Device for controlling well entering spacing of pipelines on two sides of inspection well

By designing a pipeline inlet spacing control device for inspection well construction, the problem of inaccurate pipeline placement during construction is solved, precise control and telescopic structure is achieved, construction process is simplified, and construction period and engineering costs are reduced.

CN222758952UActive Publication Date: 2025-04-15JINAN URBAN CONSTRUCTION GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421595075.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2025-04-15
Estimated Expiration
2034-07-08

AI Technical Summary

Technical Problem

During the inspection well construction process, inaccurate pipeline placement position leads to incorrect spacing between wells, resulting in difficulty in installing pipelines in the later stage, and even pipe cutting is required to eliminate errors, the processing process is complicated, delaying construction period, and increasing project costs.

Method used

A device is designed to control the well access spacing between the pipes on both sides of the inspection well, including two symmetrical H-shaped vertical frames, horizontal rods, short sleeves and connecting rods. It is fixed by sliding sleeves and bolts to achieve precise control and telescopic structure, which is suitable for inspection wells of different pipe diameters.

Benefits of technology

The device can accurately control the well access spacing of the pipeline before construction, avoid later pipe cutting and installation difficulties, simplify the construction process, and reduce construction period and engineering costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222758952U_ABST
    Figure CN222758952U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of inspection well construction, and particularly relates to a device for controlling well entering spacing of pipelines on two sides of an inspection well, which comprises two symmetrical H-shaped vertical frames, two horizontal rods are symmetrically connected between cross rods of the two H-shaped vertical frames, short sleeves are sleeved on the two horizontal rods in a sliding manner, and the two short sleeves are fixedly connected through a connecting rod; two vertical rods are symmetrically fixed to the connecting rod downwards, the bottom ends of the vertical rods are fixedly connected with the bottom supporting frame, and the middle position of the connecting rod is fixedly connected with a center rod vertically downwards. The device can accurately control the well entering spacing of the pipelines on the two sides of the inspection well before the inspection well is constructed, the problem that the pipelines are difficult to cut or install in the later period is solved, and the telescopic structure is arranged, so that the well entering spacing of the inspection well pipelines with different pipe diameters can be controlled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of inspection well construction, and particularly relates to a device for controlling the distance between pipelines entering the inspection well at both sides. Background Art

[0002] When constructing a cast-in-place concrete inspection well or a brick concrete inspection well, it is necessary to first place the pipes on both sides, arrange the well spacing, and then cast the inspection well. If the pipe placement is not accurate, the well spacing will be wrong, which will make the later pipe installation time-consuming and laborious. Sometimes it is necessary to cut the pipe later to eliminate the well spacing error caused by the early pipe placement. The processing process is complicated, delays the construction period, and increases the project cost. Summary of the invention

[0003] The problem to be solved by the present invention is to overcome the shortcomings of the background technology and provide a device for controlling the distance between pipelines entering the well on both sides of the inspection well.

[0004] The present invention is achieved through the following technical solutions:

[0005] A device for controlling the spacing between pipelines entering an inspection well on both sides of the inspection well comprises two symmetrical H-shaped vertical frames, two horizontal bars are symmetrically connected between the cross bars of the two H-shaped vertical frames, the horizontal bars are perpendicular to the cross bars, short sleeves are slidably sleeved on the two horizontal bars, the two short sleeves are fixedly connected by a connecting rod, and the connecting rod is parallel to the cross bars of the H-shaped vertical frames; the connecting rod symmetrically fixes two vertical bars downward, the bottom ends of the vertical bars are fixedly connected to a bottom support frame, and the bottom surface of the bottom support frame is flush with the bottom surface of the H-shaped vertical frames; a center rod is fixedly connected vertically downward at the middle position of the connecting rod, and the bottom end of the center rod is flush with the bottom surface of the bottom support frame.

[0006] Preferably, the horizontal rod comprises a rod A and a rod B which are slidably sleeved together, and corresponding adjustment holes are provided on the rod A and the rod B, and the rod A and the rod B are connected together by a T-pin passing through the adjustment hole.

[0007] Preferably, a support rod is connected between the two vertical rods, and the center rod passes through the support rod.

[0008] Preferably, a threaded hole is provided on the outer side surface of the short sleeve, and the short sleeve is fixed to the horizontal rod by a bolt passing through the threaded hole.

[0009] The device of the present invention can accurately control the distance between the pipes on both sides of the inspection well before the inspection well is constructed, avoiding the problem of pipe cutting or pipeline installation difficulties at a later stage. The device of the present invention has a telescopic structure that can realize the control of the distance between the pipes in the inspection wells with different diameters. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a schematic diagram of the structure during construction of this embodiment;

[0011] Figure 2 This is a schematic diagram of the structure of this embodiment;

[0012] Figure 3 It is a structural schematic diagram of the short sleeve connection in this embodiment.

[0013] In the figure, 1 is an H-type vertical frame, 2 is a short sleeve, 3 is a connecting rod, 4 is a vertical rod, 5 is a bottom support frame, 6 is a center rod, 7 is a rod A, 8 is a rod B, 9 is an adjustment hole, 10 is a T-type pin, 11 is a support rod, 12 is a threaded hole, and 13 is a bolt. DETAILED DESCRIPTION

[0014] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0015] This embodiment includes two symmetrical H-shaped vertical frames 1, which are composed of two vertical bars and a cross bar. Two horizontal bars are symmetrically connected between the cross bars of the two H-shaped vertical frames 1. The horizontal bars are perpendicular to the cross bars. Short sleeves 2 are slidably connected on the two horizontal bars. The short sleeves 2 can slide left and right along the horizontal bars. A connecting rod 3 is fixed between the two short sleeves 2. The connecting rod 3 is parallel to the cross bars of the H-shaped vertical frame 1. Two vertical bars 4 are symmetrically fixed vertically downward on the connecting rod 3. The bottom ends of the vertical bars 4 are fixedly connected to the bottom support frame 5. The bottom surface of the bottom support frame 5 is flush with the bottom surface of the H-shaped vertical frame 1. The bottom support frame 5 is used to support the structure connected to the short sleeve 2. The structure of the bottom support frame 5 is not limited. In this embodiment, the bottom support frame 5 is composed of four horizontal bars staggered. A center rod 6 is fixedly connected vertically downward in the middle position of the connecting rod 3. The bottom end of the center rod 6, the bottom surface of the bottom support frame 5 and the bottom surface of the H-shaped vertical frame 1 are all flush. The center rod 6 is used to locate the center position of the inspection well. In order to make the structure connected by the short sleeve 2 more solid, it is preferably connected between the two vertical rods 4 with a support rod 11, the support rod 11 is parallel to the connecting rod 3, and the center rod 6 passes vertically downward through the support rod 11.

[0016] In order to make the device of the present invention suitable for controlling the distance between inspection wells of different diameters, the horizontal rod is preferably a telescopic rod. Specifically, the horizontal rod includes a rod A7 and a rod B8 that are slidably sleeved together. One end of the rod A7 and the rod B8 close to the H-shaped vertical frame 1 is fixed together with the cross bar of the H-shaped vertical frame 1, and the other end is a sleeve end. The rod B8 can slide left and right in the rod A7. Corresponding adjustment holes 9 are provided on the rod A7 and the rod B8. The total length of the horizontal rod is adjusted through the adjustment hole 9, and the rod A7 and the rod B8 are fixedly connected together by a T-pin 10 passing through the adjustment hole 9.

[0017] In order to ensure that the short sleeve 2 is not accidentally touched and displaced during construction, preferably, a threaded hole 12 is provided on the outer surface of the short sleeve 2, and the short sleeve 2 is fixed to the horizontal rod by a bolt 13 passing through the threaded hole 12 to prevent displacement.

[0018] Usage process: first adjust the total length of the horizontal rod according to the diameter of the inspection well to be constructed, then measure the center position of the horizontal rod, slide the short sleeve 2 to the center position of the horizontal rod, and then use the bolt 13 to fix the short sleeve 2. According to the construction design, find the center point of the inspection well and mark it. Place the entire device at the pre-constructed inspection well position, so that the bottom end of the center rod 6 is located at the center point of the inspection well, and then place the pipes on both sides directly against the outside of the H-shaped vertical frame 1 on both sides, as shown in the attached figure. Figure 1 As shown, the pipeline placement position at this time is the correct pipeline entry spacing during subsequent inspection well construction.

[0019] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Those skilled in the art should understand that they can still modify the technical solutions described in the above embodiments, or replace some of the technical features therein with equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A device for controlling the distance between pipelines entering the well on both sides of the inspection well, characterized in that: The invention comprises two symmetrical H-shaped vertical frames (1), two horizontal bars are symmetrically connected between the cross bars of the two H-shaped vertical frames (1), the horizontal bars are perpendicular to the cross bars, short sleeves (2) are slidably sleeved on the two horizontal bars, the two short sleeves (2) are fixedly connected by a connecting rod (3), and the connecting rod (3) is parallel to the cross bars of the H-shaped vertical frames (1); the connecting rod (3) symmetrically fixes two vertical bars (4) downward, the bottom ends of the vertical bars (4) are fixedly connected to a bottom support frame (5), and the bottom surface of the bottom support frame (5) is flush with the bottom surface of the H-shaped vertical frame (1); the middle position of the connecting rod (3) is vertically fixedly connected to a center rod (6), and the bottom end of the center rod (6) is flush with the bottom surface of the bottom support frame (5).

2. The device for controlling the distance between the pipes entering the well on both sides of the inspection well according to claim 1 is characterized in that: The horizontal rod comprises a rod A (7) and a rod B (8) which are slidably sleeved together, and corresponding adjustment holes (9) are provided on the rod A (7) and the rod B (8). The rod A (7) and the rod B (8) are connected together by a T-shaped pin (10) passing through the adjustment hole (9).

3. The device for controlling the distance between the pipes entering the well on both sides of the inspection well according to claim 1 or 2, characterized in that: The outer side surface of the short sleeve (2) is provided with a threaded hole (12), and the short sleeve (2) and the horizontal rod are fixed together by means of a bolt (13) passing through the threaded hole (12).

4. The device for controlling the distance between the pipes entering the well on both sides of the inspection well according to claim 1 or 2, characterized in that: A support rod (11) is connected between the two vertical rods (4), and the central rod (6) passes through the support rod (11).