Power management device
The power management device addresses fluctuations in VPP systems by maintaining a reference value during power transitions, reducing system burden through controlled speed adjustments.
Patent Information
- Application Number
- JP2023085475
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-24
- Publication Date
- 2024-12-05
- Estimated Expiration
- 2043-05-24
AI Technical Summary
In VPP systems, fluctuations in renewable energy generation cause demand and supply command values to deviate from expected standards, leading to periods of high burden on energy resources.
A power management device that includes a processor to determine and maintain a reference value during transitions in power supply and demand, allowing the system to operate within this value for extended periods, thereby reducing burden.
The device extends the period during which the system adjusts supply and demand with minimal burden by controlling transitions to and from the reference value at maximum controllable speeds.
Smart Images

Figure 2024168634000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a power management device, and more particularly to a power management device that manages the adjustment capacity of power provided by a trading company to an electricity transmission and distribution company. [Background technology]
[0002] In recent years, a supply and demand adjustment market has been established, which is a market where trading companies such as aggregators procure the adjustment power of the electricity supplied to general electricity transmission and distribution companies. VPPs (Virtual Power Plants) can be utilized in this supply and demand adjustment market. A VPP is a system in which the owner or a third party such as an aggregator controls (including reverse power flow) energy resources such as demand equipment, storage equipment or power generation equipment on the consumer side, and energy resources such as power generation equipment or storage equipment directly connected to the power grid, thereby providing functions equivalent to those of a power plant (for example, see Patent Document 1).
[0003] In a VPP, power supply and demand can be adjusted using Demand Response (DR). DR is when the owner of the energy resource on the consumer side or a third party controls the energy resource to change the power supply and demand pattern. Depending on the supply and demand control pattern, DR is mainly divided into downward DR, which reduces demand and increases supply, and upward DR, which increases demand and reduces supply. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2022-113460 A Summary of the Invention [Problem to be solved by the invention]
[0005] In supply and demand adjustment in a VPP, fluctuations in the amount of power generated by renewable energy (hereinafter also referred to as "RE") may cause the supply and demand command value to fluctuate, resulting in deviation from the reference value expected for that time period. The reference value is the value of the power supply and demand adjustment capability when DR is not performed. For this reason, the reference value is a value that places a low burden on energy resources. When the command value fluctuates from the first command value to the second command value across the reference value, if the command value passes through the reference value in an instant, the period of low burden on energy resources will be short.
[0006] This disclosure has been made to solve the above-mentioned problems, and its purpose is to provide a power management device that can extend as long as possible the period during which the burden on the system that adjusts the supply and demand of electricity is low. [Means for solving the problem]
[0007] The power management device according to the present disclosure is a power management device that manages the adjustment capacity of power provided by a trading company to a power transmission and distribution company. The power management device is capable of controlling an adjustment system for power supply and demand, and includes a memory that stores a predetermined program, and a processor that executes the predetermined program. By executing the predetermined program, the processor controls the adjustment system so that, when a command value for power supply and demand to the adjustment system transitions from a first command value before the change to a second command value after the change, the adjustment system goes through a period during which the reference value is maintained if the reference value for power supply and demand set by the adjustment system is crossed.
[0008] According to this configuration, when the command value for the power supply and demand to the adjustment system transitions from the first command value to the second command value, if the command value crosses the reference value, a period during which the reference value is maintained can be passed. As a result, it is possible to provide a power management device that can extend as long as possible the period during which the burden on the system for adjusting the power supply and demand is low.
[0009] The processor may execute a predetermined program to control the adjustment system with the goal of changing linearly from the first command value to the second command value when the command value for power supply and demand to the adjustment system transitions from a first command value before the change to a second command value after the change, if the reference value for power supply and demand by the adjustment system is not crossed.
[0010] According to this configuration, the first command value can be changed to the second command value through easy control.
[0011] When controlling the adjustment system to go through a period in which the reference value is maintained, the processor may control the rate at which the adjustment system changes the supply and demand of power during the period in which the reference value transitions from the first command value to the reference value and during the period in which the reference value transitions to the second command value to be the maximum controllable rate.
[0012] With this configuration, the period during which the burden on the system for adjusting the supply and demand of power is low can be further extended. Effect of the Invention
[0013] According to this disclosure, it is possible to provide a power management device that can extend, as long as possible, the period during which the burden on a system that adjusts the supply and demand of power is low. [Brief description of the drawings]
[0014] [Figure 1] 1 is a block diagram showing an outline of the configuration of a power management system according to an embodiment of the present invention; [Diagram 2] 10 is a flowchart showing the flow of adjustment power-related processing executed by the aggregator server in this embodiment. [Diagram 3] 1 is a diagram showing changes in supply and demand of power exchanged with a power transmission and distribution company in this embodiment. FIG. [Figure 4] 1 is an enlarged view showing changes in supply and demand power exchanged with a power transmission and distribution company in this embodiment before and after a reference value when the reference value is crossed. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0015] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. In the drawings, the same or corresponding parts are designated by the same reference characters and their description will not be repeated.
[0016] Fig. 1 is a block diagram showing an outline of the configuration of a power management system 1 according to this embodiment. With reference to Fig. 1, thick solid lines with arrows indicate the flow of power, and thin solid lines and dashed lines with arrows indicate the flow of data. In the power management system 1, power generated by a power generation company 60 is consigned by a power transmission and distribution company 50 (e.g., a general power transmission and distribution company) to consumers 20 who are retail customers of a retail electricity company 30 (e.g., a regional power company, a new power company).
[0017] The supply and demand adjustment market 40 is a market where the power transmission and distribution business operator 50 procures adjustment power for adjusting supply and demand and frequency. The adjustment power includes primary adjustment power, secondary adjustment power (1) and (2), and tertiary adjustment power (1) and (2). Of these, the secondary adjustment power (2) and tertiary adjustment power (1) are adjustment powers provided by the aggregator 10 or the power generation business operator 60 to the power transmission and distribution business operator 50 in order to deal with forecast errors in the demand plan. The tertiary adjustment power (2) is adjustment power provided by the aggregator 10 or the power generation business operator 60 to the power transmission and distribution business operator 50 in order to deal with forecast errors in renewable energy such as electricity generated by solar power generation or wind power generation. The bids for the tertiary adjustment powers (1) and (2) are submitted to the supply and demand adjustment market 40 by the aggregator 10 or the power generation business operator 60 for a block (e.g., 3 hours) of the target period on the day before the block. The aggregator 10 or the power generation company 60 is obligated to provide the contracted amount of adjustment capacity (ΔkW) of the successful bid in the target block to the power transmission and distribution company 50, based on the reference value of the power demand (kW). The primary adjustment capacity and secondary adjustment capacity (1), (2) have not yet been traded in the supply and demand adjustment market 40. The supply and demand adjustment market and adjustment capacity are explained in detail on the websites of the Ministry of Economy, Trade and Industry and the Electricity Transmission and Distribution Grid Council, among others.
[0018] The power generation company 60 has power generation facilities 610 (for example, nuclear power generation facilities, thermal power generation facilities, hydroelectric power generation facilities, solar power generation facilities, wind power generation facilities, geothermal power generation facilities, etc.) that generate electric power, and a power generation company server 600 that manages the power generation business. The power transmission and distribution company 50 has power transmission and distribution facilities 510 that transmit and distribute electric power, and a power transmission and distribution company server 500 that manages the power transmission and distribution business. The power generation facilities 610 and the power transmission and distribution facilities 510 constitute an electric power system (electricity grid). The supply and demand adjustment market 40 has a supply and demand adjustment market server 400 for managing the supply and demand of electric power. The electricity retailer 30 has a retail electricity company server 300 that manages the retail electricity business.
[0019] The consumer 20 has a DSR 210 including at least one of demand equipment (e.g., electrical appliances, machines, electric vehicles that can be charged or discharged, etc.) which is an energy resource connected below the receiving point, storage equipment (e.g., stationary batteries, electric vehicles that can be charged or discharged, etc.), and power generation equipment (e.g., solar power generation equipment, wind power generation equipment, etc.), and a Home Energy Management System (HEMS) 200 which manages the DSR 210.
[0020] The aggregator 10 includes an aggregator server 100. The aggregator server 100 controls and manages the DSR 210 or DER (Distributed Energy Resources) 310 including at least one of a power generation facility or a power storage facility (for example, a rechargeable electric vehicle, a rechargeable electric vehicle, or a stationary battery) that is an energy resource directly connected to the power grid.
[0021] The aggregator server 100 includes a processor 110, a memory 120, an input unit 130, an output unit 140, an auxiliary storage device 160, and a communication unit 190. The memory 120 includes a random access memory (RAM), a read only memory (ROM), a flash memory, and the like, and stores software such as a program executed by the aggregator server 100 and data to be processed. The auxiliary storage device 160 includes a hard disk drive (HDD), a solid state drive (SSD), a removable media drive, and the like, and supports the memory 120, stores a large amount of data compared to the memory 120, and stores software such as a program executed by the aggregator server 100 and data to be processed. The input unit 130 includes input devices such as a keyboard and a mouse, and transmits information input by a user from the input device to the processor 110. The output unit 140 includes output devices such as a display and a speaker, and outputs information received from the processor 110 to the output device. The communication unit 190 is a device capable of communicating with external devices such as other servers via a communication network 900 such as the Internet, and transmits and receives predetermined information between the external devices. The processor 110 processes data from the input unit 130 or the communication unit 190 or data stored in the memory 120 or the auxiliary storage device 160 according to a program stored in the memory 120 or the auxiliary storage device 160, and outputs the data to the output unit 140 or the communication unit 190, or stores the data in the memory 120 or the auxiliary storage device 160.
[0022] The electricity retailer server 300, the supply and demand balancing market server 400, the electricity transmission and distribution company server 500, and the power generation company server 600 have the same configuration as the aggregator server 100 described above.
[0023] The HEMS 200 can communicate with external devices such as the aggregator server 100, the retail electricity supplier server 300, or the electricity transmission and distribution supplier server 500 via a communication network 900, and controls the supply and demand of electricity at the DSR 210, and acquires the measured amount of electricity from a smart meter that measures the amount of electricity exchanged between the DSR 210 and the power grid.
[0024] The HEMS 200 may have a function of a smart meter. The aggregator server 100 may control or manage the DSR 210 directly or indirectly.
[0025] In supply and demand adjustment in the VPP in such a power management system 1, the supply and demand command value may fluctuate in response to fluctuations in the amount of power generated by renewable energy, and may deviate from the reference value expected for that time period. The reference value is the value of the power supply and demand adjustment ability when DR is not performed. For this reason, the reference value is a value that places a low burden on energy resources. When the command value fluctuates from the first command value to the second command value across the reference value, if the command value passes through the reference value in an instant, the period of low burden on the energy resources will be short.
[0026] Therefore, when the command value for power supply and demand to DER310 or DSR210 transitions from a first command value before the change to a second command value after the change, and crosses the previously declared reference value for power supply and demand by DER310 or DSR210, the processor 110 of the aggregator server 100 controls DER310 or DSR210 so that a period of time during which the reference value is maintained is passed.
[0027] This makes it possible to pass a period during which the reference value is maintained when the command value for the power supply and demand to the DER 310 or the DSR 210 transitions from the first command value to the second command value and crosses the reference value. As a result, it is possible to lengthen as much as possible the period during which the burden on the system that adjusts the power supply and demand is low.
[0028] Fig. 2 is a flowchart showing the flow of adjustment capacity-related processing executed by the aggregator server 100 in this embodiment. Referring to Fig. 2, the processor 110 of the aggregator server 100 judges whether the current time is the bidding timing (step S111). The bidding timing is a specific time such as a predetermined time before the bidding deadline, and in the case of tertiary adjustment capacity (2), since the bidding time is from 12:00 to 14:00 on the previous day, for example, it is 13:00, one hour before the bidding deadline of 14:00.
[0029] When it is determined that the current time has come to the bidding timing (YES in step S111), the processor 110 determines the bid amount and the bid unit price from the possible amount predicted to be available for supply by the DER 310 (or the DSR 210) during the time period for which the bid is being made (step S112). The possible amount is the adjustment capacity of the demand for electricity that is predicted to be able to be suppressed, predicted from the information of the DER 310. The power that is added with a safety margin to this possible amount is set as the tertiary adjustment capacity (2), and the bid amount is determined. The processor 110 then submits a bid amount and bid unit price determined in step S112 to the supply and demand adjustment market server 400 (step S113).
[0030] If it is determined that the current time is not the bidding timing (NO in step S111), or after step S113, the processor 110 determines whether or not the contract result has been notified from the supply and demand adjustment market server 400 (step S121). The contract amount of the tertiary adjustment capacity (2) is determined within the range of the bidding amount. If it is determined that the contract result has been notified (YES in step S121), the contract result is stored in the memory 120 or the auxiliary storage device 160 (step S122).
[0031] If it is determined that the timing has not been that for the contract result to be confirmed (NO in step S121), or after step S122, processor 110 determines whether the current time is the timing for reporting the reference value (step S131). The timing for reporting the reference value is a specific time, such as a predetermined number of minutes before the deadline for reporting the reference value, and in the case of tertiary control capacity (2), since the deadline is one hour before the start of the target period, it is, for example, 30 minutes before the deadline.
[0032] If it is determined that the current time has come to declare the reference value (YES in step S131), the processor 110 declares the demand required for the tertiary adjustment capacity (2) slot (if the DER 310 is an electric vehicle, the charging power for the electric vehicle that must be charged) as a reference value to the supply and demand adjustment market server 400 (step S132).
[0033] If it is determined that the current time is not the timing to declare the reference value (NO in step S131), or after step S132, processor 110 determines whether the current time is the start of the target frame (step S141). If it is determined that the current time is not the start of the target frame (NO in step S141), processor 110 returns the process to be executed to the upper process that called this adjustment power related process.
[0034] On the other hand, if it is determined that the current time is the start of the target frame (YES in step S141), the processor 110 determines whether or not it has received an instruction from the power transmission and distribution company server 500 to change the command value of the adjustment capacity of power supply and demand with the power transmission and distribution company 50, which is the trading partner for the power adjustment capacity based on the agreement result (step S142).
[0035] If it is determined that an instruction to change the command value has been received (YES in step S142), processor 110 determines whether the transition from the command value before the change in the supply and demand power to the command value after the change will cross the reference value declared in step S132 (step S143).
[0036] If it is determined that the transition will not cross the reference value (NO in step S143), the processor 110 starts control of the DER 310 (or the DSR 210) for transitioning to the command value of the supply and demand power exchanged with the power transmission and distribution company 50 (step S144), and returns the process to be executed to the higher-level process that called this adjustment capacity-related process. In this control, the transition to the changed command value needs to be completed within the response period, and the transition may be made at the maximum controllable speed. The maximum controllable speed is specified in advance by experiment, trial, or simulation.
[0037] Fig. 3 is a diagram showing changes in the supply and demand of power exchanged with the power transmission and distribution business operator 50 in this embodiment. Referring to Fig. 3, when there is an instruction to change the command value from the reference value to command value 1, the reference value is not crossed during the transition, so that the supply and demand of power is changed at the maximum controllable speed within the response period.
[0038] Returning to FIG. 2, when it is determined that the reference value will be crossed during the transition (YES in step S143), the processor 110 starts control of the DER 310 (or the DSR 210) for transitioning to the command value of the supply and demand power exchanged with the power transmission and distribution business operator, controls so that the period during which the reference value is maintained is maximized during this transition (step S145), and returns the process to be executed to the upper process that called this adjustment capacity related process. In this control, the transition to the changed command value needs to be completed within the response period. In the transition from the command value before the change to the reference value and in the transition from the reference value to the changed command value, it is desirable to change the supply and demand power at the maximum controllable speed. The maximum controllable speed is specified in advance by experiment, trial, or simulation.
[0039] Referring again to FIG. 3, when there is an instruction to change the command value from command value 1 to command value 2, and when there is an instruction to change the command value from command value 2 to command value 3, the reference value is crossed during the transition, so that the supply and demand power is changed at the maximum controllable speed within the response period, and the period during which the reference value is maintained is controlled to be as long as possible.
[0040] When the reference value is not crossed during the transition, the command value before the change is changed to the command value after the change in a linear function. FIG. 4 is an enlarged view showing the change before and after the reference value when the reference value is crossed in the change in the supply and demand power exchanged with the power transmission and distribution business operator 50 in this embodiment. On the other hand, referring to FIG. 4, when the reference value is crossed during the transition, the command value before the change is changed to the reference value and the reference value after the change are changed in a linear function, and inflection points are provided before and after the reference value. This provides a period during which the reference value is maintained.
[0041] 2, on the other hand, if it is determined that the timing has not come when an instruction to change the command value has been received (NO in step S142), processor 110 determines whether the changed command value has been reached in the transition to the changed command value (step S146). If it is determined that the changed command value has not been reached (NO in step S146), processor 110 continues control to transition to the changed command value (step S147), and returns the process to be executed to the upper process that called this adjustment capacity related process.
[0042] On the other hand, if it is determined that the changed command value has been reached (YES in step S146), the processor 110 switches the control of the DER 310 (or DSR 210) so that the supply and demand power maintains the command value (step S148), and returns the processing to be executed to the higher-level processing that called this adjustment power-related processing.
[0043] [Variations] (1) In the above-described embodiment, as shown in Fig. 1 etc., the DER 310 (or the DSR 210) mainly includes a demand facility such as a chargeable electric vehicle, and may additionally include a power storage facility such as a chargeable and dischargeable electric vehicle. However, the present invention is not limited to this, and the DER 310 (or the DSR 210) may include at least one of a demand facility, a power storage facility, and a power generation facility.
[0044] (2) In the above-described embodiment, as shown in Fig. 2 etc., the aggregator 10 exchanges supply and demand of electric power with the electric power transmission and distribution company 50. However, this is not limited to this, and a trading company such as a power generation company 60, a consumer 20, or an electricity retailer 30, or an individual may exchange supply and demand of electric power with the electric power transmission and distribution company 50.
[0045] (3) In the embodiment described above, as shown in step S145 in Fig. 2, when the supply and demand power is shifted from the command value before the change to the command value after the change, if the reference value is crossed, the period during which the reference value is maintained is controlled to be the longest possible period. However, this is not limited to this, and the period during which the reference value is maintained may be any period as long as it is at least more than 0 and is between 0 and the maximum, but it is preferable that the period be as long as possible.
[0046] (4) In the above-described embodiment, the power management device that manages the adjustment capacity of power provided to the power transmission and distribution company 50 by trading companies such as the aggregator 10 or the power generation company 60 is the aggregator server 100. However, without being limited thereto, the power management device may be another device, for example, the supply and demand adjustment market server 400, the power generation company server 600, the electricity retailer server 300, or the power transmission and distribution company server 500.
[0047] [summary] (1) As shown in Fig. 1, the power management device (e.g., aggregator server 100, power generation company server 600) is a device that manages the adjustment capacity of power provided by trading companies (e.g., aggregator 10, power generation company 60) to the power transmission and distribution company 50. As shown in Fig. 1, the power management device is capable of controlling an adjustment system for power supply and demand (e.g., DER 310, DSR 210), and includes a memory 120 that stores a predetermined program (e.g., a program for adjustment capacity-related processing shown in Fig. 2) and a processor 110 that executes the predetermined program.
[0048] As shown in Figures 2 to 4, by executing a predetermined program, processor 110 controls the adjustment system so that when the command value for power supply and demand to the adjustment system transitions from the first command value before the change to the second command value after the change, and crosses the reference value for power supply and demand by the adjustment system that was previously declared, a period of time during which the reference value is maintained is passed (for example, step S145).
[0049] This makes it possible to have a period during which the reference value is maintained when the command value for the power supply and demand to the adjustment system transitions from the first command value to the second command value, crossing the reference value. As a result, it is possible to lengthen as much as possible the period during which the burden on the system for adjusting the power supply and demand is low.
[0050] (2) As shown in Fig. 2 and Fig. 3, the processor 110 may execute a predetermined program to control the adjustment system so that the command value for power supply and demand to the adjustment system changes linearly from the first command value to the second command value if the command value does not cross the reference value for power supply and demand by the adjustment system declared in advance (for example, step S144). This allows the first command value to be changed to the second command value with easy control.
[0051] (3) As shown in Figures 2 to 4, when processor 110 controls the adjustment system to go through a period in which the reference value is maintained, it may control the rate at which the adjustment system changes the supply and demand of electricity during the period in which the first command value transitions to the reference value and during the period in which the reference value transitions to the second command value to be the maximum controllable rate (for example, step S145).
[0052] This will enable the period during which the burden on the system for regulating power supply and demand to be low to be extended even further.
[0053] The embodiments disclosed herein should be considered to be illustrative and not restrictive in all respects. The scope of the present disclosure is defined by the claims, not by the description of the embodiments described above, and is intended to include all modifications within the meaning and scope of the claims. [Explanation of symbols]
[0054] 1 Power management system, 10 aggregator, 20 consumer, 30 retail electricity supplier, 40 supply and demand adjustment market, 50 power transmission and distribution supplier, 60 power generation supplier, 100 aggregator server, 110 processor, 120 memory, 130 input section, 140 output section, 160 auxiliary storage device, 190 communication section, 200 HEMS, 210 DSR, 300 retail electricity supplier server, 310 DER, 400 supply and demand adjustment market server, 500 power transmission and distribution supplier server, 510 power transmission and distribution equipment, 600 power generation supplier server, 610 power generation equipment, 900 communication network.
Claims
1. A power management device that manages the adjustment power of power provided by a trading company to a power transmission and distribution company, The power management device is capable of controlling a power supply and demand adjustment system, A memory for storing a predetermined program; A processor for executing the predetermined program, The processor executes the predetermined program, A power management device that controls the adjustment system to go through a period during which the reference value is maintained when a command value for power supply and demand to the adjustment system transitions from a first command value before the change to a second command value after the change, crossing a reference value for power supply and demand by the adjustment system.
2. The power management device of claim 1, wherein the processor controls the adjustment system with the goal of changing linearly from the first command value to the second command value when the command value for power supply and demand to the adjustment system transitions from a first command value before the change to a second command value after the change, if the reference value for power supply and demand by the adjustment system is not crossed.
3. The power management device of claim 1, wherein when the processor controls the adjustment system to go through a period in which the reference value is maintained, the processor controls the rate at which the adjustment system changes the supply and demand of power during the period in which the first command value transitions to the reference value and the period in which the reference value transitions to the second command value to be the maximum controllable rate.
Citation Information
Patent Citations
Host control device, power system, and subordinate control device
JP2021125885A
Systems and methods to aggregate distributed energy resources
US20200004212A1
Power adjustment device, power supply-demand balance adjustment system and method
JP2022113460A