A conical belt breaking station
By designing a tracked cone crusher station, the high cost and time consumption problems of traditional cone crushers during relocation are solved, realizing convenient equipment movement and continuous feeding, and improving crushing efficiency and equipment life.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- HENAN ZHONGJI IND TECHNOLOGY CO LTD
- Filing Date
- 2025-08-28
- Publication Date
- 2026-07-24
AI Technical Summary
Traditional stationary cone crushers are costly, time-consuming, and difficult to adjust during frequent relocation, which affects crushing efficiency and results in insufficient feeding continuity.
Design a cone crusher track station, which adopts an integrated mobile frame setup, combined with automatic feeding components and angle adjustment, to achieve convenient equipment movement and continuous feeding.
It improves the flexibility and mobility of the equipment, shortens the construction period, reduces the workload of workers, ensures the continuity of material feeding, and extends the service life of the equipment.
Smart Images

Figure CN224541926U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of crushing equipment technology, and in particular to a cone crusher track station. Background Technology
[0002] As a core component of a stationary production line, the installation of a traditional cone crusher is a massive and complex undertaking. The equipment needs to be installed on a robust concrete foundation and securely fixed with anchor bolts to withstand the enormous impact and vibration generated during the crushing process. The construction and maintenance of this foundation, as well as the subsequent hoisting, alignment, and commissioning of large equipment, often take weeks or even months, requiring significant investment of manpower and resources.
[0003] Once a project is completed or mining operations progress and a site relocation is necessary, the above process must be repeated in reverse: dismantling the equipment and foundations, disconnecting all power and transport connections, hoisting and transporting heavy main and auxiliary equipment, and then repeating all installation and commissioning steps at the new site. This process is not only extremely costly and time-consuming, but the frequent disassembly and reassembly may also potentially damage the equipment's accuracy and reliability. This makes traditional stationary cone crushers unsuitable for projects requiring frequent site relocation, such as different sections of highway / railway construction or mining at small to medium-sized, scattered mines, thus severely limiting their operational adaptability.
[0004] In addition, most existing equipment relies on manual adjustment of the feed angle, resulting in insufficient feed continuity and affecting crushing efficiency. Utility Model Content
[0005] In view of the above situation and to overcome the defects of the prior art, this utility model provides a cone crusher track station. This design effectively solves the problems of poor flexibility, high relocation cost and difficult equipment adjustment of existing crushers.
[0006] To achieve the above objectives, the present invention provides the following technical solution: The present invention includes a mobile frame, a crushing chamber in the middle of the mobile frame, a conical rotor rotatably connected inside the crushing chamber, a feed inlet on the upper side of the crushing chamber of the conical rotor, a feed pipe fixedly connected inside the feed inlet, a feeding assembly on the side of the feed pipe, a discharge outlet on the lower side of the crushing chamber of the conical rotor, a discharge funnel fixedly connected to the discharge outlet, a discharge frame below the discharge funnel, and a first conveyor belt installed on the discharge frame.
[0007] Preferably, the feed pipe is provided with a top cover rotary table, the top cover rotary table is rotatably connected to the mobile frame, and a feed hopper is fixedly connected to the top cover rotary table. The feed hopper is connected to the crushing chamber through the feed pipe.
[0008] Preferably, the feeding assembly includes a feeding rack with a second conveyor belt mounted on it. One side of the feeding rack is connected to a mobile frame, and the other side of the feeding rack is located above the feed hopper.
[0009] Preferably, the loading rack is hinged to the mobile frame, and a first hydraulic rod is hinged to the middle of the loading rack, with the other end of the first hydraulic rod hinged to the mobile frame.
[0010] Preferably, a screening frame is hinged to the bottom of the discharge frame, and a second hydraulic rod is installed between the middle of the screening frame and the discharge frame.
[0011] Preferably, the screening rack is equipped with a finished product screen, a third conveyor belt is provided below the finished product screen, a return frame is provided on the side of the finished product screen, the return frame is hinged to the screening rack, and a fourth conveyor belt is provided on the return frame.
[0012] Compared with the prior art, the outstanding advantages of this utility model are:
[0013] This invention improves the ease of equipment movement by integrating the design on a mobile frame, reduces the time required for preliminary preparation, and shortens the construction period. In addition, the automatic feeding and angle adjustment of the feeding components reduce the workload of workers and ensure the continuity of equipment feeding. Attached Figure Description
[0014] Figure 1 This is a schematic diagram of the forward structure of Embodiment 1 of this utility model.
[0015] Figure 2 This is a schematic diagram of the left side of Embodiment 1 of this utility model.
[0016] Figure 3 This is a schematic diagram of the rear structure of Embodiment 1 of this utility model.
[0017] Figure 4 This is a top view of the structure of Embodiment 1 of this utility model.
[0018] Figure 5 This is a schematic diagram of the front cross-sectional structure of Embodiment 1 of this utility model.
[0019] Figure 6 This is a schematic diagram of the forward structure of Embodiment 2 of this utility model.
[0020] Figure 7 This is a schematic diagram of the rear structure of Embodiment 2 of this utility model.
[0021] Figure 8 This is a top view of the structure of Embodiment 2 of this utility model.
[0022] Figure 9This is a front cross-sectional structural diagram of Embodiment 2 of this utility model.
[0023] The diagram is labeled as follows: 1. Moving frame; 2. Crushing chamber; 3. Conical rotor; 4. Feed pipe; 5. Feeding assembly; 501. Feeding rack; 502. Second conveyor belt; 503. First hydraulic rod; 6. Discharge hopper; 7. Discharge rack; 8. First conveyor belt; 9. Top cover rotary table; 10. Feed hopper; 11. Screening rack; 12. Second hydraulic rod; 13. Finished product screen; 14. Third conveyor belt; 15. Return rack; 16. Fourth conveyor belt. Detailed Implementation
[0024] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model. Example 1
[0025] Please see the appendix Figure 1-5 This embodiment provides a cone crusher tracked station, comprising a mobile frame 1, a crushing chamber 2 in the middle of the mobile frame 1, a cone rotor 3 rotatably connected inside the crushing chamber 2, a feed inlet on the upper side of the crushing chamber 2 of the cone rotor 3, a feed pipe 4 fixedly connected inside the feed inlet, a feeding assembly 5 on the side of the feed pipe 4, a discharge outlet on the lower side of the crushing chamber 2 of the cone rotor 3, a discharge funnel 6 fixedly connected to the discharge outlet, a discharge frame 7 below the discharge funnel 6, and a first conveyor belt 8 installed on the discharge frame 7.
[0026] The mobile frame 1 is equipped with tracked wheels at its bottom. The crushing chamber 2 is located directly above the tracked wheels and is a vertical cylindrical cavity. A conical rotor 3 is rotatably mounted inside the crushing chamber 2. The crushing chamber 2 and the conical rotor 3 must be coaxial. The bottom of the conical rotor 3 is the main support assembly, which is mounted inside the crushing chamber 2 via multiple transverse support rods. Gaps exist between these transverse support rods, which both support the main support assembly and prevent the crushed stone from falling downwards. The crushing chamber 2 is placed vertically. The upper end of the crushing chamber 2 is the feed inlet, and the lower end is the discharge outlet. The material enters the crushing chamber 2 from the feed pipe 4 and the feed inlet. Under the action of gravity, it enters the periphery of the cone rotor 3. Then, the cone rotor 3 rotates and crushes it into small-sized stones. The small-sized stones fall into the discharge outlet through the gap between the cone rotor 3 and the crushing chamber 2. The discharge funnel 6 below the discharge outlet is connected to the discharge frame 7 and the first conveyor belt 8. The discharge frame 7 extends to the upper left side of the moving frame 1. The first conveyor belt 8 has the same structure as the existing conveyor belt and is existing technology.
[0027] The feed pipe 4 is surrounded by a top cover rotary table 9, which can rotate on the moving frame 1. The feed hopper 10 is connected to the rotary table and can rotate with the rotary table. This allows the feed hopper 10 to receive the material. At the same time, by adjusting the rotary table, the material is ensured to enter the crushing chamber 2 through the feed pipe 4 at a suitable angle, so that the material contacts the cone rotor 3 at the best impact angle. This avoids excessive wear of the blades on the cone rotor 3 and improves the service life of the cone rotor 3.
[0028] The feeding rack 501 is located on the right side of the discharge pipe. The left side of the feeding rack 501 is hinged to the left side of the mobile frame 1. The left side of the feeding rack 501 is lower than the right side. During construction, the material is moved to the left side of the feeding rack 501 by a loader. The lower position of the left side of the feeding rack 501 makes it easier for the loader to release the material. The second conveyor belt 502 on the feeding rack 501 is used to transport the material upward. The second conveyor belt 502 moves the material obliquely upward. The other end of the second conveyor belt 502 is located above the feed hopper 10. The material falls into the feed hopper 10 under the action of inertia and gravity at the rightmost end of the second conveyor belt 502, and then enters the crushing chamber 2 from the feed hopper 10. Furthermore, a flexible connecting belt is connected between the right end of the feeding rack and the feed hopper 10. In this way, the material enters the feed hopper 10 in a relatively sealed space, which avoids dust from being scattered outward.
[0029] In addition, the loading rack 501 can be hinged to the mobile frame 1 at one end, and the middle part of the loading rack 501 is hinged to the mobile frame 1 through the first hydraulic rod 503. The first hydraulic rod 503 can be extended and retracted to change the tilt angle of the loading rack 501 by changing its length. Example 2
[0030] like Figure 6-9 As shown, a screening rack 11 is installed below the discharge rack 7. The screening rack 11 is mainly used to screen the finished stone. The upward extension length of the screening rack 11 is greater than that of the discharge rack 7. Therefore, after the stones on the second conveyor belt 502 are released from above, they enter the finished screen 13 under the action of gravity. The finished screen 13 has screen holes. Stones that meet the size requirements fall through the screen holes to the third conveyor belt 14 and move to the right from the third conveyor belt 14. The larger stones above the finished screen 13 are transferred back to the loading rack 501 through the return rack 15 and the fourth conveyor belt 16. The return rack 15 has two horizontal connecting platforms at both ends. At the same time, the return rack 15 has an angle adjustment function and has a degree of freedom of rotation between it and the two horizontal connecting platforms, which can move large stones to other positions.
[0031] Finally, it should be noted that the above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Although the present utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.
Claims
1. A conical track crusher station, characterized in that: The device includes a mobile frame (1), a crushing chamber (2) in the middle of the mobile frame (1), a conical rotor (3) rotatably connected inside the crushing chamber (2), a feed inlet on the upper side of the crushing chamber (2) of the conical rotor (3), a feed pipe (4) fixedly connected inside the feed inlet, a feeding assembly (5) on the side of the feed pipe (4), a discharge port on the lower side of the crushing chamber (2) of the conical rotor (3), a discharge funnel (6) fixedly connected at the discharge port, a discharge rack (7) below the discharge funnel (6), and a first conveyor belt (8) installed on the discharge rack (7).
2. The conical crusher track station according to claim 1, characterized in that: The feed pipe (4) is provided with a top cover turntable (9), which is rotatably connected to the mobile frame (1). A feed hopper (10) is fixedly connected to the top cover turntable (9), and the feed hopper (10) is connected to the crushing chamber (2) through the feed pipe (4).
3. A conical track crusher station according to claim 2, characterized in that: The feeding assembly (5) includes a feeding rack (501) on which a second conveyor belt (502) is installed. One side of the feeding rack (501) is connected to the mobile frame (1), and the other side of the feeding rack (501) is located above the feed hopper (10).
4. A conical track crusher station according to claim 3, characterized in that: The loading rack (501) is hinged to the mobile frame (1), and a first hydraulic rod (503) is hinged in the middle of the loading rack (501). The other end of the first hydraulic rod (503) is hinged to the mobile frame (1).
5. A conical track crusher station according to claim 1, characterized in that: The bottom of the discharge rack (7) is hinged to a screening rack (11), and a second hydraulic rod (12) is installed between the middle of the screening rack (11) and the discharge rack (7).
6. A conical track crusher station according to claim 5, characterized in that: The screening rack (11) is equipped with a finished product screen (13), and a third conveyor belt (14) is provided below the finished product screen (13). A return rack (15) is provided on the side of the finished product screen (13). The return rack (15) is hinged to the screening rack (11), and a fourth conveyor belt (16) is provided on the return rack (15).