Continuous preparation device for deuterated sodium methoxide
By designing a continuous preparation device for sodium deuterated methoxide and using components such as a quantitative tank and an electronically controlled dosing valve, the problem of uneven reaction and quality in the preparation of sodium deuterated methoxide has been solved, and the continuous small-batch preparation of sodium deuterated sodium methoxide has been achieved. and uniform reaction, ensuring product quality and preparation efficiency.
Patent Information
- Application Number
- CN202420419696.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-05
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-05
AI Technical Summary
In the preparation process of large quantities of sodium deuterated methoxide, it is difficult to ensure the uniformity and quality of the reaction, which leads to difficulties in spot inspection and rework after packaging, as well as insufficient reaction problems.
A continuous preparation device for sodium deuterated methoxide is designed, including a dosing tank, a heating component, an electronically controlled dosing valve and a piston. The piston position is detected by a stroke sensor, and gas entry and heating are controlled to ensure uniform and sufficient reaction, and through triggering Switches and catalyst tubes speed up reactions.
The continuous small-batch preparation of sodium deuterated methoxide is realized, which facilitates packaging and sampling inspection, ensures the uniformity and quality of the reaction, and improves the preparation efficiency and quality of the product.
Smart Images

Figure CN221868386U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of chemical industry, in particular to a device for continuously preparing deuterated sodium methoxide. Background Art
[0002] Sodium is a very active metal that reacts with hydroxide to produce sodium hydroxide and hydrogen. In deuterated methanol, the hydrogen atoms are replaced by deuterium atoms, so the gas produced in this reaction is deuterium gas.
[0003] In the process of industrial preparation of sodium deuterated methanol, if large quantities of sodium deuterated methanol are prepared, it will cause difficulties in the random inspection of deuterated methanol, that is, the entire packaging process must be completed before random inspection. If quality problems occur, the same batch of preparation and packaging must be reworked. At the same time, in the preparation of large quantities of sodium deuterated methanol, uniform heating cannot be guaranteed, resulting in insufficient reaction.
[0004] Therefore, we propose a continuous preparation device for deuterated sodium methoxide, which is conducive to the continuous small-batch preparation of deuterated sodium methoxide, convenient for continuous packaging and sampling, and conducive to uniform heating so that the reaction can fully guarantee the product quality. Utility Model Content
[0005] In order to overcome the above-mentioned defects of the prior art, the utility model provides a continuous preparation device for deuterated sodium methoxide to solve the problems existing in the above-mentioned background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a deuterated sodium methoxide continuous preparation device, comprising a quantitative tank body, a heating assembly is installed on the outer wall of the quantitative tank body, a round table is connected to the bottom of the quantitative tank body, a first gas pipe and a second gas pipe are connected to the left and right sides of the round table respectively, the first gas pipe and the second gas pipe are both connected to an electrically controlled quantitative valve, a piston is slidably arranged inside the quantitative tank body, and a rod body at the top of the piston penetrates the quantitative tank body and is connected to a discharge assembly;
[0007] The discharge assembly comprises an electric push rod and a stroke sensor, the push rod drives the piston to reach the bottom of the quantitative tank, and the stroke sensor reaches a maximum value, and the maximum value signal output end of the stroke sensor is connected to the start signal input end of the electric-controlled quantitative valve;
[0008] The push rod drives the piston to reach the top of the quantitative tank, and the stroke sensor reaches the minimum value, and the minimum value signal output end of the stroke sensor is connected to the closing signal input end of the electric-controlled quantitative valve.
[0009] Further: a trigger switch is installed on the top of the quantitative tank body, and the outer wall of the quantitative tank body is connected to a catalyst tube. The trigger switch starts the additive in the catalyst tube to immerse into the quantitative tank body, and the signal output end of the trigger switch is connected to the signal input end of the heating component.
[0010] Furthermore: the push rod drives the piston to reach the top of the quantitative tank body, and the piston squeezes the trigger switch.
[0011] Further: the bottom of the truncated cone is connected to a discharge valve through a discharge pipe, and the inner diameter of the truncated cone is smaller than the inner diameter of the quantitative tank.
[0012] Further: the heating component includes an electric heating plate and a temperature control module, the electric heating plate is attached to the outer wall of the quantitative tank, and the temperature control module is used to control the temperature of the electric heating plate.
[0013] Furthermore: the electrically controlled quantitative valve comprises a valve component and an electrically controlled component, the valve component controls the on-off of the gas pipeline, and the electrically controlled component notifies the valve component of the opening and closing time.
[0014] Compared with the prior art, the technical effects and advantages of the utility model are as follows:
[0015] 1) The deuterated sodium methoxide continuous preparation device of the utility model is provided with a quantitative tank body, a discharge component, an electric-controlled quantitative valve and a piston. The stroke sensor detects that the piston moves to the maximum value, and then the electric-controlled quantitative valve is started, and then the external gas enters the quantitative tank body through the first gas pipe and the second gas pipe. After the stroke sensor detects that the piston moves to the minimum value, the electric-controlled quantitative valve is closed, and the heating component is started to prepare the deuterated sodium methoxide. The piston is pushed by starting the discharge component, and then the product is discharged through the discharge valve, which is conducive to the continuous small batch preparation of deuterated sodium methoxide, convenient for continuous packaging and sampling, and conducive to uniform heating so that the reaction is sufficient to ensure product quality.
[0016] 2) The deuterated sodium methoxide continuous preparation device of the utility model, through the setting of the trigger switch and the catalyst tube, drives the piston to move to the top of the quantitative tank body through the electric push rod, and then the piston squeezes the trigger switch and the catalyst tube enters the quantitative tank body, and the heating component is started simultaneously, thereby accelerating the reaction, which is beneficial to accelerate the reaction after the quantitative tank body material is filled according to the proportion. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic diagram of the overall structure of the continuous preparation device for deuterated sodium methoxide of the utility model;
[0018] Figure 2 This is a schematic cross-sectional view of the overall internal structure of the continuous preparation device for deuterated sodium methoxide of the utility model;
[0019] Figure 3 This is a schematic diagram of the valve assembly structure of the deuterated sodium methoxide continuous preparation device of the utility model;
[0020] Figure 4 The utility model is a schematic diagram of the heating component structure of the continuous preparation device of deuterated sodium methoxide.
[0021] The accompanying drawings are marked as follows: 1. quantitative tank; 11. trigger switch; 12. round table; 2. first gas pipe; 3. electric-controlled quantitative valve; 31. valve assembly; 32. electric control assembly; 4. discharge valve; 5. discharge pipe; 6. second gas pipe; 7. catalyst tube; 8. heating assembly; 81. electric heating plate; 82. temperature control module; 9. discharge assembly; 91. piston. DETAILED DESCRIPTION
[0022] The technical solution of the present invention will be clearly and completely described below in conjunction with the drawings in the present invention. In addition, the forms of the various structures recorded in the following embodiments are merely illustrative, and the structures involved in the present invention are not limited to the various structures recorded in the following embodiments. All other implementations obtained by ordinary technicians in this field without making creative work belong to the scope of protection of the present invention.
[0023] Example:
[0024] See also Figure 1-4 The utility model provides a technical solution: a continuous preparation device for deuterated sodium methoxide, comprising a quantitative tank body 1, a heating assembly 8 is installed on the outer wall of the quantitative tank body 1, a round platform 12 is connected to the bottom of the quantitative tank body 1, and the left and right sides of the round platform 12 are respectively connected to a first gas pipe 2 and a second gas pipe 6, the first gas pipe 2 and the second gas pipe 6 are both connected to an electrically controlled quantitative valve 3, and different external gas tanks are respectively connected to the first gas pipe 2 and the second gas pipe 6, a piston 91 is slidably arranged inside the quantitative tank body 1, and the top rod of the piston 91 passes through the quantitative tank body 1 and is connected to a discharge assembly 9, the piston 91 moves up and down in the quantitative tank body 1, and the piston 91 moves from top to bottom in the quantitative tank body 1 to discharge the product of the quantitative tank body 1; the discharge component 9 contains an electric push rod and a stroke sensor, the push rod drives the piston 91 to reach the bottom of the quantitative tank body 1, and the stroke sensor reaches the maximum value, and the maximum value signal output end of the stroke sensor is connected to the start signal input end of the electric-controlled quantitative valve 3; the push rod drives the piston 91 to the top of the quantitative tank body 1, and the stroke sensor reaches the minimum value, and the minimum value signal output end of the stroke sensor is connected to the closing signal input end of the electric-controlled quantitative valve 3;
[0025] The stroke sensor detects that the piston 91 moves to the maximum value, and then the electronically controlled quantitative valve 3 is started, and then the external gas enters the quantitative tank body 1 through the first gas pipe 2 and the second gas pipe 6. After the stroke sensor detects that the piston 91 moves to the minimum value, the electronically controlled quantitative valve 3 is closed, and the heating component 8 is started to carry out deuterated sodium methoxide. The piston 91 is pushed by starting the discharge component 9, and then the product is discharged through the discharge valve 4, which is conducive to the continuous small batch preparation of deuterated sodium methoxide, convenient for continuous packaging and random inspection, and conducive to uniform heating so that the reaction is fully guaranteed to ensure product quality.
[0026] A trigger switch 11 is installed at the top of the quantitative tank body 1, and the outer wall of the quantitative tank body 1 is connected to the catalyst tube 7. The trigger switch 11 starts the additive in the catalyst tube 7 to immerse into the quantitative tank body 1, and the push rod drives the piston 91 to reach the top of the quantitative tank body 1. The piston 91 squeezes the trigger switch 11, and the signal output end of the trigger switch 11 is connected to the signal input end of the heating component 8;
[0027] When the piston 91 moves to the top of the quantitative tank body 1, the piston 91 squeezes the trigger switch 11, and the catalyst tube 7 enters the quantitative tank body 1, and the heating component 8 is started simultaneously to accelerate the reaction, which is beneficial to accelerate the reaction after the quantitative tank body 1 is filled with materials in proportion.
[0028] Among them, the bottom of the truncated cone 12 is connected to a discharge valve 4 through a discharge pipe 5. The inner diameter of the truncated cone 12 is smaller than the inner diameter of the quantitative tank body 1. The piston 91 moves to the bottom of the quantitative tank body 1, opens the discharge valve 4, and allows the product to be discharged through the discharge pipe 5.
[0029] Among them, the heating component 8 includes an electric heating plate 81 and a temperature control module 82. The electric heating plate 81 is attached to the outer wall of the quantitative tank body 1. The temperature control module 82 is used to control the temperature of the electric heating plate 81. The temperature control module 82 controls the temperature drop of the electric heating plate 81 to ensure that the temperature is maintained at 260°-350°.
[0030] Among them, the electrically controlled quantitative valve 3 includes a valve component 31 and an electrically controlled component 32. The valve component 31 controls the on and off of the gas pipeline, and the electrically controlled component 32 notifies the valve component 31 of the opening and closing time. The on and off time of the valve component 31 is controlled by the electrically controlled component 32, and the valve opening time can be set by the central control time relay. Since the gas flow speed in the pipeline is constant, the amount of material delivered to the quantitative tank 1 can be obtained based on the valve opening time and the gas flow rate in the pipeline.
[0031] The working principle in the embodiment of the utility model is as follows: the on-off time of the valve assembly 31 is controlled by the electric control assembly 32, and the valve opening time can be set by the time relay of the central control. Since the gas flow speed in the pipeline is constant, the amount of material fed into the quantitative tank body 1 can be obtained according to the valve opening time and the gas flow rate in the pipeline. The piston 91 is driven up and down in the quantitative tank body 1 by the electric push rod, and the piston 91 is detected to move to the maximum value by the stroke sensor, and then the electric control quantitative valve 3 is started, and then the external gas enters the quantitative tank body 1 through the first gas pipe 2 and the second gas pipe 6. After the stroke sensor detects that the piston 91 moves to the minimum value, the electric control quantitative valve 3 is closed;
[0032] The piston 91 is driven by an electric push rod to move to the top of the quantitative tank body 1, and then the piston 91 squeezes the trigger switch 11, so that the catalyst tube 7 enters the quantitative tank body 1, and the heating component 8 is started simultaneously to prepare deuterated sodium methoxide. The temperature of the electric heating plate 81 is controlled to drop by the temperature control module 82 to ensure that the temperature is maintained at 260°-350°. The piston 91 is pushed by starting the discharge component 9, and the product is discharged from the discharge pipe 5 through the discharge valve 4.
[0033] The above shows and describes the basic principles and main features of the utility model and the advantages of the utility model. For those skilled in the art, it is obvious that the utility model is not limited to the details of the above exemplary embodiments, and the utility model can be implemented in other specific forms without departing from the spirit or basic features of the utility model; therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the utility model is limited by the attached claims rather than the above description. Therefore, it is intended to include all changes within the meaning and scope of the equivalent elements of the claims in the utility model, and any figure marks in the claims should not be regarded as limiting the claims involved.
[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A continuous preparation device for deuterated sodium methoxide, comprising a quantitative tank body (1), the outer wall of which is provided with a heating assembly (8), the bottom of which is connected to a truncated cone (12), the left and right sides of which are respectively connected to a first gas pipe (2) and a second gas pipe (6), characterized in that: The first gas pipe (2) and the second gas pipe (6) are both connected to an electrically controlled quantitative valve (3); a piston (91) is slidably arranged inside the quantitative tank body (1); a rod at the top of the piston (91) penetrates the quantitative tank body (1) and is connected to a discharge assembly (9); The discharge assembly (9) comprises an electric push rod and a stroke sensor, the push rod drives the piston (91) to reach the bottom of the quantitative tank (1), and the stroke sensor reaches a maximum value, and the maximum value signal output end of the stroke sensor is connected to the start signal input end of the electric-controlled quantitative valve (3); The push rod drives the piston (91) to reach the top of the quantitative tank (1), and the stroke sensor reaches the minimum value, and the minimum value signal output end of the stroke sensor is connected to the closing signal input end of the electric-controlled quantitative valve (3).
2. A continuous preparation device for deuterated sodium methoxide according to claim 1, characterized in that: A trigger switch (11) is installed at the top of the quantitative tank body (1), and the outer wall of the quantitative tank body (1) is connected to a catalyst tube (7). The trigger switch (11) starts the additive in the catalyst tube (7) to immerse into the quantitative tank body (1), and the signal output end of the trigger switch (11) is connected to the signal input end of the heating component (8).
3. A continuous preparation device for sodium deuterated methoxide according to claim 2, characterized in that: The push rod drives the piston (91) to reach the top of the quantitative tank (1), and the piston (91) squeezes the trigger switch (11).
4. A continuous preparation device for deuterated sodium methoxide according to claim 1, characterized in that: The bottom of the truncated platform (12) is connected to a discharge valve (4) via a discharge pipe (5), and the inner diameter of the truncated platform (12) is smaller than the inner diameter of the quantitative tank body (1).
5. A continuous preparation device for deuterated sodium methoxide according to claim 1, characterized in that: The heating assembly (8) comprises an electric heating plate (81) and a temperature control module (82); the electric heating plate (81) is attached to the outer wall of the quantitative tank body (1); and the temperature control module (82) is used to control the temperature of the electric heating plate (81).
6. A continuous preparation device for deuterated sodium methoxide according to claim 1, characterized in that: The electrically controlled quantitative valve (3) comprises a valve component (31) and an electrically controlled component (32), wherein the electrically controlled component (32) notifies the valve component (31) of the opening and closing times.