The auxiliary chamber for the TBM tunneling construction adit leading to the main tunnel is arranged in a forward orientation.
By arranging a material transfer tunnel between the main branch tunnel and the main branch tunnel, and using the newly added branch tunnel for material transportation, the problems of low construction efficiency and high safety risks in TBM tunneling were solved. This enabled the TBM to continuously tunnel into the main tunnel from the small-slope construction branch tunnel, improving transportation and construction efficiency while reducing safety risks.
Patent Information
- Application Number
- CN202522690120.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-18
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-12-18
AI Technical Summary
When the adit is continuously excavated to the main tunnel on a small slope, the excavation of the material transfer tunnel causes the TBM to stop and wait, resulting in low construction efficiency. The junction of the main and adit tunnels needs to meet the transportation needs of the upstream TBM excavation and the downstream drilling and blasting excavation, resulting in low transportation efficiency. The excavation height of the enlarged section at the junction of the main and adit tunnels is large, which poses a high safety risk.
A material transfer tunnel is arranged between the intersection of the main tunnel and the branch tunnel. The angle between the branch tunnel and the main tunnel is used to create a new branch tunnel that connects to the main tunnel. The material transfer tunnel is collinear with the axis of the main tunnel. Material is transported through the branch tunnel, so that the TBM tunneling and the drilling and blasting of the material transfer tunnel can be carried out simultaneously, reducing downtime.
It improves the efficiency of tunnel excavation and support, reduces interference between upstream and downstream working faces, saves construction time and costs, improves construction efficiency, and reduces safety risks.
Smart Images

Figure CN224955748U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of tunnel excavation and construction, and more specifically, to a forward-arranged structure for an auxiliary chamber for a TBM tunneling adit leading into the main tunnel. Background Technology
[0002] Construction adits for deep-buried, long-distance water conveyance tunnels are often long. TBMs (Tunnel Boring Machines) continuously excavate from the adits into the main tunnel, offering advantages such as high construction efficiency, safety, a clean and professional appearance, and controllable quality, making them widely used in tunnel excavation and construction. For construction adits with gentle slopes (less than 5%), to ensure transportation efficiency, a combination of trackless transport in the adits and tracked transport in the main tunnel is often used. Material transfer tunnels are required at the junction of the main and adits for material transfer. These material transfer tunnels are typically located in front of the junction, where secondary excavation is carried out after the TBM has passed through. During this secondary excavation, the TBM needs to be stopped for extended periods, resulting in lower construction efficiency.
[0003] Downstream drilling and blasting faces also transport materials through the junction of the main and branch tunnels. As a result, the junction of the main and branch tunnels has to handle the transportation needs of both the upstream TBM tunneling and the downstream drilling and blasting excavation faces, resulting in low transportation efficiency.
[0004] The excavation height of the widened section at the junction of the main and branch tunnels is large, which does not utilize the stability of the tunnel and poses a great safety risk. Utility Model Content
[0005] The purpose of this utility model is to provide a forward-oriented auxiliary chamber arrangement structure for TBM tunneling construction, which can alleviate the technical problems in the existing technology where, when TBMs continuously tunnel from small-slope adits to the main tunnel, under the conventional arrangement of main and adit junctions and auxiliary chambers, the TBM needs to stop and wait due to the excavation of material transfer tunnels, resulting in low construction efficiency; the main and adit junctions need to bear the transportation needs of both upstream TBM tunneling and downstream drill-and-blast excavation faces, resulting in low transportation efficiency; and the large excavation height of the enlarged cross-section at the main and adit junctions poses a high safety risk.
[0006] To solve the above-mentioned technical problems, the technical solution provided by this utility model is as follows: The auxiliary tunnel layout structure for the TBM tunneling construction adit leading to the main tunnel provided by this utility model includes an adit, a main tunnel, a material transfer tunnel, a first connecting tunnel, a second connecting tunnel, and a branch tunnel; The axis of the branch tunnel is set at an angle to the axis of the main tunnel, and the end of the branch tunnel is connected to the main tunnel at the junction of the main tunnel and the branch tunnel. One end of the branch tunnel is connected to the branch tunnel, and the other end is connected to the main tunnel at the junction of the main and branch tunnels. The junction of the main and branch tunnels is located downstream of the junction of the main and branch tunnels along the direction of water flow. The axis of the material conversion tunnel is collinear with the axis of the main tunnel, and one end of the material conversion tunnel is connected to the intersection of the main branch tunnel through the first connecting tunnel, and the other end is connected to the intersection of the main branch tunnel through the second connecting tunnel.
[0007] Furthermore, the diameter of the material conversion hole is larger than the diameters of the first connecting hole and the second connecting hole.
[0008] Furthermore, the material conversion tunnel includes a through section and a variable diameter section, the through section being connected to the first connecting tunnel and the variable diameter section; The diameter of the variable-diameter section gradually increases from the end near the second connecting hole to the end near the through section.
[0009] Furthermore, a reversing tunnel is provided at the intersection of the main tunnel and the branch tunnel. The axis of the reversing tunnel is set at an angle to the axis of the main tunnel and extends away from the branch tunnel.
[0010] Furthermore, the cross-sectional dimension of the main tunnel junction is expanded to the junction of the main tunnel and the branch tunnel, which is greater than the sum of the cross-sectional dimensions of the main tunnel and the branch tunnel.
[0011] Furthermore, at the junction of the main tunnel and the branch tunnel, a pillar is provided between the branch tunnel and the main tunnel.
[0012] Furthermore, a through-type prestressed anchor rod is provided between the branch hole and the first connecting hole.
[0013] Furthermore, the cross-sectional profile at the junction of the main tunnel and the branch tunnel includes a first profile and a second profile, wherein the first profile is aligned with the cross-sectional profile of the main tunnel and the second profile is aligned with the cross-sectional profile of the branch tunnel.
[0014] Furthermore, the cross-sectional profile at the intersection of the main and branch tunnels also includes the top profile; The top contour line is located at the top, and its two ends are connected to the first contour line and the second contour line respectively, forming an arc shape that is concave towards the center of the intersection of the main branch tunnel.
[0015] Furthermore, the beginning of the branch tunnel is provided with a starting tunnel.
[0016] Based on the above technical solutions, the technical effects achievable by this utility model can be analyzed as follows: The auxiliary tunnel structure for the TBM tunneling construction adit leading to the main tunnel, provided by this utility model, includes an adit, a main tunnel, a material transfer tunnel, a first connecting tunnel, a second connecting tunnel, and a branch tunnel. The axis of the adit is set at an angle to the axis of the main tunnel, and the end of the adit is connected to the main tunnel at the junction of the main and adit tunnels. One end of the branch tunnel is connected to the adit, and the other end is connected to the main tunnel at the junction of the main and branch tunnels, and the junction of the main and branch tunnels is located downstream of the junction of the main and adit tunnels along the water flow direction. The axis of the material transfer tunnel is collinear with the axis of the main tunnel, and one end of the material transfer tunnel is connected to the junction of the main and adit tunnels through the first connecting tunnel, and the other end is connected to the junction of the main and branch tunnels through the second connecting tunnel. The auxiliary chamber layout of this TBM excavation construction adit leading into the main tunnel is suitable for the starting and excavation of construction adits with a small slope (slope less than 5%). The material transfer tunnel is arranged between the intersection of the main adit and the intersection of the main branch tunnel. Compared with the conventional TBM, which enters the main tunnel from the adit, stops, and then expands the material transfer tunnel before continuing to excavate, this greatly improves the excavation and support efficiency of the tunnel, reduces interference between upstream and downstream working faces, and saves construction time and cost.
[0017] The auxiliary chamber layout of this TBM excavation tunnel, connecting the adit to the main tunnel, utilizes the small elevation difference between the adit and the main tunnel. A large-span branch tunnel, running in the opposite direction to the TBM excavation, connects the adit to the main tunnel. Sufficient length is reserved in the main tunnel section between the main and adit junctions for a material transfer tunnel. This branch tunnel allows for simultaneous drilling and blasting of the material transfer tunnel and the main tunnel in the opposite direction, minimizing downtime and saving time. TBM material transport, muck removal from the main tunnel in the opposite direction, and material transport can all be carried out through the branch tunnel without interfering with upstream TBM excavation and muck removal, thus improving construction efficiency. This layout method enables continuous TBM excavation from the adit to the main tunnel, reducing mutual interference between upstream and downstream working faces, improving construction efficiency, and shortening the construction period. This auxiliary chamber layout of the TBM excavation tunnel connecting the adit to the main tunnel can be widely adopted in the excavation of deep-buried long tunnels using TBMs.
[0018] The construction sequence of the auxiliary tunnel structure for the TBM tunneling construction adit leading to the main tunnel is as follows: The TBM starts from the adit and begins tunneling; after the TBM tunnels to a suitable position in the adit, the branch tunnel, the second connecting tunnel, the material transfer tunnel and the first connecting tunnel are simultaneously drilled and blasted; after the TBM passes the junction of the main and adit tunnels, it continues to excavate forward for a certain distance and then stops to carry out the widening excavation at the junction of the main and adit tunnels. After the widening excavation is completed, the TBM can continue to tunnel forward. During this period, the excavation of the downstream first connecting tunnel, the second connecting tunnel and the material transfer tunnel can be carried out simultaneously.
[0019] The auxiliary tunnel connecting the TBM tunneling adit to the main tunnel is arranged in a forward orientation. By adding a branch tunnel, the mutual interference between upstream and downstream transportation is avoided, and the transportation efficiency is improved. The material transfer tunnel is located between the intersection of the main adit and the main branch tunnel, which allows TBM tunneling and drilling and blasting of the material transfer tunnel to be carried out simultaneously, thus shortening the construction period. Attached Figure Description
[0020] To more clearly illustrate the technical solutions of the embodiments of this application, the accompanying drawings used in the embodiments of this application will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this application and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0021] Figure 1 A three-dimensional axonometric schematic diagram of the forward arrangement structure of the auxiliary chamber for the TBM tunneling adit leading into the main tunnel, provided in an embodiment of this application; Figure 2 A plan view of the intersection of the main tunnel and the auxiliary tunnel in the forward arrangement structure of the auxiliary tunnel leading to the main tunnel in the TBM tunneling construction adit provided in the embodiment of this application; Figure 3 This is a cross-sectional view of the intersection of the main tunnel and the auxiliary tunnel in the forward arrangement structure of the auxiliary tunnel leading to the main tunnel in the TBM tunneling construction provided in the embodiments of this application.
[0022] icon: 1-Side tunnel; 11-Starting tunnel; 2-Main tunnel; 21-Intersection of main and branch tunnels; 211-First outline; 212-Second outline; 213-Top outline; 22-Intersection of main and branch tunnels; 3-Material transfer tunnel; 31-Through section; 32-Variation section; 41 - First connecting hole; 42 - Second connecting hole; 5-Fork in the tunnel; 6- Reversing hole; 7-Column; 8- Through-through prestressed anchor bolt. Detailed Implementation
[0023] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. The components of the embodiments of this application described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.
[0024] In the description of this application, it should be noted that the terms "inner" and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the product is in use. They are used only for the convenience of describing this application and for simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application. Furthermore, the terms "first," "second," etc., are used only to distinguish descriptions and should not be construed as indicating or implying relative importance.
[0025] In the description of this application, it should also be noted that, unless otherwise expressly specified and limited, the terms "setup" and "connection" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0026] Material transfer tunnels are required at the junction of the main and branch tunnels for material transfer. These tunnels are typically located in front of the junction and are used for secondary widening after the TBM (Tunnel Boring Machine) has passed through. During this widening process, the TBM needs to be stopped for extended periods, resulting in low construction efficiency. No additional branch tunnels are usually excavated at the junction of the main and branch tunnels. Downstream drilling and blasting faces also use this junction for material transport. Thus, the junction must handle the transport needs of both the upstream TBM tunneling and the downstream drilling and blasting faces, leading to low transport efficiency. The widening section at the junction often uses a standard five-centered circle cross-section. This cross-section design results in a large excavation height, is not conducive to tunnel stability, and poses significant safety risks.
[0027] In view of this, see Figure 1 The auxiliary tunnel structure for the TBM tunneling construction adit leading to the main tunnel provided in this embodiment includes an adit 1, a main tunnel 2, a material transfer tunnel 3, a first connecting tunnel 41, a second connecting tunnel 42, and a branch tunnel 5. The axis of the adit 1 is set at an angle to the axis of the main tunnel 2, and the end of the adit 1 is connected to the main tunnel 2 at the main-adit junction 21. One end of the branch tunnel 5 is connected to the adit 1, and the other end is connected to the main tunnel 2 at the main-branch junction 22, and the main-branch junction 22 is located downstream of the main-adit junction 21 along the water flow direction. The axis of the material transfer tunnel 3 is collinear with the axis of the main tunnel 2, and one end of the material transfer tunnel 3 is connected to the main-adit junction 21 through the first connecting tunnel 41, and the other end is connected to the main-branch junction 22 through the second connecting tunnel 42.
[0028] Specifically, materials required for the drilling and blasting face downstream of the main tunnel 2 can be transported through the branch tunnel 5, while materials required for TBM excavation upstream of the main tunnel 2 can be transferred through the branch tunnel 5 to the material transfer tunnel 3, without needing to pass through the circular cross-section of the branch tunnel 1 or to set up a roadway at the bottom of the branch tunnel 1. In this way, upstream TBM excavation and downstream drilling and blasting construction do not interfere with each other, improving construction efficiency. For the small-slope construction branch tunnel 1, transportation efficiency can be improved by combining trackless transportation in the branch tunnel 1 with rail transportation in the main tunnel 2. The material transfer tunnel 3, the interface between trackless and rail transportation, is located between the intersection 21 of the main and branch tunnels and the branch tunnel 5. The material transfer tunnel 3 is connected to the main tunnel 2 by first connecting tunnels 41 and second connecting tunnels 42 on both sides. Drilling and blasting excavation can be carried out through the branch tunnel 5, simultaneously with the TBM excavation.
[0029] The auxiliary chamber layout of this TBM excavation construction adit leading into the main tunnel is suitable for the starting and excavation of construction adit 1 with a small slope (slope less than 5%). The material transfer tunnel 3 is arranged between the intersection of the main adit 21 and the intersection of the main branch tunnel 22. Compared with the conventional TBM, which stops after excavating into the main tunnel 2 from adit 1, expands the material transfer tunnel 3 and then continues to excavate, this greatly improves the excavation and support efficiency of the tunnel, reduces interference between upstream and downstream working faces, and saves construction time and cost.
[0030] The auxiliary tunnel structure for the TBM excavation construction adit leading to the main tunnel utilizes the small slope of the adit 1 and the small elevation difference between the main tunnel 2. A large-span branch tunnel 5, opposite to the TBM excavation direction, is arranged in the adit 1 to connect to the main tunnel 2. Sufficient length is reserved in the main tunnel 2 section between the main adit intersection 21 and the branch tunnel intersection 22 for a material transfer tunnel 3. Drilling and blasting of the material transfer tunnel 3 and the main tunnel 2 in the opposite direction can be carried out through the branch tunnel 5, simultaneously with the TBM excavation, minimizing downtime and saving construction time. TBM material transportation, drilling and blasting of muck in the main tunnel 2 in the opposite direction, and material transportation can all be carried out through the branch tunnel 5, without interfering with the upstream TBM excavation and muck removal, thus improving construction efficiency. This arrangement method enables continuous TBM excavation from the small-slope adit 1 into the main tunnel 2, reducing mutual interference between upstream and downstream working faces, improving construction efficiency, and shortening the construction period. The forward-facing arrangement of the auxiliary chambers for the TBM tunneling adit into the main tunnel can be widely used in the TBM tunneling construction of deep-buried long tunnels.
[0031] The construction sequence of the auxiliary tunnel structure for the TBM tunneling construction adit leading to the main tunnel is as follows: The TBM starts from adit 1 and begins tunneling; after the TBM tunnels to a suitable position in adit 1, the branch tunnel 5, the second connecting tunnel 42, the material transfer tunnel 3 and the first connecting tunnel 41 are simultaneously drilled and blasted; after the TBM passes the junction 21 of the main and adit tunnels, it continues to excavate forward for a certain distance and then stops to widen the junction 21. After the widening is completed, the TBM can continue to tunnel forward. During this period, the excavation of the downstream first connecting tunnel 41, the second connecting tunnel 42 and the material transfer tunnel 3 can be carried out simultaneously.
[0032] The auxiliary tunnel structure for the TBM tunneling construction adit leading into the main tunnel is arranged in a forward direction. The addition of a branch tunnel 5 avoids mutual interference between upstream and downstream transportation and improves transportation efficiency. The material transfer tunnel 3 is arranged between the intersection of the main and adit tunnels 21 and the intersection of the main and branch tunnels 22, which can realize the simultaneous excavation of the TBM tunneling and the drilling and blasting of the material transfer tunnel 3, and can shorten the construction period.
[0033] In the optional solution provided by this utility model embodiment, the diameter of the material conversion hole 3 is larger than the diameter of the first connecting hole 41 and the diameter of the second connecting hole 42.
[0034] Specifically, in this embodiment, the first connecting hole 41, the second connecting hole 42, and the branch hole 5 are excavated into a horseshoe shape or a city gate shape to facilitate material transportation.
[0035] The large diameter of material transfer tunnel 3 facilitates the transportation and transfer of materials.
[0036] In the optional solution provided by this utility model embodiment, the material conversion hole 3 includes a through section 31 and a variable diameter section 32. The through section 31 is connected to the first connecting hole 41 and the variable diameter section 32. The diameter of the variable diameter section 32 gradually increases from the end near the second connecting hole 42 to the end near the through section 31.
[0037] Specifically, the bottom of the variable diameter section 32 is flush with the bottom plate of the through section 31, and the top gradually slopes upward from the end near the second connecting hole 42 to the end near the through section 31.
[0038] The variable diameter section 32 facilitates the transition connection between the through section 31 and the second connecting hole 42.
[0039] In the optional solution provided by this utility model embodiment, a reversing tunnel 6 is provided at the intersection 22 of the main tunnel and the reversing tunnel 6 is set at an angle to the axis of the main tunnel 2 and extends away from the tunnel 5.
[0040] Specifically, a long branch tunnel 5 is set in the branch tunnel 1 to connect to the main tunnel 2, and a reversing tunnel 6 is arranged at the junction 22 of the main and branch tunnels. A material transfer tunnel 3 is arranged between the junction 21 of the main and branch tunnels and the junction 22 of the main and branch tunnels. The two ends of the material transfer tunnel 3 are arranged with a first connecting tunnel 41 and a second connecting tunnel 42 to connect to the main tunnel 2.
[0041] The reversing hole 6 is used for reversing, etc.
[0042] In the optional scheme provided by this utility model embodiment, the cross-sectional dimension of the main tunnel junction 21 is expanded to be greater than the sum of the cross-sectional dimensions of the main tunnel 2 and the cross-sectional dimensions of the branch tunnel 1.
[0043] Specifically, after passing the junction of the main tunnel and the branch tunnel 21, the TBM continues to excavate forward for a certain distance before stopping to widen the junction of the main tunnel and the branch tunnel 21. After the widening is completed, the TBM can continue to excavate forward. During this period, the excavation of the downstream connecting tunnel and the material transfer tunnel 3 can be carried out simultaneously.
[0044] The main tunnel junction 21 is enlarged so that the cross-sectional dimensions of the main tunnel junction 21 are greater than the sum of the cross-sectional dimensions of the main tunnel 2 and the branch tunnel 1, thus making the space at the main tunnel junction 21 sufficiently large.
[0045] In the optional solutions provided by the embodiments of this utility model, see Figure 1 and Figure 2 At the junction of the main tunnel and the branch tunnel 21, a pillar 7 is provided between the branch tunnel 1 and the main tunnel 2.
[0046] Specifically, column 7 is a C35 concrete column. After the first connecting hole 41 and the second connecting hole 42 are connected, column 7 at the junction of the main and branch holes 21 will be constructed in a timely manner.
[0047] A concrete column 7 is installed in the middle of the widened section at the junction of the main tunnel and the branch tunnel to support the rock and increase the overall stability of the surrounding rock.
[0048] In the optional solutions provided by the embodiments of this utility model, see Figure 1 and Figure 2 A through-hole prestressed anchor rod 8 is provided between the branch tunnel 1 and the first connecting tunnel 41.
[0049] Specifically, after the first connecting tunnel 41 and the second connecting tunnel 42 are connected, the through prestressed anchor rods 8 of the section between the main tunnel 2 and the branch tunnel 1 are promptly installed to enhance the overall stability.
[0050] In the optional solutions provided by the embodiments of this utility model, see Figure 3 The cross-sectional outline of the junction 21 of the main tunnel and the branch tunnel includes a first outline 211 and a second outline 212. The first outline 211 is in line with the cross-sectional outline of the main tunnel 2, and the second outline 212 is in line with the cross-sectional outline of the branch tunnel 1.
[0051] Specifically, the enlarged section at the junction of the main tunnel and the branch tunnel 21 adopts an irregular cross-section that is more closely aligned with the shape of the main tunnel 2 and the branch tunnel 1. In order to reduce the amount of excavation in the enlarged section, the sides and bottom of the enlarged section are closely aligned with the outlines of the main tunnel 2 and the branch tunnel 1.
[0052] The first outline 211 fits the cross-sectional outline of the main tunnel 2, and the second outline 212 fits the cross-sectional outline of the branch tunnel 1, reducing the amount of excavation required for the enlarged cross-section.
[0053] In the optional solution provided by this utility model embodiment, the cross-sectional outline of the main branch tunnel junction 21 also includes a top outline 213; the top outline 213 is located at the top, and its two ends are respectively connected to the first outline 211 and the second outline 212, forming an arc shape that is concave towards the center of the main branch tunnel junction 21.
[0054] Specifically, the top of the junction 21 between the main tunnel and the branch tunnel is smoothly connected by an arc to reduce the excavation height of the expanded section.
[0055] The enlarged section at the junction of the main tunnel and the branch tunnel 21 adopts an irregular cross-section that is more closely aligned with the shapes of the main tunnel 2 and the branch tunnel 1. Furthermore, a concrete column 7 is added in the middle of the irregular cross-section, which greatly reduces the amount of excavation, lowers the cost, increases the stability of the structure, saves investment, and reduces safety risks.
[0056] In the optional solution provided by this utility model embodiment, the first end of the branch tunnel 1 is provided with a starting tunnel 11.
[0057] Specifically, the TBM started from the starting tunnel 11 and began excavation.
[0058] The construction organization design for the auxiliary chambers of the TBM tunneling adit leading into the main tunnel during the excavation of the main tunnel 2 is as follows: Materials required for upstream TBM tunneling are transported to the working face via a path consisting of branch tunnel 5, first connecting tunnel 41, second connecting tunnel 42, material transfer tunnel 3, and the intersection 21 of the main and branch tunnels. Before material transfer tunnel 3, transport is trackless; after material transfer tunnel 3, transport is tracked. Materials required for downstream drill-and-blast excavation are transported to the downstream working face via branch tunnel 5, also trackless. The upstream TBM tunneling and downstream drill-and-blast construction do not interfere with each other, improving construction efficiency.
[0059] The construction steps for the auxiliary chamber layout structure of the TBM tunneling adit leading to the main tunnel are as follows: The TBM started excavation from the starting tunnel 11 of the branch tunnel 1; After the TBM tunnels to a suitable position in the adit 1, the branch tunnel 5, the second connecting tunnel 42, the material transfer tunnel 3 and the first connecting tunnel 41 are simultaneously drilled and blasted. After passing the junction of the main tunnel and the branch tunnel 21, the TBM will briefly pause to widen the junction of the main tunnel and the branch tunnel 21. After the widening is completed, the TBM can continue to tunnel forward. After the first connecting tunnel 41 was completed, the second phase of through-hole prestressed hollow grouting anchor rods and C35 concrete columns 7 were promptly constructed.
[0060] The advantages of a forward-facing auxiliary chamber layout for TBM tunneling adit access to the main tunnel are: This method is applicable to situations where the TBM starts construction from the adit 1 and tunnels into the main tunnel 2 from a small slope (slope less than 5%).
[0061] By adding the fifth branch tunnel, interference between upstream and downstream transportation was avoided, and transportation efficiency was improved.
[0062] The material transfer tunnel 3 is located between the intersection of the main tunnel and the branch tunnel 21 and the branch tunnel 5, which allows TBM tunneling and drilling and blasting excavation of the material transfer tunnel 3 to be carried out simultaneously, thus shortening the construction period.
[0063] Optimizing the shape of the enlarged cross-section at the junction of the main tunnel and the branch tunnel can save investment and reduce safety risks.
[0064] It should be noted that, where there is no conflict, the features in the embodiments of this application can be combined with each other.
[0065] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
Claims
1. A TBM tunneling construction auxiliary chamber forward arrangement structure of a branch tunnel into a main tunnel, characterized in that, include: Branch tunnel (1), main tunnel (2), material transfer tunnel (3), first connecting tunnel (41), second connecting tunnel (42) and branch tunnel (5); The axis of the branch tunnel (1) is set at an angle to the axis of the main tunnel (2), and the end of the branch tunnel (1) is connected to the main tunnel (2) at the junction (21) of the main tunnel and the branch tunnel; One end of the branch tunnel (5) is connected to the branch tunnel (1), and the other end is connected to the main tunnel (2) at the junction of the main and branch tunnels (22). The junction of the main and branch tunnels (22) is located downstream of the junction of the main and branch tunnels (21) along the direction of water flow. The axis of the material conversion tunnel (3) is collinear with the axis of the main tunnel (2), and one end of the material conversion tunnel (3) is connected to the intersection (21) of the main branch tunnel through the first connecting tunnel (41), and the other end is connected to the intersection (22) of the main branch tunnel through the second connecting tunnel (42).
2. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 1, characterized in that, The diameter of the material conversion hole (3) is greater than the diameter of the first connecting hole (41) and the diameter of the second connecting hole (42).
3. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 2, characterized in that, The material conversion tunnel (3) includes a through section (31) and a variable diameter section (32), wherein the through section (31) is connected to the first connecting tunnel (41) and the variable diameter section (32); The diameter of the variable diameter section (32) gradually increases from one end near the second connecting hole (42) to one end near the through section (31).
4. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 1, characterized in that, The intersection of the main tunnel (22) is provided with a reversing tunnel (6). The axis of the reversing tunnel (6) is set at an angle to the axis of the main tunnel (2) and extends away from the tunnel (5).
5. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 1, characterized in that, The cross-sectional dimension of the main tunnel junction (21) is larger than the sum of the cross-sectional dimensions of the main tunnel (2) and the branch tunnel (1).
6. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 5, characterized in that, At the junction of the main tunnel and the branch tunnel (21), a pillar (7) is provided between the branch tunnel (1) and the main tunnel (2).
7. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 6, characterized in that, A through-hole prestressed anchor rod (8) is provided between the branch hole (1) and the first connecting hole (41).
8. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 5, characterized in that, The cross-sectional outline of the junction of the main tunnel and the branch tunnel (21) includes a first outline (211) and a second outline (212). The first outline (211) fits the cross-sectional outline of the main tunnel (2), and the second outline (212) fits the cross-sectional outline of the branch tunnel (1).
9. The auxiliary chamber layout structure for the TBM tunneling adit leading into the main tunnel according to claim 8, characterized in that, The cross-sectional profile of the junction of the main and branch tunnels (21) also includes the top profile (213). The top contour line (213) is located at the top and its two ends are connected to the first contour line (211) and the second contour line (212) respectively, forming an arc shape that is concave towards the center of the intersection of the main branch tunnel (21).
10. The auxiliary chamber layout structure for the TBM tunneling adit leading to the main tunnel according to any one of claims 1-9, characterized in that, The branch tunnel (1) has a starting tunnel (11) at its head end.