Flood-prevention quick sandbag device
Patent Information
- Application Number
- CN202522099267.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-09-29
- Publication Date
- 2026-10-20
- Estimated Expiration
- 2035-09-29
AI Technical Summary
[0002]河道工程防汛是重中之重,加快施工进度,减少人员和机械投入是发展的必要目标;在雨季防汛施工中,沙袋是防汛重要物资,传统装沙袋是一个工人撑沙袋,另外一个工人使用铁锹进行装填,速度较慢,投入施工人员较多;防汛属于抢险工程,如果不能快速施工,将会导致不可挽回的损失
本实用新型可以平稳的支撑沙袋,使用时通过挂钩部固定沙袋袋口,装沙后可以上提脱袋把手部实现快速脱钩,可以解放人员撑袋,避免装沙过程中施工人员误伤,并且提高施工效率,实现了抢险救灾更快一步,可以更好的保证人民的生命和财产安全。
Smart Images

Figure CN224870524U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of flood control construction equipment technology, and in particular to a rapid flood control sandbag device. Background Technology
[0002] Flood control is of paramount importance in river engineering. Accelerating construction progress and reducing the input of personnel and machinery are necessary development goals. During flood control construction in the rainy season, sandbags are an important material. Traditionally, one worker holds the sandbag while another worker fills it with a shovel, which is slow and requires a large number of workers. Flood control is an emergency rescue project. If construction cannot be carried out quickly, it will lead to irreparable losses. Utility Model Content
[0003] The purpose of this utility model is to provide a rapid sandbag filling device for flood control by using a sandbag filling tool to achieve rapid sand filling, reduce manual labor input, speed up construction during disaster relief, and ensure the safety of people's lives and property.
[0004] To achieve the above objectives, this utility model provides the following technical solution: A rapid sandbag control device for flood control includes a frame; the frame surrounds sandbags on three sides and has an opening on one side; the frame includes two horizontal bars located on both sides of the sandbag opening, a rotating part is sleeved on the outer side of the horizontal bar, and hooks and bag release handles connected to the two sides of the rotating part are respectively provided on the inner and outer sides of the horizontal bar, driving the bag release handle to drive the rotating part and hooks to rotate.
[0005] Furthermore, both ends of the crossbar are provided with rotating parts, and hooks are connected to the inner side of each rotating part. The bag-removing handle is a V-shaped rod structure with both ends connected to the rotating parts at both ends of the crossbar.
[0006] Furthermore, the rotating part is a spiral structure sleeved on the outside of the crossbar part.
[0007] Furthermore, the hook, rotating part, and bag-removing handle are integrally bent steel strips.
[0008] Furthermore, each of the crossbar sections near the opening end of the frame is connected to a long vertical support leg, and the crossbar sections away from the opening end of the frame are connected to a V-shaped connecting rod section, with a short support leg connected to the lower side of the middle of the connecting rod section.
[0009] Furthermore, the crossbar, long support leg, and connecting rod are integrally bent threaded steel bars; the short support leg is a vertical threaded steel bar, and the connection between the short support leg and the connecting rod is welding.
[0010] Furthermore, the lower ends of both the long and short legs are bent in a direction away from the center of the frame to form a bent section.
[0011] Furthermore, the lower part of the frame is provided with a U-shaped reinforcing rod, the end of which is connected to the long support leg and the middle part of which is connected to the short support leg.
[0012] Compared with the prior art, the beneficial effects of this utility model are as follows: This utility model can stably support sandbags. When in use, the opening of the sandbag is fixed by the hook. After filling with sand, the handle can be lifted to quickly release the hook. This frees up personnel from holding the bag, avoids accidental injury to construction workers during the sand filling process, improves construction efficiency, enables faster disaster relief, and better protects people's lives and property. Attached Figure Description
[0013] Figure 1 This is a first-view three-dimensional structural diagram of the present invention.
[0014] Figure 2 This is a second-view three-dimensional structural diagram of the present invention.
[0015] Figure 3 This is a front view schematic diagram of the present utility model.
[0016] Figure 4 This is a right-side view of the present invention.
[0017] Figure 5 This is a top view of the present invention.
[0018] Figure 6 This is a bottom view of the present invention.
[0019] In the diagram: 1. Horizontal bar; 2. Hook; 3. Rotating part; 4. Bag removal handle; 5. Long support leg; 6. Connecting rod; 7. Short support leg; 8. Bending section; 9. Reinforcing bar. Detailed Implementation
[0020] The present invention will now be described in further detail with reference to the accompanying drawings. The drawings are simplified schematic diagrams, illustrating only the basic structure of the present invention, and therefore only show the components relevant to the present invention.
[0021] Specific embodiments of the flood control rapid sandbag device provided by this utility model: Please see Figures 1-6 The flood control rapid sandbag device includes a frame, which is formed by bending and welding several threaded steel bars and several steel bars. The frame is open from top to bottom, surrounds sandbags on three sides, and has an opening on one side. The three sides of the frame protect the sandbags and form a three-sided support structure to ensure the stability of the sandbags during the sand filling process. The opening facilitates the removal and placement of the sandbags.
[0022] The frame includes two horizontal bars 1 located on either side of the sandbag opening. In this embodiment, during the sand filling process after the sandbag opening is fixed, the horizontal bars 1 are slightly higher than the sandbag opening. Each horizontal bar 1 is connected to a long vertical support leg 5 near the opening of the frame. The horizontal bars 1 are connected to a V-shaped connecting rod 6 away from the opening of the frame. A short support leg 7 is connected to the lower middle part of the connecting rod 6, i.e., the outer side of its V-shaped tip.
[0023] The lower ends of the long support leg 5 and the short support leg 7 are at the same height, so that the crossbar 1 is horizontal and the long support leg 5 and the short support leg 7 are vertical.
[0024] The crossbar 1, long support leg 5 and connecting rod 6 are integrally bent threaded steel bars. During manufacturing, a suitable length of threaded steel bar is selected and bent from the middle to form a V-shaped connecting rod 6; two crossbars 1 are formed on both sides of the V-shaped bend, and then two long support legs 5 are formed by bending both ends.
[0025] The short support leg 7 is a vertical threaded steel bar. The connection between the short support leg 7 and the connecting rod part 6 is by welding. In this embodiment, the connecting rod part 6 can be set vertically or inclined. During the bending process, the forming bending direction of the connecting rod part 6 is different from that of the forming bending direction of the crossbar part 1. Through the V-shaped connecting rod part 6, the strength of the frame can be improved and the deformation of the frame can be reduced.
[0026] Vertical outriggers are prone to piercing the ground at the sand loading site, causing the frame to tilt and easily collapse upon impact. Therefore, the lower ends of both the long outrigger 5 and the short outrigger 7 are bent away from the center of the frame to form a bent section 8. The bent section 8 can improve the stability of the support and reduce the phenomenon of collapse, and can also reduce the tilting of the frame.
[0027] The lower part of the frame is equipped with a U-shaped reinforcing rod 9, which is made of bent steel strip. The end of the reinforcing rod 9 is connected to the long support leg 5, and the middle part of the reinforcing rod 9 is connected to the short support leg 7. Both ends of the reinforcing rod 9 are connected to the two long support legs 5 respectively. The connection between the reinforcing rod 9 and the long support legs 5 and the short support legs 7 is by welding.
[0028] Two rotating parts 3 are fitted on the outer sides of both ends of the crossbar 1, for a total of four rotating parts 3. Hook parts 2 and bag-removing handle parts 4 are respectively provided on the inner and outer sides of the crossbar 1, connecting to the two sides of the rotating parts 3. Each rotating part 3 has one hook part 2 connected to its inner side, for a total of four hook parts 2. The bag-removing handle parts 4 are V-shaped rod structures, with both ends connected to the rotating parts 3 at both ends of the crossbar 1. There are two bag-removing handle parts 4, each connected to two rotating parts 3.
[0029] The rotating part 3 is a spiral structure sleeved on the outside of the crossbar part 1. The hook part 2, the rotating part 3, and the bag-removing handle part 4 are all integrally bent steel strips. In the manufacturing process, a steel strip of appropriate length is selected and bent in the middle to form the bag-removing handle part 4. The two ends are bent into a spiral shape on the outside of the crossbar part 1 to form the rotating part 3, and then the end is bent to form the hook part 2.
[0030] When the sandbag opening is hung on the hook part 2, the bag release handle part 4 is in an inclined state. After the sand is filled, the upward drive of the bag release handle part 4 drives the rotating part 3 and the hook part 2 to rotate, so that the hook part 2 is quickly separated from the sandbag.
[0031] When in use, multiple frames are arranged in a row, the mouths of the sandbags are turned outward and hung on the hook part 2, and a small excavator is used to fill them. After filling, the bag release handle part 4 is lifted to release the hook, achieving the effect of quick release.
[0032] The flood control rapid sandbag device in this embodiment is used for sand filling and support. It can stably support the sandbag. When in use, the sandbag opening is fixed by the hook part 2. After filling with sand, the bag release handle part 4 can be lifted to quickly release the hook. This frees up personnel from holding the bag, avoids accidental injury to construction workers during the sand filling process, and improves construction efficiency. It enables faster disaster relief and rescue, and can better protect people's lives and property.
[0033] Finally, it should be noted that the above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still make modifications to the technical solutions described in the foregoing embodiments without creative effort, or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.
Claims
1. A rapid-response sandbag device for flood control, comprising a frame; characterized in that, The frame is surrounded by sandbags on three sides and has an opening on one side. The frame includes two horizontal bars (1) located on both sides of the opening of the sandbags. A rotating part (3) is sleeved on the outside of the horizontal bar (1). Hooks (2) and bag removal handles (4) are respectively connected to the two sides of the rotating part (3) on the inside and outside of the horizontal bar (1). The bag removal handles (4) drive the rotating part (3) and hooks (2) to rotate.
2. The flood control rapid sandbag device according to claim 1, characterized in that, The crossbar (1) has a rotating part (3) at both ends, and a hook part (2) is connected to the inside of the rotating part (3). The bag removal handle (4) is a V-shaped rod structure, and its two ends are connected to the rotating parts (3) at both ends of the crossbar (1).
3. The flood control rapid sandbag device according to claim 1 or 2, characterized in that, The rotating part (3) is a spiral structure sleeved on the outside of the crossbar part (1).
4. The flood control rapid sandbag device according to claim 3, characterized in that, The hook part (2), the rotating part (3) and the bag-removing handle part (4) are integrally bent steel strips.
5. The flood control rapid sandbag device according to claim 1, characterized in that, The horizontal bar (1) is connected to a vertical long support leg (5) near the opening end of the frame. The horizontal bar (1) is connected to a V-shaped connecting rod (6) away from the opening end of the frame. The lower side of the middle part of the connecting rod (6) is connected to a short support leg (7).
6. The flood control rapid sandbag device according to claim 5, characterized in that, The crossbar (1), long support leg (5) and connecting rod (6) are integrally bent threaded steel bars; the short support leg (7) is a vertical threaded steel bar, and the connection between the short support leg (7) and the connecting rod (6) is by welding.
7. The flood control rapid sandbag device according to claim 5, characterized in that, The lower ends of the long support leg (5) and the short support leg (7) are bent in a direction away from the center of the frame to form a bent section (8).
8. The flood control rapid sandbag device according to claim 5, characterized in that, The lower part of the frame is provided with a U-shaped reinforcing rod (9), the end of the reinforcing rod (9) is connected to the long support leg (5), and the middle part of the reinforcing rod (9) is connected to the short support leg (7).