Creation device, creation method, program, and storage medium

The creation device efficiently allocates workers and tasks based on qualifications and constraints, addressing inefficiencies in creating work schedules by ensuring compliance with deadlines and objective conditions, particularly effective for large-scale facilities.

JP2024137061APending Publication Date: 2024-10-07KK TOSHIBA +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023048414
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-24
Publication Date
2024-10-07

AI Technical Summary

Technical Problem

Existing technologies face challenges in efficiently creating work schedules that consider multiple tasks, worker qualifications, and constraints, often requiring significant time and expertise, leading to inconsistencies and inefficiencies.

Method used

A creation device and method that acquires tasks, worker qualifications, and constraints to select and allocate workers and tasks within shorter periods, ensuring compliance with deadlines and constraints, while considering objective conditions like vacation and workload balance.

Benefits of technology

The solution enables efficient and consistent creation of work schedules that satisfy both work-related and objective conditions, reducing the time required and eliminating inconsistencies, even for large-scale facilities with many tasks and workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024137061000001_ABST
    Figure 2024137061000001_ABST
Patent Text Reader

Abstract

To provide a creation device, a method, a program and a storage medium which can more easily create a work schedule and a job schedule.SOLUTION: A method acquires a plurality of jobs, each deadline of the plurality of jobs, a plurality of workers, qualifications indicating jobs chargeable by each of the plurality of workers, and a constraint condition relating to a work, selects a combination of working workers and jobs executed by the working workers for each second period shorter than a first period during which a work schedule and the job schedule are created, in the first period, selects a worker who satisfies the constraint condition and has a qualification according to the job to be executed as a working worker, selects a job to be executed so that it is completed until the period, allocates the selected combination to the job schedule and the work schedule, and creates a work schedule indicating each work schedule of the plurality of workers, and a job schedule indicating a schedule in which each of the plurality of jobs are executed.SELECTED DRAWING: Figure 7
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a creating device, a creating method, a program, and a storage medium. [Background technology]

[0002] When multiple tasks are performed by multiple workers, work schedules and task schedules may be created to perform the tasks more efficiently and reliably. There is a demand for a technology that can more easily create work schedules and task schedules. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2018-45341 A [Patent Document 2] JP 2022-63687 A Summary of the Invention [Problem to be solved by the invention]

[0004] The problem to be solved by the present invention is to provide a creation device, creation method, program, and storage medium that make it easier to create work schedules and task schedules. [Means for solving the problem]

[0005] The creation device according to the embodiment executes an acquisition step, a selection step, and an allocation step. In the acquisition step, a plurality of tasks, the deadlines of the plurality of tasks, a plurality of workers, the qualifications indicating the tasks that each of the plurality of workers can handle, and constraint conditions related to work are acquired. In the selection step, in a first period in which a work schedule and a task schedule are created, a combination of the workers who work and the tasks performed by the workers is selected for each second period that is shorter than the first period. The workers who satisfy the constraint conditions and have the qualifications corresponding to the tasks to be performed are selected as the workers who work. The tasks to be performed are selected so that they are completed by the deadline. In the allocation step, the selected combination is allocated to the task schedule and the work schedule. As a result, the work schedule indicating the work schedule of each of the plurality of workers and the task schedule indicating the schedule for performing each of the plurality of tasks are created. [Brief description of the drawings]

[0006] [Figure 1] FIG. 1 is a schematic diagram showing the configuration of a creation system according to an embodiment. [Diagram 2] FIG. 2 is a schematic diagram showing data used to create a schedule. [Diagram 3] FIG. 3 is a table illustrating the employee master data. [Figure 4] FIG. 4 is a table illustrating the business master data. [Diagram 5] FIG. 5 is a table illustrating an order. [Figure 6] FIG. 6 is a schedule illustrating the work performance data, vacation request data, and work request data. [Figure 7] FIG. 7 is a flowchart showing an outline of the creating method according to the embodiment. [Figure 8] FIG. 8 is a flowchart showing a method for allocating workers and tasks for the night shift. [Figure 9] FIG. 9 is a flowchart showing a method for selecting a person in charge of the night shift. [Figure 10] FIG. 10 is a flowchart showing a method for selecting tasks for the night shift. [Figure 11] FIG. 11 is a flowchart showing a method for selecting a person in charge of the night shift. [Figure 12] FIG. 12 is a flow chart showing a method for checking workers and work on the night shift. [Figure 13] FIG. 13 is a flowchart showing a method for allocating workers and tasks for the day shift. [Figure 14] FIG. 14 is a flowchart showing a method for selecting a person in charge of the day shift. [Figure 15] FIG. 15 is a flowchart showing a method for selecting tasks for the day shift. [Figure 16] FIG. 16 is a flowchart showing a method for selecting a person in charge of the day shift. [Figure 17] FIG. 17 is a flow chart showing a method for checking workers and work performed during the day shift. [Figure 18] FIG. 18 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Figure 19] FIG. 19 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Figure 20] FIG. 20 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Figure 21] FIG. 21 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Figure 22] FIG. 22 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Diagram 23] FIG. 23 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Figure 24] FIG. 24 is a schematic diagram illustrating an output result by the creating device according to the embodiment. [Diagram 25]FIG. 25 is a schematic diagram showing a hardware configuration. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0007] Hereinafter, each embodiment of the present invention will be described with reference to the drawings. In this specification and each drawing, the same elements as those already described are designated by the same reference numerals, and detailed description thereof will be omitted as appropriate.

[0008] The invention according to the embodiment is used to more easily create work schedules and task schedules. A work schedule defines which workers will work and when. A task schedule defines which tasks will be performed and when. Once work schedules and task schedules are created, workers will work and perform tasks according to these schedules.

[0009] FIG. 1 is a schematic diagram showing the configuration of a creation system according to an embodiment. The creation system 1 according to the embodiment includes a creation device 10, an input device 20, an output device 30, and a storage device 40.

[0010] The creation device 10 executes various processes required for creating a schedule. The input device 20 is used by a user to input data to the creation device 10. The output device 30 outputs data to a user so that the user can confirm the data. The storage device 40 stores data required for the processing of the creation device 10, data obtained by the processing, etc.

[0011] The creation device 10 includes a central processing unit (CPU). The input device 20 includes one or more selected from a mouse, a keyboard, a microphone (audio input), and a touchpad. The output device 30 includes one or more selected from a monitor, a projector, and a printer. A device having the functions of both the input device 20 and the output device 30, such as a touch panel, may be used. The storage device 40 includes one or more selected from a hard disk drive (HDD) and a solid state drive (SSD).

[0012] The creation device 10 is connected to the input device 20, the output device 30, and the storage device 40 by wired or wireless communication. A network HDD (NAS) may be used as the storage device 40, and the creation device 10 and the storage device 40 may be connected via a network. The creation device 10 may be a server that is connected to other client terminals via a network and executes processing in response to requests from the client terminals.

[0013] FIG. 2 is a schematic diagram showing data used to create a schedule. A schedule is created mainly using a plurality of tasks to be performed, a deadline for each task, a plurality of workers who can perform the tasks, the qualifications of each worker, and constraint conditions. FIG. 2 shows an example in which worker master data, task master data, input data, and constraint conditions, which include these data, are used. Using these data, the creation device 10 assigns workers to work and tasks to be performed for each second period of the first period for which the schedule is created. The second period is shorter than the first period.

[0014] Here, an example will be described in which the first period is one month and the second period is one day. In this example, workers and tasks to be performed are assigned to the daytime and nighttime periods of a day. Hereinafter, work during the daytime period will be referred to as the "day shift." Work during the nighttime period will be referred to as the "night shift." "Work" refers to at least either the day shift or the night shift.

[0015] The employee master data 100 includes a list of all employees and information about each employee. The employee information includes the upper limit of the number of times (number of days) that an employee can work in one month, the upper limit of the number of consecutive days that an employee can work, the upper limit of the number of night shifts that an employee can work in one month, the upper limit of the number of consecutive night shifts that an employee can work, etc.

[0016] The task master data 110 includes a list of all tasks and information about each task. The task information includes the time required for the task, a list of workers who can perform the task, and the number of workers required for the task. The workers who can perform the task are registered according to the qualifications of the workers. For example, each task includes a task to be performed as a manager and a task to be performed as a person in charge. In the task master data 110, for each task, a worker who can perform the task as a manager and a worker who can perform the task as a person in charge are registered.

[0017] Input data 120 includes orders, work records, vacation requests, and work requests. Orders indicate tasks to be performed during the month for which the schedule is created. For each task, the period during the month in which it will be performed is registered. Work records are the work records of each employee during the previous month. Vacation requests indicate the days on which each employee wishes to take vacation. Work requests indicate the days on which each employee wishes to work and the tasks they wish to perform.

[0018] The constraint conditions 130 indicate constraints when creating a schedule. In the illustrated example, the constraint conditions to be observed are the deadline for work, the qualifications of the worker, the upper limit of the number of shifts, the upper limit of the number of consecutive shifts, taking daytime leave after a night shift, prohibiting daytime work the day after taking the leave, the upper limit of the number of night shifts, and the upper limit of the number of consecutive night shifts.

[0019] In the example shown in FIG. 2, objective conditions 140 are registered to create a better schedule. In the objective conditions 140, preferred conditions for creating a schedule are registered. In the example shown, the objective conditions set include leveling out the number of night shifts among employees, leveling out the workload among employees, balance between work and vacation, consecutive night shifts, reflection of vacation requests, and reflection of work requests. The balance between work and vacation is set so that excessively long vacations do not occur consecutively. In addition, alternating daytime work and night shifts places a burden on employees. For this reason, consecutive night shifts are set so that the same employee will be in charge of night shifts consecutively as much as possible.

[0020] For example, the employee master data 100, the task master data 110, the input data 120, the constraint conditions 130, and the objective conditions 140 are stored in the storage device 40. The creation device 10 acquires these pieces of data from the storage device 40. At least a part of these pieces of data may be input to the creation device 10 by the input device 20.

[0021] FIG. 3 is a table illustrating the employee master data. The employee master data 100 shown in FIG. 3 includes an employee code 101, a name 102, a work count limit 103, a consecutive work count limit 104, a night shift count limit 105, and a consecutive night shift count limit 106. The employee code 101 is a character string for identifying each employee. The name 102 is the name of each employee. The work count limit 103 is the limit on the number of work days (number of days) in one month. The consecutive work count limit 104 is the limit on the number of consecutive night shifts that can be worked. The night shift count limit 105 is the limit on the number of night shifts in one month. The consecutive night shift count limit 106 is the limit on the number of consecutive night shifts that can be worked.

[0022] FIG. 4 is a table illustrating the business master data. The task master data 110 shown in FIG. 4 includes a task code 111, a task content 112, a time 113, an employee code 114, a required number of employees 115, an employee code 116, a required number of employees 117, and a flag 118. The task code 111 is a character string for identifying each task. The task content 112 indicates the content of each task. The time 113 indicates the time required to perform the task. The employee code 114 indicates the code of an employee who can handle the task as a first qualified person. The required number of employees 115 indicates the number of first qualified people required. The employee code 116 indicates the code of an employee who can handle the task as a second qualified person. The required number of employees 117 indicates the number of second qualified people required. The flag 118 indicates whether each task is performed at night or during the day. In the illustrated example, a flag is attached to the tasks performed at night. No flag is attached to the tasks performed during the day.

[0023] For example, when each task is performed, a responsible person and a person in charge are determined. The responsible person manages, supervises, or guides the work for each task, such as monitoring, patrolling, and inspection. The person in charge accompanies the responsible person to handle the task. In this example, the first qualified person is the responsible person, and the second qualified person is the person in charge. If only one person is required for the task, only the responsible person is determined.

[0024] FIG. 5 is a table illustrating an order. The order 150 shown in FIG. 5 includes an order code 151, a business code 152, business content 153, a start date and time 154, and a deadline 155. The order code 151 is a character string for identifying the order. The business code 152 indicates the business that has been ordered, and a code defined in the business master data 110 is used. The business content 153 indicates the content of the business. The start date and time 154 indicates the timing at which the business can be started. In the illustrated example, the timing is defined by a date. The deadline 155 indicates the deadline for the business. The business is required to be completed between the start date and time 154 and the deadline 155.

[0025] FIG. 6 is a schedule illustrating the work performance data, vacation request data, and work request data. The schedule 160 shown in FIG. 6 includes an employee code 161, a name 162, performance data 163, and desired data 164. The employee code 161 is a character string for identifying an employee, and a code defined in the employee master data 100 is used. The name 162 is the name of the employee. The performance data 163 indicates the work performance of each employee on each day of the last month. In other words, the performance data 163 indicates the work performance of each employee for each second period in the immediately preceding first period. "Day" indicates day shift. "Night" indicates night shift. The desired data 164 indicates the preference of each employee for each day of the current month. In other words, the desired data 164 indicates the preference of each employee for each second period in the first period for which the schedule is created. "Off" is entered on days on which an employee wishes to take a holiday. A task code indicating the desired task is entered on days on which an employee wishes to work.

[0026] FIG. 7 is a flowchart showing an outline of the creating method according to the embodiment. First, the creation device 10 acquires data such as a plurality of tasks to be performed, a deadline for each task, a plurality of workers capable of performing the tasks, the qualifications of each worker, constraint conditions, etc. (Step S0: Acquisition step).

[0027] Next, the creation device 10 executes a selection step of selecting an employee and a task for each day during one month, and an allocation step of allocating the selected employee and task. Here, an example will be described in which the work for one day is divided into a day shift and a night shift, and employees and tasks are allocated to the day shift and night shift.

[0028] The creation device 10 executes allocation of workers and tasks to night shifts (step S10). The creation device 10 executes allocation of workers and tasks to day shifts (step S20). When workers and tasks are allocated, the constraint conditions and objective conditions are referred to. The creation device 10 outputs the schedule obtained by allocating workers and tasks (step S30).

[0029] In the following, we will specifically explain how to assign workers and tasks to day and night shifts.

[0030] FIG. 8 is a flowchart showing a method for allocating workers and tasks for the night shift. First, the creation device 10 sets a processing date (step S11). The processing date is the date on which workers and tasks are assigned. For example, when a schedule is created for November 1st to November 30th, November 1st is first set as the processing date.

[0031] The creation device 10 selects a person in charge (step S12). The creation device 10 selects a task to be performed by the selected person in charge (step S13). The creation device 10 selects a person in charge of performing the selected task (step S14). The creation device 10 determines whether the constraints are satisfied for the selected worker and task (step S15).

[0032] If the constraints are satisfied in step S15, the creation device 10 assigns the selected workers and tasks (step S16). The creation device 10 determines whether any tasks remain to be assigned among the ordered tasks (step S17). If no tasks remain, the creation device 10 ends the assignment to the night shift.

[0033] If it is determined in step S15 that the constraint conditions are not satisfied, or if it is determined in step S17 that tasks remain, the creation device 10 determines whether unassigned tasks can be assigned to the processing date (step S18). If there is no task whose start date and time is before the processing date, or if there is no worker who can be assigned to the processing date, the creation device 10 determines that there is no task that can be assigned to the processing date. Note that if it is determined in step S15 that the constraint conditions are not satisfied, the combinations of workers and tasks selected in steps S12 to S14 up to that point are excluded from the targets for assignment. In step S18, the creation device 10 determines whether workers and tasks can be assigned to combinations other than the excluded combinations.

[0034] If there is an allocatable task, the creation device 10 executes step S12 again. In step S12 again, a different person from the person selected up until that point is selected. If there is no allocatable task, the creation device 10 updates the processing date (step S19). As a result, the day following the previous processing date is set as the new processing date. After that, step S12 is executed again for the new processing date.

[0035] FIG. 9 is a flowchart showing a method for selecting a person in charge of the night shift. In step S12, the creation device 10 executes the process shown in Fig. 9. First, the creation device 10 extracts workers whose processing date is not a day on which they wish to take a holiday from among all workers. The creation device 10 judges whether the number a1 of extracted workers is 1 or not (step S12a).

[0036] If the number a1 of workers extracted in step S12a is 2 or more, the creation device 10 extracts workers whose desired work date is the processing date from the extracted workers. If the number a1 is zero, the creation device 10 extracts workers whose desired work date is the processing date from all workers. The creation device 10 determines whether the number a2 of workers extracted is 1 or not (step S12b).

[0037] If the number a2 of workers extracted in step S12b is two or more, the creation device 10 extracts workers whose number of night shifts in one month is equal to or less than the upper limit from the extracted workers. Specifically, the number of night shifts is counted from workers and tasks already assigned during the period for which the schedule is created. The counted value is compared with the upper limit. If the number a2 is zero, the creation device 10 extracts workers whose number of night shifts in one month is equal to or less than the upper limit from the two or more workers extracted in step S12a. The creation device 10 determines whether the number a3 of extracted workers is one (step S12c).

[0038] If the number a3 of workers extracted in step S12c is 2 or more, the creation device 10 extracts workers whose number of consecutive night shifts in one month is equal to or less than the upper limit from the extracted workers. If the number a3 is zero, the creation device 10 extracts workers whose number of consecutive night shifts in one month is equal to or less than the upper limit from the two or more workers extracted in step S12b. The creation device 10 determines whether the number a4 of workers extracted is 1 (step S12d).

[0039] If the number a4 of workers extracted in step S12d is 2 or more, the creation device 10 extracts workers who have worked a night shift within the past 24 hours from the extracted workers. If the number a4 is zero, the creation device 10 extracts workers who have worked a night shift within the past 24 hours from the two or more workers extracted in step S12c. The creation device 10 determines whether the number a5 of workers extracted is 1 (step S12e).

[0040] If the number a5 of workers extracted in step S12e is 2 or more, the creation device 10 extracts the worker who has worked the fewest number of night shifts in that month from the extracted workers (step S12f). The creation device 10 selects that worker as the person in charge (step S12g). If the number of workers extracted in any of steps S12a to S12e is 1, the creation device 10 selects that worker as the person in charge (step S12g).

[0041] If the number a5 is zero, the worker with the fewest number of night shifts in that month is extracted from the two or more workers extracted in step S12d. If the number of workers extracted in any of steps S12a to S12d is zero, steps up to step S12e may be omitted and the process may skip to step S12f.

[0042] In the flowchart shown in FIG. 9, the judgment processes of steps S12a and S12b are performed to reflect the wishes of the workers. The judgment processes of steps S12c and S12d are performed to satisfy the constraint conditions. The judgment process of step S12e is performed to set consecutive night shifts for the same worker. The process of step S12f is performed to equalize the workload among the workers.

[0043] FIG. 10 is a flowchart showing a method for selecting tasks for the night shift. In step S13, the creation device 10 executes the process shown in FIG. 10. First, the creation device 10 extracts, from all tasks, tasks that can be started on the processing date and that have been assigned the flag shown in FIG. 4. From the extracted tasks, the creation device 10 further extracts tasks that the selected worker can handle as a responsible person. The creation device 10 judges the number b1 of extracted tasks (step S13a). If the number b1 is zero, the creation device 10 ends the process and executes step S12 again. In the next step S12, a different responsible person is selected.

[0044] If the number b1 of tasks extracted in step S13a is 2 or more, the creation device 10 judges whether the extracted tasks include a task desired by the selected worker (step S13b). If there is no desired task, the creation device 10 extracts the task with the earliest deadline from the multiple tasks (step S13c). The creation device 10 selects the extracted task as the task to be executed (step S13d). If the number b1 of tasks extracted in step S13a is 1, or if a desired task exists in step S13b, that task is selected (step S13d).

[0045] In the flowchart shown in Fig. 10, the determination process in step S12a is executed to have an employee with the necessary qualifications carry out the work, and the determination process in step S12b is executed to reflect the employee's wishes.

[0046] FIG. 11 is a flowchart showing a method for selecting a person in charge of the night shift. In step S14, the creation device 10 executes the process shown in Fig. 11. First, the creation device 10 refers to all workers other than the selected manager. The creation device 10 extracts workers who can perform the work selected in step S13 as a person in charge from all workers. The creation device 10 determines whether the number c1 of extracted workers is 1 or not (step S14a).

[0047] If the number c1 of workers extracted in step S14a is 2 or more, the creation device 10 extracts workers whose processing date is not a day on which they would like to take a vacation from the extracted workers. If the number c1 is zero, the creation device 10 extracts workers whose processing date is not a day on which they would like to take a vacation from all workers. The creation device 10 determines whether the number c2 of workers extracted is 1 or not (step S14b).

[0048] If the number c2 of workers extracted in step S14b is 2 or more, the creation device 10 extracts workers whose desired work date is the processing date from the extracted workers. If the number c2 is zero, the creation device 10 extracts workers whose desired work date is the processing date from the two or more workers extracted in step S14a. The creation device 10 determines whether the number c3 of workers extracted is 1 (step S14c).

[0049] If the number c3 of workers extracted in step S14c is 2 or more, the creation device 10 extracts workers whose number of night shifts per month is equal to or less than the upper limit from the extracted workers. If the number c3 is zero, the creation device 10 extracts workers whose number of night shifts per month is equal to or less than the upper limit from the two or more workers extracted in step S14b. The creation device 10 determines whether the number c4 of workers extracted is 1 (step S14d).

[0050] If the number c4 of the workers extracted in step S14d is 2 or more, the creation device 10 extracts workers whose number of consecutive night shifts in one month is equal to or less than the upper limit from the extracted workers. If the number c4 is zero, the creation device 10 extracts workers whose number of consecutive night shifts in one month is equal to or less than the upper limit from the two or more workers extracted in step S14c. The creation device 10 determines whether the number c5 of the extracted workers is 1 (step S14e).

[0051] If the number c5 of workers extracted in step S14e is 2 or more, the creation device 10 extracts workers who have worked a night shift within the past 24 hours from the extracted workers. If the number c5 is zero, the creation device 10 extracts workers who have worked a night shift within the past 24 hours from the two or more workers extracted in step S14d. The creation device 10 determines whether the number c6 of workers extracted is 1 (step S14f).

[0052] If the number c6 of workers extracted in step S14f is 2 or more, the creation device 10 extracts the worker who has worked the least number of night shifts in that month from the extracted workers (step S14g). The creation device 10 selects the worker as the person in charge (step S14h).

[0053] If the number of extracted workers is 1 in any of steps S14a to S14f, the creating device 10 selects that worker as the person in charge (step S14h).

[0054] If the number c6 of workers extracted in step S14f is zero, the worker who has worked the fewest number of night shifts in that month is extracted from the two or more workers extracted in step S14e. If the number of workers extracted in any of steps S14a to S14e is zero, steps up to S14f may be omitted and the process may skip to step S14g.

[0055] In the flowchart shown in FIG. 11, the judgment process of step S14a is performed to have a worker with the necessary qualifications perform the work. The judgment processes of steps S14b and S14c are performed to reflect the wishes of the worker. The judgment processes of steps S14d and S14e are performed to satisfy the constraint conditions. The judgment process of step S14f is performed to set consecutive night shifts for the same worker. The process of step S14g is performed to equalize the number of night shifts among workers.

[0056] FIG. 12 is a flow chart showing a method for checking workers and work on the night shift. In step S15, the creation device 10 executes the process shown in Fig. 12. First, the creation device 10 judges whether the number of night shifts for the selected manager and person in charge is equal to or less than the upper limit (step S15a). If it is judged that the number of night shifts is equal to or less than the upper limit, the creation device 10 judges whether the number of consecutive night shifts is equal to or less than the upper limit (step S15b). If it is judged that the number of consecutive night shifts is equal to or less than the upper limit, the creation device 10 permits the allocation of the selected manager, the selected person in charge, and the selected task (step S15c).

[0057] If it is determined that the number of night shifts exceeds the upper limit, or if it is determined that the number of consecutive night shifts exceeds the upper limit, it is determined that the constraint condition is not satisfied. The creation device 10 excludes the combination of the selected worker and task (step S15d). After the exclusion, the combination of the selected worker and task cannot be assigned on that processing date. A combination of another worker and the task, or a combination of the worker and another task, is permitted. Then, in step S18, it is determined whether another worker and task can be assigned.

[0058] If the selected manager, person in charge, and task are permitted, the creation device 10 assigns the manager, person in charge, and task to the processing date (step S16). At this time, the creation device 10 assigns vacation to the daytime of the day following the processing date for the schedule of the assigned manager and person in charge. This achieves the constraint condition of "taking vacation during the daytime after the night shift." After that, steps S17 to S19 are executed as shown in FIG. 8. With the above, the assignment of workers and tasks to the night shift is completed.

[0059] Next, workers and tasks are assigned to the day shift. The method of assigning workers and tasks to the day shift is generally the same as the method of assigning workers and tasks to the night shift described above.

[0060] FIG. 13 is a flowchart showing a method for allocating workers and tasks for the day shift. In step S20, first, the creation device 10 sets a processing date (step S21). The creation device 10 selects a person in charge (step S22). The creation device 10 selects a task to be performed by the selected person in charge (step S23). The creation device 10 selects a person in charge of performing the selected task (step S24). The creation device 10 determines whether the constraints are satisfied for the selected worker and task (step S25).

[0061] If the constraints are satisfied in step S25, the creation device 10 assigns the selected workers and tasks (step S26). The creation device 10 determines whether any tasks remain to be assigned among the ordered tasks (step S27). If no tasks remain, the creation device 10 ends the assignment to the day shift.

[0062] If it is determined in step S25 that the constraints are not satisfied, or if it is determined in step S27 that tasks remain, it is determined whether the remaining tasks can be assigned to the processing date (step S28). If there is an assignable task, the creation device 10 executes step S22 again. If there is no assignable task, the creation device 10 updates the processing date (step S29).

[0063] FIG. 14 is a flowchart showing a method for selecting a person in charge of the day shift. In step S22, the creation device 10 executes the process shown in Fig. 14. First, the creation device 10 extracts workers whose processing date is not a day on which they wish to take a holiday from among all workers. The creation device 10 determines whether the number d1 of extracted workers is 1 or not (step S22a).

[0064] If the number d1 of workers extracted in step S22a is 2 or more, the creation device 10 extracts workers whose desired work date is the processing date from the extracted workers. If the number d1 is zero, the creation device 10 extracts workers whose desired work date is the processing date from all workers. The creation device 10 determines whether the number d2 of workers extracted is 1 or not (step S22b).

[0065] If the number d2 of workers extracted in step S22b is 2 or more, the creation device 10 extracts workers whose number of work days per month is equal to or less than the upper limit from the extracted workers. If the number d2 is zero, the creation device 10 extracts workers whose number of work days per month is equal to or less than the upper limit from the two or more workers extracted in step S22a. The creation device 10 determines whether the number d3 of workers extracted is 1 (step S22c).

[0066] If the number d3 of workers extracted in step S22c is 2 or more, the creation device 10 extracts workers whose number of consecutive work days in one month is equal to or less than the upper limit from the extracted workers. If the number d3 is zero, the creation device 10 extracts workers whose number of consecutive work days in one month is equal to or less than the upper limit from the two or more workers extracted in step S22b. The creation device 10 determines whether the number d4 of workers extracted is 1 (step S22d).

[0067] If the number d4 of workers extracted in step S22d is 2 or more, the creation device 10 extracts workers who have not worked a night shift within the past 24 hours from the extracted workers. If the number d4 is zero, the creation device 10 extracts workers who have not worked a night shift within the past 24 hours from the two or more workers extracted in step S22c. The creation device 10 determines whether the number d5 of workers extracted is 1 (step S22e).

[0068] If the number d5 of workers extracted in step S22e is two or more, the creation device 10 extracts workers who have not performed a task within the past 48 hours from the extracted workers. If the number d5 is zero, the creation device 10 extracts workers who have not performed a task within the past 48 hours from the two or more workers extracted in step S22d. The creation device 10 determines whether the number d6 of workers extracted is one (step S22f).

[0069] If the number d6 of workers extracted in step S22f is 2 or more, the creation device 10 extracts the worker who worked the least number of times in that month from the extracted workers (step S22g). The creation device 10 selects that worker as the person in charge (step S22h). If the number of workers extracted in any of steps S22a to S22f is 1, the creation device 10 selects that worker as the person in charge (step S22h).

[0070] If the number d6 is zero, the worker who worked the least number of times in that month is extracted from the two or more workers extracted in step S22e. If the number of workers extracted in any of steps S22a to S22e is zero, steps up to S22f may be omitted and the process may skip to step S22g.

[0071] In the flowchart shown in Fig. 14, the judgment process in step S22e is executed to comply with the prohibition of taking daytime vacation after a night shift and working a day shift the day after taking the vacation. The judgment process in step S22f is executed to improve the balance between work and vacation.

[0072] FIG. 15 is a flowchart showing a method for selecting tasks for the day shift. In step S23, the creation device 10 executes the process shown in FIG. 15. First, the creation device 10 extracts, from all tasks, tasks that can be started on the processing date and that are not assigned the flag shown in FIG. 4. From the extracted tasks, the creation device 10 further extracts tasks that the selected worker can handle as a responsible person. The creation device 10 determines the number e1 of extracted tasks (step S23a). If the number e1 of extracted tasks is zero, the creation device 10 ends the process and executes step S22 again.

[0073] If the number of tasks e1 extracted in step S23a is 2 or more, the creation device 10 judges whether the extracted tasks include a task desired by the worker (step S23b). If there is no desired task, the creation device 10 extracts the task with the shortest delivery date from the extracted tasks. The creation device 10 judges whether the number of extracted tasks e2 is 1 or not (step S23c).

[0074] If the number e2 of tasks extracted in step S23c is 2 or more, the creation device 10 extracts repeated tasks from the extracted tasks. A repeated task is a task that is periodically repeated during a first period. For example, a task that is performed every day corresponds to a repeated task. The creation device 10 determines whether the number e3 of extracted repeated tasks is 1 or not (step S23d).

[0075] If the number of tasks e3 extracted in step S23d is 2 or more, the creation device 10 extracts the task with the fewest available workers from the extracted tasks (step S23e). The creation device 10 selects the extracted task as the task to be performed by the selected person in charge (step S23f). If the number of tasks extracted in any of steps S23a, S23c, or S23d is 1, or if a desired task is found in step S23b, the creation device 10 selects that task (step S23f).

[0076] FIG. 16 is a flowchart showing a method for selecting a person in charge of the day shift. In step S24, the creation device 10 executes the process shown in Fig. 16. First, the creation device 10 refers to all workers other than the selected manager. The creation device 10 extracts workers who can perform the work selected in step S23 as a person in charge from all workers. The creation device 10 determines whether the number f1 of extracted workers is 1 or not (step S24a).

[0077] If the number f1 of workers extracted in step S24a is 2 or more, the creation device 10 extracts workers whose processing date is not a desired vacation day from the extracted workers. If the number f1 is zero, the creation device 10 extracts workers whose processing date is not a desired vacation day from all workers. The creation device 10 determines whether the number f2 of workers extracted is 1 or not (step S24b).

[0078] If the number f2 of workers extracted in step S24b is 2 or more, the creation device 10 extracts workers whose desired work date is the processing date from the extracted workers. If the number f2 is zero, the creation device 10 extracts workers whose desired work date is the processing date from the two or more workers extracted in step S24a. The creation device 10 determines whether the number f3 of workers extracted is 1 or not (step S24c).

[0079] If the number f3 of workers extracted in step S24c is 2 or more, the creation device 10 extracts workers whose number of work days per month is equal to or less than the upper limit from the extracted workers. If the number f3 is zero, the creation device 10 extracts workers whose number of work days per month is equal to or less than the upper limit from the two or more workers extracted in step S24b. The creation device 10 determines whether the number f4 of workers extracted is 1 (step S24d).

[0080] If the number f4 of workers extracted in step S24d is 2 or more, the creation device 10 extracts workers whose number of consecutive work days in one month is equal to or less than the upper limit from the extracted workers. If the number f4 is zero, the creation device 10 extracts workers whose number of consecutive work days in one month is equal to or less than the upper limit from the two or more workers extracted in step S24c. The creation device 10 determines whether the number f5 of workers extracted is 1 (step S24e).

[0081] If the number f5 of workers extracted in step S24e is 2 or more, the creation device 10 extracts workers who have not worked a night shift within the past 24 hours from the extracted workers. If the number f5 is zero, the creation device 10 extracts workers who have not worked a night shift within the past 24 hours from the two or more workers extracted in step S24d. The creation device 10 determines whether the number f6 of workers extracted is 1 (step S24f).

[0082] If the number f6 of workers extracted in step S24f is 2 or more, the creation device 10 extracts workers who have not performed a task within the past 48 hours from the extracted workers. If the number f6 is zero, the creation device 10 extracts workers who have not performed a task within the past 48 hours from the two or more workers extracted in step S24e. The creation device 10 determines whether the number f7 of extracted workers is 1 (step S24g).

[0083] If the number f7 of workers extracted in step S24g is 2 or more, the creation device 10 extracts the worker who has worked the least number of times in that month from the extracted workers (step S24h). The creation device 10 selects that worker as the person in charge of performing the selected task (step S24i). If the number of workers extracted in any of steps S24a to S24g is 1, the creation device 10 selects that worker as the person in charge (step S24i).

[0084] If the number f7 is zero, the worker who worked the least number of shifts in that month is extracted from the two or more workers extracted in step S24f. If the number of workers extracted in any of steps S24a to S24f is zero, steps up to S24g may be omitted and the process may skip to step S24h.

[0085] FIG. 17 is a flow chart showing a method for checking workers and work performed during the day shift. In step S25, the creation device 10 executes the process shown in FIG. 17. First, the creation device 10 judges whether the number of work days in one month for the selected manager and person in charge is equal to or less than the upper limit (step S25a). If it is judged that the number of work days is equal to or less than the upper limit, the creation device 10 judges whether the number of consecutive work days is equal to or less than the upper limit (step S25b). If it is judged that the number of consecutive work days is equal to or less than the upper limit, the creation device 10 judges whether a night shift has been assigned to the selected manager and person in charge within 24 hours of the processing date (step S25c). The fact that a night shift has not been assigned within 24 hours corresponds to satisfying the constraint condition of "prohibition of day shifts on the day after taking a vacation". If a night shift has not been assigned within 24 hours, the creation device 10 permits the assignment of the selected manager, selected person in charge, and selected task (step S25d).

[0086] If it is determined that the number of work shifts in one month exceeds the upper limit, or if it is determined that the number of consecutive work shifts exceeds the upper limit, it is determined that the constraint condition is not satisfied. The creation device 10 excludes the selected combination of worker and task (step S25e). Thereafter, in step S28, it is determined whether another worker and task can be assigned.

[0087] If the selected manager, person in charge, and task are permitted, the creation device 10 assigns the manager, person in charge, and task to the processing date. After that, steps S27 to S29 are executed as shown in Fig. 13. With the above, the assignment of workers and tasks to the day shift is completed.

[0088] When the allocation to night shifts and day shifts is completed, a schedule is obtained in which workers and scheduled tasks for each day (second period) in one month (first period) are registered. The creation device 10 creates a work schedule and a task schedule through the allocation. The task schedule specifies when a task is to be performed. The task schedule may link each task to a worker who will perform the task. The work schedule specifies when a worker will work. The work schedule may link each worker to a task to be performed.

[0089] 18 to 20 are schematic diagrams illustrating output results by the creating device according to the embodiment. The creation device 10 outputs, for example, a work schedule 200 shown in Fig. 18 and a task schedule 210 shown in Fig. 19. In the illustrated example, each schedule is shown in a Gantt chart.

[0090] As shown in FIG. 18, the work schedule 200 includes an employee code 201, a name 202, and a work schedule 203. In each row of the columns of the employee code 201 and the name 202, data of an employee is described. In each column of the work schedule 203, a second period is indicated. In the work schedule 203, it is indicated which employee will work during the day or night for each second period. In addition, each employee's work schedule is linked to the work to be performed. Furthermore, in the work schedule 200, the work schedule for working as a supervisor and the work schedule for working as a person in charge are displayed in different modes. In the illustrated example, the days on which the employee will perform work as a supervisor are marked with dots with a higher density. The days on which the employee will perform work as a supervisor are marked with dots with a lower density.

[0091] As shown in FIG. 19, the work schedule 210 includes an order code 211, a work code 212, and a work schedule 213. Work data is described in each row of the columns of the order code 211 and the work code 212. A second period is indicated in each column of the work schedule 213. The work schedule 213 indicates which work is performed during the day shift and the night shift for each second period. Each work is also linked to which worker will perform it. In the illustrated example, the worker code of the person responsible for performing each work is indicated. The worker code of the person in charge of performing each work may also be indicated.

[0092] FIG. 20 shows an example of a schedule different from those in FIG. 18 and FIG. 19. As shown in FIG. 20, the creation device 10 is also capable of outputting a longer-term schedule. In the schedule shown in FIG. 20, each row shows the work schedule of each worker. For each worker, a pattern is assigned to the day and time period when the work is performed. Also, a different pattern is assigned to each work. The period of the schedule to be output can be arbitrarily set by the user. Also, the schedule may be displayed on a graphical user interface (GUI) or the like, and the period of the schedule displayed on the GUI may be adjusted by the user.

[0093] A general scheduler can be used to create the schedule described above. Frexche (registered trademark) can be used as the scheduler. The invention according to the embodiment can be realized by implementing a program for executing the various processes described above in any of the schedulers. In addition to Frexche (registered trademark), Asprova (registered trademark), JoyScheduler (registered trademark), etc. may also be used as the scheduler.

[0094] Advantages of the embodiment will be described. When multiple tasks are performed by multiple workers, work schedules and task schedules may be created to perform the tasks more efficiently and reliably. When a task schedule is created, constraints on the tasks, such as the deadline for each task and the qualifications of the workers, are taken into consideration. When a work schedule is created, the upper limit of the number of times each worker can work, the upper limit of the number of consecutive work sessions, vacation time, and work preferences are taken into consideration. It is also preferable that tasks are not concentrated on a specific worker, and that work and vacation time are allocated to each worker in a balanced manner. Conventionally, work schedules and task schedules were created individually by people while taking these multiple conditions into consideration. For this reason, a lot of time was spent on creating work schedules and task schedules. In addition, knowledge and experience are also required to create these schedules, and the number of people who can create schedules was limited. The created schedules did not take into consideration all combinations of tasks and workers, and there were many cases where there was room for improvement. Furthermore, after the work schedule and task schedule were completed, inconsistencies were sometimes found between the task schedule and the work schedule. For example, workers performing some tasks may not have the appropriate qualifications, workers may not be scheduled to work during the period when some tasks are to be performed, some workers may be scheduled to work beyond their limits, etc. In order to resolve these inconsistencies, it may be necessary to adjust work schedules or task schedules by trial and error so as not to deviate from work constraints or task constraints.

[0095] In regard to this issue, the creation device 10 according to the embodiment acquires a plurality of tasks, the deadline for each task, a plurality of workers, the qualifications of each worker, constraints on work, etc., and selects a combination of workers to be worked and tasks to be performed for each second period. When selecting a combination, workers who satisfy the constraints on work and have the qualifications according to the tasks to be performed are selected. In addition, tasks to be performed are selected so that the tasks are completed by their deadlines. In other words, a combination of workers and tasks is selected taking into consideration both the constraints on tasks and the constraints on work. Then, a work schedule and a task schedule are created by allocating the selected combination.

[0096] According to the embodiment, the creation device 10 simultaneously creates a work schedule and a task schedule that satisfy both the task-related constraints and the work-related constraints. Therefore, there is no inconsistency between the created work schedule and the created task schedule. By using the creation device 10, there is no need for a person to create a work schedule and a task schedule, and the time required to create the schedule can be significantly reduced. Even a person who has no knowledge of creating schedules can easily create a work schedule and a task schedule that do not contradict each other using the creation device 10. In addition, since the creation device 10 considers the allocation of various combinations of workers and tasks, a more preferable schedule is more likely to be obtained than when a schedule is created by a person.

[0097] The creation device 10 outputs the created work schedule and business schedule to the user. For example, the work schedule and business schedule are displayed on the output device 30. This allows the user to easily check the created work schedule and business schedule.

[0098] The invention according to the embodiment is particularly effective when creating a schedule for the management and operation of a large facility such as a plant. Plants include water purification plants, power plants, large factories, etc. In large facilities, many tasks are performed, and each task often requires a qualification. This makes it difficult for humans to create a schedule. The invention according to the embodiment is particularly effective when there are many tasks and workers.

[0099] It is preferable that the creation device 10 further acquires a target condition and creates a schedule according to the target condition. The target condition defines more preferable conditions such as a balance between vacation and work, and preferences regarding vacation or work. A more preferable schedule is obtained by creating a schedule that satisfies the target condition while satisfying the constraint condition.

[0100] In principle, the creation device 10 selects tasks so that they can be completed by the deadline. However, if a combination of an employee and a task that can be completed by the deadline cannot be obtained, the creation device 10 selects a combination of an employee and a task whose deadline has passed in the second period after the deadline. In other words, even if a task will not be completed by the deadline, the creation device 10 does not ignore the task, but assigns the task and the employee so that the task is executed with a delay. For example, the creation device 10 creates and outputs a work schedule and a task schedule in which some tasks will not be completed by the deadline. By outputting a work schedule and a task schedule in which the constraint conditions are not satisfied, the user can easily confirm which period or which task is likely to have a problem within the entire first period.

[0101] 21 to 23 are schematic diagrams illustrating output results by the creating device according to the embodiment. For example, as shown in Fig. 21, the creation device 10 displays a task that is past its deadline so that it can be distinguished from other tasks. For example, the color or pattern of the cell of the task that is past its deadline is different from the color or pattern of the cell of the task that is not past its deadline. Alternatively, at least one of the color, font, thickness, size, character decoration, and background color of the characters indicating the task that is past its deadline may be different from at least one of the color, font, thickness, size, character decoration, and background color of the characters indicating the task that is not past its deadline. As shown in Fig. 21, the creation device 10 may attach a message 215 to the task that is past its deadline.

[0102] If any task is past its deadline, the creation device 10 may output a list of the tasks that are past their deadline. For example, as shown in Fig. 22, the creation device 10 outputs a list 220. The list 220 includes an order code 221, a task code 222, task content 223, a deadline 224, and a planned implementation date 225. The planned implementation date 225 indicates the time when each task is scheduled to be implemented in the created schedule.

[0103] If the creation device 10 cannot create a work schedule and a task schedule that satisfy the constraint conditions, the creation device 10 may change a part of the data used to create the schedule. For example, the creation device 10 adds an employee and creates a work schedule and a task schedule. When an employee is added, the task is more likely to be completed by the deadline. The creation device 10 may continue to add employees until a work schedule and a task schedule that satisfy the constraint conditions is created. This allows the user to easily understand how many employees need to be added to satisfy the constraint conditions.

[0104] The creation device 10 outputs a schedule to which workers have been added, for example, as shown in FIG. 23. The added workers 201a and 201b are displayed so as to be distinguishable from the other workers. The added workers are distinguished from the other workers by their codes or names. As shown in the figure, the display mode of the added workers may be different from the display mode of the other workers. By outputting the schedule when a worker has been added, the user can easily understand how the schedule will change due to the addition of a worker.

[0105] When the creation device 10 cannot create a work schedule and a task schedule that satisfy the objective conditions and the constraint conditions, the creation device 10 may relax or ignore part of the objective conditions or part of the constraint conditions related to work. For example, the creation device 10 executes one or more selected from raising the upper limit of the number of times of work, raising the upper limit of the number of consecutive work days, ignoring requests for vacation, and ignoring requests for work. The creation device 10 creates a work schedule and a task schedule by relaxing or ignoring part of the conditions. The creation device 10 may create multiple task schedules and multiple work schedules while changing the conditions to be relaxed or ignored.

[0106] The creation device 10 outputs the schedule created using the relaxed or ignored conditions, for example, as shown in Fig. 24. This allows the user to easily understand how the schedule will change when the objective conditions or constraint conditions are changed. The creation device 10 may display a message 205 indicating the relaxed or ignored conditions.

[0107] A mark may be added to the difference between a schedule created without relaxing or ignoring the objective conditions and constraint conditions and a schedule created by ignoring or relaxing some of the conditions. In the schedule shown in FIG. 22, "TAK3" was scheduled to be on vacation on November 2nd. No work was assigned to "WAT8" on the night of November 3rd. In contrast, in the schedule shown in FIG. 24, work schedule 203a is assigned to "TAK3" on November 2nd. Work schedule 203b is assigned to "WAT8" on the night of November 3rd. Schedules 203a and 203b are displayed so as to be distinguishable from other schedules. This allows the user to easily understand the schedule that has changed due to relaxing or ignoring the conditions.

[0108] For example, if ignoring vacation requests or work requests can result in work schedules and task schedules that satisfy other constraints, negotiations can be performed with the employee who submitted the vacation request or task request. If the vacation request or task request can be changed, the result is a work schedule and task schedule that satisfies both constraints.

[0109] FIG. 25 is a schematic diagram showing a hardware configuration. 25 is used as the creation device 10. The computer 90 includes a CPU 91, a ROM 92, a RAM 93, a storage device 94, an input interface 95, an output interface 96, and a communication interface 97.

[0110] The ROM 92 stores a program for controlling the operation of the computer 90. The ROM 92 stores a program necessary for causing the computer 90 to realize each of the above-mentioned processes. The RAM 93 functions as a storage area in which the programs stored in the ROM 92 are expanded.

[0111] The CPU 91 includes a processing circuit. The CPU 91 uses a RAM 93 as a working memory and executes a program stored in at least one of a ROM 92 and a storage device 94. During execution of the program, the CPU 91 controls each component via a system bus 98 and executes various processes.

[0112] The storage device 94 stores data necessary for executing the programs and data obtained by executing the programs.

[0113] The input interface (I / F) 95 can connect the computer 90 and the input device 20. The input I / F 95 is, for example, a serial bus interface such as USB. The CPU 91 can read various data from the input device 20 via the input I / F 95.

[0114] The output interface (I / F) 96 can connect the computer 90 and the output device 30. The output I / F 96 is, for example, a video output interface such as a Digital Visual Interface (DVI) or a High-Definition Multimedia Interface (HPMI (registered trademark)). The CPU 91 can transmit data to the output device 30 via the output I / F 96 and cause the output device 30 to display a schedule.

[0115] The communication interface (I / F) 97 can connect the computer 90 to a server external to the computer 90. The communication I / F 97 is, for example, a network card such as a LAN card. The CPU 91 can read various data from the server via the communication I / F 97.

[0116] The storage device 94 includes one or more selected from a HDD and an SSD. The storage device 94 may be used as the storage device 40. The input device 20 includes one or more selected from a mouse, a keyboard, a microphone (audio input), and a touchpad. The output device 30 includes one or more selected from a monitor, a projector, and a printer. A device having the functions of both the input device 20 and the output device 30, such as a touch panel, may be used.

[0117] Each process executed by the creation device 10 may be realized by one computer 90, or may be realized by a plurality of computers 90 working together.

[0118] The various data processing operations described above may be recorded as a program that can be executed by a computer on a magnetic disk (such as a flexible disk or a hard disk), an optical disk (such as a CD-ROM, CD-R, CD-RW, DVD-ROM, DVD±R, DVD±RW), a semiconductor memory, or other non-transitory computer-readable storage medium.

[0119] For example, information recorded on a recording medium can be read by a computer (or an embedded system). The recording medium may have any recording format (storage format). For example, the computer reads a program from the recording medium and causes a CPU to execute instructions described in the program based on the program. The computer may acquire (or read) the program via a network.

[0120] According to the embodiment described above, a creation device, creation method, program, and storage medium are provided that can easily create work schedules and task schedules.

[0121] Although some embodiments of the present invention have been illustrated above, these embodiments are presented as examples and are not intended to limit the scope of the invention. These novel embodiments can be implemented in various other forms, and various omissions, substitutions, modifications, etc. can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are included in the scope of the invention and its equivalents described in the claims. In addition, the above-mentioned embodiments can be implemented in combination with each other. [Explanation of symbols]

[0122] 1: Creation system, 10: Creation device, 20: Input device, 30: Output device, 40: Storage device, 90: Computer, 100: Employee master data, 110: Business master data, 120: Input data, 130: Constraint conditions, 140: Objective conditions, 150: Order, 160: Schedule, 200: Work schedule, 210: Business schedule

Claims

1. An acquisition step of acquiring a plurality of tasks, deadlines for each of the plurality of tasks, a plurality of workers, qualifications indicating the tasks that each of the plurality of workers can handle, and work-related constraints; a selection step of selecting a combination of the worker to work and the task to be performed by the worker for each second period shorter than the first period during a first period for which a work schedule and a task schedule are created, the selection step being such that the worker who satisfies the constraints and has the qualifications corresponding to the task to be performed is selected as the worker to work, and the task to be performed is selected so as to be completed by the deadline; an allocation step of allocating the selected combination to the task schedule and the work schedule to create the work schedule indicating the work schedule of each of the plurality of workers and the task schedule indicating the schedule for executing each of the plurality of tasks; A creation device that runs.

2. In the acquisition step, a target condition is further acquired, which defines at least one of a desire for vacation or work and a number of consecutive vacations; The creation device according to claim 1 , wherein in the selection step, the workers and the jobs are selected so as to satisfy the objective conditions.

3. In the selection step, if the deadline for any of the tasks has passed, the task whose deadline has passed is selected in the second period after the deadline; 3. The creation device according to claim 1, wherein in the allocating step, the combination including the task whose deadline has passed is allocated to the task schedule and the work schedule.

4. The creation device according to claim 1 or 2, wherein, in the selection step, if the deadline for any of the tasks has passed, the number of the plurality of workers is increased, and the selection step and the allocation step are performed using the increased number of the plurality of workers.

5. 3 . The creating device according to claim 1 , wherein, in the selection step, if the deadline for any of the tasks has passed, a part of the constraints is relaxed or ignored, and the selection step and the allocation step are executed.

6. On the computer, An acquisition step of acquiring a plurality of tasks, deadlines for each of the plurality of tasks, a plurality of workers, qualifications indicating the tasks that each of the plurality of workers can handle, and work-related constraints; a selection step of selecting a combination of the worker to work and the task to be performed by the worker for each second period shorter than the first period during a first period for which a work schedule and a task schedule are created, the selection step being such that the worker who satisfies the constraints and has the qualifications corresponding to the task to be performed is selected as the worker to work, and the task to be performed is selected so as to be completed by the deadline; an allocation step of allocating the selected combination to the task schedule and the work schedule to create the work schedule indicating the work schedule of each of the plurality of workers and the task schedule indicating the schedule for executing each of the plurality of tasks; How to create a program that will execute the command.

7. A program for causing a computer to execute the creation method according to claim 6.

8. A storage medium storing the program according to claim 7.

Citation Information

Patent Citations

  • Work table generation supporting system

    JP2000099569A

  • Roster creation system

    JP2006236173A

  • Operation planning support system and operation planning support method

    JP2014241020A

  • Construction support system

    JP2018045341A

  • Processing apparatus, creation method, program, and storage medium

    JP2022063687A