Power distribution method for power generator sets in DC grid
Patent Information
- Application Number
- GB2022014622
- Authority / Receiving Office
- GB · GB
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2020-03-18
- Filing Date
- 2021-02-27
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2041-02-27
AI Technical Summary
In a waterborne vessel's DC grid, the small number of generator sets leads to frequent load changes, causing frequency fluctuations and uneven power distribution, resulting in some sets being overloaded while others operate inefficiently, and existing methods fail to accurately account for environmental changes and optimal energy usage.
A power distribution method for generator sets in a DC grid that includes multiple diesel generators connected to a DC bus through a rectifier power module, with current and voltage sensors, and a main controller that sets optimal operating load ranges and adjusts generator states using a cross-coupling control strategy to optimize power allocation and reduce energy waste.
This method accurately determines the total load power and fuel consumption, ensuring generators operate at optimal levels, improving energy efficiency and reducing waste by dynamically adjusting voltage and power distribution among multiple diesel generators.
Abstract
Description
POWER DISTRIBUTION METHOD FOR GENERATORSETSIN DC GRID TECHNICAL FIELD The present invention relates to a power distribution method for generator sets in a direct current (DC) grid. BACKGROUND For a waterborne vessel power station, in the case of not connecting to the large power grid, due to the small number of generator sets, the change of the load can easily change the power grid, and cause frequency fluctuation of the power grid, resulting in the uneven distribution of active loads of the generator sets. Even some generator sets are overloaded, and some generator sets operate as motors (operate at reverse power). The advantages and disadvantages of power distribution among generator sets of the waterborne vessel may have a direct impact on the stability and safety of power grid operation of the waterborne vessel. The relative capacity of a synchronous generator and the grid parallel with the synchronous generator has a great impact on the motor. Therefore, it is particularly important to discuss the power distribution and automatic adjustment of parallel synchronous generators in different scales of power grids. It is found through retrieval of the existing literature that the Chinese Patent Application No. CN201710859634.6 discloses "a power distribution method for parallel operation of AC generator sets with an asymmetric structure". In the method, the power distribution controller identifies all AC generator sets as a host and a slave. A power distribution controller of the host controls the host to operate at a rated frequency and a rated voltage, and a power distribution controller of the slave controls the slave to operate with an active power distribution adjustment target value and a reactive power distribution adjustment target value. However, the method is power distribution when the voltage difference of the generator set exceeds the set value, so that the output power of the generator set is balanced. In the method, the impact of the change of the driving environment of the waterborne vessel on the load power of the waterborne vessel and the power consumed by the entire power system are not considered. As a result, the PMS cannot accurately obtain the current total load power of the system, and thus cannot accurately distribute the power of the generator set. The journal "Application of Improved Droop Control in Parallel Operation of Waterborne Vessel Power Stations" in "Ship Engineering" (Issue 3, 2018) published by Wang Feihu and Gao Jian also provides a power distribution method. However, the power management system mentioned in the method cannot accurately determine the relationship between the proportion of the output power of diesel generators and fuel consumption, and cannot ensure that the generator set operates at the optimal economic time, resulting in energy waste. SUMMARY A solution to the technical problem in the present invention is to provide a power distribution method for generator sets in direct current (DC) grid, so as to reduce energy consumption. In order to solve the above technical problem, the technical scheme adopted in the present invention is as follows. A generator set in a DC grid power system includes at least two generator-based power supply mechanisms connected to a DC bus and a main controller. Each of the generator-based power supply mechanisms includes a diesel generator, the diesel generator is sequentially connected to a circuit breaker, a rectifier power module, and a fuse through a power supply line, and the power supply line is finally connected to the DC bus. A current sensor is arranged on a wire between the circuit breaker and the rectifier power module, and a DC voltage sensor is arranged on a wire between the rectifier power module and the fuse. The current sensor, the rectifier power module, and the DC voltage sensor are all electrically connected to an A / D sampling module, and the A / D sampling module is electrically connected to a sub-controller. All sub-controllers are electrically connected to the main controller, and a power distribution method for generator sets in a DC grid includes the following steps: step a: setting parameters for each diesel generator and setting power parameters for each diesel generator set through the main controller, that is, respectively setting a lower limit A and an upper limit A of an optimal operating load power of an i® (i = 1, 2, ..., N) diesel generator, and selecting a first diesel generator set as a default start item; step b: continuously detecting, by the main controller, a total power k of the DC grid power system, where when a load operates in the DC bus, the power generation system starts operating, and the first diesel generator set starts operating; calculating, by the sub-controller, a service power A of the first diesel generator set; and causing an alternating current (AC) generated by the first diesel generator set to pass through the rectifier power module, and setting rectifier parameters of the rectifier power module to keep a rectified voltage value within Vimin Vines to ensure Br <B <u. step c: calculating, by the main controller, a range of a total optimal operating load power of the diesel generator sets, where since only the first diesel generator set is in the operating state, a lower limit of the total optimal operating load power of the diesel generator sets is h=h , and an upper limit of the total optimal operating load power of the diesel generator sets is k= Bu, step d: successively determining, by the main controller, operating states of all of the diesel generator sets, where the sub-controller calculates a service power B ofan i® diesel generator set if the i® diesel generator set is in an operating state; and causing the AC generated by the i diesel generator set to pass through the rectifier power module, and setting rectification parameters of the rectifier power module are set to keep the rectified voltage value within Vin Vmax to ensure Ri<h< Ba, step e: calculating, by the main controller, the range of the total optimal operating load power of the diesel generator sets by using the following formula: the lower limit of the total optimal operating load power of the diesel generator sets N 2 =S 7, being calculated by: i=l and the upper limit of the total optimal operating load power of the diesel generator set being N B=%P calculated by: dsl step f: comparing, by the main controller, a total power R of the DC bus with the lower limit © and the upper limit A of the total optimal operating load power of the diesel generator sets, where if 5 <F<5 , it indicates that a generating power of the each diesel generator is within the optimal operating load power range when a total generating power of the diesel generator sets reaches A, and step (g) is performed, and if R does not satisfy Bi <E<E , that is, when E> or R<h , step (h) is performed; step g: synchronously controlling, by the main controller, voltages of the diesel generators through the sub-controller according to a cross-coupling control strategy; step h: establishing an optimization model and solving an optimal operating sequence of the diesel generator sets, including: h-1: setting an existing operating generator sequence to “= Ey We MD and a non-operating generator sequence to Bm {83820 Band, where Wiag= HR, ne, 1, - L(p6), pls) J =ary =p 4p remax (28) 2) ven make TTL h-2: calculating 68-1 2 if k >, that is, finding a diesel generator from the non-operating diesel generators with a largest average optimal operating load power, then performing step h-3, and performing step h-4 if <4 3 p= > pv w; S. 5 )) 1 (pt 2) 4 pt ) Lipw) pe Nez ' > +4 2 rm lay my Wg J a ng SR ; h-3: calculating a2 2 where if P' <b w= wus] = Sh 483 and &=L +1 tyming on the diesel generator with the largest average optimal operating load power found in step h-2, then performing step h-2, and performing step h-6 until P'> £ 3 =argmax (A) + A) ocict 2 h-4: calculating sist & , that is, finding a diesel generator with a largest average optimal operating load power from the operating diesel generators; L(pt) + pi) 0)-=(p 3 Pr= 3 {p+ A)! A Sod Fr vu hl i h-5: calculating w2 2 where if P" > hi WERE =F} ang L=E-1 turning on the diesel generator with the largest average optimal operating load power found in step h-4, then performing step h-4, and performing step h-6 until P" <k, 0, =P + RB). (p+) + 0) h-6: calculating ~~ <4 he ~~, wherei=1,2,.., N-L, that is, respectively calculating a difference between the average optimal operating load power of any diesel generator in the operating sequence and the average optimal operating load power 1 . . . Oy; =1(p8) p8) of any diesel generator in the non-operating sequence, where 2 and 1 Oo = -—p +B™) then calculating d. d= Lo1 / rw . argmin E2640), -2f osisLosjN-L| $2 where if [= 0, W=WU{S,}, S=85\{8,} L=L+1 ifJ=0, W=W\{w}, S=SUW,}, L=L-1 ifLJ#0, w=wUS\{W,}, S=sUWN{S,} L=L the above process is the process of solving the optimal operating sequence of the diesel generators, that is, a maximum value Pian of h and a minimum value Pinas of k that satisfy F<R<K are found, so that the lower limit Band the upper limit R of the total optimal operating load power of the diesel generator sets are closest to the total power R of the DC bus; W=wWUfs,} S=S\{5,} L=L+l 1:4 indicates that Fie Dmx and if1 =0, Bim Fin are satisfied after a diesel generator in a non-operating sequence is turned on without turning off the diesel generator in the operating sequence; if] =0, B Bi W=wW\{W} S=SU{w} L=L-1 which indicates that f1="Im= and Bim Fin are satisfied after a diesel generator in an operating sequence is turned off without turning on the diesel generator in the non-operating sequence; and w=wWU{S hw}, s=SU{WNS,} L=L if J#0, 2 which indicates that B= Fina and Bi Pine are satisfied after a diesel generator in the non-operating sequence is turned on and a diesel generator in the operating sequence is turned off; and h-7: upon completion of the above steps, that is, the process of optimizing and solving the optimal operating sequence of the diesel generator set is completed, periodically detecting, by the main controller, the total power A of the DC bus, if £ changes, performing step 4, and if k does not change, ending the optimization, and maintaining the existing sequence of the diesel generator sets for operation. As a preferred solution, step g includes the following: g-1: calculating, by the main controller, an average voltage according to the current total power Pt of the DC grid system when £<F <k, where B<E<F, is satisfied when output voltages of all of the operating diesel generators are 7": g-2: sending, by the main controller, a voltage regulation command to each sub-controller after 7" is calculated; g-3: controlling, by the sub-controller, the rectifier power module to adjust a rectified DC voltage value after receiving the voltage regulation command from the main controller; g-4: continuously feeding back, by an A / D conversion module on each power generation circuit, the output voltage of the diesel generator to each sub-controller, and sending, by the sub-controller, the voltage data to the main controller through the bus; g-5: calculating, by the main controller, a difference between V' and each output voltage after obtaining the voltage data sent by the sub-controller on the power generation circuit, and sending a voltage compensation signal to the each sub-controller according to a voltage difference; g-6: controlling, by the sub-controller, the rectifier power module to adjust a rectified DC voltage value again after receiving the voltage compensation signal from the main controller; and g-7: cyclically performing the operations from step g-4. As a preferred solution, in step b, the calculation method for calculating the service power B of the first diesel generator set by the sub-controller specifically includes: reading, by an AC current sensor, an AC 4 generated by the first diesel generator set, detecting, by the voltage sensor, a rectified DC voltage value hn, reading, by an A / D sampling module, data about 4 and i , sending the data to the sub-controller, calculating, by the sub-controller, an AC voltage Vac according to Ii and n, and then calculating, by the sub-controller, a service power R of the first diesel generator set by using the following formula B= V3 x1 xg , where ¢ is a power factor. As a preferred solution, in step c, the calculation method for calculating the service power B of the i diesel generator set by the sub-controller specifically includes: reading, by an AC current sensor of a power generation circuit of the i diesel generator set, an AC 5 generated by the diesel generator set, detecting, by the voltage sensor, a rectified DC voltage value Ki, reading, by an A / D sampling module, data about 4 and Vi sending the data to the sub-controller, calculating, by the sub-controller, the AC voltage Vici according to 4 and Vi and then calculating, by the sub-controller, a service power FR of the i® diesel generator set by using the following formula B= Va 2 , where ¢ is a power factor. As a preferred solution, step g-3 of controlling, by the sub-controller, the rectifier power module to adjust the rectified DC voltage value after receiving the voltage regulation command from the main controller specifically includes: sending, by the sub-controller, a control signal to the A / D sampling module after receiving the voltage regulation command from the main controller, and sending, by the A / D sampling module, a PWM wave to the rectifier power module after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value. As a preferred solution, step g-6 of controlling, by the sub-controller, the rectifier power module to adjust the rectified DC voltage value again after receiving the voltage compensation signal from the main controller specifically includes: sending, by the sub-controller, a control signal to the A / D sampling module after receiving the voltage compensation signal from the main controller, and sending, by the A / D sampling module, a PWM wave to the rectifier power module after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value. The beneficial effects of the present invention are as follows. According to the power distribution method for diesel generator sets, the impact of changes in the marine environment on the load power of the waterborne vessel and the power consumed by the entire power system are considered, the total load power under the operating state of the system can be accurately obtained in real time, and the relationship between the output power ratio of diesel generators and fuel consumption can be accurately determined by establishing a power distribution optimization model. In this way, the power allocation accuracy of a generator set is improved, and it is ensured that the generator set is running in a most fuel-efficient state, thereby improving the energy efficiency and reducing energy waste and pollution. Different from the disadvantage that only two diesel generators can be controlled through traditional cross-coupling control, according to the control method adopted in the method, a plurality of diesel generators can be controlled simultaneously. The sub-controller of each diesel generator set continuously interacts with the main controller, and the status of each diesel generator is compared with the target value to implement separate compensation for each diesel generator. In this way, the voltage value of each diesel generator set can be effectively and quickly adjusted to the target state when the total system power changes. BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic diagram of a circuit structure of a power generation system. FIG. 2 is a schematic diagram of a power distribution process for a waterborne vessel. In the figures: 1-Sub-controller, 2-Diesel generator, 3-Circuit breaker, 4-Current sensor, 5-Rectifier power module, 6-Fuse, 7-DC voltage sensor, 8-A / D sampling module, 9-DC bus, 10-Main controller, DETAILED DESCRIPTION Specific implementations of the present invention are described in detail below with reference to the accompanying drawings. As shown in FIG. 1 and FIG. 2, a generator set in a direct current (DC) grid power system includes N generator-based power supply mechanisms connected to a DC bus 9 and a main controller 10. Each of the generator-based power supply mechanisms includes a diesel generator 2, the diesel generator 2 is sequentially connected to a circuit breaker 3, a rectifier power module 5, and a fuse 6 through a power supply line, and the power supply line is finally connected to the DC bus 9. A current sensor 4 is arranged on a wire between the circuit breaker 3 and the rectifier power module 5, and a DC voltage sensor 7 is arranged on a wire between the rectifier power module 5 and the fuse 6. The current sensor 4, the rectifier power module 5, and the DC voltage sensor 7 are all electrically connected to an A / D sampling module 8, and the A / D sampling module 8 is electrically connected to a sub-controller 1. All sub-controllers 1 are electrically connected to the main controller 10, and a power distribution method for generator sets in a DC grid includes the following steps: (a): setting parameters for each diesel generator and setting power parameters for each diesel generator set through the main controller 10, that is, respectively setting a lower limit Br and an upper limit Bs of an optimal operating load power of an it (i=1,2,..,N) diesel generator, and selecting a first diesel generator set as a default start item; (b) continuously detecting, by the main controller 10, a total power & of the power system in the DC grid 9, where when the load operates in the DC bus 9, the power generation system starts operating, and the first diesel generator set starts operating; reading, by the current sensor 4, an AC 4 generated by the first diesel generator set, detecting, by the voltage sensor 7, a rectified DC voltage value ", reading, by an A / D sampling module 8, data about / 1 and ", sending the data to a sub-controller 1 through a bus, calculating, by the sub-controller 1, an AC voltage Vict according to 41 and ", and then calculating, by the sub-controller 1, a service power BR of the first diesel generator set by using the following formula: P, =, xI,x¢ causing the generated AC to pass through the rectifier power module 5, and setting rectification parameters of the rectifier power module 5 to keep the rectified voltage value within Yimin Vian to ensure A <B<Ah, where in this embodiment, Via =1050V and Vv. =1100V (c) calculating, by the main controller 10, a range of a total optimal operating load power of the diesel generator sets, where since only the first diesel generator set is in the operating state, a lower limit of the total optimal operating load power of the diesel generator sets is h=h , and an upper limit of the total optimal operating load power of the diesel generator sets is k= A, (d) successively determining, by the main controller, operating states of all of the diesel generator sets, if an i diesel generator set is in an operating state, reading, by the AC current sensor 4 of a generator circuit, an AC 5 generated by the diesel generator set, detecting, by the voltage sensor 7, a rectified DC voltage value K, reading, by an A / D sampling module 8, data about 4 and K , sending the data to the sub-controller 1, calculating, by the sub-controller 1, the AC voltage Vai according to 4 and n, and then calculating, by the sub-controller 1, a service power B of the i diesel generator set by using the following formula: 2 =, x1. x¢ causing the generated AC to pass through the rectifier power module 5, and setting rectification parameters of the rectifier power module 5 to keep the rectified voltage value witin Fie Pross to ensure PB, <R<Ph, . (e) calculating, by the main controller 10, the range of the total optimal operating load power of the diesel generator sets by using the following formula: the lower limit of the total optimal operating load power of the diesel generator sets being calculated by: N =P 1=1 the upper limit of the total optimal operating load power of the diesel generator sets being calculated by: N E=XY 5, 1=1 (f) comparing, by the main controller 10, a total power R of the DC bus 9 with the lower limit A and the upper limit A of the total optimal operating load power of the diesel generator sets, where if b<R<k , it indicates that a generating power of the each diesel generator is within the optimal operating load power range when a total generating power of the diesel generator sets reaches E, and step (g) of synchronously controlling the voltages of the diesel generators according to the cross-coupling control strategy is performed, and if k does not satisfy Bh <E<F, , that is, when R>E, or h<h , step (h) of and if “t does not satisfy “ / ~°t “7#, that is, when “t”°# or “t ~° / , step (h) of establishing the optimization model and solving the optimal operating sequence of the diesel generator sets is performed; (g) synchronously controlling the voltages of the diesel generators according to the cross-coupling control strategy, including: (g.1): calculating, by the main controller 10, an average voltage v' according to the current total power Pt of the DC grid system when f<k<F , where V' satisfies: Refer when output voltages of all of the operating diesel generators are all v'. (g.2) sending, by the main controller 10, a voltage regulation command to each sub-controller 1 after Vv is calculated; (g.3) sending, by the sub-controller 1, a control signal to the A / D sampling module 8 after receiving the voltage regulation command from the main controller 10, and sending, by the A / D sampling module 8, a PWM wave to the rectifier power module 5 after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value; (g4) continuously feeding back, by an A / D conversion module 8 on each power generation circuit, the output voltage of the diesel generator to the each sub-controller 1, and sending, by the sub-controller 1, the voltage data to the main controller 10 through the bus; (g.5) calculating, by the main controller 10, a difference between V' and each output voltage after obtaining the voltage data sent by the sub-controller 1 on the power generation circuit, and sending, by the main controller 10, a voltage compensation signal to the each sub-controller 1 according to a voltage difference; (g.6) sending, by the sub-controller 1, a control signal to the A / D sampling module 8 after receiving the voltage compensation signal from the main controller 10, and sending, by the A / D sampling module 8, a PWM wave to the rectifier power module 5 after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value; (g.7) cyclically performing the operations from step (g.4); (h) establishing the optimization model and solving the optimal operating sequence of the diesel generator sets, including: h-1: setting an existing operating generator sequence to Wom {We War Wal and a non-operating generator sequence to = S1e3p + Sy-g} where WW — {LBS Mf, J =argmax (2%) + £8) 15j<N-L 2 ot Eel eta Xe tL h-2: calculating wisn 2 it b> A, that is, finding a diesel generator from the non-operating diesel generators with a largest average optimal operating load power, then performing step (h.3), and performing step (h.4) if E<F : Lp) + pi) hl P= Yr R0) TT Lae TAL Tae TET i h-3: calculating 2 2 where if P< W=WOLS] 5=8%{8} and L=L +L wming on the diesel generator with the largest average optimal operating load power found in step h-2, then performing step h-2, and performing step h-6 until P'> R 3 = argmax : (pt) +p™ ) ocic; 2 h-4: calculating SSL A , that is, finding a diesel generator with a largest average optimal operating load power from the operating diesel generators; L (pw) 4 p(w) P= Yr pp pt ) ST daw TDL] A Nw TL) ” h-5: calculating 2 2 where if P" > k B= ERE S=SUE and E=E—1 (yming on the diesel generator with the largest average optimal operating load power found in step h-4, then performing step h-4, and performing step h-6 until P” <F, w, 4) 1 (W,) BW L(p®) AS). (7 QO; Su 5 h-6: calculating ~~ 4 Toe ~~, where 1= 1.2, .., N-L, that is, respectively calculating a difference between the average optimal operating load power of any diesel generator in the operating sequence and the average optimal operating load power 1 0,,==(p®+ EY) of any diesel generator in the non-operating sequence, where 2 and 1 0 == (PM) +B) then calculating df= Le . argmin |Y —(P™) + B+ 5-H) amin 3° * ! ) Qs 4 where if I = 0, W=WU{S,} S=5\{,} L=L+1 ifJ=0, wW=W\{W,}, S=SU{W,} L=L-1 ifILJ#0, w=WU{S NW} s=SUWNS,} L=L the above process is the process of solving the optimal operating sequence of the diesel 5 : L 2 is 2 P, generators, that is, a maximum value “max of ‘I and a minimum value “umx of “vu that generators, that is, a maximum value “!mx of “I and a minimum value “vmx of “u that satisfy B<R<E, are found, so that the lower limit h and the upper limit A of the total optimal operating load power of the diesel generator sets are closest to the total power R ; t of the DC bus 9; W=WU{S,} S=S\{S,}, L=L+1 and if 1=0, WEWUSH S=S\Sip L=L+1 nich indicates that B= Fina By Bina are satisfied after a diesel generator in a non-operating sequence is turned on without turning off the diesel generator in the operating sequence; W=W\{W}, S=SU{W,}, L=L-1 and it 7-0, WEWMW S=SUWb L=L-1 ich indicates that A= Timex Bo Fon are satisfied after a diesel generator in an operating sequence is turned off without turning on the diesel generator in the non-operating sequence; and w=wUS NW} s=sUWNS,} L=L if I, J £0, 77 7 YWIURE SEER = which indicates that BeBe spy FoForws srg sui = an HR are satisfied after a diesel generator in the non-operating sequence is turned on and a diesel generator in the operating sequence is turned off; and h-7: upon completion of the above steps, that is, the process of solving the optimal operating sequence of the diesel generator sets is completed, periodically detecting, by the main controller 10, the total power R of the DC bus 9, if R changes, performing step (d) and if A does not change, ending the optimization, and maintaining the existing sequence of the diesel generator sets for operation. The above embodiments only exemplarily describe the principles and effects of the present invention, and some applied embodiments are not intended to limit the present invention. It should be noted that a person of ordinary skill in the art may further make several modifications and improvements without departing from the inventive concept of the present invention, which all fall within the protection scope of the present invention.
Claims
CLAIMS ‘What is claimed is: 1.A generator set in a direct current (DC) grid power system, comprising at least two generator-based power supply mechanisms connected to a DC bus and a main controller, wherein each of the generator-based power supply mechanisms comprises a diesel generator, the diesel generator is sequentially connected to a circuit breaker, a rectifier power module, and a fuse through a power supply line, and the power supply line is finally connected to the DC bus; a current sensor is arranged on a wire between the circuit breaker and the rectifier power module, a DC voltage sensor is arranged on a wire between the rectifier power module and the fuse, the current sensor, the rectifier power module, and the DC voltage sensor are all electrically connected to an A / D sampling module, and the A / D sampling module is electrically connected to a sub-controller; all sub-controllers are electrically connected to the main controller, and a power distribution method for generator sets in a DC grid comprises the following steps: step a: setting parameters for each diesel generator and setting power parameters for each diesel generator set through the main controller, that is, respectively setting a lower limit Bi and an upper limit Be ofan optimal operating load power of an i® (i= 1, 2, ..., N) diesel generator, and selecting a first diesel generator set as a default start item; step b: continuously detecting, by the main controller, a total power £ of the DC grid power system, wherein when a load operates in the DC bus, the power generation system starts operating, and the first diesel generator set starts operating; calculating, by the sub-controller, a service power Bi of the first diesel generator set; and causing an alternating current (AC) generated by the first diesel generator set to pass through the rectifier power module, and setting rectifier parameters of the rectifier power module to keep a rectified voltage value within Vinin Vmax to ensure Ri <E<E, ¥ step c: calculating, by the main controller, a range of a total optimal operating load power of the diesel generator sets, wherein since only the first diesel generator set is in the operating state, a lower limit of the total optimal operating load power of the diesel generator sets is £1 = hi, and an upper limit of the total optimal operating load power of the diesel generator sets is F=h 3 step d: successively determining, by the main controller, operating states of all of the diesel generator sets, wherein the sub-controller calculates a service power B of an i" diesel generator set if the i? diesel generator set is in an operating state; and causing the AC generated by the i” diesel generator set to pass through the rectifier power module, and setting rectification parameters of the rectifier power module are set to keep the rectified voltage value within Vain Vina to ensure Ri <BR <B, 3 step e: calculating, by the main controller, the range of the total optimal operating load power of the diesel generator sets by using the following formula: the lower limit of the total optimal operating load power of the diesel generator sets N Pp, =3'p, being calculated by: i=l; and the upper limit of the total optimal operating load power of the diesel generator set being N B=Y FL, calculated by: i=l step fi comparing, by the main controller, a total power A of the DC bus with the lower limit © and the upper limit Fk of the total optimal operating load power of the diesel generator sets, wherein if B<P<P, , it indicates that a generating power of the each diesel generator is within the optimal operating load power range when a total generating power of the diesel generator sets reaches Lb , and step (g) is performed, and if does not satisfy h<E<k, , that is, when B>F, or R<h , step (h) is performed; satisfy “ / ~7t “7# thatis,when “t”"¥% or “t ~7 / , step (h) is performed; step g: synchronously controlling, by the main controller, voltages of the diesel generators through the sub-controller according to a cross-coupling control strategy; step h: establishing an optimization model and solving an optimal operating sequence of the diesel generator sets, comprising: h-1: setting an existing operating generator sequence to W = {Wo Wom Wek and 2 non-operating generator sequence to © = $185 8-2} wherein WHYS = {123+ N}. J= argmax (P) +88) I1SjeN-L 2 Trg ve "LF h-2: calculating sins 2 if fn» £, that is, finding a diesel generator from the non-operating diesel generators with a largest average optimal operating load power, then performing step h-3, and performing step h-4 if E<h 3 P= 3p PO) +R) YT dau TTL 4 Kw TTL) ’ h-3: calculating 2 2 wherein if P' < k W=wuls] 8=38%{8} ang L=L +1 tyming on the diesel generator with the largest average optimal operating load power found in step h-2, then performing step h-2, and performing step h-6 until ph; = argmax Lip +p ) Ocici 2 h-4: calculating omisl & , that is, finding a diesel generator with a largest average optimal operating load power from the operating diesel generators; L (pw), pw) 2 u TH or Lt af ) TT Lae TAL Ne TE 7 h-5: calculating 2 2 wherein if P" > k Wo=Wh ME S=SU[B ang E=E-1 turning on the diesel generator with the largest average optimal operating load power found in step h-4, then performing step h-4, and performing step h-6 until P"< R, 0, ={e® 5 B®) (pt +RW) h-6: calculating ~~ <4 oe ~~ ,whereini=1, 2, .., N-L, that is, respectively calculating a difference between the average optimal operating load power of any diesel generator in the operating sequence and the average optimal operating load power 1 o Gum") of any diesel generator in the non-operating sequence, wherein 2 and 1 Oo = (P+ Bt) then calculating 1.J= in [5° L(po) 4 pt) = argmin |) —\P +B )+0,-F, rgmin [3-1 1 ) = ) wherein if [= 0, W=wU{S,}, s=S\{s,} 1.=r+1 ifJ=0, W=W\{W}, S=SU{W} L=L-1 ifI,J#£0, w=wU{S Iw} s=SU{WNS,} L=L the above process is the process of solving the optimal operating sequence of the diesel generators, that is, a maximum value Pins of h and a minimum value Pinas of k that satisfy f<F<k are found, so that the lower limit h and the upper limit A of the total optimal operating load power of the diesel generator sets are closest to the total power K of the DC bus; ifI =0, W=WUs,} S=S\{s,} L=L+1 which indicates that B= and Bo Fina are satisfied after a diesel generator in a non-operating sequence is turned on without turning off the diesel generator in the operating sequence; if] =0, B= Pax w=w\{w} s=sU{w} L=L-1 which indicates that ‘1="Imx and Bim Bane are satisfied after a diesel generator in an operating sequence is turned off without turning on the diesel generator in the non-operating sequence; and wW=wWUS, NW} S=SU{WN{S,} L=L ifJ #0, 3 which indicates that P= Boa and B= Pa are satisfied after a diesel generator in the non-operating sequence is turned on and a diesel generator in the operating sequence is turned off} and h-7: upon completion of the above steps, that is, the process of optimizing and solving the optimal operating sequence of the diesel generator set is completed, periodically detecting, by the main controller, the total power R of the DC bus, if k changes, performing step 4, and if £ does not change, ending the optimization, and maintaining the existing sequence of the diesel generator sets for operation.
2. The power distribution method for generator sets in a DC grid according to claim 1, wherein step g comprises: g-1: calculating, by the main controller, an average voltage ¥" according to the current total power Pt of the DC grid system when B<E<k , wherein F<R<k, is satisfied when output voltages of all of the operating diesel generators are Vv, g-2: sending, by the main controller, a voltage regulation command to each sub-controller after 7 is calculated; g-3: controlling, by the sub-controller, the rectifier power module to adjust a rectified DC voltage value after receiving the voltage regulation command from the main controller; g-4: continuously feeding back, by an A / D conversion module on each power generation circuit, the output voltage of the diesel generator to each sub-controller, and sending, by the sub-controller, the voltage data to the main controller through the bus; g-5: calculating, by the main controller, a difference between Vand each output voltage after obtaining the voltage data sent by the sub-controller on the power generation circuit, and sending a voltage compensation signal to the each sub-controller according to a voltage difference; g-6: controlling, by the sub-controller, the rectifier power module to adjust a rectified DC voltage value again after receiving the voltage compensation signal from the main controller; and g-7: cyclically performing the operations from step g-4; 3. The power distribution method for generator sets in a DC grid according to claim 2, wherein in step b, the calculation method for calculating the service power A of the first diesel generator set by the sub-controller specifically comprises: reading, by an AC current sensor, an AC 5 generated by the first diesel generator set, detecting, by the voltage sensor, a rectified DC voltage value h , reading, by an A / D sampling module, data about 4 and nh , sending the data to the sub-controller, calculating, by the sub-controller, an AC voltage Vac according to 5 and Vi and then calculating, by the sub-controller, a service power BR of the first diesel generator set by using the following formula A= Va xp ¢, wherein ¢ is a power factor.
4. The power distribution method for generator sets in a DC grid according to claim 2, wherein in step c, the calculation method for calculating the service power Roof the i® diesel generator set by the sub-controller specifically comprises: reading, by an AC current sensor of a power generation circuit of the i” diesel generator set, an AC 5 generated by the diesel generator set, detecting, by the voltage sensor, a rectified DC voltage value i , reading, by an A / D sampling module, data about 4 and n , sending the data to the sub-controller, calculating, by the sub-controller, the AC voltage Via according to 4 and n, and then calculating, by the sub-controller, a service power B of the i® diesel generator set by using P=y3V,.xI.x¢ the following formula “i= Y7 4G 7777 wherein ¢ is a power factor.
5. The power distribution method for generator sets in a DC grid according to claim 3 or 4, wherein step g-3 of controlling, by the sub-controller, the rectifier power module to adjust the rectified DC voltage value after receiving the voltage regulation command from the main controller specifically comprises: sending, by the sub-controller, a control signal to the A / D sampling module after receiving the voltage regulation command from the main controller, and sending, by the A / D sampling module, a PWM wave to the rectifier power module after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value.
6. The power distribution method for generator sets in a DC grid according to claim 3 or 4, wherein step g-6 of controlling, by the sub-controller, the rectifier power module to adjust the rectified DC voltage value again after receiving the voltage compensation signal from the main controller specifically comprises: sending, by the sub-controller, a control signal to the A / D sampling module after receiving the voltage compensation signal from the main controller, and sending, by the A / D sampling module, a PWM wave to the rectifier power module after receiving the signal, the PWM wave changing a duty cycle of an IGBT in the rectifier power module to adjust the rectified DC voltage value.
Citation Information
Patent Citations
Method and device for dynamically distributing load of diesel power generation units of ships
CN106451570A
Electric propulsion ship DC networking electric power system
CN107147103A
Power distribution method for diesel generator sets of DC network power generation system
CN109830953A
Direct-current networking generator set power distribution method
CN111404202A