Structure suitable for slag falling prevention, core filling and bottom sealing of prefabricated pipe pile
By designing a structure including prefabricated pipe piles, sealing parts and long handles, the problems of pile tops being susceptible to slag chip drops and personnel falling accidents during prefabricated pipe pile construction are solved, and efficient and safe slag chip prevention and Core-filling back cover effect.
Patent Information
- Application Number
- CN202421271177.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-05
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-06-05
AI Technical Summary
In the construction of prefabricated pipe piles, the pile top is easily affected by external mud, earthwork and slag chips, and there is a risk of falling accidents for personnel. The traditional cleaning method is labor-intensive, inefficient, and is not conducive to mechanized operations.
A structure including prefabricated pipe piles, sealing parts and long handles is designed. The sealing parts are threaded to the prefabricated pipe piles. The long handle cooperates with the sealing parts through a slot to rotate the long handle to control the verticality of the sealing parts. Move to achieve the function of preventing slag chips from falling into the core and filling the back cover.
Effectively prevent external slag and personnel fall accidents, improve construction safety and mechanized operating conditions, and significantly improve cleaning efficiency and safety.
Smart Images

Figure CN222477454U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prefabricated pipe pile construction, in particular to a structure suitable for preventing slag from falling and filling the core and sealing the bottom of prefabricated pipe piles. Background Art
[0002] During the process of sinking and after the pile sinking is completed, the top of the prefabricated pipe pile is generally lower than the ground. Especially in power transmission and transformation projects, in order to avoid the inconvenience of long-term expansion and sinking, the long-term pipe piles are often sunk in place at one time in this period. In order to prevent safety accidents, the top of the prefabricated pipe pile needs to be covered with soil in time and then dug up during expansion. This causes external mud, earthwork, and debris such as broken stones to easily fall into the core of the pipe pile. Before filling the core at the top of the pile, the debris in the pile head must be cleaned up first, otherwise the core filling depth required by the design cannot be guaranteed, and the holes on the top of the pile are prone to cause personnel falling accidents, which poses a major safety hazard and is not conducive to the passage of mechanical equipment, and mechanized operating conditions are difficult to guarantee. The traditional solution is to use a hook spoon or a shovel to bend the front section to clean it, which is labor-intensive, inefficient, time-consuming, and ineffective; or use templates or steel plates for capping or setting safety guardrails, which are easy to slide and run, and safety guardrails are overkill.
[0003] For this purpose, we design a structure suitable for preventing slag from falling off and filling the core and sealing the bottom of prefabricated pipe piles. Utility Model Content
[0004] The utility model aims to solve the problems in the prior art by providing a structure suitable for preventing slag from falling and filling the core and sealing the bottom of prefabricated pipe piles, so as to solve the problems raised in the background art.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a structure suitable for preventing slag from falling and filling the core and sealing the bottom of a prefabricated pipe pile, comprising a prefabricated pipe pile, a plugging piece and a long handle, wherein the plugging piece comprises a sealing plate, a stiffener and a short round tube, wherein the sealing plate is fixedly mounted on the top of the short round tube, the stiffener is fixedly mounted at the top center of the sealing plate, an external thread is arranged on the outer side wall of the short round tube, an internal thread matching the external thread is arranged on the inner side wall of the prefabricated pipe pile, and the plugging piece is connected to the prefabricated pipe pile by threads;
[0006] The long handle is composed of multiple sections of sleeves, and the side of each section of the sleeve is provided with a plurality of circular holes that are equally spaced and penetrate the sleeve. Two adjacent sleeves are locked by bolts passing through the circular holes, and nuts are tightened on the bolts. A slot is provided at the bottom end of the lowest sleeve.
[0007] Preferably, the reinforcement aid is in a cross shape, and the slot at the bottom end of the sleeve is in a cross shape, and the slot can cooperate with the reinforcement aid.
[0008] Preferably, the interior of the short circular tube is filled with concrete.
[0009] Preferably, the sealing plate is made of steel plate, the stiffener is made of steel stiffener, and the short round tube is made of steel tube.
[0010] Preferably, the sleeve is made of a steel pipe, and the bolts are made of steel bolts.
[0011] Compared with the prior art, the utility model provides a structure suitable for preventing slag from falling and filling the core and sealing the bottom of prefabricated pipe piles, which has the following beneficial effects:
[0012] 1. This structure is suitable for preventing slag from falling and filling the core to seal the bottom of the prefabricated pipe pile. Through the cooperation of the internal thread on the prefabricated pipe pile and the external thread on the short round tube, the plugging piece can be sealed near the pile top of the prefabricated pipe pile, which plays a role in preventing external mud, earthwork, gravel and other debris from falling in and preventing people from falling. When filling the core, the plugging piece 2 is moved to the bottom of the filling core to play the role of filling and sealing the core;
[0013] 2. This structure is suitable for preventing slag from falling off and filling the core and sealing the bottom of prefabricated pipe piles. Through the cooperation of the card slot set on the long handle and the reinforcement aid on the plugging piece, the rotation of the plugging piece can be controlled by rotating the long handle, thereby controlling the vertical movement of the plugging piece to the designed position. The length of the long handle can be adjusted as needed. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0015] Figure 2 This is a schematic diagram of the structure of the plugging member of the utility model;
[0016] Figure 3 This is a schematic diagram of the stiffening auxiliary structure of the utility model;
[0017] Figure 4 This is a schematic diagram of the long handle structure of the utility model;
[0018] Figure 5 This is a schematic diagram of the card slot of the utility model;
[0019] Figure 6 It is a schematic diagram of a circular hole of the utility model.
[0020] Figure numerals: 1. Prefabricated pipe pile; 1-1. Internal thread; 2. Sealing piece; 21. Sealing plate; 22. Stiffening rib; 23. Short round tube; 23-1. External thread; 3. Long handle; 31. Sleeve; 31-1. Slot; 31-2. Round hole; 32. Bolt. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] See also Figure 1-Figure 6 In this embodiment: a structure suitable for preventing slag from falling off and filling the core and sealing the bottom of a prefabricated pipe pile, comprising a prefabricated pipe pile 1, a plugging member 2 and a long handle 3, please refer to Figure 2 and Figure 3 The plugging member 2 includes a sealing plate 21, a reinforcing aid 22 and a short round tube 23. The sealing plate 21 is fixedly mounted on the top of the short round tube 23. The reinforcing aid 22 is fixedly mounted at the top center of the sealing plate 21. The reinforcing aid 22 is cross-shaped. An external thread 23-1 is arranged on the outer wall of the short round tube 23. The interior of the short round tube 23 is filled with concrete. Please refer to Figure 1 The inner wall of the prefabricated pipe pile 1 is provided with an internal thread 1-1 that cooperates with the external thread 23-1. The plugging piece 2 is connected to the prefabricated pipe pile 1 through a thread. The plugging piece 2 can play a role in plugging the prefabricated pipe pile 1, thereby preventing external mud, earthwork, and debris such as broken stones from falling in and preventing personnel from falling. When the plugging piece 2 is moved to the bottom of the core-filled concrete, it can play a role in core-filling plugging. Through the cooperation of the thread, the plugging piece 2 can be rotated to make the plugging piece 2 move vertically. , thereby adjusting its position in the prefabricated pipe pile 1. The internal thread 1-1 on the inner side of the prefabricated pipe pile 1 can enhance the friction and bonding between the core-filled concrete and the inner wall of the prefabricated pipe pile after core filling, thereby reducing the core filling depth. The length of the internal thread 1-1 satisfies the rotation and fixation of the core filling assembly. Generally, the core filling depth is more than 3m, so the length of the internal thread 1-1 is preferably about 5m. The sealing plate 21 is made of steel plate, the stiffener 22 is made of steel stiffener, and the short round tube 23 is made of steel pipe;
[0023] See also Figure 4-Figure 6 The long handle 3 is composed of a plurality of sleeve sections 31, and the overall length of the long handle 3 can be adjusted by adjusting the extended length of each sleeve section 31. The side of each sleeve section 31 is provided with a plurality of equally spaced circular holes 31-2 that penetrate the sleeve 31. Two adjacent sleeves 31 are locked by bolts 32 passing through the circular holes 31-2. Nuts are tightened on the bolts 32. A slot 31-1 is provided at the bottom end of the lowest sleeve 31. The slot 31-1 is cross-shaped and can cooperate with the stiffening aid 22. The sleeve 31 is made of steel pipe, and the slot 31-1 is connected to the stiffening aid 22. The plugging member 2 can be driven to rotate by rotating the long handle 3. The bolt 32 is made of steel bolt.
[0024] The working principle and use process of the utility model: when the utility model is used for the structure of preventing slag from falling and filling the core to seal the bottom of the prefabricated pipe pile, before sinking the pile, place the plugging piece 2 on the prefabricated pipe pile 1, align the external thread 23-1 on the short round tube 23 with the internal thread 1-1 on the prefabricated pipe pile 1, and then screw the plugging piece 2 into the top of the pipe pile until the top of the reinforcement 22 is about 100mm away from the top of the prefabricated pipe pile 1. After sinking and delivering the pile, backfill the earth and use the plugging piece 2 to seal the top of the prefabricated pipe pile 1. During and after pile sinking, prevent external mud, earth, gravel and other debris from falling in, and prevent people from falling accidents. When filling the core, dig up the top of the pile to fill the soil. After cleaning the soil and rocks on the top of the sealing member 2, connect the slot 31-1 on the long handle 3 with the reinforcement 22 on the sealing member 2, and then rotate the long handle 3 to move the sealing member 2 to the bottom of the designed pile core, which can play the role of core filling and plugging. After tying the core filling steel cage, put it into the pile top hole, pour the core filling concrete, and complete the core filling work.
[0025] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A structure suitable for preventing slag from falling off and for filling and sealing the bottom of a prefabricated pipe pile, comprising a prefabricated pipe pile (1), a plugging member (2) and a long handle (3), characterized in that: The plugging member (2) comprises a sealing plate (21), a stiffening aid (22) and a short round tube (23); the sealing plate (21) is fixedly mounted on the top of the short round tube (23); the stiffening aid (22) is fixedly mounted at the top center of the sealing plate (21); an outer wall of the short round tube (23) is provided with an external thread (23-1); an inner wall of the prefabricated pipe pile (1) is provided with an internal thread (1-1) matching the external thread (23-1); and the plugging member (2) is connected to the prefabricated pipe pile (1) by means of threads; The long handle (3) is formed by a plurality of sleeve sections (31) being sleeved together. The side surface of each sleeve section (31) is provided with a plurality of circular holes (31-2) at equal intervals and penetrating the sleeve (31). Two adjacent sleeves (31) are locked by bolts (32) passing through the circular holes (31-2). Nuts are tightened on the bolts (32). A slot (31-1) is provided at the bottom end of the lowest sleeve (31).
2. A structure suitable for preventing slag dropping and filling the core and sealing the bottom of prefabricated pipe piles according to claim 1, characterized in that: The stiffening aid (22) is in a cross shape, the clamping groove (31-1) at the bottom end of the sleeve (31) is in a cross shape, and the clamping groove (31-1) can cooperate with the stiffening aid (22).
3. The structure for preventing slag dropping and filling the core and sealing the bottom of prefabricated pipe piles according to claim 1 is characterized in that: The interior of the short circular tube (23) is filled with concrete.
4. The structure for preventing slag dropping and filling the core and sealing the bottom of prefabricated pipe piles according to claim 1 is characterized in that: The sealing plate (21) is made of a steel plate, the stiffener (22) is made of a steel stiffener, and the short round tube (23) is made of a steel tube.
5. The structure for preventing slag dropping and filling the core and sealing the bottom of prefabricated pipe piles according to claim 1 is characterized in that: The sleeve (31) is made of a steel pipe, and the bolt (32) is made of a steel bolt.