Construction frame mounting device for building engineering construction
Through the combination of expansion bolts and arc-shaped block structures, the problem of unstable installation of scaffolds in high-rise buildings is solved, and stable connection and lossless installation are achieved.
Patent Information
- Application Number
- CN202423199006.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-24
- Publication Date
- 2025-08-22
- Estimated Expiration
- 2034-12-24
AI Technical Summary
Existing scaffolding requires the use of simple wall connecting parts in the installation of high-rise buildings, which leads to unstable installation and requires cutting or destroying the wall for connection.
The connecting plate and the wall are fixed by expanding bolts, the position of the scaffolding column is adjusted by using a screw and an arc-shaped block structure, and the arc-shaped block is fixed by a second fixing bolt to improve installation stability.
The stable installation of the scaffolding is achieved, which avoids cutting and damage to the wall and improves the use effect.
Smart Images

Figure CN223256437U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction engineering, and in particular relates to a construction frame installation device for construction engineering. Background Art
[0002] Construction frame is also called scaffolding. Scaffolding is a working platform set up to ensure the smooth progress of each construction process. According to the location of the scaffolding, it can be divided into external scaffolding and internal scaffolding; according to different materials, it can be divided into wooden scaffolding, bamboo scaffolding, and steel pipe scaffolding; according to the structural form, it can be divided into vertical pole scaffolding, bridge scaffolding, portal scaffolding, suspended scaffolding, hanging scaffolding, cantilever scaffolding, and climbing scaffolding.
[0003] Existing scaffolding needs to be installed and fixed with wall connecting parts during the installation of high-rise buildings. However, most of the wall connecting parts have a relatively simple structure. Some are pre-buried and need to be cut later, and some require the wall to be destroyed before connection and installation, resulting in poor use effect. For this reason, we propose a construction frame installation device for construction engineering construction. Utility Model Content
[0004] The purpose of the utility model is to provide a construction frame installation device for construction engineering to solve the problems raised in the above background technology.
[0005] To achieve the above-mentioned objectives, the present invention provides the following technical solutions: a construction frame installation device for construction engineering construction, comprising a fixing rod, a connecting plate is provided at one end of the fixing rod, a fixing hole is provided on one side of the connecting plate, a limiting plate is provided on one side of the connecting plate, a connecting block is provided between the limiting plates, a first fixing bolt is provided between the limiting plate and the connecting block, a rotating shaft is provided at the other end of the fixing rod, a connecting hole is provided on the inner side of the fixing rod, a screw rod is provided on the inner side of the connecting hole, a fixing block is provided at one end of the screw rod, a support rod is provided on the surface of the fixing block, a first arc block is provided on one side of the fixing block, a second arc block is provided on one side of the first arc block, and a second fixing bolt is provided between the first arc block and the second arc block.
[0006] Preferably, a connecting plate is fixedly mounted on one end of the fixing rod, a fixing hole is penetrated through a surface of one side of the connecting plate, and limiting plates are mounted on both upper and lower ends of one side of the connecting plate.
[0007] Preferably, a connecting block is rotatably installed between the limiting plates, and the limiting plates and the connecting block are fixedly connected by a first fixing bolt.
[0008] Preferably, the other end surface of the fixing rod is rotatably connected to a rotating shaft, a connecting hole is fixedly opened on the inner side of the fixing rod, a screw rod is passed through the inner side of the connecting hole and connected, and the screw rod is rotatably connected to the inner side of the rotating shaft by a thread.
[0009] Preferably, one end of the screw rod is fixedly connected to a fixed block, a support rod is passed through and fixedly connected to the surface of the fixed block, and one side of the fixed block is rotatably connected to a first arc block.
[0010] Preferably, one side of the first arc block is rotatably connected to the second arc block, and the first arc block and the second arc block are fixedly connected by a second fixing bolt.
[0011] Compared with the prior art, the beneficial effects of the present invention are:
[0012] Expansion bolts are used to fix the fixing holes on the surface of the connecting plate and the holes in the wall. The scaffolding column that needs to be reinforced is placed between the first arc block and the second arc block through the length of the screw rod extending from one end of the connecting hole. The first arc block and the second arc block are fixed with the second fixing bolt, thereby improving the installation stability of the scaffolding, eliminating the need for cutting and pre-embedding in the later stage, and improving the use effect of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a schematic diagram of the front structure of the utility model;
[0014] Figure 2 It is a schematic diagram of the overall structure of the utility model;
[0015] Figure 3 This is a schematic diagram of the connecting hole structure of the present utility model.
[0016] In the figure: 1. fixing rod; 2. connecting plate; 3. fixing hole; 4. limiting plate; 5. connecting block; 6. first fixing bolt; 7. rotating shaft; 8. connecting hole; 9. screw rod; 10. fixing block; 11. support rod; 12. first arc block; 13. second arc block; 14. second fixing bolt. DETAILED DESCRIPTION
[0017] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0018] See also Figure 1-3The utility model provides a technical solution: a construction frame installation device for construction engineering, comprising a fixing rod 1, a connecting plate 2 is provided at one end of the fixing rod 1, a fixing hole 3 is provided on one side of the connecting plate 2, a limiting plate 4 is provided on one side of the connecting plate 2, a connecting block 5 is provided between the limiting plates 4, a first fixing bolt 6 is provided between the limiting plate 4 and the connecting block 5, a rotating shaft 7 is provided at the other end of the fixing rod 1, a connecting hole 8 is provided on the inner side of the fixing rod 1, a screw rod 9 is provided on the inner side of the connecting hole 8, a fixing block 10 is provided at one end of the screw rod 9, a support rod 11 is provided on the surface of the fixing block 10, a first arc block 12 is provided on one side of the fixing block 10, a second arc block 13 is provided on one side of the first arc block 12, and a second fixing bolt 14 is provided between the first arc block 12 and the second arc block 13.
[0019] Specifically, a connecting plate 2 is fixedly installed at one end of the fixing rod 1, and a fixing hole 3 is penetrated on the surface of one side of the connecting plate 2. Limiting plates 4 are installed on the upper and lower ends of one side of the connecting plate 2, and a connecting block 5 is rotatably installed between the limiting plates 4. The limiting plate 4 and the connecting block 5 are fixedly connected by a first fixing bolt 6. The other end surface of the fixing rod 1 is rotatably connected to a rotating shaft 7, and a connecting hole 8 is fixed on the inner side of the fixing rod 1. A screw rod 9 is penetrated and connected to the inner side of the connecting hole 8. The screw rod 9 is rotatably connected to the inner side of the rotating shaft 7 by a thread. One end of the screw rod 9 is fixedly connected to a fixing block 10, and a support rod 11 is fixedly connected to the surface of the fixing block 10. One side of the fixing block 10 is rotatably connected to a first arc block 12, and one side of the first arc block 12 is rotatably connected to a second arc block 13. The first arc block 12 and the second arc block 13 are fixedly connected by a second fixing bolt 14.
[0020] In this embodiment, when fixing and installing the outside of the scaffolding, a suitable wall position on one side of the scaffolding is selected for drilling, and then the fixing holes 3 on the surface of the connecting plate 2 are fixed and installed with expansion bolts. According to the position of the scaffolding column, the angle of the fixing rod 1 and the connecting block 5 on the inner side of the limit plate 4 is adjusted, and then it is fixed by the first fixing bolt 6. The screw rod 9 is driven to rotate by the support rod 11, and the length of the screw rod 9 extending out of one end of the connecting hole 8 is adjusted. The first arc block 12 and the second arc block 13 are opened, and the scaffolding column to be reinforced is placed between the first arc block 12 and the second arc block 13, and then the first arc block 12 and the second arc block 13 are fixed with the second fixing bolt 14, thereby improving the installation stability of the scaffolding.
[0021] Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations may be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction frame installation device for construction engineering, comprising a fixing rod (1), characterized in that: A connecting plate (2) is provided at one end of the fixing rod (1), a fixing hole (3) is provided on one side of the connecting plate (2), a limiting plate (4) is provided on one side of the connecting plate (2), a connecting block (5) is provided between the limiting plates (4), a first fixing bolt (6) is provided between the limiting plate (4) and the connecting block (5), a rotating shaft (7) is provided at the other end of the fixing rod (1), a connecting hole (8) is provided on the inner side of the fixing rod (1), a screw rod (9) is provided on the inner side of the connecting hole (8), a fixing block (10) is provided at one end of the screw rod (9), a support rod (11) is provided on the surface of the fixing block (10), a first arc block (12) is provided on one side of the fixing block (10), a second arc block (13) is provided on one side of the first arc block (12), and a second fixing bolt (14) is provided between the first arc block (12) and the second arc block (13).
2. A construction scaffolding installation device for construction engineering according to claim 1, characterized in that: A connecting plate (2) is fixedly mounted on one end of the fixing rod (1), a fixing hole (3) is provided through a surface of one side of the connecting plate (2), and limiting plates (4) are mounted on both upper and lower ends of one side of the connecting plate (2).
3. The construction scaffolding installation device for construction engineering according to claim 1, characterized in that: A connecting block (5) is rotatably mounted between the limiting plates (4), and the limiting plates (4) and the connecting block (5) are fixedly connected via a first fixing bolt (6).
4. The construction scaffolding installation device for construction engineering according to claim 1, characterized in that: The other end surface of the fixing rod (1) is rotatably connected to a rotating shaft (7), and a connecting hole (8) is fixedly opened on the inner side of the fixing rod (1). A screw rod (9) is passed through the inner side of the connecting hole (8) and connected, and the screw rod (9) is rotatably connected to the inner side of the rotating shaft (7) via a thread.
5. The construction scaffolding installation device for construction engineering according to claim 1, characterized in that: One end of the screw rod (9) is fixedly connected to a fixed block (10), a support rod (11) is fixedly connected to the surface of the fixed block (10), and one side of the fixed block (10) is rotatably connected to a first arc block (12).
6. The construction scaffolding installation device for construction engineering according to claim 1, characterized in that: One side of the first arc block (12) is rotatably connected to the second arc block (13), and the first arc block (12) and the second arc block (13) are fixedly connected via a second fixing bolt (14).