Project balance management system, project balance management method, and project balance management program

The system addresses the lack of future cost registration by enabling detailed cost analysis and forecasting, enhancing project management through accurate monthly and quarterly expenditure tracking.

JP2024141989AActive Publication Date: 2024-10-10OBIC CO LTD

Patent Information

Application Number
JP2023053912
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-10
Estimated Expiration
2043-03-29

AI Technical Summary

Technical Problem

Existing systems fail to register actual and estimated costs for future months, limiting the ability to analyze project income and expenditure effectively.

Method used

A project income and expenditure management system that includes a storage unit for project information, a control unit, and functions for registering and updating planned and actual costs, allowing for detailed analysis and forecasting of costs by month, quarter, or half-year.

Benefits of technology

Enables accurate forecasting and analysis of income and expenditure by month, identifying discrepancies, and improving future planning through detailed cost management, facilitating quick business decision-making.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024141989000001_ABST
    Figure 2024141989000001_ABST
Patent Text Reader

Abstract

To provide a project balance management system capable of analyzing by managing the actual and estimated costs of each project every month and storing the estimated cost for each processing month, a project balance management method, and a project balance management program.SOLUTION: The project balance management system is configured to register a piece of information on the planned cost of a project while linking the estimated monthly actual amount, estimated annual actual amount, and estimated actual amount for the next fiscal year and after for each cost item during the order period based on project information, obtain project cost details with actual monthly costs for each cost item, update the project information planned cost based on the project cost breakdown, and based on the information on the project cost, obtain a piece of information on the project analytics for a predetermined time unit.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a project balance management device, a project balance management method, and a project balance management program. [Background technology]

[0002] Patent Document 1 discloses a configuration in which, when an update of a contract amount as a monthly process is detected, the cumulative progress sales amount and the single-period progress sales amount are recalculated based on the contract amount after taking into account increases or decreases. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2022-182779 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, the invention described in the above Patent Document 1 had a problem in that it was not possible to register actual costs and expected costs to be incurred in future months for each processing year and month.

[0005] The present invention has been made in consideration of the above problems, and has an object to provide a project balance management device, a project balance management method, and a project balance management program that manage the actual costs and estimated costs of each project as a monthly process and enable analysis by retaining the estimated costs for each processing month. [Means for solving the problem]

[0006] In order to solve the above-mentioned problems and achieve the object, the project balance management device of the present invention is a project balance management device equipped with a memory unit and a control unit, the memory unit comprises a project storage means for storing project information including contract information setting an order period for the project and budget information setting a budget amount for each cost item of the project, and the control unit comprises: a project registration means for registering project planned cost information that is set by linking the monthly expected actual amount, the annual expected actual amount, and the expected actual amount for the next year and thereafter for each cost item during the order period based on the project information, a cost detail acquisition means for acquiring project cost details that set the monthly actual amount for each cost item, an update means for updating the project planned cost information based on the project cost details, and an analysis acquisition means for acquiring project analysis information for a specified period based on the project planned cost information.

[0007] In addition, in the project income and expenditure management device of the present invention, the analysis and acquisition means acquires the project analysis information based on the project planned cost information, which sets a specified period actual amount obtained by summing up the monthly actual amount for each cost item for each specified period.

[0008] In addition, in the project income and expenditure management device of the present invention, the analysis and acquisition means acquires the project analysis information based on the projected cost information, the projected actual amount to be incurred for each specified period, the projected actual amount for the following year and thereafter, and the difference between the projected actual amount to be incurred for the given year and the projected actual amount for the following year and thereafter.

[0009] In addition, in the project income and expenditure management device of the present invention, the analysis acquisition means is characterized in that when the cost item and the specified period are set on the analysis screen, it acquires the project analysis information of the cost item for the specified period based on the project planned cost information.

[0010] In the project balance management device according to the present invention, the analysis acquisition means further displays the project analysis information.

[0011] In the project balance management apparatus according to the present invention, the predetermined period is a month, a quarter, a trimester, or a half year.

[0012] In addition, in the project income and expenditure management device of the present invention, the update means replaces the monthly estimated actual amount for each cost item set in the project planned cost information with the monthly actual amount based on the project cost details, and updates the annual estimated actual amount and the estimated actual amount for the next year and thereafter set in the project planned cost information based on the difference between the monthly estimated actual amount and the monthly actual amount.

[0013] Furthermore, a project balance management method according to the present invention is a project balance management method to be executed by a project balance management device having a memory unit and a control unit, the memory unit having a project storage means for storing project information including contract information setting an order period for a project and budget information setting a budget amount for each cost item of the project, and the control unit includes the following steps executed in the control unit: a project registration step for registering project planned cost information that links together a monthly estimated actual amount, an annual estimated actual amount, and an estimated actual amount for the next year and thereafter for each cost item during the order period based on the project information; a cost detail acquisition step for acquiring project cost details in which a monthly actual amount for each cost item is set; an update step for updating the project planned cost information based on the project cost details; and an analysis acquisition step for acquiring project analysis information for a specified period based on the project planned cost information.

[0014] Furthermore, the project balance management program of the present invention is a project balance management program to be executed by a project balance management device having a memory unit and a control unit, the memory unit having a project storage means for storing project information including contract information setting an order period for the project and budget information setting a budget amount for each cost item of the project, and the control unit is caused to execute the following steps in the control unit: a project registration step for registering project planned cost information that links together the monthly estimated actual amount, the annual estimated actual amount, and the estimated actual amount for the next year and thereafter for each cost item during the order period based on the project information; a cost detail acquisition step for acquiring project cost details that set the monthly actual amount for each cost item; an update step for updating the project planned cost information based on the project cost details; and an analysis acquisition step for acquiring project analysis information for a specified period based on the project planned cost information. Effect of the Invention

[0015] According to the present invention, it is possible to grasp the income and expenditure for each fiscal year, and to compare the forecast and the cost on a quarterly or monthly basis. In addition, according to the present invention, it is possible to predict the income and expenditure for each fiscal year. In addition, according to the present invention, it is possible to identify when the expected cost is changed by holding the future expected cost for each processing month. In addition, according to the present invention, it is possible to grasp when the deviation between the plan and the actual result occurred by managing the cost incurred for each monthly processing and the expected cost, and it is possible to analyze the cause of the deviation and to refine the future plan. In addition, according to the present invention, it is possible to calculate the forecast at the end of the current fiscal year. In addition, according to the present invention, it is possible to quickly confirm information necessary for management judgment by the income and expenditure forecast based on the expected cost. In addition, according to the present invention, it is possible to grasp the change in the expected cost for each processing month, which makes it possible to visualize the cause and take measures quickly, and it is possible to contribute to the refinement of the income and expenditure forecast by trend analysis. In addition, the present invention has the effect of improving the accuracy of income and expenditure forecasts by making it possible to grasp income and expenditure for each fiscal year. In addition, the present invention has the effect of registering not only the final income and expenditure but also the estimated cost for grasping income and expenditure for each fiscal year, switching between actual and estimated results based on the base date, and making it possible to refer to data using an analysis screen. [Brief description of the drawings]

[0016] [Figure 1] FIG. 1 is a block diagram showing an example of the configuration of a project balance management device according to this embodiment. [Diagram 2] FIG. 2 is a flowchart showing an example of the process of the project balance management device in this embodiment. [Diagram 3] FIG. 3 is a diagram showing an example of a project balance management process in this embodiment. [Figure 4] FIG. 4 is a diagram showing an example of a project balance management process in this embodiment. [Diagram 5]FIG. 5 is a diagram showing an example of a project balance management process in this embodiment. [Figure 6] FIG. 6 is a diagram showing an example of a project balance management process in this embodiment. [Figure 7] FIG. 7 is a diagram showing an example of the project balance management process in this embodiment. [Figure 8] FIG. 8 is a diagram showing an example of the project balance management process in this embodiment. [Figure 9] FIG. 9 is a diagram showing an example of the project balance management process in this embodiment. [Figure 10] FIG. 10 is a diagram showing an example of the project balance management process in this embodiment. [Figure 11] FIG. 11 is a diagram showing an example of the project balance management process in this embodiment. [Figure 12] FIG. 12 is a diagram showing an example of the project balance management process in this embodiment. [Figure 13] FIG. 13 is a diagram showing an example of the project balance management process in this embodiment. [Figure 14] FIG. 14 is a diagram showing an example of the project balance management process in this embodiment. [Figure 15] FIG. 15 is a diagram showing an example of a cost-based budget / actual variance analysis in this embodiment. [Figure 16] FIG. 16 is a diagram showing an example of a cost-based budget / actual variance analysis in this embodiment. [Figure 17] FIG. 17 is a diagram showing an example of a cost-based budget / actual variance analysis in this embodiment. [Figure 18] FIG. 18 is a diagram showing an example of a cost-based budget / actual variance analysis in this embodiment. [Figure 19] FIG. 19 is a diagram showing an example of the cost-by-year balance analysis in this embodiment. [Figure 20] FIG. 20 is a diagram showing an example of the annual balance analysis by cost in this embodiment. [Figure 21]FIG. 21 is a diagram showing an example of the annual balance analysis by cost in this embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0017] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described in detail with reference to the drawings. However, the present invention is not limited to the embodiment.

[0018] [1. Overview] First, an overview of the present invention will be described.

[0019] Conventionally, systems used in the construction industry and other fields were designed to capture final income and expenditures, and forecasts of income and expenditures for each fiscal year were often made outside the system.

[0020] Therefore, in this embodiment, a mechanism is provided for automatically calculating the estimated cost at the end of the current fiscal year by making it possible to register estimated costs for each future month in the final forecast.

[0021] Here, in this embodiment, basic information about the project is registered as the project basic information input, the order amount of each construction is registered as the contract information input, the budget for each project cost category such as material cost, subcontract cost, labor cost, and expenses is registered as the budget input, the actual results linked to the project number, order number, and order line number registered in the project basic information input and contract information input are registered as the registration of each cost (purchase input, project cost recording input, etc.), and the estimated final amount is registered as the final forecast input. Note that in the final forecast input program in this embodiment, the cost of past months (including the current month) is automatically set from the actual cost based on the current monthly value (only displayed on the screen, cannot be modified), and the cost of future months is set as the initial value registered in the monthly processing of the previous month.

[0022] [2. Configuration] An example of the configuration of a project balance management apparatus 100 according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing an example of the configuration of the project balance management apparatus 100 according to this embodiment.

[0023] 1, the project balance management apparatus 100 is a commercially available desktop personal computer. Note that the project balance management apparatus 100 is not limited to a stationary information processing device such as a desktop personal computer, and may be a portable information processing device such as a commercially available notebook personal computer, a PDA (Personal Digital Assistant), a smartphone, or a tablet personal computer.

[0024] The project balance management apparatus 100 includes a control unit 102, a communication interface unit 104, a storage unit 106, and an input / output interface unit 108. The units included in the project balance management apparatus 100 are connected to each other so as to be able to communicate with each other via any communication path.

[0025] The communication interface unit 104 communicably connects the project balance management apparatus 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via the communication line. Here, the network 300 has a function of connecting the project balance management apparatus 100 and the server 200 so that they can communicate with each other, and is, for example, the Internet or a LAN (Local Area Network).

[0026] An input device 112 and an output device 114 are connected to the input / output interface unit 108. The output device 114 may be a monitor (including a touch panel), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that cooperates with a mouse to realize a pointing device function. In the following, the output device 114 may be referred to as the monitor 114 or the printer 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112.

[0027] The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs for cooperating with an OS (Operating System) to give instructions to a CPU (Central Processing Unit) to perform various processes. For example, memory devices such as RAM (Random Access Memory) and ROM (Read Only Memory), fixed disk devices such as hard disks, flexible disks, and optical disks can be used as the storage unit 106. The storage unit 106 includes a basic information management master 106a, a monthly period master 106b, and a project database 106c.

[0028] The basic information management master 106a is a master in which the accounting year, the start month and year, and the accounting year and month are set.

[0029] The monthly period master 106b is a master that associates the start and end of each month.

[0030] The project database 106c stores project information of the project. Here, the project database 106c may store project information including contract information that sets the order period of the project, and budget information that sets the budget amount for each cost item of the project. The project information may also include project planned cost information, project analysis information, and the like.

[0031] The control unit 102 is a CPU or the like that performs overall control of the project balance management apparatus 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, required data, and the like, and executes various information processing based on these stored programs. The control unit 102 conceptually includes a project registration unit 102a, a cost detail acquisition unit 102b, an update unit 102c, and an analysis acquisition unit 102d.

[0032] The project registration unit 102a registers project information. Here, the project registration unit 102a may register project planned cost information. In addition, the project registration unit 102a may register project planned cost information that is set by linking the monthly estimated actual amount, the annual estimated actual amount, and the estimated actual amount for the next year and thereafter for each cost item during the order acceptance period based on the project information.

[0033] The cost detail acquiring unit 102b acquires the project cost details in which the monthly actual amount is set. Here, the cost detail acquiring unit 102b may acquire the project cost details in which the monthly actual amount is set for each cost item.

[0034] The update unit 102c updates the project planned cost information. Here, the update unit 102c may update the project planned cost information based on the project cost details. In addition, the update unit 102c may replace the monthly estimated actual amount for each cost item set in the project planned cost information with the monthly actual amount based on the project cost details, and update the annual estimated actual amount and the estimated actual amount for the next year and thereafter set in the project planned cost information based on the difference between the monthly estimated actual amount and the monthly actual amount.

[0035] The analysis acquisition unit 102d acquires project analysis information. Here, the analysis acquisition unit 102d may acquire project analysis information for a predetermined period based on the project planned cost information. The analysis acquisition unit 102d may acquire project analysis information in which a predetermined period actual amount is set by summing up the monthly actual amount for each cost item for each predetermined period based on the project planned cost information. The analysis acquisition unit 102d may acquire project analysis information in which an annual estimated actual amount for each predetermined period, an estimated actual amount for the next year and thereafter, and a difference between the estimated actual amount for the current year and the estimated actual amount for the next year and thereafter are set based on the project planned cost information. When a cost item and a predetermined period are set on the analysis screen, the analysis acquisition unit 102d may acquire project analysis information for the cost item for the predetermined period based on the project planned cost information. The analysis acquisition unit 102d may display the project analysis information. Here, the predetermined period may be a month, a quarter, a trimester, or a half year.

[0036] [3. Specific Examples] A specific example of this embodiment will be described with reference to FIGS.

[0037] [Project Income and Expenditure Management Processing] An example of a project balance management process in this embodiment will now be described with reference to Fig. 2. Fig. 2 is a flowchart showing an example of the process of the project balance management apparatus 100 in this embodiment.

[0038] As shown in FIG. 2, the project registration unit 102a registers project planned cost information, which is set by linking the monthly expected actual amount, the annual expected actual amount, and the expected actual amount for the next fiscal year and thereafter for each cost item during the order period, in the project database 106c based on the project information stored in the project database 106c (step SA-1).

[0039] Then, the cost detail acquiring unit 102b acquires, as a monthly process, project cost details in which the monthly actual amount for each cost item is set (step SA-2).

[0040] Then, the updating unit 102c replaces the monthly estimated actual amount for each cost item set in the project planned cost information stored in the project database 106c with the monthly actual amount based on the project cost details, and updates the annual estimated actual amount and the estimated actual amounts for the next year and thereafter set in the project planned cost information stored in the project database 106c based on the difference between the monthly estimated actual amount and the monthly actual amount (step SA-3).

[0041] Then, the analysis acquisition unit 102d determines whether or not an analysis instruction specifying a cost item and a predetermined period has been set by the user via the input device 112 on the analysis screen displayed on the output device 114 (step SA-4).

[0042] If the analysis acquisition unit 102d determines that an analysis instruction has not been set on the analysis screen (step SA-4: No), the analysis acquisition unit 102d shifts the process to step SA-2.

[0043] On the other hand, if the analysis acquisition unit 102d determines that an analysis instruction has been set on the analysis screen (step SA-4: Yes), it shifts the process to step SA-5.

[0044] Then, the analysis acquisition unit 102d acquires project analysis information based on the project planned cost information, which includes the actual amount expected to be incurred in the current year for each specified period, the actual amount expected to be incurred in the following year and thereafter, and the difference between the actual amount expected to be incurred in the current year and the actual amount expected to be incurred in the following year and thereafter (step SA-5).

[0045] Then, the analysis and acquisition unit 102d determines whether the current time is the final month of the order period based on the monthly period master 106b and the project information (step SA-6).

[0046] If the analysis and acquisition unit 102d determines that the current time is not the final month of the order period (step SA-6: No), it shifts the process to step SA-2.

[0047] If the analysis and acquisition unit 102d determines that the current time is the final month of the order period (step SA-6: Yes), the analysis and acquisition unit 102d ends the process.

[0048] An example of the project balance management process in this embodiment will now be described with reference to Fig. 3 to Fig. 14. Fig. 3 to Fig. 14 are diagrams showing an example of the project balance management process in this embodiment.

[0049] As shown in FIG. 3, in this embodiment, when a project is ordered to be concluded on April 1, 2022 and to be sold on March 31, 2024, the basic information management master 106a and the monthly period master 106b are referenced. Here, the fiscal year set in the basic information management master 106a in this embodiment holds the current fiscal year and is updated at the time of completion of monthly processing at the end of the current fiscal year (monthly processing in March 2023), the start year and month hold the start year and month of the current fiscal year and is updated at the time of completion of monthly processing at the end of the current fiscal year (monthly processing in March 2023), and the fiscal year and month hold the current processing year and month and may be updated at the time of monthly processing of the current month (monthly processing in April 2022). In addition, the month numbers set in the monthly period master 106b in this embodiment are numbered 1 to 12 for each month of each year (numbered so that the start of the period is 1 and the end of the period is 12).

[0050] 4, in this embodiment, when the contract is concluded in April 2022, project basic information is set, contract information for the project order is set, and budget information for the project budget is set, thereby setting the project planned cost information. Here, in the project planned cost information in this embodiment, for yyyyMM01 to yyyyMM12, the current year (2022) is obtained from the accounting year set in the basic information management master 106a, the monthly period master 106b is referenced from the accounting year set in the basic information management master 106a, the item names (yyyyMM01⇒202204, yyyyMM02⇒202205) are set in the order of month numbers, and the expected occurrence from April 2022 onwards is registered as 100,000 yen as the expected landing input. In addition, in the project planned cost information in this embodiment, for the amount incurred in the previous year or earlier, the current year (2022) is obtained from the fiscal year of the basic information management master 106a, the fiscal year and month of the last fiscal year (202203) is obtained from the monthly period master 106b, the project number, order number, and order line number are obtained from the budget information, the fiscal year and month (before the fiscal year and month of the last fiscal year) is obtained, and the amount is aggregated for each cost item category. In addition, in the project planned cost information in this embodiment, for the cost of the past month (including the current month), the processing year and month (202204) is obtained from the fiscal year and month set in the basic information management master 106a, the project number, order number, order line number, and fiscal year and month are set from the cost details, the cost for each cost item category is aggregated and set, the cost before the current month is locked and cannot be changed, the input result of the previous month is set for the future month cost, and the project budget is referenced for the final landing forecast.

[0051] As shown in FIG. 5, in this embodiment, when the cost is recorded in April 2022, a project cost detail is obtained by registering each cost item (purchase input, project cost recording input, etc.), and the cost incurred for each cost item for the current month and the estimated cost for each cost item for the future month are initially displayed based on the project cost detail, and the project planned cost information is updated. Here, in the project planned cost information in this embodiment, the estimated actual annual occurrence is set as the cumulative total (cumulative total of yyyyMM01 to yyyyMM12) of the actual amount incurred up to the current term and the estimated amount (input value) from the next month onwards, and the estimated actual amount from the next fiscal year onwards is set as the estimated amount obtained by subtracting the amount incurred before the previous fiscal year and the estimated actual annual occurrence from the final landing forecast. In the project planned cost information in this embodiment, the accounting year and month set in the basic information management master 106a is set, and the base months 1 to 12 are set to yyyyMM01 to yyyyMM12, which are initially displayed.

[0052] Then, as shown in FIG. 6, in this embodiment, when costs are recorded for May 2022, the basic information management master 106a is referenced, and each cost registration obtains project cost details that set the actual costs incurred for each cost item for May 2022.

[0053] As shown in Fig. 7, in this embodiment, the cost incurred for each cost item in the current month and the estimated cost for each cost item in the future month are initially displayed based on the project cost details, and the project planned cost information is updated. Here, in the project planned cost information in this embodiment, the estimated cost from June 2022 onwards is registered as 100,000 yen as the final forecast input. In addition, in the project planned cost information in this embodiment, the accounting year and month are included in the key, so the updated information from the next month onwards can be added and updated without deleting the information from the current month onwards.

[0054] As shown in Figure 8, in this embodiment, when recording costs from April 2022 to March 2023, the basic information management master 106a is referenced, and by registering the costs of each incurred cost, project cost details are obtained that include the actual costs incurred for each cost item from April 2022 to March 2023.

[0055] As shown in FIG. 9 to FIG. 12, in this embodiment, the project planned cost information is updated and set based on the project cost details for each month.

[0056] As shown in FIG. 13, in this embodiment, the basic information management master 106a is referenced, and when costs are recorded in April 2023, the new fiscal year, project cost details are obtained by registering each cost, which includes the actual costs incurred for each cost item for April 2023.

[0057] As shown in Fig. 14, in this embodiment, the amount incurred in the previous year or earlier, the cost incurred for each cost item in the current month, and the estimated cost for each cost item in the future month are initially displayed based on the project cost details, and the project planned cost information is updated. Here, in the project planned cost information in this embodiment, the amount incurred in the previous year or earlier is aggregated from the project cost details. Also, in the project planned cost information in this embodiment, the expected cost from May 2023 onwards is registered as 100,000 yen as the expected final cost input.

[0058] Moreover, an example of a cost-based budget / actual variance analysis in this embodiment will be described with reference to Figures 15 to 18. Figures 15 to 18 are diagrams showing an example of a cost-based budget / actual variance analysis in this embodiment.

[0059] In this embodiment, as shown in FIG. 15, when the user specifies the project number, order number, order line number, and cost item category on the analysis screen and selects the analysis method, as shown in FIG. 16, the project planned cost from April 2022 to March 2023 is acquired as the analysis source data from the project number, order number, order line number, and cost item category specified on the analysis screen, and the acquired results are re-extracted by analysis method. As shown in FIG. 17, the acquired results are output on a monthly basis without being re-extracted, and as shown in FIG. 18, the results at the end of the quarter are re-acquired from the acquired results on a quarterly basis (the results in which the monthly period master 106b. month number is "multiple of 3" are acquired) and output. In this way, in this embodiment, the results are output using the analysis method (by month, by quarter) that specifies the base months 1 to 12 set in the project planned cost information, so that the expected cost for each processing year and month is managed, making it possible to grasp when a deviation from the plan occurred, and it is possible to grasp the deviation between the forecast and the actual results, and it is possible to look back on when the plan should have been reviewed.

[0060] Moreover, an example of the cost-by-year balance analysis in this embodiment will be described with reference to Fig. 19 to Fig. 21. Fig. 19 to Fig. 21 are diagrams showing an example of the cost-by-year balance analysis in this embodiment.

[0061] In this embodiment, as shown in FIG. 19, when the user specifies the project number, order number, order line number, and cost account category on the analysis screen and selects an analysis method, as shown in FIG. 20, the project planned cost from April 2022 to March 2023 is obtained as the source data for analysis from the project number, order number, order line number, and cost account category specified on the analysis screen, and the obtained results are re-extracted by analysis method. As shown in FIG. 21, the order date and scheduled completion date are referenced to the contract information of the project order, and the "difference from the following year onwards = expected actual results for the year - expected actual results for the following year onwards" is calculated, and the obtained results are output on a monthly basis without being re-extracted, and on a quarterly basis, the end-of-quarter results are re-obtained from the obtained results (the results in the monthly period master 106b where the month number is a "multiple of 3" are obtained) and output. In this manner, in this embodiment, the results of the expected actual costs for the current year and the expected actual costs for the following year and beyond, set in the project planned cost information, are output using the specified analysis method (by month or quarter), making it possible to analyze the balance between the current year and the following year and to check the point at which the balance fluctuated significantly, and in the analysis of labor costs, it becomes possible to consider assignments based on the balance results.

[0062] [4. Contribution to the United Nations-led Sustainable Development Goals (SDGs)] This embodiment can contribute to improving business efficiency and promoting appropriate management decisions by companies, thereby contributing to goals 8 and 9 of the SDGs.

[0063] Furthermore, this embodiment can contribute to reducing waste and promoting paperless and electronic systems, thereby contributing to the achievement of goals 12, 13, and 15 of the SDGs.

[0064] Furthermore, this embodiment can contribute to strengthening control and governance, making it possible to contribute to Goal 16 of the SDGs.

[0065] 5. Other embodiments The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.

[0066] For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using known methods.

[0067] In addition, the processing procedures, control procedures, specific names, registered data for each process, information including parameters such as search conditions, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.

[0068] Moreover, with regard to the project balance management apparatus 100, each of the components shown in the figures is a functional concept, and it is not necessary that the components are physically configured as shown in the figures.

[0069] For example, the processing functions of the project balance management apparatus 100, particularly the processing functions performed by the control unit 102, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded in a non-transient computer-readable recording medium including programmed instructions for causing an information processing device to execute the processes described in this embodiment, and is mechanically read by the project balance management apparatus 100 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive). This computer program is executed by being loaded into a RAM, and constitutes a control unit in cooperation with the CPU.

[0070] In addition, this computer program may be stored in an application program server connected to the project balance management apparatus 100 via any network, and it is also possible to download all or a part of it as necessary.

[0071] In addition, the program for executing the process described in this embodiment may be stored in a non-transient computer-readable recording medium, or may be configured as a program product. Here, the "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.

[0072] Moreover, a "program" is a data processing method written in any language or description method, and may be in any form, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a configuration that is distributed as a plurality of modules or libraries, and a program that achieves its function by cooperating with a separate program, such as an OS. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in this embodiment, as well as the installation procedure after reading, may use well-known configurations and procedures.

[0073] The various databases etc. stored in the memory unit 106 are storage means such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files etc. used for various processes and providing websites.

[0074] The project balance management apparatus 100 may be configured as an information processing device such as a known personal computer or a workstation, or may be configured as the information processing device to which any peripheral device is connected. The project balance management apparatus 100 may be realized by installing software (including programs or data) that causes the device to realize the processing described in this embodiment.

[0075] Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the drawings, and all or part of them can be functionally or physically distributed and integrated in any unit according to various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively. [Industrial Applicability]

[0076] The present invention is useful in industries such as the IT industry, the equipment industry with a large number of projects, and the construction industry which predicts income and expenditure based on final results. [Explanation of symbols]

[0077] 100 Project Income and Expenditure Management Device 102 Control section 102a Project Registration Department 102b Cost Detail Acquisition Department 102c update section 102d Analysis and acquisition department 104 Communication interface section 106 Storage section 106a Basic Information Management Master 106b Monthly Period Master 106c Project Database 108 Input / Output Interface Section 112 Input Devices 114 Output Device 200 Servers 300 Network

Claims

1. A project balance management device including a storage unit and a control unit, The storage unit is a project storage means for storing project information including contract information that sets an order period for a project, and budget information that sets a budget amount for each cost item of the project; Equipped with The control unit is a project registration means for registering project planned cost information that is set by linking the estimated monthly actual amount, the estimated annual actual amount, and the estimated actual amount for the next fiscal year and thereafter for each cost item during the order acceptance period based on the project information; a cost detail acquisition means for acquiring project cost details in which the monthly actual amount for each cost item is set; an updating means for updating the project planned cost information based on the project cost details; an analysis and acquisition means for acquiring project analysis information for a predetermined period based on the project planned cost information; A project balance management device comprising:

2. The analysis and acquisition means includes: The project balance management device according to claim 1, characterized in that the project analysis information is acquired based on the project planned cost information, and includes a specified period actual amount set by summing up the monthly actual amount for each cost item for each specified period.

3. The analysis and acquisition means includes:

2. A project income and expenditure management device according to claim 1, characterized in that, based on the project planned cost information, the project analysis information is obtained in which the expected actual amount to be incurred for the year, the expected actual amount for the next year and thereafter, and the difference between the expected actual amount to be incurred for the current year and the expected actual amount for the next year and thereafter are set for each of the specified periods.

4. The analysis and acquisition means includes: A project balance management device as described in claim 1, characterized in that when the cost item and the specified period are set on an analysis screen, the project analysis information of the cost item for the specified period unit is obtained based on the project planned cost information.

5. The analysis and acquisition means includes:

5. A project balance management apparatus according to claim 1, further comprising: a display unit that displays the project analysis information.

6. The predetermined period is:

5. The project balance management device according to claim 1, wherein the time period is one month, one quarter, one trimester, or one half year.

7. The update means includes:

5. A project income and expenditure management device as described in any one of claims 1 to 4, characterized in that the monthly estimated actual amount for each cost item set in the project planned cost information is replaced with the monthly actual amount based on the project cost details, and the annual estimated actual amount and the estimated actual amount for the next year and thereafter set in the project planned cost information are updated based on the difference between the monthly estimated actual amount and the monthly actual amount.

8. A project balance management method to be executed by a project balance management device having a storage unit and a control unit, The storage unit is a project storage means for storing project information including contract information that sets an order period for a project, and budget information that sets a budget amount for each cost item of the project; Equipped with Executed in the control unit: a project registration step of registering project planned cost information that is set by linking the estimated monthly actual amount, estimated annual actual amount, and estimated actual amount for the next fiscal year and thereafter for each cost item during the order acceptance period based on the project information; A cost detail acquisition step of acquiring project cost details in which the monthly actual amount for each cost item is set; an updating step of updating the project planned cost information based on the project cost details; An analysis and acquisition step of acquiring project analysis information for a predetermined period based on the project planned cost information; A project balance management method comprising:

9. A project balance management program to be executed by a project balance management device having a storage unit and a control unit, The storage unit is a project storage means for storing project information including contract information that sets an order period for a project, and budget information that sets a budget amount for each cost item of the project; Equipped with In the control unit, a project registration step of registering project planned cost information that is set by linking the estimated monthly actual amount, estimated annual actual amount, and estimated actual amount for the next fiscal year and thereafter for each cost item during the order acceptance period based on the project information; A cost detail acquisition step of acquiring project cost details in which the monthly actual amount for each cost item is set; an updating step of updating the project planned cost information based on the project cost details; An analysis and acquisition step of acquiring project analysis information for a predetermined period based on the project planned cost information; A project income and expenditure management program for carrying out the project.

Citation Information

Patent Citations

  • Terminal equipment, system and method for managing progress and recording medium

    JP2001014402A

  • Project Planning System

    JP7487147B2

  • Grade management device, grade management method, and grade management program

    JP7492399B2

  • Information processing device, information processing method, and program

    JP2022182779A

Cited By

  • Business support device, business support method, and business support program

    JP2026158309A