Production device for preparing dry-mixed concrete from coal gangue

By designing a coal gangue-based dry-mixed concrete production device, the problems of complex processes and low efficiency of existing equipment have been solved. This device enables efficient sorting and sand making of coal gangue, improves the degree of automation, and promotes the comprehensive utilization of resources and environmental protection.

CN223775006UActive Publication Date: 2026-01-09QINGDAO HAIZOU HEAVY MACHINERY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423050986.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-11
Publication Date
2026-01-09
Estimated Expiration
2034-12-11

AI Technical Summary

Technical Problem

Existing coal gangue processing equipment has complex processes, low efficiency, and low automation, resulting in low resource utilization efficiency and serious environmental pollution.

Method used

A coal gangue dry-mixed concrete production device was designed, including a storage silo, a feeder, a crusher, a separator, a sand making machine, a vibrating screen, a mixer, and other equipment, realizing an automated process for efficient coal gangue sorting, sand making, and concrete production.

Benefits of technology

It improves production efficiency, realizes the efficient utilization of coal gangue and the recovery of clean coal and pyrite, reduces environmental pollution, conforms to the development trend of green building materials, and ensures the quality stability of dry-mixed concrete.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223775006U_ABST
    Figure CN223775006U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building material preparation, and discloses a production device for preparing dry-mixed concrete from coal gangue, which comprises a storage bin, a feeder arranged on one side of the storage bin, a crusher arranged on one side of the feeder, a first elevator arranged on one side of the crusher, a first belt conveyor arranged between the first elevator and the crusher, and a second belt conveyor arranged between the first belt conveyor and the crusher. A first sorting machine is arranged on one side of the first elevator, and a second sorting machine is arranged on one side of the first sorting machine; the whole production process is highly automatic, manual intervention is reduced, and the production efficiency is improved; comprehensive utilization of resources: efficient utilization of coal gangue is realized through processes of separation, sand making and the like, and separated clean coal and pyrite are also recycled; coal gangue accumulation and environmental pollution are reduced, and the development trend of green building materials is met; accurate control: a metering screw and other accurate control equipment are adopted, so that the quality stability of the dry-mixed concrete is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to building material preparation technical field, concretely is a kind of coal gangue preparation dry mixing concrete production device. BACKGROUND

[0002] Coal gangue is solid waste generated in the process of coal mining and washing, and its large accumulation not only occupies land resources, but also may pollute the environment. In recent years, with the enhancement of environmental awareness and the diversification demand of building materials, the comprehensive utilization of coal gangue has become a research hotspot. Processing coal gangue into dry mixing concrete sand not only realizes the resource utilization of waste, but also reduces the production cost of concrete, which has significant economic and environmental benefits. However, the existing coal gangue processing equipment has the problems of complex process, low efficiency and low automation degree. SUMMARY

[0003] In view of the above situation, in order to overcome the defects of the prior art, the utility model provides a coal gangue preparation dry mixing concrete production device, which effectively solves the problems raised in the above background.

[0004] In order to achieve the above purpose, the utility model provides the following technical scheme: a coal gangue preparation dry mixing concrete production device, which comprises a storage bin, one side of the storage bin is provided with a feeder, one side of the feeder is provided with a crusher, one side of the crusher is provided with a first elevator, a first belt conveyor is arranged between the first elevator and the crusher, one side of the first elevator is provided with a first sorting machine, one side of the first sorting machine is provided with a second sorting machine, a second belt conveyor is arranged between the second sorting machine and the first sorting machine, one side of the second sorting machine is provided with a second elevator, one side of the second elevator is provided with a coal gangue storage bin, one side of the coal gangue storage bin is provided with a sand making machine, a third belt conveyor is arranged between the sand making machine and the coal gangue storage bin, one side of the sand making machine is provided with a vibrating screen, a fourth belt conveyor and a return belt conveyor are arranged between the vibrating screen and the sand making machine, one side of the vibrating screen is provided with a third elevator, a fifth belt conveyor is arranged between the third elevator and the vibrating screen, one side of the third elevator is provided with a finished sand storage bin, a metering screw is connected to the lower end of the finished sand storage bin, a supporting platform is arranged on one side of the finished sand storage bin, a mixer is installed at the lower part of the supporting platform, a metering hopper is arranged above the mixer, a packaging machine is arranged below the mixer, a conveying line is arranged on one side of the packaging machine, and a stacking robot is arranged on one side of the conveying line.

[0005] Preferably, the first sorting machine is provided with a clean coal belt conveyor at the lower end of the discharge end for transporting clean coal.

[0006] Preferably, the second sorting machine is provided with a pyrite belt conveyor at the lower end of the discharge end for transporting pyrite.

[0007] Compared with the prior art, the utility model has the advantages that:

[0008] 1. High-efficiency automation: the entire production process is highly automated, reducing manual intervention and improving production efficiency;

[0009] 2. Comprehensive utilization of resources: through sorting, sand making and other processes, efficient utilization of coal gangue is achieved, and the separated clean coal and pyrite are also recycled;

[0010] 3. Environmental protection and energy saving: reduces the accumulation of coal gangue and environmental pollution, and meets the development trend of green building materials;

[0011] 4. Precise control: using metering screw and other precise control equipment to ensure the quality stability of dry-mixed concrete. BRIEF DESCRIPTION OF DRAWINGS

[0012] The accompanying drawings are used to provide a further understanding of the present application, and constitute a part of the specification, together with the embodiments of the present application, to explain the present application, and do not constitute a limitation on the present application.

[0013] In the drawings:

[0014] Fig. 1 is a schematic diagram of the overall structure of the present application;

[0015] Fig. 2 is a schematic diagram of the top-down layout structure of the cabinet body of the present application;

[0016] In the figure: 1, storage bin; 2, feeder; 3, crusher; 4, first elevator; 5, first belt conveyor; 6, first sorting machine; 7, second sorting machine; 8, second belt conveyor; 9, second elevator; 10, coal gangue storage bin; 11, sand making machine; 12, third belt conveyor; 13, vibrating screen; 14, fourth belt conveyor; 15, return belt conveyor; 16, third elevator; 17, fifth belt conveyor; 18, finished sand storage bin; 19, metering screw; 20, support platform; 21, mixer; 22, metering hopper; 23, packaging machine; 24, conveying line; 25, palletizing robot; 26, clean coal belt conveyor; 27, pyrite belt conveyor. DETAILED DESCRIPTION

[0017] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, not all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of the present application.

[0018] Embodiment one,Figs. 1-2 The utility model discloses a coal gangue processing system, including the storage bin 1, the one side of storage bin 1 is equipped with feeder 2, the one side of feeder 2 is equipped with breaker 3, the one side of breaker 3 is equipped with first elevator 4, and is equipped with first belt conveyor 5 between first elevator 4 and breaker 3, and the one side of first elevator 4 is equipped with first sorting machine 6, and the one side of first sorting machine 6 is equipped with second sorting machine 7, and is equipped with second belt conveyor 8 between second sorting machine 7 and first sorting machine 6, and the one side of second sorting machine 7 is equipped with second elevator 9, and the one side of second elevator 9 is equipped with coal gangue storage bin 10, and the one side of coal gangue storage bin 10 is equipped with sand making machine 11, and is equipped with third belt conveyor 12 between sand making machine 11 and coal gangue storage bin 10, and the one side of sand making machine 11 is equipped with vibrating screen 13, and is equipped with fourth belt conveyor 14 and return belt conveyor 15 between vibrating screen 13 and sand making machine 11, and the one side of vibrating screen 13 is equipped with third elevator 16, and is equipped with fifth belt conveyor 17 between third elevator 16 and vibrating screen 13, and the one side of third elevator 16 is equipped with finished sand storage bin 18, and finished sand storage bin 18 lower end is connected with metering screw 19, and the one side of finished sand storage bin 18 is equipped with support platform 20, and is installed mixer 21 in support platform 20 lower part, and is equipped with measuring hopper 22 in mixer 21 upper portion, and is equipped with packing machine 23 below mixer 21, and is equipped with conveying line 24 on the one side of packing machine 23, and is equipped with palletizing robot 25 on the one side of conveying line 24;

[0019] The first sorting machine 6 lower end discharge end is equipped with the coal belt conveyor 26 for transporting the clean coal;

[0020] The second sorting machine 7 lower end discharge end is equipped with the pyrite belt conveyor 27 for transporting the pyrite.

[0021] Working principle:

[0022] The storage bin 1 is used for storing the coal gangue raw materials to be processed, and the raw materials are preliminarily piled and arranged to prepare for subsequent processing.

[0023] When the coal gangue raw materials in the storage bin 1 reach a certain amount, the feeder 2 is started to continuously and uniformly convey the coal gangue raw materials to the breaker 3.

[0024] The breaker 3 is used for receiving the coal gangue raw materials from the feeder 2 and crushing them into smaller particles through strong crushing force.

[0025] The crushed coal gangue is conveyed to the first elevator 4 through the first belt conveyor 5, the first elevator 4 lifts the coal gangue to a certain height through the lifting mechanism, and then sends the coal gangue into the first sorting machine 6 through the discharge port.

[0026] The coal gangue is preliminarily sorted in the first sorting machine 6, and different quality materials are separated according to particle size and density and other characteristics. Some of the separated materials may contain valuable components such as clean coal, which is transported out by the clean coal belt conveyor 26, and the remaining materials enter the second sorting machine 7 for further sorting to remove more impurities and unqualified particles. The second sorting machine 7 is provided with a pyrite belt conveyor 27 at the discharge end for transporting out the separated by-products such as pyrite;

[0027] The qualified coal gangue particles after sorting are lifted to the coal gangue storage bin 10 by the second elevator 9 for temporary storage, providing stable raw material supply for the subsequent sand making process;

[0028] The coal gangue in the coal gangue storage bin 10 is transported to the sand making machine 11 by the third belt conveyor 12. The sand making machine 11 further crushes and shapes the coal gangue particles into required sand particles by impact and shearing principles;

[0029] The sand particles produced by the sand making machine 11 are transported to the vibrating screen 13 by the fourth belt conveyor 14 for screening. The vibrating screen 13 classifies the sand particles by particle size using the vibration principle. The qualified products fall into the collection device below the screen, and the unqualified products are returned to the sand making machine 11 for reprocessing by the return belt conveyor 15, ensuring the uniformity of particle size and the stability of quality of the finished sand;

[0030] The screened finished sand is transported to the third elevator 16 by the fifth belt conveyor 17. The third elevator 16 lifts the finished sand to a certain height and then sends it into the finished sand storage bin 18 through the discharge port for storage;

[0031] The sand particles in the finished sand storage bin 18 are accurately metered and controlled by the metering screw 19. The metering screw 19 adjusts the speed and discharge amount according to production requirements to ensure the accuracy of raw material ratio in the subsequent mixing process;

[0032] The metered finished sand and other ingredients such as cement and water are sent into the mixer 21 through the metering hopper 22 for mixing and stirring. The mixer 21 uses the rotation and shearing action of the stirring blades to fully mix and uniform various raw materials, forming the required dry-mixed concrete;

[0033] The mixed dry-mixed concrete is packaged by the packaging machine 23. The packaged concrete products are transported to the palletizing robot 25 through the conveying line 24 for automatic palletizing according to the preset program and parameters. The palletizing robot 25 neatly stacks the concrete products on pallets or shelves for outbound or transportation.

[0034] In summary, the coal gangue preparation dry mixing concrete production device realizes efficient conversion of coal gangue and production and preparation of dry mixing concrete through a series of orderly process steps and equipment cooperation. The entire production process has high automation degree, high production efficiency and stable and reliable product quality.

Claims

1. A coal gangue preparation dry-mixed concrete production device, comprising a storage bin (1), characterized in that: The side of the storage bin (1) is provided with a feeder (2), one side of the feeder (2) is provided with a crusher (3), one side of the crusher (3) is provided with a first elevator (4), a first belt conveyor (5) is arranged between the first elevator (4) and the crusher (3), one side of the first elevator (4) is provided with a first sorting machine (6), one side of the first sorting machine (6) is provided with a second sorting machine (7), a second belt conveyor (8) is arranged between the second sorting machine (7) and the first sorting machine (6), one side of the second sorting machine (7) is provided with a second elevator (9), one side of the second elevator (9) is provided with a coal gangue storage bin (10), one side of the coal gangue storage bin (10) is provided with a sand making machine (11), a third belt conveyor (12) is arranged between the sand making machine (11) and the coal gangue storage bin (10), one side of the sand making machine (11) is provided with a vibrating screen (13), a fourth belt conveyor (14) and a return belt conveyor (15) are arranged between the vibrating screen (13) and the sand making machine (11), one side of the vibrating screen (13) is provided with a third elevator (16), a fifth belt conveyor (17) is arranged between the third elevator (16) and the vibrating screen (13), one side of the third elevator (16) is provided with a finished sand storage bin (18), a metering screw (19) is connected to the lower end of the finished sand storage bin (18), one side of the finished sand storage bin (18) is provided with a support platform (20), a mixer (21) is installed at the lower part of the support platform (20), a metering hopper (22) is arranged above the mixer (21), a packaging machine (23) is arranged below the mixer (21), a conveying line (24) is arranged on one side of the packaging machine (23), and a stacking robot (25) is arranged on one side of the conveying line (24).

2. The coal gangue preparation dry-mixed concrete production device according to claim 1, characterized in that: The first sorting machine (6) is provided with a clean coal belt conveyor (26) at the lower end of the discharge end.

3. The coal gangue preparation device for producing dry-mixed concrete according to claim 1, characterized in that: The second sorting machine (7) is provided with a pyrite belt conveyor (27) at the lower end of the discharge end.