Project integration management device and method
The project integrated management device addresses the challenge of integrating drawings and material status in construction projects by classifying CWPs and simulating schedules, enhancing proactive management through real-time material availability and risk assessment.
Patent Information
- Application Number
- JP2023560770
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-08-24
- Publication Date
- 2024-09-24
- Estimated Expiration
- 2042-08-24
AI Technical Summary
Construction project management systems fail to integrate drawings and material status in real time, making it difficult to intuitively grasp construction progress and risk levels, especially in projects spread across multiple areas.
A project integrated management device that classifies construction work packages (CWPs) based on progress and material availability, using a grid format to display and simulate construction schedules, combining design, procurement, and construction data to calculate and visualize material availability and risk levels.
Enables proactive construction management by automatically calculating material availability and classifying risk levels, facilitating intuitive understanding and scheduling adjustments.
Smart Images

Figure 0007555500000014 
Figure 0007555500000027 
Figure 0007555500000031
Abstract
Description
[Technical field]
[0001] The present invention relates to an apparatus and method for integrated project management that exchanges information between design, procurement and construction that constitute a construction project, establishes a project schedule and manages the actual status of the project. [Background technology]
[0002] The systems that manage construction projects do not consider the status of drawings and materials, or they operate by directly uploading only materials or drawings. However, to ensure smooth construction progress, a project integration management method that simultaneously collects and combines drawings and materials in real time is required.
[0003] In addition, since construction projects are carried out simultaneously in dozens of areas, it is difficult to know the current status of construction progress and construction feasibility of sub-projects being carried out in any area, and information on the current status of construction progress and construction feasibility of sub-projects is collected manually. Also, it is difficult to intuitively grasp whether a certain sub-project is high risk or not. Summary of the Invention [Problem to be solved by the invention]
[0004] A preferred embodiment of the present invention provides an apparatus and method for integrated project management that can intuitively grasp the current construction progress status and the current construction feasibility status of a project and classify and recognize the risk level. [Means for solving the problem]
[0005] In a preferred embodiment of the present invention, the project integrated management apparatus includes a classification unit for classifying a project into n construction work packages (CWPs) based on the construction type constituting the project, the smallest unit area for managing the project, and design information, and a display unit for classifying the n CWPs based on a current construction progress status and a current available quantity status and displaying them in a lattice form. When the construction type is piping, the current available quantity status is calculated by dividing it into a current standard and a future standard. When calculating the future standard, three simulations are independently performed in order based on a line, which is an individual component unit of piping, in the order of a weld map of a detailed drawing state for actual construction execution, an ISO drawing, which is a drawing state before detailed construction drawings are created, and a 3D drawing, which is a state before the line drawing is created. Procurement and scheduled materials are matched with the line set according to the priority order, and the current available quantity status is first calculated for each individual component unit, and then summed up by the CWP unit to derive the current available quantity status for each CWP. Effect of the Invention
[0006] In a preferred embodiment of the present invention, the project integrated management device can collect construction schedules and results, automatically calculate the amount of work that can be completed every day, and manage risk levels based on construction status and work front status.
[0007] As a preferred embodiment of the present invention, the project integration management device can automatically collect and share information between design drawings, procured materials, and construction work that constitute a construction project, which has the effect of enabling forward-looking construction management and construction schedule planning.
[0008] In a preferred embodiment of the present invention, the project integrated management device creates a schedule by defining a CWP corresponding to a group of individual constituent units, which are the construction object defined in the design, thereby having the effect of automatically compiling design, procurement, and construction data in the system based on the construction object.
[0009] In a preferred embodiment of the present invention, the project integrated management device simultaneously reflects the drawings and material data received from the operation system used by the person in charge, and can independently divide the individual structural unit work front into three types: drawings, materials, and drawings and materials.
[0010] The integrated project management system automatically outputs six types of status (not yet started, started this month, in progress, delayed start, delayed finish, finished) for each CWP unit based on the current month and future (next three months) points in time, using the actual data (start date, finish date, actual quantity) of individual construction objects that are automatically compiled in comparison with the planned schedule. [Brief description of the drawings]
[0011] [Figure 1] 1 is a diagram illustrating an internal configuration of a project integration management apparatus according to a preferred embodiment of the present invention;
[0012] [Diagram 2] 1 is a diagram illustrating a system diagram in which a project integration management apparatus is implemented according to a preferred embodiment of the present invention.
[0013] [Figure 3A] 1 is a diagram illustrating a procedure and a criterion for calculating construction status management in a project integrated management apparatus according to a preferred embodiment of the present invention. [Figure 3B] 1 is a diagram illustrating a procedure and a criterion for calculating construction status management in a project integrated management apparatus according to a preferred embodiment of the present invention. [Figure 3C]1 is a diagram illustrating a procedure and a criterion for calculating construction status management in a project integrated management apparatus according to a preferred embodiment of the present invention.
[0014] [Figure 4] FIG. 1 is a diagram showing planning criteria for CWP according to a preferred embodiment of the present invention.
[0015] [Diagram 5] FIG. 1 is a diagram illustrating an example of automatically collecting construction records, design records, and procurement records for each individual component unit in a database ERP (enterprise resource planning) according to a preferred embodiment of the present invention.
[0016] [Figure 6] 1 is a diagram illustrating necessary data and result data required to output a current status of constructable quantity according to a preferred embodiment of the present invention;
[0017] [Figure 7] FIG. 1 is a diagram illustrating an example in which necessary data for calculating the current status of workable volume and work front types according to work types are distinguished, according to a preferred embodiment of the present invention.
[0018] [Figure 8] FIG. 1 is a diagram illustrating an example of calculating the amount of CWP workable material by type of work, according to a preferred embodiment of the present invention.
[0019] [Figure 9A] FIG. 1 is a diagram illustrating an example in which the construction progress status is determined for each individual component unit and then determined for each CWP unit, according to a preferred embodiment of the present invention. [Figure 9B] FIG. 1 is a diagram illustrating an example in which the construction progress status is determined for each individual component unit and then determined for each CWP unit, according to a preferred embodiment of the present invention.
[0020] [Figure 10A]FIG. 13 is a diagram illustrating an example in which, when calculating the future construction volume, three simulations are performed sequentially for each line, which is an individual structural unit, according to the order of drawing generation (3D, ISO, weld map), as a preferred embodiment of the present invention. [Figure 10B] FIG. 13 is a diagram illustrating an example in which, when calculating the future construction volume, three simulations are performed sequentially for each line, which is an individual structural unit, according to the order of drawing generation (3D, ISO, weld map), as a preferred embodiment of the present invention. [Figure 10C] FIG. 13 is a diagram illustrating an example in which, when calculating the future construction volume, three simulations are performed sequentially for each line, which is an individual structural unit, according to the order of drawing generation (3D, ISO, weld map), as a preferred embodiment of the present invention.
[0021] [Figure 11A] 1 is a flowchart illustrating a process of simulating a current reference piping installable quantity according to a preferred embodiment of the present invention; [Figure 11B] 1 is a flowchart illustrating a process of simulating a current reference piping installable quantity according to a preferred embodiment of the present invention;
[0022] [Figure 12A] 1 is a diagram illustrating an example of classifying the current status of workable volume in CWP units according to work front type 1 for piping and steel frame work types based on future and current standards, according to a preferred embodiment of the present invention. [Figure 12B] 1 is a diagram illustrating an example of classifying the current status of workable volume in CWP units according to work front type 1 for piping and steel frame work types based on future and current standards, according to a preferred embodiment of the present invention.
[0023] [Figure 13] 1 is a diagram illustrating a display unit of a project integration management apparatus according to a preferred embodiment of the present invention;
[0024] [Figure 14] 1 is a diagram illustrating a display unit of a project integration management apparatus according to a preferred embodiment of the present invention;
[0025] [Figure 15] 1 is a diagram illustrating a display unit of a project integration management apparatus according to a preferred embodiment of the present invention; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0026] In a preferred embodiment of the present invention, the project integrated management apparatus includes a classification unit for classifying a project into n construction work packages (CWPs) based on the construction type constituting the project, the smallest unit area for managing the project, and design information, and a display unit for classifying the n CWPs based on a current construction progress status and a current available quantity status and displaying them in a lattice form. When the construction type is piping, the current available quantity status is calculated by dividing it into a current standard and a future standard. When calculating the future standard, three simulations are independently performed in order based on a line, which is an individual component unit of piping, in the order of a weld map of a detailed drawing state for actual construction execution, an ISO drawing, which is a drawing state before detailed construction drawings are created, and a 3D drawing, which is a state before the line drawing is created. Procurement and scheduled materials are matched with the line set according to the priority order, and the current available quantity status is first calculated for each individual component unit, and then summed up by the CWP unit to derive the current available quantity status for each CWP.
[0027] In a preferred embodiment of the present invention, in a display unit of the project integrated management device, the horizontal axis of a lattice pattern indicates a current construction progress status by stage, and the vertical axis indicates a current constructable volume status by stage, and each lattice indicates information on a current construction progress stage and a current constructable volume stage, and each lattice displays information on the number of CWPs belonging to the current construction progress stage and the current constructable volume stage indicated by the lattice.
[0028] In a preferred embodiment of the present invention, a display unit of the project integrated management apparatus is capable of grasping risk information by using position information of each grid constituting the grid pattern.
[0029] In a preferred embodiment of the present invention, when the number information of CWPs in each grid of the display unit of the project integrated management device is clicked, only the CWPs corresponding to the grid among the n CWPs are filtered, and detailed information of each of the filtered CWPs is displayed.
[0030] In a preferred embodiment of the present invention, the types of work include piping, steel, machinery and equipment, and civil engineering, and the current status of the amount of work that can be performed is calculated by first calculating the current status of the amount of work that can be performed in individual constituent units for each type of work, taking into consideration at least one of drawings and materials depending on the type of work that constitutes the project, and then adding up the results in the CWP unit to derive the current status of the amount of work that can be performed by CWP.
[0031] In a preferred embodiment of the present invention, a method for integrated project management includes the steps of: classifying the project into n construction work packages (CWPs) based on the construction type constituting the project, the smallest unit area for managing the project, and design information in a classification unit; and classifying the n CWPs based on a current construction progress status and a current available quantity status and displaying them in a lattice format in a display unit. When the construction type is piping, the current available quantity status is calculated by dividing it into a current standard and a future standard. When calculating the future standard, three simulations are independently performed in order based on a line, which is an individual component unit of piping, in the order of a weld map of a detailed drawing state for actual construction execution, an ISO drawing, which is a drawing state before detailed construction drawings are created, and a 3D drawing, which is a state before the line drawings are created. Procurement and scheduled materials are matched with the line set according to the priority order, and the available quantity for each individual component unit is first calculated, and then summed up in units of the CWP to derive the available quantity for each CWP.
[0032] In yet another preferred embodiment of the present invention, a method for integrated project management includes the steps of: classifying the project into n construction work packages (CWPs) based on the types of work constituting the project, the smallest unit area for managing the project, and design information in a classification unit; and classifying the n CWPs based on a current construction progress status and a current available volume of work in a display unit and displaying them in a lattice format, wherein a horizontal axis of the lattice format indicates a current construction progress status by stage, a vertical axis indicates a current available volume of work in each stage, each lattice indicates information on a current construction progress stage and a current available volume of work in each stage, and each lattice displays information on the number of CWPs belonging to the current construction progress stage and the current available volume of work in the stage indicated by the lattice.
[0033] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS In the following, with reference to the drawings, the present invention will be described in detail so that those having ordinary skill in the art to which the present invention pertains can easily understand and reproduce the present invention.
[0034] Fig. 1 illustrates an internal configuration of a project integration management apparatus 100 according to a preferred embodiment of the present invention. Fig. 2 illustrates a system diagram in which the project integration management apparatus 100 according to a preferred embodiment of the present invention is implemented.
[0035] The project integration management device 100 can provide a platform that can automatically collect and share drawing data 210, material data 220, and construction information data 230 via a database ERP (enterprise resource planning) used by people in charge of design, procurement, and construction that constitute a construction project. The project integration management device 100 can perform construction management in advance based on the collected business data, calculate the amount of work that can be completed, and plan the construction schedule based on the calculated amount.
[0036] In a preferred embodiment of the present invention, the project integration management apparatus 100 includes a classification unit 110 and a display unit 120 .
[0037] The classification unit 110 classifies a project into n construction work packages (CWPs) based on the types of work constituting the project, the smallest unit area for managing the project, and design information. The display unit 120 classifies the n CWPs based on the current status of construction progress and the current status of available work volume, and displays them in a lattice format. See FIGS. 13 to 15 for specific examples of the display unit.
[0038] In a preferred embodiment of the present invention, a CWP may be used as a standard unit for project management. With reference to Table 1, the CWP may be defined as a collection of individual constituent units. With further reference to FIGS. 3A to 34C, for example, one construction project 310 may be classified into 70 to 90 CWPs 311 based on the smallest unit area, and further classified into 700 to 900 CWPs 312 based on design information. Each classified CWP 312 may be assigned an identification code that distinguishes each identified CWP. Also, each CWP may be mapped with information related to the area to which the CWP belongs and the project to which the CWP belongs.
[0039] [Table 1]
[0040] In Table 1, Mhr means the amount of work done by one person in one hour.
[0041] In a preferred embodiment of the present invention, the database can automatically collect plans 321, 322, and 323 established for each CWP. Figure 4 shows an example of the standards for a construction plan 410, a design plan 420, and a procurement plan 430 of a CWP. Each of the CWPs is established based on the same design information. In this case, the design information is also information on individual building blocks 401 such as lines, assemblies, items, and foundations.
[0042] As shown in Figure 4, if a plan is established for each CWP, the performance information entered by the respective design, construction, and procurement personnel in the database ERP (enterprise resource planning) is automatically collected according to the plan. An example of the collected performance in the database ERP (enterprise resource planning) is shown in Figure 5. The project integration management device S-AWP performs matching with the automatically collected performance via the database EPR.
[0043] As shown in the example of FIG. 5, if each person in charge inputs actual results for each individual component unit 501 via the company database ERP (enterprise resource planning) 500 and the actual results are compiled, the current construction progress status for each CWP can be classified based on the compiled actual results. As shown in one embodiment of FIG. 9, the current construction progress status for each CWP is calculated by aggregating the current construction progress status for each individual component unit that constitutes the CWP (S910) and outputting the results for each CWP (S920). The current construction progress status for each CWP can be shown based on the monthly cut-off as shown in Table 2, not only based on the current status for this month based on today, but also based on the upcoming future cut-off.
[0044] [Table 2]
[0045] 9A and 9B, the project integration management device S-AWP can classify the construction schedule of the CWP into six stages (921 to 926). The construction progress status of each CWP shown in FIG. 4 can also be used for filtering the CWPs based on cut-off criteria. In FIG. 9A and 9B, the six stages are "before start" 921, "Target Start" within the cut-off (922), "in progress" 923, "late start" 924, "late finish" 925, and "complete" 926. "Before start" 921 is a state in which all individual components of the CWP have not yet started. "Target start within cut-off" 922 is a state where the cut-off CWP construction plan start date, such as this month (M), next month (M+1), or the month after (M+2), has arrived and all individual components below have not yet started. "In progress" 923 is a state where one or more individual components below the CWP are in progress or completed without any completion delay. "Late start" 924 is a state where all individual components are delayed in start without being in progress, completion delay, or completion. "Late finish" 925 is a state where one or more individual components are delayed in completion. And "complete" 926 is a state where all individual components are completed.
[0046] 6 illustrates necessary data 610 and result data 620 required to output the current status of available work volume according to a preferred embodiment of the present invention. The project integrated management device S-AWP uses the current standard available work volume status 611 for which drawings and materials are prepared, and the future standard data of the expected material arrival date (ETA) and the expected drawing issue date 613 to independently calculate the future standard available work volume status 612 based on a cut-off between the present and the future. The current standard available work volume status 611 is the amount of work that can be started, which is meaningful for the work, and the future standard available work volume status 612 allows the user to grasp the priority order between design and procurement work.
[0047] The project integrated management device S-AWP calculates the work front quantity for construction advance management by work type based on the information on construction, design, and procurement collected from each database ERP (enterprise resource planning). The work front status 621 is grasped by comparing the construction plan by CWP with the CWP workable quantity.
[0048] The construction plan (target plan) for each CWP is calculated by assuming the total amount of the construction plan allocated during the period based on the construction plan start date and construction plan end date established for each CWP as the daily construction target amount, and calculating it daily based on today's date. The daily construction target amount can be determined as "total construction plan amount / (construction plan end date - construction plan start date)", but it can be modified in various ways depending on the allocation method. The cumulative daily construction target amount means the cumulative daily construction target amount based on today's date.
[0049] The information required for the CWP workable volume differs depending on the characteristics of the work type, and depending on the characteristics of the work type, the work front type can be classified into a first type 710 of work front that considers drawings and materials, a second type 720 of work front that considers only materials, and a third type 730 of work front that considers only drawings, as shown in Figure 7. The CWP workable volume is calculated by first calculating the workable volume for each individual component unit by work type (810) and then adding them up by CWP unit (820), as shown in Figure 8.
[0050] An example of calculating the amount of workable material for each individual unit is as follows. Figures 10A, 10B, and 10C show an example of performing three simulations in sequence for each line, which is an individual unit, according to the order of drawing (3D, ISO, weld map) when calculating the amount of work to be performed in the future, as a preferred embodiment of the present invention. Referring to Figures 10A, 10B, and 10C, for an example of piping work, the construction priority of each line, which is an individual unit, is set within the range between the planned start date and planned end date of the piping CWP. Then, the drawing status, bill of materials (BOM), and welding material quantity information are collected for each line from ERP (enterprise resource planning), and then a weld map is created through the state of Table 3. In Table 3, spool refers to a unit into which a line is segmented for the production and construction of piping when drawing out a weld map, and joint refers to a welded joint portion shown in the weld map for actual construction.
[0051] [Table 3]
[0052] Once a weld map has been created, the amount of piping that can be installed is calculated separately for the shop and the field. The target material lists for the shop and the field are divided and materials to be excluded from the calculation simulation are set. The amount of installation material can be calculated separately for future and present standards. The difference between what is calculated based on the future standard and what is calculated based on the present standard is the difference between the design information and procurement information used during the simulation, as shown in Table 4.
[0053] Table 4 illustrates an example of the data required to understand the calculation of the future construction volume status and the current construction volume status. Table 5 shows an example of matching weld map materials when calculating the future standard construction volume status. Table 6 shows an example of matching ISO drawings and 3D materials when calculating the future standard construction volume status. Table 7 illustrates the result data of calculating the future standard construction volume status. Table 8 shows the future standard construction volume calculation criteria.
[0054] [Table 4]
[0055] [Table 5]
[0056] [Table 6]
[0057] [Table 7]
[0058] [Table 8]
[0059] In a preferred embodiment of the present invention, when calculating the current construction quantity status, a simulation is performed using only the weld map. Table 8 illustrates an example of matching procured and stored materials to a line set according to priority through performing a weld map simulation based on a current reference individual component unit. Table 9 illustrates an example of a calculation result value of the current reference construction quantity status. Table 10 illustrates an example of a calculation result value of the current reference construction quantity. Table 11 illustrates a calculation standard for the current reference construction quantity. Figures 11A and 11B illustrate a flowchart of a process of simulating the current reference piping construction possible quantity according to a preferred embodiment of the present invention. In the construction types of steel, machinery, and civil engineering, the calculation and classification of the construction quantity status are performed for each individual component unit.
[0060] [Table 9]
[0061] [Table 10]
[0062] [Table 11]
[0063] In the types of work such as piping, steel, machinery, and civil engineering, if the current status of work is calculated and classified for each individual unit, the current status of work is then classified by CWP unit. In this case, as shown in the example of Fig. 8, the current status of work is classified and applied according to the type of work. Figs. 12A and 12B respectively show an example in which the current status of work available in CWP unit for the types of work such as piping and steel is classified by work front type 1 according to future and current standards, as a preferred embodiment of the present invention.
[0064] 13 to 15 show a display unit of a project integration management apparatus according to a preferred embodiment of the present invention.
[0065] An example of classifying CWPs based on the current construction progress status and the current available volume status and displaying them in a grid format will be described with reference to FIGS. 13 and 14.
[0066] The display unit 1300 classifies n CWPs based on the current status of construction progress and the current status of available work volume, and displays them in a grid format 1310. FIG. 13 illustrates an example in which 792 CWPs 1301 are classified based on the current status of construction progress and the current status of available work volume. In FIG. 13, the horizontal axis of the grid format indicates the current status of construction progress by stage (S1310), and the vertical axis indicates the current status of available work volume by stage (S1320). Referring to FIG. 14 further, the horizontal axis first displays the current status of construction progress (S1410) of construction that has already been started on the right side of the x-axis, and then displays the current status of construction progress (S1420) of construction that has not yet been started.
[0067] The display unit 1300 includes a grid group composed of grids showing only the current construction progress stage, and the grids belonging to the grid group include information on the number of CWPs belonging to each current construction progress stage. For example, FIG. 13 shows a grid group composed of six grids, namely, "complete" 1311, "late finish" 1312, "late start" 1313, "in progress" 1314, "target start" 1315, and "before start" 1316. In FIG. 13, of the 792 CWPs 1301, 175 CWPs belong to the "late finish" 1312 stage, 95 CWPs belong to the "late start" 1313 stage, 138 CWPs belong to the "in progress" 1314 stage, 57 CWPs belong to the "target start" 1315 stage, and 105 CWPs belong to the "before start" 1316 stage.
[0068] "Complete" 1311 means that all the results have been completed. "Late finish" 1312 means that the "target plan finish" has been reached as a plan, but the end of at least one individual component unit has been delayed as a result. The individual component units are foundation for civil engineering work, assembly for steel structure work, item for mechanical equipment work, and line for plumbing work. "Late start" 1313 means that the "target plan start" has been reached as a plan, but the start of all the individual component units has been delayed as a result. "In progress" 1314 means that the "target plan start" has been reached within the cut off of this month, next month, or the month after (M+1 / 2 / 3) as a plan, or has not been reached, and that at least one individual component unit has been started or completed as a result. "Target start" 1315 means that the "target plan start" has come as planned, but the actual construction has not yet started. "Before start" 1316 means that the "target plan start" has not come as planned, and the actual construction has not yet started.
[0069] The current status of the amount of workable material (S1320) is classified into “W / FC” 1321, “no W / FE” 1322, and “no W / FP” 1323.
[0070] "W / FC" 1321 indicates a CWP whose current workable quantity status is "enough," "no W / FE" 1322 indicates a CWP whose current workable quantity status is "drawing shortage" or "(all shortage)," and "no W / FP" 1323 indicates a CWP whose current workable quantity status is "material shortage" or "(all shortage)."
[0071] In a preferred embodiment of the present invention, each grid indicates information on a current construction progress stage and a current workable amount stage, and also indicates information on the number of CWPs belonging to the current construction progress stage and the current workable amount stage indicated by the grid.
[0072] For example, the first grid 1341 indicates the current construction progress stage of “late finish” and the current workable quantity stage of “no W / FP” 1323, and indicates that the number of CWPs belonging to this stage is 63 (1341a). In a preferred embodiment of the present invention, risk information can be obtained using position information of each grid constituting the grid pattern.
[0073] The grids 1341, 1342, 1343, and 1344 belonging to the first region 1340 in the grid board 1330 are classified as the highest risk 1345. In FIG. 13, of the 792 CWPs, excluding 222 that have been completed, 570 CWPs are under construction. Of these, 138 CWPs belong to the first region, which is about 25% classified as the highest risk. The grids 1351, 1352, 1353, and 1354 belonging to the second region 1350 are classified as the medium risk 1355. In FIG. 13, of the 570 CWPs under construction, 161 CWPs belong to the second region, which is about 29% classified as the medium risk. The grids 1361, 1362, 1363, and 1364 belonging to the third region 1360 are classified as the low risk 1365. In Fig. 13, of the 570 CWPs under construction, 78 CWPs belong to the third region, and approximately 15% are classified as low risk. The remaining grids 1371, 1372, and 1373 in the other region 1370 are classified as safe (no risk) 1375. In Fig. 13, of the 570 CWPs under construction, approximately 31% are classified as safe (no risk).
[0074] In one preferred embodiment of the present invention, the lattice board 1330 may have a first region 1340, a second region 1350, a third region 1360, and a remaining region 1370 each having a different color.
[0075] FIG. 15 illustrates an example in which the grid of the display performs a filtering function according to a preferred embodiment of the present invention. When the number information 1542a of CWPs in any grid 1542 constituting the grid board is clicked, only the CWP 1510 corresponding to the grid 1542 among n CWPs is filtered, and detailed information of the filtered CWP 1510 is displayed. If there are multiple filtered CWPs, detailed information of each CWP is displayed. The detailed information includes a work type 1501, a CWP area 1502 indicating an area of the smallest unit for managing a project, a CWP identification code 1503 for identifying each CWP, a CWP category 1504, an individual unit identification number 1505, construction schedule information 1520, and material quantity information 1530. The construction schedule information includes information on the current construction status 1521, a target plan start date 1522 and a target plan end date 1523, an actual construction start date 1524, and an actual construction end date 1525. The material quantity information 1530 includes available work quantity current status information 1531 , total material quantity information 1532 , and target material quantity information 1533 .
[0076] Methods according to embodiments of the present invention may be embodied in the form of program instructions executable by various computer means and recorded on a computer readable medium. The computer readable medium may include, alone or in combination with, program instructions, data files, data structures, and the like. The program instructions recorded on the medium may be those specially designed and constructed for the present invention, or they may be well known and available to those skilled in the art of computer software.
[0077] As described above, even if the present invention has been described using limited embodiments and drawings, the present invention is not limited to the above-described embodiments, and various modifications and variations are possible from such descriptions if one has ordinary knowledge in the field to which the present invention pertains.
Claims
1. A classification unit that classifies the project into n construction work packages (CWPs) based on the construction types constituting the project, the minimum unit area for managing the project, and design information; a display unit for classifying the n sub-project CWPs based on a construction progress status and a constructable quantity status and displaying the classified sub-project CWPs in a grid format; Including, The horizontal axis of the grid indicates the current status of construction work by stage, and the vertical axis indicates the current status of the amount of work that can be performed by stage. Each grid indicates information on the current status of construction work and the current status of the amount of work that can be performed. Each grid indicates the number of sub-projects CWPs that belong to the current status of construction work and the current status of the amount of work that can be performed that the grid indicates. On the horizontal axis, the current status of construction work that has already been started is displayed on the right side of the x-axis, and then the current status of construction work that has not been started is displayed. If the work type is piping, the current status of the amount of workable material is calculated by dividing it into a current standard and a future standard. When calculating the future standard, three simulations are independently performed in sequence based on a line, which is an individual component unit of piping, in the order of a weld map in a detailed drawing state for actual construction, an ISO drawing, which is a drawing state before detailed construction drawings are created, and a 3D, which is a state before the line drawings are created. Procurement and inventory and scheduled materials are matched to the line set according to the priority order, and the current status of the amount of workable material in each component unit is first calculated, and then the results are summed up by the sub-project CWP unit to derive the current status of the amount of workable material by CWP. A project integration management device comprising:
2. The display unit grasps a degree of danger using position information of each grid constituting the grid pattern and displays the degree of danger information.
2. The project integration management device according to claim 1.
3. When the number information of the sub-project CWPs in each grid is clicked, only the sub-project CWPs corresponding to the grid among the n sub-project CWPs are filtered, and detailed information of each of the filtered sub-project CWPs is displayed.
2. The project integration management device according to claim 1.
4. The display unit further includes a grid group composed of grids showing only a construction progress status stage, and the grids belonging to the grid group include information on the number of sub-projects CWP belonging to each construction progress status stage.
2. The project integration management device according to claim 1.
5. When calculating the current status of the workable quantity based on the current standard, only the weld map is simulated and the procured and in-stocked materials are matched to the lines set according to the priority order.
2. The project integration management device according to claim 1.
6. The types of work include piping, steel, machinery and equipment, and civil engineering. The current status of the amount of work that can be performed is calculated by first calculating the current status of the amount of work that can be performed in individual component units for each type of work based on at least one of drawings and materials according to the type of work that constitutes the project, and then adding up the results in the sub-project CWP unit to derive the current status of the amount of work that can be performed by CWP.
2. The project integration management device according to claim 1.
7. classifying the project into n construction work packages (CWPs) based on the construction types constituting the project, the minimum unit area for managing the project, and design information in a classification unit; classifying the n sub-project CWPs based on a construction progress status and a constructable quantity status in a display unit and displaying the classified sub-project CWPs in a grid format; Including, The horizontal axis of the grid indicates the current status of construction work by stage, and the vertical axis indicates the current status of the amount of work that can be performed by stage. Each grid indicates information on the current status of construction work and the current status of the amount of work that can be performed. Each grid indicates the number of sub-projects CWPs that belong to the current status of construction work and the current status of the amount of work that can be performed that the grid indicates. On the horizontal axis, the current status of construction work that has already been started is displayed on the right side of the x-axis, and then the current status of construction work that has not been started is displayed. If the work type is piping, the current status of the amount of workable material is calculated by dividing it into a current standard and a future standard. When calculating the future standard, three simulations are independently performed in sequence based on a line, which is an individual component unit of piping, in the order of a weld map in a detailed drawing state for actual construction, an ISO drawing, which is a drawing state before detailed construction drawings are created, and a 3D, which is a state before the line drawings are created. Procurement and inventory and scheduled materials are matched to the line set according to the priority order, and the amount of workable material per individual component unit is first calculated, and then the amounts are summed up by the sub-project CWP unit to derive the amount of workable material per CWP. A project integration management method comprising:
8. The display unit may further include determining a degree of danger using position information of each grid constituting the grid pattern and displaying the degree of danger as risk information.
8. The project integration management method according to claim 7.
9. classifying the project into n construction work packages (CWPs) based on the construction types constituting the project, the minimum unit area for managing the project, and design information in a classification unit; classifying the n sub-project CWPs based on a construction progress status and a constructable quantity status in a display unit and displaying the classified sub-project CWPs in a grid format; Including, The horizontal axis of the grid indicates the current status of construction progress by stage, and the vertical axis indicates the current status of the amount of work that can be performed by stage, and each grid indicates information on the current status of construction progress and the current status of the amount of work that can be performed, and each grid indicates the number of sub-project CWPs belonging to the current status of construction progress and the current status of the amount of work that can be performed that the grid indicates, The method further includes a step of filtering out only the sub-project CWPs corresponding to the grid among the n sub-project CWPs by clicking on the number information of the sub-project CWPs in each grid, and in this case, displaying detailed information of each of the filtered sub-project CWPs. A project integration management method comprising:
10. 10. A computer-readable recording medium having recorded thereon a program for executing the project integration management method according to claim 7.
Citation Information
Patent Citations
Boiler small-diameter pipeline construction method based on BIM technology
CN107256318A
Process management support system, process management support method, and process management support program
JP2021179920A
Construction project management system and method
US20050171790A1
Information management detailed task scheduler system
US20160149974A1
Development progress management device and development progress management method
WO2017122285A1