A low-power dual-tower intelligent peak-shaving desiccant

By adding a preheating mechanism to the dual-tower desiccant dryer, the high electricity cost problem caused by the peak-valley difference in electricity prices is solved by using hot regenerated gas to preheat the output gas of the variable frequency blower, and electricity cost savings are achieved during off-peak hours.

CN224976116UActive Publication Date: 2026-11-17FUJIAN YIPUSI IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522728325.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-17
Estimated Expiration
2035-12-23

AI Technical Summary

Technical Problem

Existing adsorption dryers have difficulty effectively controlling the regeneration process during off-peak hours when there are large differences in electricity prices, resulting in high electricity costs.

Method used

A preheating mechanism is added to the dual-tower desiccant dryer to preheat the air output from the variable frequency blower by heat exchange with the regenerated gas, thereby reducing the power consumption of the heater. The air preheating effect is optimized by designing the corrugated pipe and filter.

Benefits of technology

This allows for the effective use of waste heat during off-peak hours, reducing the electricity consumption of the desiccant dryer and achieving the effect of saving electricity costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224976116U_ABST
    Figure CN224976116U_ABST
Patent Text Reader

Abstract

This utility model relates to a low-power-consumption dual-tower intelligent peak-shaving desiccant, comprising: an adsorption mechanism including two parallel and identical adsorption towers; a regeneration mechanism including a variable frequency blower, an integrated cooler, and a heater, with regeneration inlet pipes connected to the tops of the adsorption towers respectively, the regeneration inlet pipes being connected in parallel to the heater and the integrated cooler, and the outlet of the variable frequency blower being connected in parallel to the heater and the integrated cooler; and a preheating mechanism including a heat-insulated container connecting the outlet of the variable frequency blower and the inlet of the heater, with a three-way pipe installed at its inlet end inside the heat-insulated container, the inlet end of the three-way pipe being connected in parallel to the outlet ends of the regeneration outlet pipes of the two adsorption towers via a control valve, and a filter element that moves up and down via a corrugated pipe at the middle end of the three-way pipe. This utility model preheats the outlet air of the variable frequency blower by recycling the waste heat from heat regeneration, thereby reducing the power consumption of the heater and ultimately achieving effective savings in electricity costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of adsorption dryer technology, specifically to a low-power-consumption dual-tower intelligent peak-shaving adsorption dryer. Background Technology

[0002] Adsorption-regenerative adsorption dryers achieve drying effects through the principle of pressure swing adsorption. Since the capacity of air to hold moisture is inversely proportional to pressure, a portion of the dried air, i.e., the regenerated air, expands under reduced pressure to atmospheric pressure. This pressure change makes the expanded air even drier. It then flows through the desiccant layer that needs regeneration, which is not connected to the airflow. The dried regenerated air draws moisture from the desiccant and carries it out of the dryer, achieving dehumidification. The two towers operate in a cycle, requiring no heat source, and continuously supply dry compressed air to the user's air supply system.

[0003] Zero-air-consumption desiccant dryers require electricity to operate, and the regeneration process is the power-consuming part of the dryer. The operation of the variable frequency blower and heater is the main source of power consumption in the regeneration process, replacing the consumption of finished products by consuming electrical energy. Local electricity prices typically fluctuate between peak and off-peak hours, with off-peak electricity prices dropping by over 60%, while peak-peak prices rise by nearly 60%, and even up to 80%, resulting in significant price differences. Therefore, the main solution is to adjust and control the regeneration process to complete during off-peak hours, achieving electricity cost savings compared to other times. While controlling the usage time during power-consuming periods can save on electricity costs, electricity prices vary significantly across different regions and time periods, requiring precise control of the dual-tower regeneration process to complete entirely during off-peak hours.

[0004] Therefore, the research objective of this utility model is to design a low-power dual-tower intelligent peak-shaving desiccant that completes the regeneration process during off-peak hours, utilizes the waste heat from thermal regeneration to preheat the output air of the variable frequency blower, thereby reducing the power consumption of the heater and ultimately achieving effective savings in electricity costs. Utility Model Content

[0005] In view of the technical problems existing in the prior art, the present invention provides a low-power-consumption dual-tower intelligent peak-shaving desiccant, which can effectively solve the technical problems existing in the prior art.

[0006] The technical solution of this utility model is: A low-power-consumption dual-tower intelligent peak-shaving desiccant includes: The adsorption mechanism includes two adsorption towers arranged side by side with identical structures. The bottom sides of the two adsorption towers are connected in parallel to the inlet pipe through corresponding inlet valves, and the tops of the adsorption towers are connected in parallel to the outlet pipe through one-way outlet valves. The regeneration mechanism includes a variable frequency blower, an integrated cooler, and a heater. The top of the adsorption tower is connected to a regeneration inlet pipe via a regeneration inlet valve, and the bottom of the adsorption tower is connected to a regeneration outlet pipe via a regeneration outlet valve. The other side of the regeneration inlet pipe is connected in parallel to the outlet of the heater and the first inlet of the integrated cooler. The outlet of the variable frequency blower is connected in parallel to the inlet of the heater and the second inlet of the integrated cooler. The inlet of the variable frequency blower and the first outlet of the integrated cooler are connected in parallel to a conventional inlet pipe. The preheating mechanism includes a heat-insulated container connecting the outlet of the variable frequency blower and the inlet of the heater. A three-way pipe is installed at the inlet of the heat-insulated container. The inlet of the three-way pipe is connected in parallel to the outlet of the regeneration outlet pipes of the two adsorption towers via corresponding control valves. A solenoid valve is installed at the outlet of the three-way pipe. A corrugated pipe is connected to the middle end of the three-way pipe in the direction of airflow within the heat-insulated container. The end of the corrugated pipe is closed and a vertically movable filter element is fixedly installed thereon. The filter element is sealed to the inner wall of the heat-insulated container. When the solenoid valve is closed and hot regeneration exhaust gas is continuously flowing into the three-way pipe, the corrugated pipe inflates and stretches, causing the filter element to move along the airflow direction. When the solenoid valve is open and hot regeneration exhaust gas is continuously discharged, the corrugated pipe deflates and contracts, causing the filter element to move downwards and reset.

[0007] A corresponding spring is sleeved on the outside of the bellows, and the two ends of the spring are respectively fixed to the filter element and the three-way pipe; when the solenoid valve is closed, the spring is stretched, and when the solenoid valve is opened, the spring drives the filter element to reset and move downward.

[0008] The corrugated pipe is composed of a first corrugated section, a straight pipe section, and a second corrugated section connected in sequence. The length of the first corrugated section connected to the middle of the tee pipe is greater than the length of the second corrugated section. The preheating mechanism includes two filter elements, one above the other, which are respectively installed at the two ends of the second corrugated section. The filter holes distributed on the two filter elements are staggered. When the solenoid valve is closed and the corrugated pipe is inflated and stretched, the two filter elements are spaced apart. When the solenoid valve is open and the heat regeneration exhaust is continuously discharged, the two filter elements are fitted together.

[0009] The first air inlet of the integrated cooler is connected in parallel to the top of the two adsorption towers through a corresponding upper regeneration cooling valve; the second air outlet of the integrated cooler is connected in parallel to the regeneration air outlet valve and regeneration vent valve at the bottom of the two adsorption towers through a corresponding lower regeneration cooling valve; and the air inlet of the heater is connected to the air outlet of the variable frequency blower through a corresponding thermal regeneration valve.

[0010] A pressurization pipe equipped with a pressurization valve is connected between the tops of the two adsorption towers.

[0011] The bottom side of the adsorption tower is connected to a corresponding pressure relief valve, and the outlet end of the pressure relief valve is equipped with a corresponding first silencer. The inlet end of the conventional air inlet pipe is equipped with a corresponding second silencer.

[0012] The two adsorption towers cycle through the adsorption process during non-valley periods and complete the regeneration process during valley periods.

[0013] Advantages of this utility model: 1) This utility model adds a preheating mechanism to the double-tower adsorption dryer. By recycling the regeneration gas discharged from the adsorption tower in the thermal regeneration stage, the gas from the variable frequency blower is indirectly contacted for heat exchange and preheating, thereby saving the power consumption of the subsequent heater and effectively saving electricity costs.

[0014] The preheating mechanism includes an insulated container connecting the outlet of a variable frequency blower and the inlet of a heater. The container has an outlet and an inlet at the top and bottom, respectively, for guiding the air generated by the blower. A tee pipe is horizontally installed at the inlet of the container to guide the exhaust gas from the heat regeneration process. The inlet of the tee pipe is connected in parallel to the outlets of the regeneration exhaust pipes of the two adsorption towers via a control valve. A corresponding solenoid valve is installed at the outlet of the tee pipe. During the heat regeneration stage in the absorption tower, the control valve guides the hot exhaust gas into the tee pipe, and the solenoid valve is closed, directing the exhaust gas to the vertical section in the middle of the tee pipe. This prolongs the residence time of the hot exhaust gas within the insulated container, allowing for indirect heat transfer through contact with the air and achieving a better preheating effect.

[0015] 2) Based on preheating, this utility model sets the vertical section in the middle of the tee as a retractable bellows, and a filter element that can move up and down is fixedly installed at the closed end of the bellows. Appropriate rubber rings can be set around the filter element to ensure a sealed connection with the insulation container. Air must pass through the filter element to exit the insulation container. Besides performing preliminary particle filtration, the filter element slows down airflow to a certain extent, prolonging the heat transfer time between the air and the exhaust gas from heat regeneration, further improving waste heat utilization and preheating effects. Furthermore, after the solenoid valve is opened, the filter element will contract and move downwards like a bellows, compressing the air and promoting the filtration and discharge of preheated air, achieving a dual effect of preheating and filtration, thus improving the practical effect of this utility model.

[0016] 3) This utility model adds a corresponding spring to the outside of the corrugated pipe. The elastic force of the spring helps to drive the filter element to move down and reset, which promotes the filtration effect and further ensures the practical effect of this utility model.

[0017] 4) This utility model further configures the corrugated pipe as being composed of a first corrugated section, a straight pipe section, and a second corrugated section connected in sequence, and provides two filter elements. The length of the first corrugated section must be greater than the length of the second corrugated section. When the solenoid valve is opened for conduction, the second corrugated section contracts first, causing the two filter elements to adhere together to form a thicker filter layer, thereby improving the filtration effect. Meanwhile, the longer first corrugated section retains the effect of the corrugated pipe, causing the two filter elements to move down and reset. Moreover, the filter holes distributed on the upper and lower filter elements are staggered. When the corrugated pipe is stretched and the filter elements are spaced apart, the staggered filter holes ensure the filtration effect after the filter elements are separated. Attached Figure Description

[0018] Figure 1 This is one of the structural schematic diagrams of this utility model.

[0019] Figure 2 This is the second structural schematic diagram of the present invention.

[0020] Figure 3 This is a schematic diagram showing the connection between the two absorption towers and the preheating mechanism.

[0021] Figure 4 for Figure 2 A cross-sectional diagram.

[0022] Figure 5 for Figure 4 A schematic diagram of the expanded preheating mechanism.

[0023] Figure 6 This is a schematic diagram of the preheating mechanism in Example 2 (a schematic diagram of the state when the solenoid valve is open).

[0024] Figure 7 for Figure 6 A schematic diagram showing the state of the solenoid valve after it is opened.

[0025] In the attached diagram: 1. Adsorption tower; 2. Inlet valve; 3. Inlet pipe; 4. Outlet check valve; 5. Outlet pipe; 6. Variable frequency blower; 7. Integrated cooler; 8. Heater; 9. Preheating mechanism; 901. Insulated container; 902. T-pipe; 903. Control valve; 904. Solenoid valve; 905. Corrugated pipe; 906. Filter element; 907. Spring; 9051. First corrugated section; 9052. Straight pipe section; 9053. Second corrugated section; 10. Regeneration inlet valve; 11. Regeneration inlet pipe; 12. Regeneration outlet pipe; 13. Regeneration outlet valve; 14. Upper regeneration cooling valve; 15. Lower regeneration cooling valve; 16. Regeneration vent valve; 17. Pressurization valve; 18. Pressurization pipe; 19. Pressure relief valve; 20. First silencer; 21. Second silencer; 22. Thermal regeneration valve; 23. Conventional inlet pipe. Detailed Implementation

[0026] To facilitate understanding by those skilled in the art, the structure of this utility model will now be described in further detail with reference to the accompanying drawings: Example 1 refer to Figure 1-5 A low-power-consumption dual-tower intelligent peak-shaving desiccant dryer, comprising: The adsorption mechanism includes two adsorption towers 1 arranged side by side with identical structures. The bottom sides of the two adsorption towers 1 are respectively connected in parallel to the inlet pipe 3 through corresponding inlet valves 2. The tops of the adsorption towers 1 are respectively connected in parallel to the outlet pipe 5 through outlet one-way valves 4. The regeneration mechanism includes a variable frequency blower 6, an integrated cooler 7, and a heater 8. The top of the adsorption tower 1 is connected to a regeneration inlet pipe 11 via a regeneration inlet valve 10, and the bottom of the adsorption tower 1 is connected to a regeneration outlet pipe 12 via a regeneration outlet valve 13. The other side of the regeneration inlet pipe 11 is connected in parallel to the outlet end of the heater 8 and the first inlet end of the integrated cooler 7. The outlet end of the variable frequency blower 6 is connected in parallel to the inlet end of the heater 6 and the second inlet end of the integrated cooler 7. The inlet end of the variable frequency blower 6 and the first outlet end of the integrated cooler 7 are connected in parallel to a conventional inlet pipe 23. The preheating mechanism 9 includes a heat-insulating container 901 connecting the outlet of the variable frequency blower 6 and the inlet of the heater 8. A corresponding three-way pipe 902 is installed inside the heat-insulating container 901 at its inlet end. The inlet end of the three-way pipe 902 is connected in parallel to the outlet ends of the regeneration outlet pipes of the two adsorption towers 1 via corresponding control valves 903. A corresponding solenoid valve 904 is installed at the outlet end of the three-way pipe 902. A corresponding wave valve is connected to the middle end of the three-way pipe 902 in the airflow direction within the heat-insulating container 901. The corrugated pipe 905 has a closed end and a filter element 906 that can move up and down is fixedly installed thereon. The filter element 906 is sealed to the inner wall of the heat insulation container 901. When the solenoid valve 904 is closed and heat regeneration exhaust gas is continuously introduced into the three-way pipe 902, the corrugated pipe 905 is inflated and stretched, causing the filter element 906 to move along the airflow direction. After the solenoid valve 904 is opened and heat regeneration exhaust gas is continuously discharged, the corrugated pipe 905 is deflated and contracted, causing the filter element 906 to move down and reset.

[0027] This invention adds a preheating mechanism 9 to the dual-tower desiccant dryer. By recycling the regeneration gas discharged from the adsorption tower 1 during the thermal regeneration stage, it indirectly contacts the outlet gas of the variable frequency blower 6 for heat exchange preheating, thereby saving the power consumption of the subsequent heater 8 and effectively achieving the effect of saving electricity costs.

[0028] The preheating mechanism 9 is equipped with a heat-insulated container 901 connecting the outlet of the variable frequency blower 6 and the inlet of the heater 8. The heat-insulated container 901 has an air outlet and an inlet at its top and bottom, respectively, for guiding the air generated by the variable frequency blower 6. A three-way pipe 902 is horizontally arranged at the inlet end of the heat-insulated container 901 to guide the exhaust gas from the heat regeneration process. The inlet end of the three-way pipe 902 is connected in parallel to the outlet ends of the regeneration exhaust pipes of the two adsorption towers 1 via a control valve 903. A corresponding solenoid valve 904 is installed at the outlet end of the three-way pipe 902. During the heat regeneration stage of the absorption tower, the hot exhaust gas is guided into the three-way pipe 902 via the control valve 903, and the solenoid valve 904 is intermittently opened and closed. Closing the solenoid valve 904 allows the hot regeneration exhaust gas to flow into the vertical section in the middle of the three-way pipe 902, thereby prolonging the residence time of the hot exhaust gas in the heat-insulated container 901 and indirectly contacting the air for heat transfer, thus achieving a better preheating effect.

[0029] This invention, based on preheating, sets the vertical section in the middle of the tee as a retractable bellows 905, and fixes a vertically movable filter element 906 at the closed end of the bellows 905. Appropriate rubber rings can be set around the filter element 906 to ensure a sealed connection with the heat-insulating container 901. Air must pass through the filter element 906 to exit the heat-insulating container 901. The filter element 906 not only performs preliminary particle filtration of the air but also slows down air conduction to a certain extent, prolonging the heat transfer time between the air and the exhaust gas from heat regeneration, further improving waste heat utilization and preheating effects. Furthermore, after the solenoid valve 904 is opened, the filter element 906 contracts and moves downwards along the bellows 905, compressing the air and promoting the filtration and discharge of preheated air, achieving a dual effect of preheating and filtration, thus improving the practical effect of this invention.

[0030] A corresponding spring 907 is sleeved on the outside of the bellows 905. The two ends of the spring 907 are respectively fixed to the filter element 906 and the three-way pipe 902. When the solenoid valve 904 is closed, the spring 907 is stretched. When the solenoid valve 904 is opened, the spring 907 drives the filter element 906 to reset and move downward.

[0031] This invention adds a corresponding spring 907 to the outside of the corrugated pipe 905. The elastic force of the spring 907 is used to assist in moving the filter element 906 down to reset, thereby promoting the filtration effect and further ensuring the practical effect of this invention.

[0032] The first air inlet of the integrated cooler 7 is connected in parallel to the top of the two adsorption towers 1 through the corresponding upper regeneration cooling valve 14; the second air outlet of the integrated cooler 7 is connected in parallel to the regeneration air outlet valve 13 and the regeneration vent valve 16 on the bottom side of the two adsorption towers 1 through the corresponding lower regeneration cooling valve 15; and the air inlet of the heater 8 is connected to the air outlet of the variable frequency blower 6 through the corresponding thermal regeneration valve 22.

[0033] A pressurization pipe 18 equipped with a pressurization valve 17 is connected between the tops of the two adsorption towers 1.

[0034] The bottom side of the adsorption tower 1 is connected to a corresponding pressure relief valve 19. The outlet end of the pressure relief valve 19 is provided with a corresponding first silencer 20. The inlet end of the conventional air inlet pipe 23 is provided with a corresponding second silencer 21.

[0035] The two adsorption towers 1 perform the adsorption process in a cycle during non-valley periods and complete the regeneration process during valley periods.

[0036] Example 2 refer to Figure 6-7 The difference between this embodiment and Embodiment 1 is that: the corrugated pipe 905 is composed of a first corrugated section 9051, a straight pipe section 9052, and a second corrugated section 9053 connected in sequence, and the length of the first corrugated section 9051 connected to the middle of the tee pipe 902 is greater than the length of the second corrugated section 9053; the preheating mechanism 9 includes two filter elements 906, and the two filter elements 906 are respectively installed at the two ends of the second corrugated section 9053, and the filter holes distributed on the two filter elements 906 are staggered; when the solenoid valve 904 is closed and the corrugated pipe 905 is inflated and stretched, the two filter elements 906 are spaced apart; when the solenoid valve 904 is open and the heat regeneration exhaust is continuously discharged, the two filter elements 906 are fitted together.

[0037] This invention further specifies that the bellows 905 is composed of a first corrugated section 9051, a straight section 9052, and a second corrugated section 9053 connected sequentially, and includes two filter elements 906. The length of the first corrugated section 9051 must be greater than the length of the second corrugated section 9053. When the solenoid valve 904 is opened for conduction, the second corrugated section 9053 contracts first, causing the two filter elements 906 to adhere and form a thicker filter layer to improve the filtration effect. Meanwhile, the longer first corrugated section 9051 retains the effect of the bellows 905, causing the two filter elements 906 to move downward and reset. Moreover, the filter holes distributed on the upper and lower filter elements 906 are staggered. When the bellows 905 is stretched and causes the filter elements 906 to be spaced apart, the staggered filter holes ensure the filtration effect after the filter elements 906 are separated.

[0038] It should be noted that this embodiment is implemented in the same way as embodiment one in terms of principle and technical effect. For the sake of brevity, any parts not mentioned in this embodiment can be referred to the corresponding content in embodiment one.

[0039] The above description is only a preferred embodiment of the present utility model. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present utility model, and these improvements and modifications should also be considered within the protection scope of the present utility model.

Claims

1. A low power consumption fee double-tower intelligent peak shaving suction dryer, characterized in that, include: The adsorption mechanism includes two adsorption towers (1) arranged side by side and with the same structure. The bottom sides of the two adsorption towers (1) are connected in parallel to the inlet pipe (3) through corresponding inlet valves (2). The tops of the adsorption towers (1) are connected in parallel to the outlet pipe (5) through outlet one-way valves (4). The regeneration mechanism includes a variable frequency blower (6), an integrated cooler (7), and a heater (8). The top of the adsorption tower (1) is connected to the regeneration inlet pipe (11) through the regeneration inlet valve (10), and the bottom of the adsorption tower (1) is connected to the regeneration outlet pipe (12) through the regeneration outlet valve (13). The other side of the regeneration inlet pipe (11) is connected in parallel to the outlet end of the heater (8) and the first inlet end of the integrated cooler (7). The outlet end of the variable frequency blower (6) is connected in parallel to the inlet end of the heater (8) and the second inlet end of the integrated cooler (7). The inlet end of the variable frequency blower (6) and the first outlet end of the integrated cooler (7) are connected in parallel to the conventional inlet pipe (23). The preheating mechanism (9) includes a heat-insulating container (901) connecting the outlet end of the variable frequency blower (6) and the inlet end of the heater (8). A corresponding three-way pipe (902) is provided at the inlet end of the heat-insulating container (901). The inlet end of the three-way pipe (902) is connected in parallel to the outlet end of the regeneration outlet pipe of the two adsorption towers (1) through a corresponding control valve (903). A corresponding solenoid valve (904) is installed at the outlet end of the three-way pipe (902). The middle end of the three-way pipe (902) is connected to a corresponding control valve in the airflow direction within the heat-insulating container (901). A bellows (905) has a closed end and a filter element (906) that can move up and down is fixedly installed thereon. The filter element (906) is sealed to the inner wall of the heat insulation container (901). When the solenoid valve (904) is closed and heat regeneration exhaust gas is continuously introduced into the three-way pipe (902), the bellows (905) is inflated and stretched, causing the filter element (906) to move along the airflow direction. After the solenoid valve (904) is opened and heat regeneration exhaust gas is continuously discharged, the bellows (905) is deflated and contracted, causing the filter element (906) to move down and reset.

2. A low power consumption dual-tower intelligent peak shaving and drying machine according to claim 1, characterized in that, A corresponding spring (907) is sleeved on the outside of the bellows (905). The two ends of the spring (907) are fixed to the filter element (906) and the three-way pipe (902) respectively. When the solenoid valve (904) is closed, the spring (907) is stretched. When the solenoid valve (904) is opened, the spring (907) drives the filter element (906) to reset and move downward.

3. The low-power-consumption dual-tower intelligent peak-shaving and dry-pumping machine according to claim 1 or 2, characterized in that, The corrugated pipe (905) is composed of a first corrugated section (9051), a straight pipe section (9052), and a second corrugated section (9053) connected in sequence. The length of the first corrugated section (9051) connected to the middle of the tee pipe (902) is greater than the length of the second corrugated section (9053). The preheating mechanism (9) includes two filter elements (906), and the two filter elements (906) are respectively installed at the two ends of the second corrugated section (9053). The filter holes distributed on the two filter elements (906) are staggered. When the solenoid valve (904) is closed and the corrugated pipe (905) is inflated and stretched, the two filter elements (906) are spaced apart. When the solenoid valve (904) is open and the heat regeneration exhaust is continuously discharged, the two filter elements (906) are fitted together.

4. The low power consumption dual-tower intelligent peak shaving and drying machine of claim 1, wherein, The first air inlet of the integrated cooler (7) is connected in parallel to the top of the two adsorption towers (1) through the corresponding upper regeneration cooling valve (14); the second air outlet of the integrated cooler (7) is connected in parallel to the regeneration air outlet valve (13) and regeneration vent valve (16) on the bottom side of the two adsorption towers (1) through the corresponding lower regeneration cooling valve (15); and the air inlet of the heater (8) is connected to the air outlet of the variable frequency blower (6) through the corresponding thermal regeneration valve (22).

5. The low power consumption dual-tower intelligent peak shaving and drying machine according to claim 1, characterized in that, A pressurization pipe (18) with a pressurization valve (17) is connected between the tops of the two adsorption towers (1).

6. The low power consumption dual-tower intelligent peak shaving and drying machine of claim 1, wherein, The bottom side of the adsorption tower (1) is connected to a corresponding pressure relief valve (19), and the outlet end of the pressure relief valve (19) is provided with a corresponding first silencer (20). The inlet end of the conventional air inlet pipe (23) is provided with a corresponding second silencer (21).

7. The low power consumption dual-tower intelligent peak shaving and drying machine according to claim 1, characterized in that, The two adsorption towers (1) cycle the adsorption process during non-valley periods and complete the regeneration process during valley periods.