Temporary consolidation structure for construction of tower and beam penetrating structure

By setting up a transverse and longitudinal temporary consolidation system in the tower beam cross-through structure, the combination of limit stops and stop pads is used to solve the problems of tight space and unfavorable stress during construction, and safe and reliable construction control is achieved.

CN223061448UActive Publication Date: 2025-07-04中铁大桥勘测设计院集团有限公司武汉分公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421761016.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2025-07-04
Estimated Expiration
2034-07-24

AI Technical Summary

Technical Problem

In the construction of tower beam cross-through structures, the temporary consolidation space is tight and the traditional vertical consolidation is unfavorable, making it difficult to control construction safety risks.

Method used

The transverse and longitudinal temporary consolidation system is adopted, which is arranged between the main tower and the main beam respectively. The transverse temporary consolidation system includes a transverse limit stop and a stop cushion stone. The longitudinal temporary consolidation system includes a longitudinal limit stop and a stop cushion stone. Through the combination of the oil felt isolation layer and the sulfur cement mortar layer, the effective fixation and limit of the main tower and the main beam are achieved.

Benefits of technology

It effectively solves the problem of temporary consolidation space tightness, avoids the unfavorable stress situation of traditional vertical consolidation under the combined action of bend, shear and torsion, ensures construction safety and simplifies the demolition process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223061448U_ABST
    Figure CN223061448U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of bridge engineering, and particularly relates to a temporary consolidation structure for construction of a tower and beam penetrating structure, a main beam and a main tower are both arranged on a lower tower pier, the main tower vertically penetrates through the main beam, transverse temporary consolidation systems are arranged between the two sides of the main tower in the longitudinal bridge direction and the main beam, and the transverse temporary consolidation systems are arranged on the lower tower pier. Longitudinal temporary consolidation systems are arranged between the two sides, in the transverse bridge direction, of the main tower and the main beam, and the transverse temporary consolidation systems and the longitudinal temporary consolidation systems are arranged in the horizontal direction. According to the utility model, the temporary consolidation system is horizontally arranged by utilizing the characteristics of the tower-beam penetrating structure, so that the problem that the temporary consolidation space of the tower-beam penetrating structure is limited is effectively solved; and longitudinal and transverse consolidation are separated, so that the adverse stress condition of traditional vertical consolidation under the combined action of bending, shearing and twisting is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of bridge engineering, and particularly relates to a temporary fixing structure for the construction of a tower-beam through structure. Background Art

[0002] In a single-column tower bridge structure, the tower-beam through structure has become a common structural form. However, during the construction process, due to the particularity and complexity of the tower-beam through structure, its stress state and deformation conditions are difficult to accurately predict and control, which easily leads to construction safety risks.

[0003] The lower tower pier under the tower-beam through structure is relatively smaller than that of a double-column tower. There are many components on the bearing plane of the lower tower pier, such as: bearing systems, longitudinal dampers, lateral wind-resistant bearings, etc., and the space is relatively tight. Therefore, the implementation of traditional vertical consolidation measures will be affected, resulting in a contradiction between the temporary consolidation installation and the permanent structure. Therefore, it is necessary to design a temporary fixing structure for the construction of the tower-beam through structure to solve the above problems. Summary of the Utility Model

[0004] In order to overcome the deficiencies of the above-mentioned prior art, the purpose of the utility model is to provide a temporary fixing structure for the construction of a tower-beam through structure, which can effectively solve the problem of the tight space of the temporary fixing structure of the tower-beam through structure.

[0005] To achieve the above purpose, the technical solution of the utility model is a temporary fixing structure for the construction of a tower-beam through structure. The main beam and the main tower are both arranged on the lower tower pier, and the main tower vertically penetrates the main beam. Transverse temporary consolidation systems are arranged between both sides of the main tower in the longitudinal bridge direction and the main beam, and longitudinal temporary consolidation systems are arranged between both sides of the main tower in the transverse bridge direction and the main beam. The transverse temporary consolidation systems and the longitudinal temporary consolidation systems are both arranged in the horizontal direction.

[0006] As one of the implementation manners, the transverse temporary consolidation system includes a transverse limit block and a transverse block cushion stone. One end of the transverse block cushion stone abuts against the main tower, and the transverse limit block is arranged between the other end and the main beam.

[0007] As one of the implementation manners, first asphalt felt isolation layers are arranged on both end faces of the transverse limit block.

[0008] As one of the implementation manners, a first sulfuric acid-slag cement mortar layer is arranged between the end face of at least one end of the transverse limit block and the corresponding first asphalt felt isolation layer.

[0009] As one of the implementation manners, the thickness of the first sulfuric acid-slag cement mortar layer is 5 - 15 cm.

[0010] As one of the implementation modes, the longitudinal temporary consolidation system includes a longitudinal limit block and a longitudinal block pad stone, one end of the longitudinal block pad stone is against the main tower, and the longitudinal limit block is arranged between the other end and the main beam.

[0011] As one of the implementation modes, a second oil felt isolation layer is provided on the end surfaces at both ends of the longitudinal limit stop.

[0012] As one of the implementation modes, a second sulfur cement mortar layer is provided between the end surface of at least one end of the longitudinal limit block and the corresponding second oil felt isolation layer.

[0013] As one of the implementation modes, the main beam includes a main beam top plate, a middle main beam, a side main beam and a cross beam, and the main tower vertically penetrates the main beam top plate from the space surrounded by the two middle main beams and the two cross beams; the transverse temporary consolidation system is arranged between the main tower and the middle main beam, and the longitudinal temporary consolidation system is arranged between the main tower and the cross beam.

[0014] As one of the implementation modes, the main tower includes an upper tower column and two lower tower columns arranged along the longitudinal bridge direction, and the tops of the two lower tower columns are fixed to the bottom of the upper tower column, and the bottoms of the two lower tower columns are arranged on the lower tower pier; a transverse temporary consolidation system is arranged between the two sides of the longitudinal bridge direction of each lower tower column and the main beam; a longitudinal temporary consolidation system is arranged between the opposite ends of the two lower tower columns and the main beam.

[0015] Compared with the prior art, the utility model has the following beneficial effects:

[0016] (1) The utility model utilizes the characteristics of the tower-beam interpenetrating structure to horizontally arrange the temporary consolidation system, effectively solving the problem of tight temporary consolidation space in the tower-beam interpenetrating structure; and separates the longitudinal and transverse consolidation to avoid the unfavorable stress of traditional vertical consolidation under the combined action of bending, shearing and torsion;

[0017] (2) The utility model realizes effective fixation and limitation of the main tower and the main beam in the transverse direction and the longitudinal direction of the bridge by using a combination of limit blocks and block pads; and facilitates the removal of the temporary consolidation system by providing an oil felt isolation layer and sulfur cement mortar at both ends of the limit blocks. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 The plan view of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0020] Figure 2 The side view (longitudinal bridge direction) of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0021] Figure 3 The cross-sectional view (transverse bridge direction) of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0022] Figure 4 The longitudinal bending moment consolidation principle of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0023] Figure 5 The transverse bending moment consolidation principle of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0024] Figure 6 The torsional consolidation principle of the temporary fixing structure for the construction of the tower-beam penetration structure provided by the embodiment of the present utility model;

[0025] In the figure: 1, main beam; 11, top surface of the main beam; 12, middle main beam; 13, side main beam; 14, cross beam; 2, main tower; 21, lower tower column; 3, lower tower pier; 4, transverse temporary consolidation system; 41, transverse limit block; 42, transverse block cushion stone; 5, longitudinal temporary consolidation system; 51, longitudinal limit block; 52, longitudinal block cushion stone; 6, longitudinal damping system. Specific embodiments

[0026] Next, the technical solutions in the embodiments of the present utility model will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all of the embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present utility model.

[0027] In the description of the present utility model, it should be understood that the orientation or positional relationship indicated by the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present utility model.

[0028] The terms "first" and "second" are used only for descriptive purposes and should not be construed as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, features defined with "first" and "second" may explicitly or implicitly include one or more of such features; in the description of the present utility model, unless otherwise specified, the meaning of "a plurality" is two or more.

[0029] As Figures 1 - 3 shown, this embodiment provides a temporary fixing structure for the construction of a tower-beam through structure. The main beam 1 and the main tower 2 are both arranged on the lower tower pier 3, and the main tower 2 vertically penetrates the main beam 1. Transverse temporary consolidation systems 4 are arranged between both longitudinal sides of the main tower 2 and the main beam 1, and longitudinal temporary consolidation systems 5 are arranged between both transverse sides of the main tower 2 and the main beam 1. The transverse temporary consolidation systems 4 and the longitudinal temporary consolidation systems 5 are both arranged in the horizontal direction. This embodiment utilizes the characteristics of the tower-beam through structure itself to horizontally arrange the temporary consolidation systems, effectively solving the problem of the tight temporary consolidation space of the tower-beam through structure; and separating the longitudinal and transverse consolidations to avoid the unfavorable stress conditions under the combined action of bending, shear, and torsion in the traditional vertical consolidation.

[0030] In some embodiments, the transverse temporary consolidation system 4 includes a transverse limiting block 41 and a transverse block cushion stone 42. One end of the transverse block cushion stone 42 abuts against the main tower 2, and the transverse limiting block 41 is arranged between the other end and the main beam 1. This embodiment realizes the effective fixation and limitation of the main tower 2 and the main beam 1 in the transverse direction through the combined use of the transverse limiting block 41 and the transverse block cushion stone 42.

[0031] Optimally, first bituminous felt isolation layers are arranged on both end faces of the transverse limiting block 41. In this embodiment, first bituminous felt isolation layers are arranged on the end face for abutting against one end of the main beam 1 and on the end face for abutting against one end of the transverse block cushion stone 42 of the transverse limiting block 41, which is beneficial for removing the transverse limiting block 41 and reducing friction and wear at the same time.

[0032] Further optimally, a first sulfuric acid mortar layer is arranged between at least one end face of the transverse limiting block 41 and the corresponding first bituminous felt isolation layer. In this embodiment, the first sulfuric acid mortar layer can be arranged only between the end face for abutting against one end of the main beam 1 of the transverse limiting block 41 and the first bituminous felt isolation layer thereon, or only between the end face for abutting against one end of the transverse block cushion stone 42 of the transverse limiting block 41 and the first bituminous felt isolation layer thereon, or the first sulfuric acid mortar layer can be arranged between both end faces of the transverse limiting block 41 and the first bituminous felt isolation layers on both end faces. The first sulfuric acid mortar layer can be removed relatively conveniently through methods such as high-temperature melting, so as to facilitate the removal of the transverse temporary consolidation system 4.

[0033] In this embodiment, the lateral limiting block 41 is a concrete block, and the sulfur cement mortar used for the first sulfur cement mortar layer is required to reach the M40 grade to ensure the strength requirement of the lateral temporary consolidation system 4. Further, the thickness of the first sulfur cement mortar layer is 5-15 cm; preferably, the thickness of the first sulfur cement mortar layer is 10 cm.

[0034] In some embodiments, the longitudinal temporary consolidation system 5 includes a longitudinal limiting block 51 and a longitudinal block cushion stone 52. One end of the longitudinal block cushion stone 52 abuts against the main tower 2, and the longitudinal limiting block 51 is arranged between the other end and the main girder 1. In this embodiment, through the combined use of the longitudinal limiting block 51 and the longitudinal block cushion stone 52, the effective fixation and limitation of the main tower 2 and the main girder 1 in the longitudinal direction of the bridge are realized.

[0035] Optimally, second felt isolation layers are arranged on the end faces at both ends of the longitudinal limiting block 51. In this embodiment, second felt isolation layers are arranged on the end face for abutting against one end of the main girder 1 and the end face for abutting against one end of the longitudinal block cushion stone 52 of the longitudinal limiting block 51, so as to facilitate the removal of the longitudinal limiting block 51 and reduce friction and wear at the same time.

[0036] Further optimally, a second sulfur cement mortar layer is arranged between the end face of at least one end of the longitudinal limiting block 51 and the corresponding second felt isolation layer. In this embodiment, the second sulfur cement mortar layer can be arranged only between the end face for abutting against one end of the main girder 1 of the longitudinal limiting block 51 and the second felt isolation layer thereon, or only between the end face for abutting against one end of the longitudinal block cushion stone 52 of the longitudinal limiting block 51 and the second felt isolation layer thereon, or the second sulfur cement mortar layer can be arranged between the end faces at both ends of the longitudinal limiting block 51 and the second felt isolation layers at both end faces. The second sulfur cement mortar layer can be removed more conveniently by means of high-temperature melting, etc., so as to facilitate the removal of the longitudinal temporary consolidation system 5.

[0037] In this embodiment, the longitudinal limiting block 51 is a concrete block, and the sulfur cement mortar used for the second sulfur cement mortar layer is required to reach the M40 grade to ensure the strength requirement of the longitudinal temporary consolidation system 5. Further, the thickness of the second sulfur cement mortar layer is 5-15 cm; preferably, the thickness of the second sulfur cement mortar layer is 10 cm.

[0038] Such as Figure 2 and Figure 3As shown, the main beam 1 includes a main beam 1 top plate, a middle main beam 12, a side main beam 13 and a cross beam 14; the main tower 2 vertically penetrates the main beam 1 top plate from the space surrounded by the two middle main beams 12 and the two cross beams 14; the transverse temporary consolidation system 4 is arranged between the main tower 2 and the middle main beam 12, and the longitudinal temporary consolidation system 5 is arranged between the main tower 2 and the cross beam 14.

[0039] Among them, the middle main beam 12 and the side main beam 13 are arranged along the longitudinal bridge direction, and the two at the two ends of the transverse bridge direction are the side main beams 13, and the two in the middle are the middle main beams 12; the two middle main beams 12 are arranged on the lower tower pier 3 through a support system; the cross beam 14 is arranged along the transverse bridge direction, and there are multiple cross beams 14; the top plate of the main beam 1 is arranged on the top of the middle main beam 12, the side main beam 13 and the cross beam 14, and the top plate of the main beam 1 is provided with a through hole for the main tower 2 to pass through, and the through hole is provided with cross beams 14 on both sides of the transverse bridge direction, and the middle main beams 12 are provided on both sides of the longitudinal bridge direction; longitudinal temporary consolidation systems 5 are provided between the two sides of the transverse bridge direction of the main tower 2 and the cross beams 14 on both sides, and transverse temporary consolidation systems 4 are provided between the two sides of the longitudinal bridge direction of the main tower 2 and the middle main beams 12 on both sides.

[0040] In one embodiment, the main tower 2 includes an upper tower column and two lower tower columns 21 arranged along the longitudinal bridge direction, and the tops of the two lower tower columns 21 are fixed to the bottom of the upper tower column, and the bottoms of the two lower tower columns 21 are arranged on the lower tower pier 3; a transverse temporary consolidation system 4 is arranged between the two sides of the longitudinal bridge direction of each lower tower column 21 and the main beam 1; a longitudinal temporary consolidation system 5 is arranged between the opposite ends of the two lower tower columns 21 and the main beam 1.

[0041] like Figure 1 and Figure 2 As shown, two through holes for two lower tower columns 21 to pass through are arranged on the top plate of the main beam 1, and the bottoms of the two lower tower columns 21 pass through the two through holes respectively and are arranged on the lower tower pier 3; and a transverse temporary consolidation system 4 is arranged between the two sides of the longitudinal bridge direction of each lower tower column 21 and the middle main beams 12 on both sides, and two longitudinal temporary consolidation systems 5 are arranged between the side of each lower tower column 21 away from the other lower tower column 21 and the corresponding cross beam 14.

[0042] The working principle of the temporary fixed structure used for the tower-beam interpenetrating structure construction of this embodiment is as follows:

[0043] like Figure 4 As shown, when there is an unbalanced bending moment M in the longitudinal direction of the bridge during construction, the longitudinal temporary consolidation system 5 comes into play. Under the action of the unbalanced bending moment M, an axial force F sufficient to balance M is generated in the longitudinal temporary consolidation system 5. At this time, the temporary consolidation system is mainly under pressure.

[0044] like Figure 5As shown in the figure, when there is a transverse unbalanced bending moment M during the construction process, the transverse temporary consolidation system 4 comes into play at this time. Under the action of the unbalanced bending moment M, an axial force F sufficient to balance M is generated in the transverse temporary consolidation system 4. At this time, the temporary consolidation system is mainly under pressure.

[0045] As Figure 6 shown in the figure, when there is an unbalanced torque Mz in the horizontal plane during the construction process, the longitudinal temporary consolidation system 5 and the transverse temporary consolidation system 4 come into play simultaneously at this time. Under the action of the unbalanced torque Mz, an axial force F sufficient to balance Mz is generated in the longitudinal temporary consolidation system 5 and the transverse temporary consolidation system 4. At this time, the temporary consolidation system is mainly under pressure.

[0046] The compressive strength of concrete is much higher than its tensile strength. By using the temporary consolidation system to be under pressure to balance the bending moment and torque, it is possible to avoid the structural complexity caused by the vertical temporary consolidation being under tension to balance the bending moment and torque, and give full play to the advantage of the strong compressive capacity of the concrete material. Moreover, the temporary consolidation structure of this embodiment is simple in structure, convenient to install and operate, and has a low cost.

[0047] The above are only the preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. A temporary fixing structure for the construction of a structure where the tower pier penetrates through the main beam. The main beam and the main tower are both arranged on the lower tower pier, and the main tower vertically penetrates through the main beam. It is characterized in that: A transverse temporary consolidation system is provided between the main beam and both sides of the longitudinal bridge direction of the main tower, and a longitudinal temporary consolidation system is provided between the main beam and both sides of the transverse bridge direction of the main tower. The transverse temporary consolidation system and the longitudinal temporary consolidation system are both arranged in the horizontal direction.

2. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 1, characterized in that: The transverse temporary consolidation system comprises a transverse limit stopper and a transverse stopper pad stone. One end of the transverse stopper pad stone abuts against the main tower, and the transverse limit stopper is arranged between the other end and the main beam.

3. The temporary fixing structure for the construction of the tower-beam penetrating structure according to claim 2, characterized in that: The end surfaces at both ends of the transverse limit stopper are both provided with a first oil felt isolation layer.

4. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 3, characterized in that: A first sulfur cement mortar layer is arranged between the end surface of at least one end of the transverse limit stopper and the corresponding first oil felt isolation layer.

5. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 4, characterized in that: The thickness of the first sulphur cement mortar layer is 5-15 cm.

6. The temporary fixing structure for the construction of the tower-beam penetrating structure according to claim 5, characterized in that: The longitudinal temporary consolidation system comprises a longitudinal limit stopper and a longitudinal stopper pad stone. One end of the longitudinal stopper pad stone abuts against the main tower, and the longitudinal limit stopper is arranged between the other end and the main beam.

7. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 6, characterized in that: The end surfaces at both ends of the longitudinal limit stopper are provided with a second oil felt isolation layer.

8. The temporary fixing structure for the construction of the tower-beam penetrating structure according to claim 7, characterized in that: A second sulfur cement mortar layer is arranged between the end surface of at least one end of the longitudinal limit block and the corresponding second oil felt isolation layer.

9. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 1, characterized in that: The main beam includes a main beam top plate, a middle main beam, a side main beam and a cross beam. The main tower vertically penetrates the main beam top plate from the space surrounded by the two middle main beams and the two cross beams. The transverse temporary consolidation system is arranged between the main tower and the middle main beam, and the longitudinal temporary consolidation system is arranged between the main tower and the cross beam.

10. The temporary fixing structure for the construction of the tower-beam penetration structure according to claim 1, characterized in that: The main tower includes an upper tower column and two lower tower columns arranged along the longitudinal bridge direction, and the tops of the two lower tower columns are fixed to the bottom of the upper tower column, and the bottoms of the two lower tower columns are arranged on the lower tower pier; a transverse temporary consolidation system is arranged between the two sides of the longitudinal bridge direction of each lower tower column and the main beam; a longitudinal temporary consolidation system is arranged between the opposite ends of the two lower tower columns and the main beam.