Efficient production line for electroplating copper on steel wire rod

By using the technology of circulating flow of annular flushing pipe and overflow tank during the copper plating process of steel strips, the traditional problems of low cleaning efficiency and unstable copper plating are solved, and efficient and stable copper plating effect is achieved.

CN221940656UActive Publication Date: 2024-11-01NANTONG HONGYANG METAL PRODS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322844870.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-23
Publication Date
2024-11-01
Estimated Expiration
2033-10-23

AI Technical Summary

Technical Problem

The cleaning efficiency is low during the copper plating process of traditional steel strips, and the speed of the agitator leads to disturbance of water flow, and the copper plating effect is unstable.

Method used

The steel strip surface is flushed by an annular flushing tube, and the electrolyte is circulated through the overflow tank in the electroplating tank. The cleaning and copper plating process is optimized using a self-priming pump and filter.

Benefits of technology

The cleaning speed and copper plating efficiency are improved, the stability of copper plating effect and copper ion diffusion are ensured, and the amount of water is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221940656U_ABST
    Figure CN221940656U_ABST
Patent Text Reader

Abstract

The utility model relates to an efficient production line for electroplating copper on a steel wire rod, which comprises a pay-off machine, a husking machine, a first acid pickling and washing pool, a first conductive roller, a pre-plating tank, a second acid pickling and washing pool, a second conductive roller, a positive plating tank, a washing pool, a drawing and polishing tank and a take-up machine which are arranged in sequence, and annular flushing pipes are arranged in the first acid pickling and washing pool, the second acid pickling and washing pool and the washing pool; a steel wire rod penetrates through the middle of the annular flushing pipe, nozzles are connected to the periphery of the annular flushing pipe, an overflow tank is arranged between the pre-plating tank and the positive plating tank, liquid collecting tanks are symmetrically arranged on the two sides of the overflow tank, circulating pumps are installed at the bottoms of the pre-plating tank and the positive plating tank, inlets in the circulating pumps are connected with the bottoms of the liquid collecting tanks, and outlets in the circulating pumps are connected with the bottoms of the liquid collecting tanks. An outlet of the circulating pump is connected to the bottom of the overflow groove. The surface of the steel wire rod is flushed by adopting the annular flushing pipe, so that the efficiency is higher, and the water consumption is less; the electrolyte circularly flows in the electroplating bath in an overflow mode, and compared with stirring of a stirrer, the flow speed is stable, and the copper plating effect is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of wire material processing, in particular to an efficient production line for electroplating copper on steel wire rods. Background Art

[0002] During the production process of copper clad steel wire, the steel wire rod is first copper-plated and then drawn. During the copper-plating process of the steel wire rod, it needs to be cleaned. Traditionally, the steel wire rod passes through a pickling tank and a water washing tank, and the cleaning is achieved by completely immersing the steel wire rod. In this way, the pickling tank and the water washing tank need to be designed to be relatively long. By exchanging space for time and extending the immersion time, cleaning is achieved, but the efficiency is relatively low. In order to improve the flow of copper ions and improve the copper plating efficiency in the electroplating tank, an agitator is installed in the existing electroplating tank. However, in actual operation, in order to obtain a faster copper plating effect, the agitator speed is increased, and the water flow disturbance is large, resulting in unstable copper plating effect on the surface of the steel wire rod. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide a high-efficiency production line for electroplating copper on steel wire rods in view of the deficiencies of the above-mentioned prior art.

[0004] In order to solve the above technical problems, the technical solution adopted by the utility model is:

[0005] The invention discloses an efficient production line for electroplating copper on steel wire rods, comprising a wire unwinding machine, a shelling machine, a first pickling and washing tank, a first conductive roller, a pre-plating tank, a second pickling and washing tank, a second conductive roller, a main plating tank, a washing tank, a polishing tank and a wire take-up machine which are arranged in sequence. The first pickling and washing tank, the second pickling and washing tank and the washing tank are provided with an annular flushing pipe, through which the steel wire rod passes, and nozzles are connected around the annular flushing pipe, through which the steel wire rod passes, and an overflow tank is provided between the pre-plating tank and the main plating tank, through which the steel wire rod passes, and liquid collecting tanks are symmetrically provided on both sides of the overflow tank, and a circulating pump is provided at the bottom of the pre-plating tank and the main plating tank, and an inlet on the circulating pump is connected to the bottom of the liquid collecting tank through a connecting pipe, and an outlet on the circulating pump is connected to the bottom of the overflow tank through a drain pipe, so that the electrolyte in the pre-plating tank and the main plating tank circulates.

[0006] Furthermore, a bracket is installed in the first pickling water washing tank, the second pickling water washing tank and the water washing tank, a lower interface and an upper interface are installed on the annular flushing pipe, the lower interface is connected to the upper end of the bracket by screws, a transition groove is installed at the bottom of the first pickling water washing tank, the second pickling water washing tank and the water washing tank, a self-priming pump is installed on the side of the transition groove, the outlet of the self-priming pump is connected to a conduit, and the end of the conduit is connected to the upper interface through a quick connector.

[0007] Furthermore, a filter screen is provided at the inlet of the self-priming pump of the transition tank.

[0008] Furthermore, a titanium plate is installed at the bottom of the pre-plating tank and the positive plating tank, a copper plate is placed on the titanium plate, and the copper plate is connected to positive electricity.

[0009] Compared with the prior art, the utility model of a steel wire rod copper electroplating high-efficiency production line has the following beneficial effects: 1. The surface of the steel wire rod is rinsed with an annular flushing pipe, which is faster, more efficient and uses less water than traditional immersion cleaning;

[0010] 2. The electrolyte circulates in the electroplating tank by overflow. Compared with the stirring by the agitator, the flow rate is stable, which can ensure the flow rate of the electrolyte and improve the diffusion of copper ions to ensure the copper plating effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a structural schematic diagram of the utility model;

[0012] Figure 2 This is a structural schematic diagram of the installation of the annular flushing pipe of the utility model;

[0013] Figure 3 This is a schematic diagram of the structure of the utility model in which the electrolyte circulates in the overflow tank;

[0014] Among them, 1. wire-laying machine, 2. shelling machine, 3. first pickling and washing tank, 4. first conductive roller, 5. pre-plating tank, 6. second pickling and washing tank, 7. second conductive roller, 8. main plating tank, 9. washing tank, 10. drawing tank, 11. wire-reeling machine, 12. annular flushing pipe, 13. nozzle, 14. bracket, 15. lower interface, 16. upper interface, 17. transition tank, 18. self-priming pump, 19. conduit, 20. filter screen, 21. overflow tank, 22. collecting tank, 23. circulating pump, 24. connecting pipe, 25. drain pipe, 26. copper plate. DETAILED DESCRIPTION

[0015] The technical solutions in the embodiments of the present utility model will be described clearly and completely below.

[0016] like Figure 1 to Figure 3As shown, a high-efficiency production line for electroplating copper on steel wire rods comprises a wire unwinding machine 1, a shelling machine 2, a first pickling water washing tank 3, a first conductive roller 4, a pre-plating tank 5, a second pickling water washing tank 6, a second conductive roller 7, a main plating tank 8, a water washing tank 9, a drawing tank 10 and a wire take-up machine 11 arranged in sequence, wherein an annular flushing pipe 12 is installed in the first pickling water washing tank 3, the second pickling water washing tank 6 and the water washing tank 9, and the steel wire rod passes through the middle of the annular flushing pipe 12, and the annular flushing pipe 12 is connected with a nozzle 13 around it, wherein a bracket 14 is installed in the first pickling water washing tank 3, the second pickling water washing tank 6 and the water washing tank 9, and a lower connection is installed on the annular flushing pipe 12 The lower interface 15 is connected to the upper end of the bracket 14 by screws. The first pickling water washing tank 3, the second pickling water washing tank 6 and the water washing tank 9 are all equipped with transition grooves 17 at the bottom. The transition groove 17 collects the liquid after cleaning. A self-priming pump 18 is installed on the side of the transition groove 17. The outlet of the self-priming pump 18 is connected to a conduit 19. The end of the conduit 19 is connected to the upper interface 16 through a quick connector. Since the annular flushing pipe 12 is a hollow pipe, the liquid enters the annular flushing pipe 12 and is flushed by the nozzle 13 on the surface of the steel wire rod. The pressure of the nozzle 13 is adjusted by controlling the pressure of the self-priming pump 18, and the liquid is circulated by the self-priming pump 18 at the same time.

[0017] The transition tank 17 is provided with a filter screen 20 at the inlet of the self-priming pump 18, and the filter screen 20 can filter out most of the debris.

[0018] An overflow trough 21 is arranged in the middle of the pre-plating tank 5 and the main plating tank 8, and the steel wire rod passes through the overflow trough 21. Liquid collecting troughs 22 are symmetrically arranged on both sides of the overflow trough 21. A circulation pump 23 is installed at the bottom of the pre-plating tank 5 and the main plating tank 8. The inlet of the circulation pump 23 is connected to the bottom of the liquid collecting troughs 22 on both sides through a connecting pipe 24, and the outlet of the circulation pump 23 is connected to the bottom of the overflow trough 21 through a drain pipe 25. A titanium plate is installed at the bottom of the pre-plating tank 5 and the main plating tank 8, and a copper plate 26 is placed on the titanium plate. The copper plate is positively charged to decompose copper ions into the tank. During the electroplating process, the electrolyte at the upper end of the overflow trough 21 overflows into the liquid collecting trough 22, and then is pumped by the circulation pump 23 to drain water to the bottom of the overflow trough 21. In this way, the flow rate of the electrolyte is more stable, and at the same time, it is ensured that the copper ions can diffuse and flow.

[0019] The present invention is not limited to the described embodiments. Those skilled in the art may make some modifications or changes without departing from the spirit and scope of the present invention, that is, within the scope of disclosure. Therefore, the scope of protection of the present invention shall be subject to the scope defined in the claims.

Claims

1. An efficient production line for electroplating copper on steel wire rods, comprising a pay-off machine, a shelling machine, a first pickling and washing tank, a first conductive roller, a pre-plating tank, a second pickling and washing tank, a second conductive roller, a main plating tank, a washing tank, a polishing tank and a take-up machine arranged in sequence, characterized in that: An annular flushing pipe is installed in the first pickling water washing tank, the second pickling water washing tank and the water washing tank, and the steel wire rod passes through the middle of the annular flushing pipe. The annular flushing pipe is connected with nozzles on all sides, and the nozzles flush the surface of the steel wire rod. An overflow trough is arranged in the middle of the pre-plating tank and the main plating tank, and the steel wire rod passes through the overflow trough. Liquid collecting troughs are symmetrically arranged on both sides of the overflow trough. A circulating pump is installed at the bottom of the pre-plating tank and the main plating tank. The inlet on the circulating pump is connected to the bottom of the liquid collecting trough through a connecting pipe, and the outlet on the circulating pump is connected to the bottom of the overflow trough through a drain pipe, so that the electrolyte in the pre-plating tank and the main plating tank circulates.

2. The high-efficiency copper electroplating production line for steel wire rod according to claim 1 is characterized in that: Brackets are installed in the first pickling water washing tank, the second pickling water washing tank and the water washing tank, and a lower interface and an upper interface are installed on the annular flushing pipe, and the lower interface is connected to the upper end of the bracket by screws. A transition groove is installed at the bottom of the first pickling water washing tank, the second pickling water washing tank and the water washing tank, and a self-priming pump is installed on the side of the transition groove. The outlet of the self-priming pump is connected to a conduit, and the end of the conduit is connected to the upper interface through a quick connector.

3. The high-efficiency copper electroplating production line for steel wire rod according to claim 2 is characterized in that: The transition tank is provided with a filter screen at the inlet of the self-priming pump.

4. The high-efficiency copper electroplating production line for steel wire rod according to claim 1 is characterized in that: A titanium plate is installed at the bottom of the pre-plating tank and the positive plating tank, a copper plate is placed on the titanium plate, and the copper plate is connected to positive electricity.