Discharging platform for constructional engineering

By designing the adjustable height of the top board and the construction engineering unloading platform of the side door, the problem of inconvenience in unloading in the existing technology is solved, and the rapid transfer and efficient unloading of the goods are realized.

CN222391028UActive Publication Date: 2025-01-24BEIJING DEHUIYANG CONSTRUCTION ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420721351.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-09
Publication Date
2025-01-24
Estimated Expiration
2034-04-09

AI Technical Summary

Technical Problem

The existing construction unloading platform needs to be operated inside the protective plate when loading and unloading goods, and cannot be opened from the side, resulting in inconvenient unloading process.

Method used

A construction engineering unloading platform is designed, including a workbench, top plate, guard plate and side-opening door. Power support is provided through a cylinder. The height of the top plate is adjustable. The installation of connecting plates and pillars facilitates the movement and transfer of goods.

Benefits of technology

The rapid transfer operation of the goods is realized, the efficiency of unloading efficiency and the practicality of the device are improved, and the goods are facilitated after unloading.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222391028U_ABST
    Figure CN222391028U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of unloading platforms, in particular to a constructional engineering unloading platform which facilitates quick transfer operation on unloaded goods, improves the unloading efficiency of a device and improves the practicability. A top plate is fixedly mounted at the top end of the worktable through a plurality of limiting mechanisms; the limiting mechanism comprises a fixing column which is longitudinally and fixedly installed at the top end of the workbench, a sliding rod is slidably installed at the top end of the fixing column, and the top end of the sliding rod is fixedly connected with the bottom end of the top plate. A plurality of protective plates are fixedly mounted at the top end of the top plate, two doors are symmetrically formed in one protective plate, a limiting block is transversely and fixedly mounted at the top end of the top plate, a connecting plate is slidably mounted on the limiting block, a plurality of first supporting columns are rotatably mounted on the periphery of the bottom end of the connecting plate, and a first wheel is mounted on each first supporting column; the top middle area of the workbench is fixedly connected with the bottom end of a top plate through a cylinder. And a fixing mechanism is arranged between the two doors.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of unloading platforms, and in particular to a construction engineering unloading platform. Background Art

[0002] The unloading platform is a temporary operating table and operating frame often set up at the construction site, which can be used for various masonry, decoration and painting operations. Generally speaking, it is a frame-type platform that can be used to carry materials and perform various operations within a certain construction period. It is called an operating platform; the operating platform is divided into mobile operating platforms, floor-standing and cantilevered operating platforms, which can also be called material transfer platforms.

[0003] For example, after searching, the utility model patent with Chinese patent publication number CN216239809U discloses: a construction unloading platform, including a first groove opened inside the platform body, and an adjustment mechanism is arranged inside the first groove. The advantages of the utility model are: the second cushion block of the construction unloading platform, under the action of the second spring, plays a buffering role on the platform body, avoids damage to the platform body when it is subjected to external force for a long time, plays a shock-absorbing and protective role on the unloading platform, thereby increasing the service life of the unloading platform and reducing the risk;

[0004] However, the above existing devices still have the following problems in actual use:

[0005] The above device needs to load and unload the goods inside the protective plate during loading and unloading, and the unloading platform of the device cannot be opened from the side, which is inconvenient when unloading. Therefore, a construction engineering unloading platform is needed. Utility Model Content

[0006] 1. Technical issues to be solved

[0007] In view of the deficiencies in the prior art, the present application provides a construction engineering unloading platform that facilitates the rapid transfer of goods after unloading, improves the efficiency of the unloading device, and improves the practicality.

[0008] (II) Technical solution

[0009] To achieve the above-mentioned purpose, the present application provides the following technical solutions: a construction engineering unloading platform, comprising a workbench, a top plate being fixedly mounted on the top of the workbench through a plurality of limiting mechanisms;

[0010] The limiting mechanism includes a fixed column, which is longitudinally fixedly installed on the top of the workbench, and a sliding rod is slidably installed on the top of the fixed column, and the top of the sliding rod is fixedly connected to the bottom end of the top plate;

[0011] A plurality of guard plates are fixedly installed on the top of the top plate, one of which has two doors symmetrically provided thereon, a limit block is fixedly installed horizontally on the top of the top plate, a connecting plate is slidably installed on the limit block, a plurality of first pillars are rotatably installed around the bottom of the connecting plate, a first wheel is installed on each first pillar, and the middle area of ​​the top of the workbench is fixedly connected to the bottom of the top plate through a cylinder;

[0012] A fixing mechanism is arranged between the two doors.

[0013] Preferably, the fixing mechanism comprises two first handles, which are respectively fixedly mounted on the outer side walls of the two doors, and a limiting column is slidably mounted between the two first handles, and a baffle is fixedly mounted on one end of the limiting column.

[0014] Furthermore, a plurality of shift rods are slidably mounted on the top end of the connecting plate.

[0015] Furthermore, a second handle is fixedly mounted on the top of the connecting plate.

[0016] On the basis of the above-mentioned solution, a plurality of second pillars are rotatably mounted around the bottom end of the workbench, and a second wheel is mounted on the bottom end of each second pillar.

[0017] (III) Beneficial effects

[0018] Compared with the prior art, the present application provides a construction engineering unloading platform, which has the following beneficial effects:

[0019] The construction engineering unloading platform provides power support for the top plate during height adjustment through a cylinder, and limits the connection plate inside the top plate by sliding the connection plate on the limit block at the top of the top plate. The installation of the first pillar and the first wheel facilitates the movement of the connection plate and the goods on the connection plate. The installation of two doors facilitates the rapid transfer of the connection plate at the top of the top plate, and facilitates the rapid transfer of the goods after unloading, thereby improving the unloading efficiency of the device and improving practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a schematic diagram of the three-dimensional structure of this application;

[0021] Figure 2 This is a schematic diagram of the cross-sectional structure of this application;

[0022] Figure 3 For this application Figure 1 A schematic diagram of the enlarged structure of the middle part A;

[0023] Figure 4 For this application Figure 2 Schematic diagram of the enlarged structure of part B in the middle.

[0024] Markings in the attached drawings: 1. workbench; 2. top plate; 3. guard plate; 4. door; 5. limit block; 6. connecting plate; 7. first pillar; 8. first wheel; 9. fixed column; 10. slide rod; 11. cylinder; 12. first handle; 13. limit column; 14. baffle; 15. gear lever; 16. second handle; 17. second pillar; 18. second wheel. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0026] Example

[0027] See also Figure 1-4 A construction engineering unloading platform comprises a workbench 1, a top plate 2 is fixedly installed on the top of the workbench 1 through a plurality of limiting mechanisms; the limiting mechanisms comprise a fixed column 9, the fixed column 9 is longitudinally fixedly installed on the top of the workbench 1, a sliding rod 10 is slidably installed on the top of the fixed column 9, and the top of the sliding rod 10 is fixedly connected to the bottom end of the top plate 2; a plurality of guard plates 3 are fixedly installed on the top of the top plate 2, one of the guard plates 3 is symmetrically provided with two doors 4, a limiting block 5 is transversely fixedly installed on the top of the top plate 2, a connecting plate 6 is slidably installed on the limiting block 5, a plurality of first pillars 7 are rotatably installed around the bottom end of the connecting plate 6, and a first wheel 8 is installed on each of the first pillars 7, and the middle area of ​​the top end of the workbench 1 is fixedly connected to the bottom end of the top plate 2 through a cylinder 11;

[0028] See also Figure 1-4A fixing mechanism is arranged between the two doors 4, and the fixing mechanism comprises two first handles 12, and the two first handles 12 are respectively fixedly installed on the outer side walls of the two doors 4, and a limiting column 13 is slidably installed between the two first handles 12, and a baffle 14 is fixedly installed at one end of the limiting column 13. Through the installation of the first handle 12, it is convenient to open the door 4, and through the installation of the first handle 12 and the limiting column 13, it is convenient to fix the two doors 4. The unloading platform of the construction project provides power support for the top plate 2 during height adjustment through the cylinder 11, and slides on the limiting block 5 at the top end of the top plate 2 through the connecting plate 6, and then limits the connecting plate 6 inside the top plate 2. Through the installation of the first pillar 7 and the first wheel 8, it is convenient to move the connecting plate 6 and the goods on the connecting plate 6. Through the installation of the two doors 4, it is convenient to quickly transfer the connecting plate 6 at the top end of the top plate 2, and it is convenient to quickly transfer the goods after unloading, thereby improving the efficiency of unloading of the device and improving practicality.

[0029] See also Figure 2 A plurality of levers 15 are slidably mounted on the top of the connecting plate 6 , and the levers 15 are installed to support the cargo on the top of the connecting plate 6 .

[0030] See also Figure 2 It should also be noted that a second handle 16 is fixedly installed on the top of the connecting plate 6. By installing the second handle 16, the sliding operation of the connecting plate 6 is facilitated.

[0031] See also Figure 1 A plurality of second pillars 17 are rotatably mounted around the bottom of the workbench 1, and a second wheel 18 is mounted at the bottom of each second pillar 17. The installation of the second pillars 17 and the second wheels 18 facilitates the user to move the device.

[0032] In summary, when the construction engineering unloading platform is in use, the cylinder 11 is started, and power is output through the top end of the cylinder 11, thereby synchronously driving the top plate 2 to adjust the height, and the sliding rod 10 slides on the top end of the fixed column 9, and then the lifted top plate 2 is effectively limited, so that the top plate 2 is lifted to the unloading height, and the goods are placed on the top end of the connecting plate 6, and the goods on the top end of the connecting plate 6 are supported by the sliding and clamped gear rod 15 on the connecting plate 6, and the baffle 14 and the limiting column 13 are slid with the first handle 12 on the door 4, so that the limiting column 13 is separated from the door 4. After opening the door 4, the connecting plate 6 is moved horizontally by the second handle 16 under the limit of the limiting block 5, so that the connecting plate 6 and the goods on the connecting plate 6 are transferred out of the top end of the top plate 2.

[0033] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. A construction engineering unloading platform, comprising a workbench (1), characterized in that: A top plate (2) is fixedly mounted on the top of the workbench (1) via a plurality of limiting mechanisms; The limiting mechanism comprises a fixed column (9), the fixed column (9) is longitudinally fixedly mounted on the top end of the workbench (1), a sliding rod (10) is slidably mounted on the top end of the fixed column (9), and the top end of the sliding rod (10) is fixedly connected to the bottom end of the top plate (2); A plurality of guard plates (3) are fixedly mounted on the top of the top plate (2), one of the guard plates (3) having two doors (4) symmetrically provided thereon; a limit block (5) is fixedly mounted transversely on the top of the top plate (2), a connecting plate (6) is slidably mounted on the limit block (5), a plurality of first pillars (7) are rotatably mounted around the bottom of the connecting plate (6), each first pillar (7) being mounted with a first wheel (8); the middle area of ​​the top of the workbench (1) is fixedly connected to the bottom of the top plate (2) via a cylinder (11); A fixing mechanism is arranged between the two doors (4).

2. A construction engineering unloading platform according to claim 1, characterized in that: The fixing mechanism comprises two first handles (12), the two first handles (12) are respectively fixedly mounted on the outer side walls of the two doors (4), a limiting column (13) is slidably mounted between the two first handles (12), and a baffle (14) is fixedly mounted on one end of the limiting column (13).

3. A construction engineering unloading platform according to claim 2, characterized in that: A plurality of shift rods (15) are slidably mounted on the top end of the connecting plate (6).

4. A construction engineering unloading platform according to claim 3, characterized in that: A second handle (16) is fixedly mounted on the top end of the connecting plate (6).

5. A construction engineering unloading platform according to claim 4, characterized in that: A plurality of second pillars (17) are rotatably mounted around the bottom end of the workbench (1), and a second wheel (18) is mounted at the bottom end of each second pillar (17).

Citation Information

Patent Citations

  • Building construction discharging platform

    CN216239809U