Pipeline mounting assembly

By designing the pipe installation components and utilizing the connection method of hangers and installation frames, the problem of multi-disciplinary cross-operations in traditional construction is solved, enabling fast and stable pipe installation and improving construction efficiency and aesthetics.

CN223563642UActive Publication Date: 2025-11-18广东天元建筑设计有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520133462.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-20
Publication Date
2025-11-18
Estimated Expiration
2035-01-20

AI Technical Summary

Technical Problem

Traditional electromechanical pipeline construction mainly uses wet methods for on-site installation, which leads to frequent cross-operations of multiple disciplines in the same time and space, causing mutual influence and constraints, and increasing the difficulty of construction.

Method used

The pipe installation assembly includes hangers and mounting frames. The main body is fixed to the mounting wall to provide a stable support point. The connection between the first hanger and the first mounting part realizes the circumferential fixation of the pipe. A decorative panel can be added for concealment, simplifying the construction process.

Benefits of technology

It reduces construction difficulty, increases the speed and efficiency of pipeline installation, and improves the reliability and aesthetics of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223563642U_ABST
    Figure CN223563642U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline installation subassembly relates to pipeline installation technical field, pipeline installation subassembly is used for fixing pipeline to the mounting wall, pipeline installation subassembly includes hanging piece and mounting frame, hanging piece includes main part and first hanging portion, the main part is used for mounting on the mounting wall, and the first hanging portion is used for mounting on the mounting wall. The first hanging part is located on the outer side face of the body, the lower end of the first hanging part is connected with the body, and the upper end of the first hanging part is spaced from the body. The mounting frame comprises a frame body and a first hanging part, the frame body is used for allowing a pipeline to penetrate through and be fixed, the first hanging part is arranged on the outer side face of the frame body, the upper end of the first hanging part is connected with the frame body, the lower end of the first hanging part is spaced from the frame body, and the first hanging part is hung on the first hanging part. According to the technical scheme, the construction difficulty is reduced, and the pipeline installation speed is increased.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to pipeline installation technical field, especially pipeline installation assembly. BACKGROUND

[0002] In prior art, the traditional mechanical and electrical pipeline construction mainly uses the method of building and installing simultaneously, and the wet construction is mainly used, and the construction is mainly concentrated in the later stage of civil construction, due to the construction of multiple professions in the same time and space, frequent cross operation, mutual influence and restriction, and the construction difficulty is improved. CONTENT

[0003] The utility model discloses a pipeline installation assembly, which aims to reduce the construction difficulty and improve the pipeline installation speed.

[0004] To achieve the above object, the utility model provides a pipeline installation assembly for fixing the pipeline to the installation wall, which comprises:

[0005] The hanging part comprises a main body and a first hanging part, the main body is used to be installed on the installation wall, the first hanging part is located on the outer side of the main body, and the lower end is connected with the main body, and the upper end is spaced from the main body.

[0006] The installation frame comprises a frame body for fixing the pipeline and a first mounting part, the first mounting part is arranged on the outer side of the frame body, the upper end of the first mounting part is connected with the frame body, and the lower end is spaced from the frame body, and the first mounting part is hung on the first hanging part.

[0007] In an embodiment, the frame body is provided with the first mounting part on the outer side.

[0008] In an embodiment, the first mounting part extends along the circumference of the frame body to be arranged on the outer side of the frame body.

[0009] In an embodiment, the first mounting part is integrally arranged with the frame body.

[0010] In an embodiment, the outer side of the frame body and below the first mounting part is provided with a second hanging part, the lower end of the second hanging part is connected with the frame body, and the upper end is spaced from the frame body.

[0011] The pipeline installation assembly further comprises a decorative plate, the inner side of the upper end of the decorative plate is provided with a second mounting part, the upper end of the second mounting part is connected with the decorative plate, and the lower end is spaced from the decorative plate, and the second mounting part is hung on the second hanging part.

[0012] In an embodiment, the frame body is provided with the second hanging part on the outer side.

[0013] In one embodiment, the second hanging portion extends circumferentially along the frame to be disposed on a plurality of outer sides of the frame.

[0014] In one embodiment, the second mounting part is integrally formed with the frame.

[0015] In one embodiment, the first mounting portion and the second mounting portion are arranged in a ring along the circumference of the frame to define a T-shaped groove between the first mounting portion and the second mounting portion.

[0016] Both the first mounting part and the second mounting part have notches at their corresponding positions.

[0017] In one embodiment, a T-shaped block is provided on the outer side of the frame, and the T-shaped block can be confined within the T-shaped groove through the notch.

[0018] In the technical solution of this utility model, by fixing the main body to the mounting wall, a stable support point is provided, allowing the first hanging part connected to it to be fixed in the air. The inner side of the frame allows the pipe to pass through and fix the pipe in its circumferential direction. When the first hanging part is hung on the first mounting bracket, the upper end of the first hanging part enters the space between the lower end of the first hanging part and the frame, and the lower end of the first hanging part enters the space between the upper end of the first hanging part and the main body, so that the two can be stably connected. Thus, by pre-installing the hanging component at the required installation position on the mounting wall, fitting the mounting frame onto the pipe, and then hanging the first hanging part on the first mounting bracket, the construction difficulty can be reduced and the speed of pipe installation can be increased. Attached Figure Description

[0019] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.

[0020] Figure 1 A schematic diagram of a structure of an embodiment of the pipe installation assembly provided by this utility model;

[0021] Figure 2 for Figure 1 Sectional view at point AA;

[0022] Figure 3 for Figure 1 Sectional view at point BB;

[0023] Figure 4 for Figure 1 sectional view at C-C;

[0024] Figure 5 for Figure 1 structure schematic diagram of the pipe installation assembly in implementation;

[0025] Figure 6 for Figure 5 sectional view at A-A;

[0026] Figure 7 for Figure 5 sectional view at B-B;

[0027] Figure 8 for Figure 5 sectional view at C-C;

[0028] Figure 9 for Figure 5 structure schematic diagram of the hanging piece in implementation;

[0029] Figure 10 for Figure 5 structure schematic diagram of the installation frame in implementation;

[0030] Figure 11 for Figure 5 structure schematic diagram of the decorative plate in implementation;

[0031] Figure 12 for Figure 5 structure schematic diagram of the pipe installation assembly in implementation completion;

[0032] Figure 13 for Figure 5 structure schematic diagram of another pipe installation assembly in implementation completion.

[0033] BRIEF DESCRIPTION OF THE DRAWINGS

[0034] 100, pipe installation assembly; 200, installation wall; 300, pipe; 310, finished chimney; 320, drain pipe;

[0035] 1, hanging piece; 11, main body; 12, first hanging part;

[0036] 2, installation frame; 21, frame body; 22, first hanging part; 23, second hanging part; 24, T-shaped groove; 25, notch; 26, T-shaped block;

[0037] 3, decorative plate; 31, second hanging part.

[0038] The realization, functional features and advantages of the present application will be further described with reference to the embodiments and the accompanying drawings. DETAILED DESCRIPTION

[0039] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work fall within the scope of the present application.

[0040] It should be noted that if the embodiments of the present application involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative positional relationship, movement condition, etc. between components in a certain specific posture, and if the specific posture changes, the directional indications also change accordingly.

[0041] In addition, if the embodiments of the present application involve descriptions such as "first", "second", etc., the descriptions of "first", "second", etc. are only for description purposes, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features with "first" and "second" can explicitly or implicitly include at least one of the features. In addition, if "and / or" or "and / or" appears throughout the text, it means that the three parallel schemes are included, for example, "A and / or B" includes A scheme, or B scheme, or A and B simultaneously satisfy the scheme. In addition, the technical solutions of each embodiment can be combined with each other, but it must be based on the fact that a person skilled in the art can realize it, and when the combination of technical solutions appears contradictory or unachievable, it should be considered that the combination of technical solutions does not exist, and is not within the scope of protection required by the present application.

[0042] In the prior art, the traditional mechanical and electrical pipeline construction is mainly based on wet construction, and the construction is mainly concentrated in the later stage of civil construction. Due to the construction of multiple specialties in the same time and space, frequent cross operation, mutual influence and restriction, the construction difficulty is increased.

[0043] In order to solve the above technical problems, such as Figures 1 to 4The utility model provides a pipeline installation assembly 100 for fixing pipeline 300 to installation wall 200, the pipeline installation assembly 100 includes and installs frame 2 of hanging piece 1. Hanging piece 1 includes main body 11 and first hanging part 12, the main body 11 is used to install to installation wall 200, the first hanging part 12 is located the outside of main body 11, and lower end is connected with main body 11, and upper end is spaced with main body 11. Install frame 2 includes the frame body 21 for pipeline 300 to pass through fixed and first mounting part 22, the first mounting part 22 is located the outside of frame body 21, the upper end of first mounting part 22 is connected with frame body 21, and its lower end is spaced with frame body 21, and the first mounting part 22 is hung in first hanging part 12.

[0044] In the technical scheme of the utility model, Figures 9 to 13 The inner side of frame body 21 can pass pipeline 300 and fix pipeline 300 in its circumferential direction. When the first mounting part 22 is hung in first hanging part 12, the upper end of first hanging part 12 enters the lower end of first mounting part 22 spaced from frame body 21, and the lower end of first mounting part 22 enters the upper end of first hanging part 12 spaced from main body 11, so that they can be stably connected. Therefore, by pre-installing hanging piece 1 at the required installation position of installation wall 200, installing frame 2 on pipeline 300, and then hanging first mounting part 22 on first hanging part 12, the assembly steps can be reduced, the construction difficulty can be reduced, and the installation speed of pipeline 300 can be improved.

[0045] It can be understood that the installation wall 200 is used to provide different support heights for the hanging piece 1, which can be a brick wall, a metal wall or a wooden wall. The pipeline 300 is used to transport medium, so it can be selected as a finished flue 310 and a drainage pipeline 320 according to the different transported medium. Here, it is worth mentioning that when the pipeline installation assembly 100 is used in the kitchen area of the building, the finished flue 310 and the drainage pipeline 320 can be arranged at the reserved installation position of the installation wall 200 at the same time, thereby forming an integrated pipe well module to realize flue gas and water flow circulation for kitchens of different floors.

[0046] It can be understood that the hanging piece 1 can be fixed on the installation wall 200 in various ways, such as bolt connection, welding or insertion. Due to the different positions of the hanging piece 1 caused by different environments during actual installation, in an embodiment, a through hole is arranged on the main body 11. The operator can quickly fix the hanging piece 1 on the installation wall 200 by using expansion bolts through the hole at the corresponding position of the installation wall 200, and reduce the influence of the external environment.

[0047] In order to further improve the fixing effect between the hanging piece 1 and the installation frame 2, in an embodiment, the plurality of outer sides of the frame body 21 are provided with the first mounting part 22. In this way, the first mounting part 22 arranged on the plurality of outer sides of the frame body 21 can be buckled with the first hanging part 12 of the plurality of hanging pieces 1 fixed on the installation wall 200. The installation frame 2 can be limited in multiple directions, and then the frame body 21 is fixed, so that the pipeline 300 located in the frame body 21 can be better fixed. The specific number of the outer sides of the frame body 21 can be set according to actual needs, for example, 2, 3, 4, 5 or 6, which is not particularly limited here.

[0048] Further, in order to facilitate the hanging of the first mounting part 22 on the first hanging part 12, in an embodiment, the first mounting part 22 extends along the circumference of the frame body 21 to be arranged on the plurality of outer sides of the frame body 21. In this way, by increasing the extension size of the first mounting part 22 in the axial direction of the frame body 21, the first mounting part 22 can be mounted on the first hanging part 12 without additional precise positioning, which is beneficial for quick installation.

[0049] In an embodiment, the first mounting part 22 is integrally arranged with the frame body 21. In this way, there is no connection gap or interface between the integrally arranged first mounting part 22 and the frame body 21, which makes the installation frame 2 more solid and stable. It is beneficial to resist external force impact and vibration, and ensures the reliability and safety of the installation frame 2 during use. The first mounting part 22 and the frame body 21 can be integrally arranged by casting (by pouring molten metal into a mold, after the metal cools and solidifies, a part with the required shape and structure can be obtained), 3D printing (by layer-by-layer stacking of materials, a part with complex shape and structure can be accurately manufactured) and stamping (by cutting, bending and other operations of the mold on the metal plate, the required shape is formed).

[0050] As Figures 5 to 8In order to shield the exposed pipeline 300, the second mounting portion 23 is arranged on the outer side of the frame 21 below the first mounting portion 22. The lower end of the second mounting portion 23 is connected to the frame 21, and the upper end of the second mounting portion 23 is spaced apart from the frame 21. The upper end of the second mounting portion 23 enters the space between the lower end of the second mounting portion 31 and the decorative plate 3 when the second mounting portion 31 is mounted on the second mounting portion 23. The lower end of the second mounting portion 31 enters the space between the upper end of the second mounting portion 23 and the frame 21, so that the second mounting portion 31 and the second mounting portion 23 can be stably connected. The exposed pipeline 300 can be shielded by the decorative plate 3 connected to the second mounting portion 31, which can improve the appearance and reduce the corrosion of the pipeline caused by the external environment.

[0051] It can be understood that the mounting frame 2 can be arranged in multiple numbers along the extension direction of the pipeline 300 to improve the fixing effect of the pipeline 300. In order to facilitate installation, the length of the decorative plate 3 can be set according to the spacing between two mounting frames 2, so as to facilitate modular assembly and improve work efficiency. In addition, in an embodiment, a decorative strip is filled between two adjacent decorative plates 3, which can improve the stability of the installation of the decorative plate 3, and can also fill the gap between the two decorative plates 3, further improving the appearance and the tightness between the decorative plates.

[0052] In order to further improve the fixing effect between the second mounting portion 31 and the second mounting portion 23, in an embodiment, the second mounting portion 23 is arranged on multiple outer sides of the frame 21. In this way, the second mounting portion 23 arranged on multiple outer sides of the frame 21 can be engaged with multiple second mounting portions 31 on which the decorative plates 3 are fixed, so as to shield the pipeline 300 in multiple directions. The specific number of outer sides of the frame 21 can be set according to actual needs, for example, 2, 3, 4, 5 or 6, which is not particularly limited herein.

[0053] Further, in order to facilitate the second mounting part 31 to be mounted on the second mounting part 23, in an embodiment, the second mounting part 23 extends along the circumference of the frame body 21 to be arranged on the plurality of outer sides of the frame body 21. In this way, by increasing the extension size of the second mounting part 23 in the axial direction of the frame body 21, the second mounting part 31 can be mounted on the second mounting part 23 without the need for additional precise positioning, which is conducive to quick installation.

[0054] In an embodiment, the second mounting part 23 is integrally arranged with the frame body 21. In this way, the second mounting part 23 and the frame body 21 are integrally arranged without connection gaps or interfaces, which makes the mounting frame 2 more solid and stable. It is conducive to resist external force impact and vibration, and ensure the reliability and safety of the mounting frame 2 during use. The second mounting part 23 and the frame body 21 can be integrally arranged by casting (by injecting molten metal into a mold, and after the metal cools and solidifies, a part with the required shape and structure can be obtained), 3D printing (by layer-by-layer stacking of materials, a part with complex shape and structure can be accurately manufactured), and stamping (by cutting, bending, etc. Operation of the metal plate by the mold to form the required shape).

[0055] In an embodiment, the first mounting part 22 and the second mounting part 23 are arranged along the circumference of the frame body 21 and arranged in a ring shape to define a T-shaped slot 24 between the first mounting part 22 and the second mounting part 23; the first mounting part 22 and the second mounting part 23 are provided with a notch 25 at the corresponding position. In this way, by arranging a corresponding T-shaped block 26 on the connecting piece, the T-shaped block 26 can be slid into the T-shaped slot 24 defined on the frame body 21 through the notch 25, which can be used to connect other components. Further, in an embodiment, the outer side of the frame body 21 is provided with a T-shaped block 26, which is limited in the T-shaped slot 24 through the notch 25, so that the mounting frame 2 with the T-shaped block 26 can be spliced together with the mounting frame 2 with the notch 25, so that the mounting frame 2 with the T-shaped block 26 can also fix a pipe 300, which is conducive to the quick assembly of two mounting frames 2, and can be used in combination to fix a plurality of pipes 300, improving assembly efficiency.

[0056] The above description is only an exemplary embodiment of the present application, and does not limit the patent scope of the present application, and any equivalent structural transformation made by using the content of the present application specification and drawings, or direct / indirect application in other related technical fields is included in the patent protection scope of the present application.

Claims

1. A pipe mounting assembly for securing a pipe to a mounting wall, characterized in that, The pipe installation assembly includes: A mounting bracket includes a main body and a first mounting portion. The main body is for mounting on a mounting wall, and the first mounting portion is located on the outer side of the main body, with its lower end connected to the main body and its upper end spaced apart from the main body. The mounting frame includes a frame body for fixing pipes through and a first mounting part. The first mounting part is located on the outer side of the frame body. The upper end of the first mounting part is connected to the frame body, and its lower end is spaced apart from the frame body. The first mounting part is hung on the first mounting part.

2. The pipe installation assembly as described in claim 1, characterized in that, The frame is provided with the first mounting part on multiple outer sides.

3. The pipe installation assembly as described in claim 2, characterized in that, The first mounting portion extends circumferentially along the frame to be disposed on multiple outer sides of the frame.

4. The pipe installation assembly as described in any one of claims 1 to 3, characterized in that, The first mounting part is integrally formed with the frame.

5. The pipe installation assembly as described in claim 1, characterized in that, A second hanging part is provided on the outer side of the frame and below the first hanging part. The lower end of the second hanging part is connected to the frame, and its upper end is spaced apart from the frame. The pipe installation assembly also includes a decorative panel, on the inner side of the upper end of the decorative panel, a second mounting part is provided, the upper end of the second mounting part is connected to the decorative panel, and its lower end is spaced apart from the decorative panel, the second mounting part is hung on the second mounting part.

6. The pipe installation assembly as described in claim 5, characterized in that, The frame is provided with the second hanging part on multiple outer sides.

7. The pipe installation assembly as described in claim 6, characterized in that, The second hanging part extends circumferentially along the frame to be disposed on multiple outer sides of the frame.

8. The pipe installation assembly as described in any one of claims 5 to 7, characterized in that, The second mounting part is integrally formed with the frame.

9. The pipe installation assembly as described in claim 5, characterized in that, The first mounting part and the second mounting part are arranged in a ring along the circumference of the frame to define a T-shaped groove between the first mounting part and the second mounting part; Both the first mounting part and the second mounting part have notches at their corresponding positions.

10. The pipe installation assembly as claimed in claim 9, characterized in that, The outer side of the frame is provided with a T-shaped block, which can be confined within the T-shaped groove by the notch.