Self-loading, unloading, transferring and storing tool for offshore wind power tower drum
By introducing hydraulic telescopic rods and arc-shaped pallet splint structures into the offshore wind power tower self-loading, unloading and transporting storage tooling, a low center of gravity installation and docking is achieved, which solves the problem of tower tipping during transportation and improves transportation stability.
Patent Information
- Application Number
- CN202420027817.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-05
AI Technical Summary
The existing self-loading, unloading and transporting storage tooling for offshore wind power towers lacks a low center of gravity installation and docking structure, resulting in longer towers being prone to tipping over during transportation.
A self-loading, unloading, and storage tool for offshore wind power towers is designed, which includes a placement plate, an arc-shaped pallet, a hydraulic telescopic rod, and a splint. The low-center-of-gravity installation and docking is achieved through the control of the hydraulic telescopic rod, and the arc-shaped pallet and plywood are used to fix the tower. tube to prevent tipping.
It effectively reduces the center of gravity of the wind power tower, avoids the danger of tipping due to excessive center of gravity during transportation, and improves the transportation stability of the tower.
Smart Images

Figure CN221915519U_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of wind turbine towers, and in particular relates to a self-loading, unloading, and storage tooling for offshore wind turbine towers. Background Art
[0002] A wind turbine tower is a pole for wind power generation. It plays a major supporting role in a wind turbine generator set and absorbs vibrations of the unit. It is also often used as a component of offshore wind power generation. Before the wind turbine tower is formally assembled, a corresponding tooling structure capable of storing and transporting the tower is required. In order to increase the convenience of its storage and transportation, self-loading and unloading storage tooling is often used to store and transport the tower. This can reduce the use of large lifting machinery to a certain extent and increase the efficiency of storage and transportation.
[0003] The utility model with the existing authorization announcement number CN216581552U discloses a self-loading, unloading and storage tooling for offshore wind power towers. A plurality of rows of arc-shaped mounting holes are cut on the pallet according to the mounting hole positions of tower flanges of different diameters. The pallet is suitable for the installation and transportation of lower tower sections of different specifications, thereby achieving the purpose of reducing costs and increasing efficiency. At the same time, the arc-shaped mounting holes are long holes, which are fixed corresponding to the mounting holes of the tower flanges, effectively shortening the lifting time and improving work efficiency.
[0004] Although the above technical solution can be docked with towers of different diameters to facilitate the storage and transportation of towers of different specifications, the structure of the above technical solution is to install and store the tower upright, and lacks a low-center-of-gravity installation docking structure, resulting in a tower with a longer length being easily tipped over during transportation due to the high center of gravity after installation.
[0005] To this end, we proposed a self-loading, unloading and storage tooling for offshore wind turbine towers to solve the above problems. Utility Model Content
[0006] The purpose of the present application is to solve the problem in the prior art that a relatively long tower is prone to tipping over during transportation due to its high center of gravity after installation, and to propose a self-loading, unloading and storage tooling for an offshore wind power tower.
[0007] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0008] A self-loading, unloading and transporting storage tool for an offshore wind power tower comprises a placement plate, five arc-shaped support plates and two clamping plates are respectively arranged above the placement plate, the inner wall of each of the arc-shaped support plates is threadedly connected to the inner wall of the placement plate with two groups of fastening bolts, the inner wall of the placement plate is fixedly connected to two first multi-stage hydraulic telescopic rods, the front of the placement plate is fixedly connected to a button controller, the inner wall of each of the clamping plates is respectively fixedly connected to a first bidirectional hydraulic telescopic rod and a second bidirectional hydraulic telescopic rod, the two telescopic ends of each of the first bidirectional hydraulic telescopic rods are fixedly connected to an arc-shaped top block, and the two telescopic ends of each of the second bidirectional hydraulic telescopic rods are fixedly connected to an arc clamping block.
[0009] Preferably, the side surfaces of the two clamps that are close to each other are fixedly connected to the telescopic ends of the first multi-stage hydraulic telescopic rod, the inner top wall of the placement plate is fixedly connected to two groups of storage cylinders, the inner walls of each group of the storage cylinders are fixedly connected to two second multi-stage hydraulic telescopic rods, the telescopic ends of each of the second multi-stage hydraulic telescopic rods are fixedly connected to a support plate, and the two first multi-stage hydraulic telescopic rods, the two first bidirectional hydraulic telescopic rods, the two second bidirectional hydraulic telescopic rods and the second multi-stage hydraulic telescopic rods are all electrically connected to the button controller via wires.
[0010] Preferably, the bottom surface of each clamping plate is fixedly connected to two auxiliary sliding blocks, and the outer surface of each auxiliary sliding block is slidably connected to the inside of the placement plate.
[0011] Preferably, the inner top wall of the placement plate is provided with a plurality of identical anti-slip grooves, and the front side and the back side of the placement plate are both fixedly connected with five belt winding racks.
[0012] Preferably, six top plates are arranged inside the placement plate, and an auxiliary bearing is fixedly connected to the inner wall of each top plate.
[0013] Preferably, the inner wall of the placement plate is threadedly connected with six tightening bolts, and the outer surface of each of the tightening bolts is fixedly connected to the inner ring of the auxiliary bearing.
[0014] In summary, the technical effects and advantages of this application are:
[0015] Through the cooperation of the placement plate, the arc-shaped support plate, the fastening bolts, the first multi-stage hydraulic telescopic rod, the clamping plate, the button controller, the first two-way hydraulic telescopic rod, the arc-shaped top block, the second two-way hydraulic telescopic rod and the arc-shaped clamping block, multiple arc-shaped support plates can drag the wind turbine tower with a cylindrical appearance, and the operation button controller can control the extension and retraction of the first multi-stage hydraulic telescopic rod, the first two-way hydraulic telescopic rod and the second two-way hydraulic telescopic rod, so that the two clamping plates can be clamped at both ends of the wind turbine tower, the four arc-shaped top blocks can be pressed against the inner wall of the wind turbine tower, and the four arc-shaped clamping blocks can wrap the outer surfaces of both ends of the wind turbine tower, thereby playing a role in low-center-of-gravity installation and docking of the wind turbine tower, so as to achieve the effect of not easily tipping over during transportation due to the high center of gravity, and avoid the problem that the long tower will be easily tipped over during transportation due to the high center of gravity after installation due to the lack of a low-center-of-gravity installation and docking structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the overall structure of the three-dimensional self-loading, unloading and transportation storage tooling for offshore wind power towers of the utility model;
[0017] Figure 2 It is a schematic diagram of the three-dimensional structure of the placement plate of the utility model;
[0018] Figure 3 This is a schematic diagram of the three-dimensional structure of the plywood of the utility model when viewed from above;
[0019] Figure 4 This is a schematic diagram of the structure of the placement plate of the utility model when viewed from above;
[0020] Figure 5 This is a schematic diagram of the three-dimensional structure of the storage tube of the utility model;
[0021] Figure 6 It is a three-dimensional structural schematic diagram of the tightening bolt of the utility model.
[0022] In the figure: 1. placement plate; 2. arc-shaped support plate; 3. fastening bolts; 4. first multi-stage hydraulic telescopic rod; 5. clamping plate; 6. button controller; 7. first bidirectional hydraulic telescopic rod; 8. arc-shaped top block; 9. second bidirectional hydraulic telescopic rod; 10. arc-shaped clamping block; 11. auxiliary sliding block; 12. anti-slip groove; 13. winding rack; 14. storage tube; 15. support plate; 16. second multi-stage hydraulic telescopic rod; 17. top plate; 18. auxiliary bearing; 19. tightening bolts. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0024] Reference Figure 1-6 , a self-loading, unloading and transporting storage tool for offshore wind power towers, including a placement plate 1, five arc-shaped support plates 2 and two clamping plates 5 are respectively arranged on the top of the placement plate 1, the inner wall of each arc-shaped support plate 2 is threadedly connected with two groups of fastening bolts 3 on the inner wall of the placement plate 1, and the inner top wall of the placement plate 1 is fixedly connected with two groups of storage cylinders 14, and the inner wall of each group of storage cylinders 14 is fixedly connected with two second multi-stage hydraulic telescopic rods 16, and the telescopic end of each second multi-stage hydraulic telescopic rod 16 is fixedly connected with a support plate 15, and the placement plate 1 can be placed on an industrial flatbed truck. By providing the storage cylinders 14, the support plates 15 and the second multi-stage hydraulic telescopic rods 16, the second multi-stage hydraulic telescopic rods 16 can be controlled to be extended and retracted, and then when the placement plate 1 is placed on the industrial flatbed truck, the distance between the support plate 15 and the bottom surface can be adjusted, so that the wind power tower placed on the placement plate 1 can be automatically loaded or unloaded from the industrial flatbed truck without large-scale lifting machinery.
[0025] Two first multi-stage hydraulic telescopic rods 4 are fixedly connected to the inner wall of the placement plate 1, a button controller 6 is fixedly connected to the front of the placement plate 1, and the side surfaces of the two clamps 5 that are close to each other are fixedly connected to the telescopic ends of the first multi-stage hydraulic telescopic rods 4. The bottom surface of each clamp 5 is fixedly connected to two auxiliary sliders 11, and the outer surface of each auxiliary slider 11 is slidably connected to the inside of the placement plate 1. By providing the auxiliary slider 11, it can slide inside the placement plate 1, thereby increasing the orientation and stability of the two clamps 5 when they approach or move away from each other.
[0026] The inner wall of each clamping plate 5 is respectively fixedly connected with a first bidirectional hydraulic telescopic rod 7 and a second bidirectional hydraulic telescopic rod 9; the two first multi-stage hydraulic telescopic rods 4, the two first bidirectional hydraulic telescopic rods 7, the two second bidirectional hydraulic telescopic rods 9 and the second multi-stage hydraulic telescopic rod 16 are all electrically connected to the button controller 6 through wires; a plurality of identical anti-skid grooves 12 are provided on the inner top wall of the placement plate 1; five belt winding racks 13 are fixedly connected to the front and back sides of the placement plate 1; by providing the anti-skid grooves 12, the friction between the inner top wall of the placement plate 1 and the contact surface of the industrial flatbed truck can be increased, thereby increasing the stability of the placement plate 1 when it is placed on the industrial flatbed truck; by providing the belt winding rack 13, high-quality straps can be wound around and the wind turbine tower can be wrapped, thereby facilitating and assisting in increasing the stability of the wind turbine tower.
[0027] The two telescopic ends of each first bidirectional hydraulic telescopic rod 7 are fixedly connected with an arc-shaped top block 8, and six top plates 17 are arranged inside the placement plate 1. The inner wall of each top plate 17 is fixedly connected with an auxiliary bearing 18. By providing the top plate 17, other tightening structures can be pressed against both sides of the industrial flatbed truck. By providing the auxiliary bearing 18, the rotation and horizontal movement of the above-mentioned tightening structure can be separated.
[0028] The two telescopic ends of each second bidirectional hydraulic telescopic rod 9 are fixedly connected with an arc-shaped clamping block 10, and the inner wall of the placement plate 1 is threadedly connected with six tightening bolts 19. The outer surface of each tightening bolt 19 is fixedly connected to the inner ring of the auxiliary bearing 18. By providing the tightening bolts 19, the top plate 17 can be pushed toward the two sides of the industrial flatbed truck after being threadedly connected to the inner wall of the placement plate 1 with the assistance of the auxiliary bearing 18, thereby increasing the stability of the placement plate 1 placed on the industrial flatbed truck.
[0029] The working principle of the utility model is: when in use, first use a mechanical lifting mechanism to load the wind turbine tower onto a placement plate 1 of corresponding length at the loading location, at this time, it is necessary to first operate the button controller 6 to control the two first multi-stage hydraulic telescopic rods 4 to extend the longest, the two first two-way hydraulic telescopic rods 7 to shorten the shortest, and the two second two-way hydraulic telescopic rods 9 to extend the longest, and then place the wind turbine tower of appropriate length on the multiple arc-shaped support plates 2 between the two clamping plates 5, and then operate the button controller 6 to shorten the two first multi-stage hydraulic telescopic rods 4, lengthen the two first two-way hydraulic telescopic rods 7, and shorten the two second two-way hydraulic telescopic rods 9, until the two clamping plates 5 clamp the two ends of the wind turbine tower, the four arc-shaped top blocks 8 support the inner wall of the wind turbine tower, and the four arc-shaped clamping blocks 10 wrap the outer surface of the wind turbine tower, and then wrap it with high-quality binding tape. After the belt winding rack 13 is installed, the wind turbine tower can be tied up, and then the button controller 6 is operated to control the four second multi-stage hydraulic telescopic rods 16 to extend until the pallet of the industrial flatbed truck can be driven under the placement plate 1. When the pallet of the industrial flatbed truck is completely driven under the placement plate 1, the button controller 6 is operated to control the four second multi-stage hydraulic telescopic rods 16 to shorten until the placement plate 1 is completely attached to the pallet of the industrial flatbed truck and the support plate 15 is far from the ground. After that, the loading and unloading of the wind turbine tower on the industrial flatbed truck only requires operating the button controller 6 to control the extension and retraction of the second multi-stage hydraulic telescopic rods 16. The design of the self-loading, unloading and storage tooling of the entire offshore wind turbine tower effectively solves the problem that the longer tower will be easily tipped over during transportation due to the high center of gravity after installation due to the lack of a low-center-of-gravity installation docking structure.
[0030] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0032] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A self-loading and unloading storage tool for offshore wind power towers, comprising a placement plate (1), characterized in that: Five arc-shaped support plates (2) and two clamping plates (5) are respectively arranged above the placement plate (1); the inner wall of each arc-shaped support plate (2) is threadedly connected to the inner wall of the placement plate (1) by two groups of fastening bolts (3); the inner wall of the placement plate (1) is fixedly connected to two first multi-stage hydraulic telescopic rods (4); the front of the placement plate (1) is fixedly connected to a button controller (6); the inner wall of each clamping plate (5) is respectively fixedly connected to a first bidirectional hydraulic telescopic rod (7) and a second bidirectional hydraulic telescopic rod (9); the two telescopic ends of each first bidirectional hydraulic telescopic rod (7) are fixedly connected to an arc-shaped top block (8); and the two telescopic ends of each second bidirectional hydraulic telescopic rod (9) are fixedly connected to an arc-shaped clamping block (10).
2. The offshore wind power tower self-loading and unloading storage tooling according to claim 1 is characterized by: The side surfaces of the two clamping plates (5) that are close to each other are fixedly connected to the telescopic ends of the first multi-stage hydraulic telescopic rods (4); the inner top wall of the placement plate (1) is fixedly connected to two groups of storage cylinders (14); the inner wall of each group of storage cylinders (14) is fixedly connected to two second multi-stage hydraulic telescopic rods (16); the telescopic end of each second multi-stage hydraulic telescopic rod (16) is fixedly connected to a support plate (15); the two first multi-stage hydraulic telescopic rods (4), the two first bidirectional hydraulic telescopic rods (7), the two second bidirectional hydraulic telescopic rods (9) and the second multi-stage hydraulic telescopic rods (16) are all electrically connected to the key controller (6) via wires.
3. The offshore wind power tower self-loading and unloading storage tooling according to claim 1 is characterized by: The bottom surface of each clamping plate (5) is fixedly connected to two auxiliary sliding blocks (11), and the outer surface of each auxiliary sliding block (11) is slidably connected to the inside of the placement plate (1).
4. The offshore wind power tower self-loading and unloading storage tooling according to claim 1 is characterized by: The inner top wall of the placement plate (1) is provided with a plurality of identical anti-slip grooves (12), and the front side of the placement plate (1) and the back side of the placement plate (1) are both fixedly connected with five belt winding racks (13).
5. The offshore wind power tower self-loading and unloading storage tooling according to claim 1 is characterized by: Six top plates (17) are arranged inside the placement plate (1), and an auxiliary bearing (18) is fixedly connected to the inner wall of each top plate (17).
6. The offshore wind power tower self-loading and unloading storage tooling according to claim 5 is characterized by: Six tightening bolts (19) are threadedly connected to the inner wall of the placement plate (1), and the outer surface of each of the tightening bolts (19) is fixedly connected to the inner ring of the auxiliary bearing (18).
Citation Information
Cited By
Self-loading, unloading, transferring and storing tool for offshore wind power tower drum
CN222592279U