the present application further provides an oil well site electric control cabinet, comprising: the oil well site electric control cabinet is internally provided with an oil well site electric control cabinet remote monitoring system as described in any of the above embodiments.
[0054] like Figure 2-3As shown, the embodiment of the present application also provides an application scenario. This application scenario takes a well team of Daqing Oilfield Drilling Company No. 2 as an example. The well team is equipped with an independent electric control room, including a turntable control cabinet, a winch control cabinet and a drilling pump control cabinet. A total of one ABB ACS880 inverter and two Huichuan MD480 inverters are used to control three motors. Among them, the ACS880 inverter has a FENA-01 communication module and supports Modbus TCP communication; the MD480 inverter has an RS-485 interface and supports Modbus RTU communication. In addition, an environmental temperature and humidity monitor with an RS-485 interface that supports Modbus RTU communication is also configured on site. Since the well team is not equipped with an MCC cabinet, the multi-channel digital input interface of the data acquisition gateway in this embodiment is not used.
[0055] Optionally, a data acquisition gateway is installed in the power distribution cabinet inside the electric control room of the well team. The data acquisition gateway is configured as follows: Figure 2 As shown in the figure, the RS-485 bus of the data acquisition gateway is used to connect two MD480 inverters and the ambient temperature and humidity monitor, and the inverter operation status word, real-time speed, output current, bus voltage, fault code, and the ambient temperature and humidity data of the electric control room are collected through the Modbus RTU protocol. The Ethernet interface of the data acquisition gateway is used to connect the ACS880 inverter, and the inverter operation status word, real-time speed, output current, bus voltage, and fault code information are collected through the ModbusTCP protocol.
[0056] Optionally, install 4G DTU and high-gain antenna in the open air outside the electric control room to prevent the signal from being blocked. The 4G DTU model is TAS-LTE-360. Insert the Alibaba Cloud IoT card and connect to the 4G network of China Mobile / China Unicom / China Telecom. Use the RS-232 interface of the data acquisition gateway to connect to the 4G DTU and upload the collected inverter operation data and the temperature and humidity data of the electric control room environment to the cloud.
[0057] Optionally, the Web platform uses the MQTT protocol to access 4G DTU data, uses the OpenTSDB database to store the operation data of the electric control cabinet, uses the Node.js backend and the Vue front-end framework to build a Web server, and deploys it in the Alibaba Cloud ECS cloud server. The mobile terminal accesses the Web platform page as follows Figure 3 shown.
[0058] The above is a detailed description of a remote monitoring system for an electric control cabinet in an oil well site provided in an embodiment of the present application. For a general technician in this field, according to the idea of the embodiment of the present application, there will be changes in the specific implementation method and the scope of application. In summary, the content of this specification should not be understood as a limitation on the present application, and any changes made according to the design idea of the present application are within the scope of protection of the present application.
Claims
1. A remote monitoring system for electric control cabinets in oil well sites based on the Internet of Things, characterized in that: include: Data acquisition gateway, 4GDTU and Web platform; The data acquisition gateway is installed on site, and includes an RS-232 interface, an RS-485 interface, an Ethernet interface, and a multi-channel digital input interface, for collecting the operating data of the on-site equipment, and uploading the collected operating data to the Web platform through the 4GDTU; The Web platform is deployed in the cloud and is used to monitor and manage the real-time working status of the on-site equipment according to the operating data uploaded by the 4GDTU.
2. The remote monitoring system for electric control cabinets in oil production well sites according to claim 1, characterized in that: The operating data of the on-site equipment includes: inverter operating parameters and motor start and stop information; The data acquisition gateway is specifically used for: Connecting to the frequency converter in the electric control cabinet through the RS-485 interface and the Ethernet interface, and collecting the frequency converter operating parameters based on the ModbusRTU / TCP protocol; Connecting to the contactor in the electric control cabinet through the multi-channel digital input interface and collecting the motor start and stop information; The inverter operating parameters and the motor start and stop information are sent to 4GDTU via the RS-232 interface.
3. The remote monitoring system for electric control cabinets in oil production well sites according to claim 1 or 2, characterized in that: The 4GDTU includes: a three-network LTE 4G network module for data transmission, a TCP / UDP data transparent transmission module and an MQTT standard Internet of Things protocol module.
4. The remote monitoring system for electric control cabinets in oil production well sites according to claim 1 or 2, characterized in that: The 4GDTU includes: a device authentication and authority management module for ensuring the security of the data transmission process.
5. The remote monitoring system for electric control cabinets in oil production well sites according to claim 1 or 2, characterized in that: The Web platform is constructed based on Node.js and HTML5 technologies, and is deployed in the cloud based on a public cloud server.
6. The oil well site electric control cabinet remote monitoring system according to claim 1 or 2, characterized in that: The web platform includes: A TCP / MQTT access module, used for receiving the operation data uploaded by the 4GDTU through TCP transparent transmission or MQTT protocol; The time series database module is used to store the received operation data for a long time.
7. The remote monitoring system for electric control cabinets in oil production well sites according to claim 6, characterized in that: The web platform also includes: A real-time working condition monitoring module, used to monitor the real-time working condition of the on-site equipment based on the operating data uploaded by the 4GDTU; A historical curve query module, used to query the historical operating condition curve of the local equipment based on the operation data stored in the time series database module for a long time; The health status monitoring module is used to monitor the health status of the on-site equipment based on the operation data stored in the time series database module for a long time.
8. The remote monitoring system for electric control cabinets in oil well fields according to claim 1 or 2, characterized in that: The web platform includes: The fault alarm / early warning module is used to send out alarm signals and fault code information when a fault occurs in the remote monitoring system of the electric control cabinet of the oil well site or in the on-site equipment.
9. The remote monitoring system for electric control cabinets in oil production well sites according to claim 1 or 2, characterized in that: The web platform includes: The display module is used to provide a front-end display page based on the PC and mobile phone Web browsers, and to receive remote guidance instructions input by the user.
10. An electric control cabinet for oil well field, characterized in that: The oil production well site electric control cabinet is provided with an oil production well site electric control cabinet remote monitoring system as claimed in any one of claims 1 to 9.
Citation Information
Cited By
Oil well intelligent terminal system
CN120238841A