Information processing device and information processing method
The information processing device uses machine learning and text mining to predict project cost overruns, addressing the limitations of conventional systems by detecting early signs of project deterioration and reducing human resource requirements for prioritization.
Patent Information
- Application Number
- JP2021205845
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-12-20
- Publication Date
- 2024-09-20
- Estimated Expiration
- 2041-12-20
AI Technical Summary
Conventional wide-area monitoring systems struggle to detect project deterioration at an early stage and require significant human resources to determine which projects should be prioritized for intensive monitoring, as they primarily rely on numerical data and cannot effectively utilize text data.
An information processing device and method that uses machine learning to generate predictive models based on explanatory variables and text mining to analyze project minutes, incorporating topic ratios from text data to predict project cost overruns, allowing for early detection of project deterioration and reducing human resource costs.
Enables early detection of project deterioration through wide-area monitoring, minimizing the need for extensive human intervention in determining priority projects by leveraging both numerical and text data for accurate prediction.
Smart Images

Figure 0007554730000001 
Figure 0007554730000002 
Figure 0007554730000003
Abstract
Description
[Technical field]
[0001] The present invention relates to an information processing device and an information processing method. [Background technology]
[0002] In recent years, there has been active development of technologies to promote Digital Transformation (DX), and as part of this, importance is being placed on status monitoring of projects such as software development. Status monitoring can be divided into two categories: focused monitoring and wide-area monitoring. Focused monitoring is monitoring of projects by the management department. Wide-area monitoring is monitoring of all projects using specified tools. In status monitoring, first, projects that are judged to have a high possibility of failure or a large impact in the event of failure in wide-area monitoring based on data such as costs entered into the tool are targeted for focused monitoring. Next, with support from the management department, efforts are made to prevent deterioration or improve the projects that are the subject of focused monitoring.
[0003] Conventional wide-area monitoring would identify projects after problems, such as costs exceeding estimates, become apparent. In light of the goal of leading a project to success, it is preferable to detect signs of project deterioration at an early stage before problems become apparent. However, conventional wide-area monitoring had the problem of making it difficult to detect signs of project deterioration at an early stage before problems become apparent.
[0004] Furthermore, in conventional wide-area monitoring, investigations are conducted to determine whether or not a project of concern should really be the subject of priority monitoring. The investigations include, for example, investigating the scale of the project and the amount of overruns in estimated costs. However, such investigations require a great deal of human resources. For this reason, projects with large order amounts and other projects that would be greatly affected if the situation were to worsen are given priority, and monitoring of all projects, including small-scale projects, is not conducted. In other words, conventional wide-area monitoring had the problem of requiring a large human resources cost to determine which projects should be the subject of priority monitoring.
[0005] In addition, conventional wide-area monitoring only utilized numerical data such as various costs and code numbers, and could not utilize text data such as project minutes. Therefore, in order to understand the signs of deterioration in a project, it was necessary to check all text data for all projects under monitoring. In other words, conventional wide-area monitoring had limitations in reducing the human cost of determining which projects should be the targets of priority monitoring.
[0006] Patent Document 1 discloses an invention that makes it possible to identify factors that lead to risks in software development. [Prior art documents] [Patent documents]
[0007] [Patent Document 1] JP 2019-148874 A Summary of the Invention [Problem to be solved by the invention]
[0008] In view of the above circumstances, an object of the present invention is to detect early signs of deterioration in a project through wide-area monitoring, and to reduce the human cost of determining whether or not to make a project a target for priority monitoring. [Means for solving the problem]
[0009] The present invention solves the above problems, The first completed project This is information for monitoring the situation. Monitoring Information The input information is the explanatory variable values that make up the above, and the output information is the estimated cost overrun of the first project. A generation unit that generates a prediction model; Explanatory variables for the second project in progress Value of is input into the prediction model, A plurality of decision trees are used that combine decision conditions using explanatory variables related to the values of the input information, and a majority vote is taken. Projected cost overruns for the second project The prediction value is calculated by using the Shapley Additive exPlanations (SHAP) algorithm. a prediction unit that outputs explanatory variables that are the basis of the predicted value; a text mining unit that performs text mining on the first text data of the first project and the second text data of the second project, The text mining unit is performing a morphological analysis of the first text data, performing a dependency analysis of the first text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the first project for each of the clusters using the extracted feature words; The generation unit generates the prediction model using the calculated topic ratio of the first project as the input information; The text mining unit is performing a morphological analysis of the first text data and the second text data, performing a dependency analysis of the first text data and the second text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the second project for each of the clusters using the extracted feature words; The prediction unit is The calculated values of the explanatory variables of the second project, including the topic ratio of the second project, are input into the prediction model, and a prediction value of the estimated cost overrun of the second project is output by majority vote using a plurality of decision trees that combine judgment conditions using explanatory variables related to the values that become the input information, and the explanatory variables that are the basis of the prediction value are output according to the contribution rate of the explanatory variables to the prediction value calculated using the SHAP algorithm. It is an information processing device.
[0010] The present invention also provides a method for producing a semiconductor device comprising the steps of: An information processing device, The first completed project This is information for monitoring the situation. Monitoring Information The input information is the explanatory variable values that make up the above, and the output information is the estimated cost overrun of the first project. Generate a predictive model No. 1 Steps and Explanatory variables for the second project in progress Value of is input into the prediction model, A plurality of decision trees are used that combine decision conditions using explanatory variables related to the values of the input information, and a majority vote is taken. Projected cost overruns for the second project The prediction value is calculated by using the SHAP algorithm. , and output the explanatory variables that are the basis for the predicted value. Second Steps and Performing text mining on the first text data of the first project and the second text data of the second project Third Step 1: Execute the steps In the third step, performing a morphological analysis of the first text data, performing a dependency analysis of the first text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the first project for each of the clusters using the extracted feature words; In the first step, the calculated topic ratio of the first project is used as the input information to generate the prediction model; The above ThirdStep by step, performing a morphological analysis of the first text data and the second text data, performing a dependency analysis of the first text data and the second text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the second project for each of the clusters using the extracted feature words; In the second step, The calculated values of the explanatory variables of the second project, including the topic ratio of the second project, are input into the prediction model, and a prediction value of the estimated cost overrun of the second project is output by majority vote using a plurality of decision trees that combine judgment conditions using explanatory variables related to the values that become the input information, and the explanatory variables that are the basis of the prediction value are output according to the contribution rate of the explanatory variables to the prediction value calculated using the SHAP algorithm. This is an information processing method. Effect of the Invention
[0011] According to the present invention, it is possible to detect early signs of deterioration in a project through wide-area monitoring, and to reduce the human cost of determining whether or not to make a project a target for priority monitoring. [Brief description of the drawings]
[0012] [Figure 1] FIG. 2 is a diagram illustrating an example of a functional configuration of an information processing device according to the present embodiment. [Diagram 2] 13 is a screen example of output information from a prediction unit. [Diagram 3] 4 is an example of a flowchart illustrating a process according to the present embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] First Embodiment [composition] The information processing device 100 shown in FIG. 1 is a computer that detects signs of deterioration in a project in progress through wide-area monitoring. The information processing device 100 includes hardware such as an input unit, an output unit, a control unit, and a storage unit. For example, when the control unit is configured with a CPU (Central Processing Unit), information processing by a computer including the control unit is realized by program execution processing by the CPU. Furthermore, the storage unit included in the computer stores various programs for realizing the functions of the computer according to instructions from the CPU. This realizes collaboration between software and hardware. The programs can be provided by recording them on a recording medium or via a network. The output unit may include a function of a display unit that displays on a screen.
[0014] A project is a task to achieve a specific purpose. Projects can be classified into past projects that have been completed and projects that are in progress. In this embodiment, past projects are called "first projects" and projects that are in progress are called "second projects." In addition, when there is no need to distinguish between past projects and projects that are in progress, they are simply called "projects."
[0015] 1, the information processing device 100 includes a generation unit 1, a prediction unit 2, and a text mining unit 5. The information processing device 100 also stores a first project DB3, a second project DB4, a first minutes DB6, and a second minutes DB7.
[0016] The generation unit 1 generates a prediction model for predicting the actual estimated cost of the second project by machine learning. The actual estimated cost is an estimated value of the cost that will occur by the end of the second project. There are multiple types of cost, such as manufacturing cost and sales cost, but in this embodiment, the cost is defined as an economic resource consumed to achieve a specific purpose, measured in monetary terms, and is described as a term that includes manufacturing cost, sales cost, etc. The prediction unit 2 uses the prediction model generated by the generation unit 1 to predict the actual estimated costs of the second project. The text mining unit 5 performs text mining on predetermined text data. The text mining of the text mining unit 5 is disclosed in JP 2019-117484 A (hereinafter referred to as "Reference 1") and is well known, so a detailed description will be omitted. The first project DB3 is a database that stores the monitoring information of the first project for each first project. The second project DB4 is a database that stores the monitoring information of the second project for each second project. The first minutes DB6 is a database that stores the first minutes, which are the minutes of the first project, for each first project. The minutes are a record of the progress of the project and are mainly composed of text data, but may also include numerical data and graphic data. The first minutes are a specific example of the "first text data" in the claims. The second minutes DB7 is a database that stores second minutes, which are minutes of the second project, for each second project. The second minutes are a specific example of the "second text data" in the claims. The text mining unit 5 can perform text mining on the first and second minutes.
[0017] <Project monitoring information> The project monitoring information is information for monitoring the status of the project. The first project monitoring information can be composed of, for example, production number information, explanatory variables, and objective variables.
[0018] The production number information is information for identifying the first project. For example, the production number information includes, but is not limited to, a production number, a progress rate (%), and a production number name. The production number is an identifier for the first project and can be expressed, for example, as an alphanumeric string. The progress rate is a parameter that quantitatively indicates the progress of the first project. The project name is the name of the first project and can be expressed in a conceivable word, for example.
[0019] The explanatory variables are variables that express the state of the first project. There are multiple types of explanatory variables. Examples of explanatory variables include, but are not limited to, the start time of work, the end time of work, actual cost, forecast cost, estimated cost, person in charge, work time, actual man-hours, and topic ratio. For example, Boruta can be used to extract explanatory variable candidates, and the optimal explanatory variable can be selected from them, but the method of selecting explanatory variables is not limited to this. The work start time is the start time (year, month, day) of the first project. The work completion date is the completion date (year, month, and date) of the first project. The actual cost is the cost incurred from the start of the work to a specified time. Projected costs are costs that are expected to occur from a specified time until the end of the work. The estimated cost is the cost expected to be incurred from the start of the work to the end of the work. The person in charge is the person(s) in charge of the first project. The working time is the time each person in charge spent working on the first project from the start of the work to a specified time. The actual man-hours are the man-hours that have been completed from the start of work to a specified time out of the total man-hours that make up the first project. The predetermined time is any time between the start time and the end time of the work. The topic ratio is the ratio of the number of occurrences of a feature word that appears in the first minutes of the first project to the number of occurrences of the same feature word that belongs to each cluster when multiple types of clusters are generated by text mining all the first minutes. Therefore, the topic ratio of the first minutes of the target is calculated for each cluster. Details of text mining for the first minutes will be described later.
[0020] The objective variable is a variable that depends on the explanatory variables. The objective variable can be, for example, the final actual cost, which is the actual cost at the end of the first project, but is not limited to this.
[0021] (Progress rate) The progress rate can be calculated, for example, based on a time standard. For example, if the period from when work on a project starts to when it ends is 30 days and the target period is the 15th day from when work starts, the progress rate is 50%. Since the first project is a past project that has been completed, the progress rate at the current time is 100%. Here, the explanatory variables of the first project can be values that change depending on the progress rate. The monitoring information of the first project can be configured as a collection of explanatory variables for each progress rate.
[0022] For example, the actual cost as an explanatory variable is a set of actual costs at all progress rates between 0% and 100%. The actual cost at a progress rate of X% is the cost incurred between the start of work and the time corresponding to the progress rate of X%. Furthermore, the forecast cost as an explanatory variable is a set of forecast costs at all progress rates between 0% and 100%. The forecast cost at a progress rate of X% is the cost expected to be incurred between the time corresponding to the progress rate of X% and the time the work is completed. Note that there are explanatory variables that do not change depending on the progress rate, such as the start and end of work, but it is preferable to treat such explanatory variables as constants that take the same value depending on the progress rate.
[0023] In addition, since the first minutes change according to the progress rate (records of the progress of the first project are accumulated), the topic ratio also changes according to the progress rate.
[0024] On the other hand, the monitoring information of the second project can be composed of, for example, production number information and explanatory variables.
[0025] The production number information is information for identifying the second project. For example, the production number information includes, but is not limited to, a production number, a progress rate (%), and a production number name. The production number is an identifier of the second project and can be expressed, for example, as an alphanumeric string. The progress rate is a parameter that quantitatively indicates the progress of the second project. The project number is the name of the second project and can be expressed, for example, in a conceivable word.
[0026] The explanatory variables are variables that express the state of the second project. There are multiple types of explanatory variables. Examples of explanatory variables include, but are not limited to, the start time of work, the end time of work, actual cost, forecast cost, estimated cost, person in charge, work time, actual man-hours, and topic ratio. For example, it is possible to extract explanatory variable candidates using Boruta and select the optimal explanatory variable from among them, but the method of selecting explanatory variables is not limited to this. The work start date is the start date of the second project. The work completion date is the completion date (year, month, and date) of the second project. The actual cost is the cost incurred from the start of the work to a specified time. Projected costs are costs that are expected to occur from a specified time until the end of the work. The estimated cost is the cost expected to be incurred from the start of the work to the end of the work. The person in charge is the person(s) in charge of the second project. The working time is the time each person in charge spent working on the second project from the start of the work to the specified time. The actual man-hours are the man-hours that are completed from the start of work to a specified time out of the total man-hours that make up the second project. The predetermined time is the present time between the work start time and the work end time. As already explained, the actual estimated cost of the second project is the sum of the actual cost and the forecast cost of the second project. The topic ratio is the ratio of the number of times a feature word appears in the second minutes of the second project to the number of times the same feature word appears in each cluster when multiple types of clusters are generated by text mining all the first minutes and the target second minutes. Therefore, the topic ratio of the target second minutes is calculated for each cluster. Details of text mining for the second minutes will be described later.
[0027] The progress rate of the second project can be calculated as the ratio of the period from the start of work to the end of work to the period from the start of work to the present. The actual cost of a progress rate of X%, which corresponds to the present, is the cost incurred from the start of work to the present. Furthermore, the forecasted cost of a progress rate of X%, which corresponds to the present, is the cost expected to be incurred from the present to the end of work. Note that there are explanatory variables that do not change depending on the progress rate, such as the start and end of work, but it is preferable to treat such explanatory variables as constants that take the same value depending on the progress rate.
[0028] In addition, since the second minutes change according to the progress rate (records of the progress of the second project are accumulated), the topic ratio also changes according to the progress rate.
[0029] <Prediction model> (training) The generation unit 1 can generate a prediction model by combining, for example, multiple decision trees used in a random forest. A random forest is a machine learning algorithm, and is an ensemble learning algorithm that uses multiple decision trees and makes predictions by majority vote. The decision tree can be configured as a tree-like logic that combines, for example, judgment conditions using explanatory variables. The judgment conditions can be designed as appropriate, and can be, for example, whether or not the average daily working hours of a person in charge are 5 hours or more.
[0030] The generation unit 1 can train the prediction model using the monitoring information of the first project as training data. For example, for each first project, explanatory variables at a time point corresponding to a progress rate of 50% in the monitoring information of the first project can be used as input to the prediction model. Also, a value based on the objective variable of the monitoring information of the first project can be used as output of the prediction model. For example, the estimated cost overrun value obtained by subtracting the estimated cost from the final actual cost of the first project can be used as output of the prediction model. The generation unit 1 trains the prediction model using monitoring information of a predetermined number of first projects.
[0031] Here, the generating unit 1 prepares a plurality of prediction models, and can output the prediction models in a plurality of stages. For example, the generating unit 1 prepares a first prediction model and a second prediction model. The input of the first prediction model targets the monitoring information of all the first projects, and can be an explanatory variable of the monitoring information at a time when the progress rate is 50%. The output of the first prediction model can be whether or not there is an estimated cost overrun (greater than 0M (0 yen)) obtained by subtracting the estimated cost from the final actual cost of the first project. Next, the input of the second prediction model targets the monitoring information of the first project in which there is an estimated cost overrun in the output of the first prediction model, and can be an explanatory variable of the monitoring information at a time when the progress rate is 50%. The output of the second prediction model can be whether or not the estimated cost overrun is 1M (1 million yen) or more. As a result, the output of the prediction model can be classified into three values: the estimated cost overrun is 0M or less, greater than 0M and less than 1M, and 1M or more.
[0032] The text mining unit 5 acquires and reads the first minutes at a time corresponding to a progress rate of 50% for each first project from the first minutes DB 6. The text mining unit 5 also performs text mining on all the read first minutes using the invention of Reference Document 1. Specifically, the text mining unit 5 performs morphological analysis on each of the first minutes. The text mining unit 5 also performs dependency analysis on each of the first minutes based on the result of the morphological analysis. The text mining unit 5 also creates a graph for each of the first minutes based on the dependency structure identified by the dependency analysis. The text mining unit 5 also merges the graphs created for each of the first minutes to create one graph. The text mining unit 5 also performs clustering on the merged graph. As a result, one or more clusters related to the merged graph are generated. The text mining unit 5 also extracts one or more feature words from each of the generated clusters. A feature word is a word that appears with a term frequency (TF) equal to or greater than a predetermined value. The predetermined value may be determined for each cluster, or may be determined as the same value for all clusters.
[0033] The text mining unit 5 sets a topic (topic) that symbolizes each of the generated clusters. The topic for each cluster plays a role of symbolizing the cluster, and can be set by the operator of the information processing device 100. The operator may, for example, set the topic by inferring it from the characteristic words included in each cluster, or may set it by inferring it from words other than the characteristic words included in each cluster, or may set it by inferring it from words other than the words included in each cluster.
[0034] The text mining unit 5 calculates the topic ratio for each generated cluster and for each first project. Specifically, the text mining unit 5 counts the number of occurrences (C1) of a feature word (hereinafter sometimes referred to as a "first feature word") that appears in the first minutes of the target first project. When multiple types of first feature words appear, the total number of occurrences of each type of first feature word (corresponding to C1) is counted. In addition, the text mining unit 5 counts the number of occurrences (c1) of the first feature word among the feature words belonging to the target cluster. The text mining unit 5 calculates the topic ratio as (c1 / C1).
[0035] For example, suppose that three clusters [1]-[3] are generated by performing text mining on all the first minutes read by the text mining unit 5. In addition, suppose that for Project A as the first project, the first characteristic word appears 100 times in the first minutes of Project A, and the first characteristic words that belong to each of Clusters [1]-[3] appear 70 times, 20 times, and 10 times, respectively. In this case, the topic ratios of each of Clusters [1]-[3] for Project A are calculated to be 70% (=70 times / 100 times), 20% (=20 times / 100 times), and 10% (=10 times / 100 times), respectively.
[0036] The generation unit 1 inputs the topic ratios calculated by the text mining unit 5 as explanatory variables into the prediction model. The same applies when multiple prediction models are prepared, such as a first prediction model and a second prediction model.
[0037] (prediction) The prediction unit 2 uses the trained prediction model to predict the actual estimated cost of the second project to be predicted. For example, the prediction unit 2 inputs explanatory variables from the monitoring information of the second project, that is, at the present time, i.e., at a time corresponding to a predetermined progress rate (preferably 50% or more, but may be less than 50%), into the prediction model. The prediction unit 2 can then obtain a value based on the actual estimated cost as the output of the prediction model. For example, the prediction unit 2 can obtain a value of the estimated cost overrun, which is obtained by subtracting the estimated cost from the actual estimated cost.
[0038] When the prediction model is the first prediction model or the second prediction model described above, the prediction unit 2 inputs the current explanatory variables from the monitoring information of the second project to be predicted into the first prediction model. Then, the prediction unit 2 can obtain a value indicating whether or not there has been an estimated cost overrun (greater than 0M (0 yen)) as the output of the first prediction model. If there has been an estimated cost overrun, the prediction unit 2 inputs the current explanatory variables from the monitoring information of the second project into the second prediction model. Then, the prediction unit 2 can obtain a value indicating whether or not the estimated cost overrun is 1M (1 million yen) or more as the output of the second prediction model. As a result, the estimated cost overrun can be classified into three values: 0M or less, greater than 0M and less than 1M, and 1M or more. Note that 1M is merely an example, and the value may be greater than 1M or less than 1M.
[0039] The text mining unit 5 acquires and reads the second minutes at a time corresponding to a predetermined progress rate (preferably 50% or more, but may be less than 50%) from the second minutes DB 7. The text mining unit 5 also performs text mining on all the read first minutes and the read second minutes using the invention of Reference 1. Specifically, for all the first minutes, the text mining unit 5 uses a graph created during training (a graph merging the graphs created for each first minutes). The text mining unit 5 also performs a morphological analysis of the second minutes to be predicted. The text mining unit 5 also performs a dependency analysis of the second minutes based on the results of the morphological analysis. The text mining unit 5 also creates a graph based on the dependency structure identified by the dependency analysis as a "graph for the second minutes." In addition, the text mining unit 5 merges the graph created during training with the graph for the second minutes to create one graph as an "overall graph."
[0040] Furthermore, the text mining unit 5 performs clustering of the merged overall graph. Here, under the condition that all the first projects are projects related to a specific business (e.g., software development) and the second projects to be predicted are also projects related to the same specific business, the vocabulary of all the first minutes and the vocabulary of the second minutes to be predicted tend to be highly similar. For this reason, it can be said that the words (including feature words) written in the second minutes belong to one of the multiple clusters generated during training for all the first minutes. In other words, it can be said that the multiple clusters generated by clustering the overall graph are the same as the multiple clusters generated during training.
[0041] The text mining unit 5 extracts one or more feature words from the multiple clusters generated by clustering the entire graph. The text mining unit 5 also sets a topic that symbolizes each of the generated clusters. Under the above conditions, the multiple clusters are the same between training and prediction, so the topics set for the clusters may also be the same.
[0042] The text mining unit 5 calculates the topic ratio of the second project to be predicted for each generated cluster. Specifically, the text mining unit 5 counts the number of occurrences (C2) of feature words (hereinafter sometimes referred to as "second feature words") that appear in the second minutes of the second project to be predicted. When multiple types of second feature words appear, the total number of occurrences of each type of second feature word (corresponding to C2) is counted. In addition, the text mining unit 5 counts the number of occurrences (c2) of the second feature words among the feature words belonging to the target cluster. The text mining unit 5 calculates the topic ratio as (c2 / C2).
[0043] The prediction unit 2 inputs the topic ratios calculated by the text mining unit 5 as explanatory variables into the prediction model. The same applies when multiple prediction models are prepared, such as a first prediction model and a second prediction model.
[0044] The prediction unit 2 can output information including the output of the prediction model. For example, the display unit of the information processing device 100 can display the output information of the prediction unit 2 on a screen as shown in Fig. 2. As shown in Fig. 2, the output information of the prediction unit 2 can be in a table format with "prediction result", "production number information", "explanatory variables and features of the prediction result", and "topic content" as columns, and the second project as rows.
[0045] The "prediction result" indicates the output content of the prediction model. The "prediction result" is composed of an "item number", a "predicted value", and a "confidence factor". "Item number" is the line number assigned to each second project. "Predicted value" is the result according to a three-value classification of estimated cost overruns when the forecast model is a combination of the first and second forecast models already explained. "1: Overrun by 1 million yen" corresponds to 1 million or more. "2: Overrun by less than 1 million yen" corresponds to greater than 0 million and less than 1 million. "3: No problem" corresponds to 0 million or less. "Confidence" is the reliability of the prediction and is indicated by a value between 0% and 100%. For example, the confidence can be calculated using bagging, but is not limited to this.
[0046] The "production number information" is the same as the production number information in the monitoring information of the second project. "Explanatory variables and features of prediction results" shows the explanatory variables that contribute to the "prediction results." "Explanatory variables and features of prediction results" consists of a "list of explanatory variables" and a "feature ranking." The "List of explanatory variables" is the same as the explanatory variables for the monitoring information of the second project. The "feature ranking" indicates the rank of explanatory variables that contribute to the "prediction result". The higher the rank, the greater the contribution rate of that explanatory variable to the output of the predicted value. For example, the contribution rate of each variable can be calculated using the Shapley Additive exPlanations (SHAP) algorithm, but is not limited to this.
[0047] "Topic content" indicates the topics set by the text mining unit 5 for the clusters generated by clustering. "Topic content" is composed of multiple types of "topic n(xxx)". Here, n is a natural number ranging from 1 to (the number of clusters). Also, xxx is a word set as a topic. Each "topic n(xxx)" is composed of a "topic ratio" (e.g., symbol 8 in FIG. 2) and a "characteristic word group" (e.g., symbol 9 in FIG. 2). "Topic ratio" is the topic ratio of topic n. A "characteristic word group" is a set of characteristic words that belong to the cluster to which topic n is set. As an example, the characteristic word group shown in Reference 8 consists of characteristic words such as "risk," "preparation," "recurrence," "avoidance," "specification change," "assertion," "accept + not" (a characteristic word that combines "accept" and "not accept" into one word), "fault," and "occurrence." The number in parentheses to the right of each characteristic word indicates the number of times it appears in the corresponding cluster. "Risk" is an end node, and "preparation," "recurrence," and "avoidance" are each nodes that are linked to "risk" (see Reference 1). "Specification change" is also an end node, and "assertion," "accept + not," "fault," and "occurrence" are each nodes that are linked to "specification change."
[0048] According to the first embodiment, it is possible to extract second projects whose estimated cost exceeds the estimated cost by 1M or more. Therefore, it is possible to detect early signs of deterioration of a project through wide-area monitoring.
[0049] (Decision on whether to subject to intensive monitoring) The management department, having obtained the output information in Figure 2, decides whether or not to make the second project, which has an estimated cost overrun of 1M yen, a target for intensive monitoring. Conventionally, even if AI detected signs of deterioration in a project, the basis for the AI's prediction results was a black box. For this reason, it was not easy for the management department to track down the causes of the signs of deterioration in the project based on the AI's prediction results, and it required a large amount of human resources to decide whether or not to make it a target for intensive monitoring.
[0050] The "Feature Ranking" in Figure 2 can be said to show the reason why the estimated cost overrun became 1M or more. By referring to the "Feature Ranking", the management department can easily identify the explanatory variables that contributed greatly to the prediction that the estimated cost overrun became 1M or more. As a result, it becomes easier to decide whether or not to subject the second project to intensive monitoring, and the human cost of deciding whether or not to subject it to intensive monitoring can be reduced. Topics that have a large contribution rate to the output of the predicted value can become explanatory variables that show a high ranking in the "feature ranking" (for example, symbol 10 in Figure 2). By paying attention to the feature words that belong to the cluster in which the highly ranked topic is set and closely examining the second minutes of the corresponding second project, the management department can deepen their understanding of the decision on whether or not to make the corresponding second project a target for priority monitoring.
[0051] In addition, because text data such as minutes can be quantified as topic ratios, the topic ratios can be input as explanatory variables in a prediction model, making it possible to use text data to predict signs of project deterioration. As a result, in order to understand signs of project deterioration, it is no longer necessary to check all the text data for all monitored projects, but rather it is possible to select specific feature words that require attention. In other words, it is possible to reduce the human cost of determining which projects should be the subject of priority monitoring. Since the minutes can be divided into multiple topics and understood, the topics can be used as a summary of the minutes. In addition, the content of the minutes can be reverse-referenced by referring to the topic ratios that serve as the basis for predictions (explanatory variables). This allows you to immediately identify the text data that you need to check to understand the basis. The topic ratio can be calculated for all projects (first and second projects). This allows us to find the numerical change between each project for the same topic, and to show the difference between projects. The clusters are not prepared in advance using a thesaurus or the like as in the past, but are generated by reflecting the dependency structure of the text data. With clusters prepared in advance, there is a possibility that features necessary for prediction may be overlooked due to human preconceptions, but according to this embodiment, such features can be picked up and used as candidates for the basis of prediction. If the multiple clusters generated between training and prediction are the same, the training target and the prediction target can be evaluated on the same scale. Therefore, predictions for the second project can be made as the numerical change between the topic ratio at training and the topic ratio at prediction in each cluster. As a result, a method can be introduced that focuses on the numerical change in the topic ratio for each cluster as a method for determining whether or not to subject the second project to intensive monitoring.
[0052] [process] The process executed by the information processing device 100 is as shown in Fig. 3. That is, first, the generating unit 1 generates a prediction model (step S1). Next, the generating unit 1 trains the prediction model using monitoring information of the first project at a predetermined progress rate (step S2). Next, the predicting unit 2 uses the prediction model to output a predicted value of the estimated cost overrun of the target second project and explanatory variables contributing to the predicted value as prediction grounds (step S3). The management department judges, based on the prediction grounds, whether or not to target the second project showing signs of deterioration as a target for intensive monitoring.
[0053] Second Embodiment In explaining the second embodiment, differences from the first embodiment will be explained, and overlapping points will be omitted. In the first embodiment, the explanatory variables of the monitoring information of the first project, which is the training data, were explanatory variables at a time when the progress rate was equivalent to 50%. In the second embodiment, the time of the explanatory variables of the first project used for the training data is periodic.
[0054] For example, if the duration of the first project, i.e., the period from the start of work to the end of work, is several months, the period of the explanatory variables used in the training data, i.e., the training date (learning date), is set to the 25th of each month. Therefore, if work on the first project of work number A starts on 4 / 15 and ends on 6 / 30, the training dates for the first project of work number A will be 4 / 25 and 5 / 25. In other words, from the monitoring information for the first project of work number A, the explanatory variables on 4 / 25 (explanatory variables with a progress rate equivalent to 4 / 25) and the explanatory variables on 5 / 25 (explanatory variables with a progress rate equivalent to 5 / 25) for a total of two times will be input into the prediction model. Also, if the work start date for the first project of work number B is 5 / 1 and the work end date is 9 / 15, the training dates for the first project of work number B will be 5 / 25, 6 / 25, 7 / 25, and 8 / 25. In other words, from the monitoring information for the first project of work number B, the explanatory variables on 5 / 25 (explanatory variables with a progress rate equivalent to 5 / 25), the explanatory variables on 6 / 25 (explanatory variables with a progress rate equivalent to 6 / 25), the explanatory variables on 7 / 25 (explanatory variables with a progress rate equivalent to 7 / 25), and the explanatory variables on 8 / 25 (explanatory variables with a progress rate equivalent to 8 / 25) for a total of four times will be input into the prediction model. In addition, if the work start date for the first project of work number C is 6 / 1 and the work end date is 7 / 10, the training date for the first project of work number C will be 6 / 25. In other words, the explanatory variables for 6 / 25 (explanatory variables with a progress rate equivalent to 6 / 25) from the monitoring information for the first project of work number C are used as input for the prediction model for one session.
[0055] As a result, explanatory variables at multiple types of progress rates are input to the prediction model for most of the first project. Using the prediction model trained in this way, the prediction unit 2 predicts the actual estimated cost of the second project. In this case, even if the progress rate of the second project is low (e.g., about 30%) and explanatory variables at a period equivalent to the low progress rate are input to the prediction model, it has been confirmed that the confidence level of the predicted value output by the prediction unit 2 (see FIG. 2) is sufficiently high.
[0056] According to the second embodiment, the training date can be set to a regular date, and explanatory variables for multiple types of progress rates for the same first project can be input to the prediction model. This allows for earlier prediction of the actual estimated cost of the second project. In addition, by regularizing the training dates, the input to the predictive model for all primary projects can be systematized, simplifying the processing required for training.
[0057] [Variations] (a): In the first and second embodiments, the progress rate is calculated based on a time standard using the period of the project. However, for example, the progress rate may be calculated based on the degree of completion of the work being undertaken in the project. (b): In the first embodiment, explanatory variables at a time point corresponding to a progress rate of 50% in the monitoring information of the first project were input to the prediction model for each first project. However, for example, explanatory variables at a time point corresponding to any same progress rate other than 50% may be input to the prediction model for each first project. Also, explanatory variables at a time point corresponding to a different progress rate for each first project may be input to the prediction model. (c): In the second embodiment, by regularizing the training days, multiple types of progress rates are substantially selected for the same first project, and explanatory variables at the selected progress rates are input to the prediction model. However, for example, a user of the information processing device 100 may operate the input unit to select multiple types of arbitrary progress rates for the same first project, and input explanatory variables at the selected progress rates to the prediction model. (d) The invention of quantifying text data as topic ratios can be applied not only to the deterioration sign detection of this embodiment but also to predetermined training (learning) and prediction using text data. Furthermore, the present invention can be introduced not only to the software industry but also to other industries. (e): In this embodiment, the overall graph used when predicting the second project is a graph created by merging the graph created during training for all first minutes (a graph obtained by merging the graphs created for each first minutes) with the graph for the second minutes. That is, the overall graph is created by merging twice. However, for example, the text mining unit 5 may create the overall graph by merging only once using the graph created for each first minutes and the graph for the second minutes. The contents of the overall graph are uniquely determined based on the contents of the first minutes and the contents of the second minutes to be predicted, and do not depend on the number or order of merging. The clusters generated by clustering are also uniquely determined based on the contents of the first minutes and the contents of the second minutes to be predicted, and do not depend on the number or order of merging. Therefore, the calculation results of the topic ratios are the same. (f): Depending on the contents of the second minutes to be predicted, the multiple clusters generated at the time of prediction for all the first minutes and the second minutes to be predicted may differ from the multiple clusters generated at the time of training for all the first minutes. As a result, a topic ratio as an explanatory variable that is input at the time of training but not input at the time of prediction (hereinafter, sometimes referred to as the "first type topic ratio") occurs. Also, a topic ratio as an explanatory variable that is not input at the time of training but is input at the time of prediction (hereinafter, sometimes referred to as the "second type topic ratio") occurs. In such a case, the second type topic ratio can be intentionally added to the topic ratio as an explanatory variable at the time of training, and the first type topic ratio can be intentionally added to the topic ratio as an explanatory variable at the time of prediction. By such adjustment, it becomes possible to unify the types (scales) of explanatory variables to be input to the prediction model between the time of training and the time of prediction, and it is possible to perform a deterioration prediction of the second project.
[0058] (g) It is also possible to realize a technology that appropriately combines the various technologies described in this embodiment. (h): The software described in this embodiment can be realized as hardware, and vice versa. (i) In addition, the hardware, software, flow charts, etc. may be modified as appropriate without departing from the spirit and scope of the present invention. [Explanation of symbols]
[0059] 100 Information processing device 1 Generation part 2. Prediction Department 3. First Project DB 4. Second Project DB 5. Text Mining Department 6. First Meeting Minutes DB 7. Second Minutes DB
Claims
1. a generation unit that uses values of explanatory variables constituting monitoring information, which is information for monitoring the status of a completed first project, as input information, uses an estimated cost overrun of the first project as output information, and executes a random forest to generate a prediction model; a prediction unit that inputs values of explanatory variables of a second project in progress into the prediction model, and uses a plurality of decision trees that combine judgment conditions using explanatory variables related to the values of the input information to take a majority vote to output a predicted value of an estimated cost overrun of the second project, and outputs explanatory variables that are the basis of the predicted value in accordance with the contribution rate of the explanatory variables to the predicted value calculated using a Shapley Additive exPlanations (SHAP) algorithm; a text mining unit that performs text mining on the first text data of the first project and the second text data of the second project, The text mining unit is performing a morphological analysis of the first text data, performing a dependency analysis of the first text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the first project for each of the clusters using the extracted feature words; The generation unit generates the prediction model using the calculated topic ratio of the first project as the input information; The text mining unit is performing a morphological analysis of the first text data and the second text data, performing a dependency analysis of the first text data and the second text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the second project for each of the clusters using the extracted feature words; The prediction unit is an information processing device that inputs the calculated values of the explanatory variables of the second project, including the topic ratio of the second project, into the prediction model, and uses a plurality of decision trees that combine judgment conditions using explanatory variables related to the values that become the input information to take a majority vote to output a predicted value of an estimated cost overrun of the second project, and also outputs explanatory variables that are the basis of the predicted value in accordance with the contribution rate of the explanatory variables to the predicted value, which is calculated using the SHAP algorithm.
2. 2. The information processing apparatus according to claim 1, wherein the forecasting model is a combination of a first forecasting model that outputs whether or not there is an estimated cost overrun, and a second forecasting model that inputs an explanatory variable of the second project in which the estimated cost overrun has occurred in the first forecasting model, and outputs whether or not the estimated cost overrun is equal to or greater than a predetermined value.
3. The information processing apparatus according to claim 1 , wherein the monitoring information of the first project used for training the prediction model is monitoring information of the first project at a predetermined progress rate.
4. An information processing device, A first step of generating a prediction model by executing a random forest using values of explanatory variables constituting monitoring information, which is information for monitoring the status of a completed first project, as input information and an estimated cost overrun of the first project as output information; a second step of inputting values of explanatory variables of a second project in progress into the prediction model, using a plurality of decision trees combining judgment conditions using explanatory variables related to the values of the input information, taking a majority vote to output a predicted value of an estimated cost overrun of the second project, and outputting explanatory variables that are the basis of the predicted value in accordance with the contribution rate of the explanatory variables to the predicted value calculated using the SHAP algorithm; a third step of performing text mining on the first text data of the first project and the second text data of the second project; In the third step, performing a morphological analysis of the first text data, performing a dependency analysis of the first text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the first project for each of the clusters using the extracted feature words; In the first step, the calculated topic ratio of the first project is used as the input information to generate the prediction model; In the third step, performing a morphological analysis of the first text data and the second text data, performing a dependency analysis of the first text data and the second text data based on a result of the morphological analysis, creating a graph based on the dependency structure identified by the dependency analysis, clustering the created graph, extracting feature words that appear with a frequency equal to or greater than a predetermined value from the clusters created by the clustering, and calculating a topic ratio of the second project for each of the clusters using the extracted feature words; In the second step, The information processing method includes inputting the calculated values of the explanatory variables of the second project, including the topic ratio of the second project, into the prediction model, utilizing a plurality of decision trees that combine judgment conditions using explanatory variables related to the values that become the input information, taking a majority vote to output a predicted value of an estimated cost overrun of the second project, and outputting the explanatory variables that are the basis of the predicted value in accordance with the contribution rate of the explanatory variables to the predicted value, which is calculated using the SHAP algorithm.
Citation Information
Patent Citations
Risk detection system, risk detection method, and program therefor
JP2008210367A
Project analysis device and its program
JP2019148874A
Project evaluation device, project evaluation method, and project evaluation program
JP2019148973A
Information operating device and information operating method
JP2020064463A