Anchor material and post-installed anchor installation method

The cylindrical steel pipe anchor material with a groove for filler injection and exhaust pipe at the bottom addresses issues of gap formation and filler leakage, enhancing construction efficiency and stability in post-installation anchors.

JP7566249B2Active Publication Date: 2024-10-15广瀬かずみ +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2020046903
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-03-17
Publication Date
2024-10-15
Estimated Expiration
2040-03-17

AI Technical Summary

Technical Problem

Existing post-installation anchors face issues such as loosening due to gaps between the anchor material and the hole wall, filler leakage during injection, and the need for additional injection pipes, leading to inefficient construction processes.

Method used

The anchor material is designed as a cylindrical steel pipe with a groove at the tip for filler injection and an exhaust pipe at the bottom to ensure contact with the anchor hole bottom, allowing direct filler injection and air suction, eliminating the need for separate injection pipes.

Benefits of technology

This design enhances workability by ensuring reliable filler filling and prevents gaps or air pockets, improving the overall construction efficiency and stability of the anchor.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007566249000001
    Figure 0007566249000001
  • Figure 0007566249000002
    Figure 0007566249000002
  • Figure 0007566249000003
    Figure 0007566249000003
Patent Text Reader

Abstract

To provide a hole-in-anchor which can be constructed in a relatively easy manner and which can perform filling with a filling material more reliably, and a construction method for the hole-in anchor.SOLUTION: Provided is a hole-in anchor 1, comprising an anchor material 5 to be inserted within an anchor hole 4 formed in a concrete member, and a filling material 6 for filling a gap between the anchor hole 4 and the anchor material 5. The anchor material 5 is composed of a steel pipe having a length greater than a depth of the anchor hole 4, and a groove 51 penetrating the inside / outside the steel pipe is formed on a tip plane of the anchor material 5.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an anchor material to be installed in a concrete structure and a method for installing a post-installed anchor. [Background technology]

[0002] Post-installed anchors may be installed as joining materials when performing earthquake-resistance reinforcement or repairs on existing concrete structures, when adding auxiliary equipment, when adding new structures, etc. Post-installed anchors are installed by forming anchor holes in the existing concrete structure and fixing the anchor material inserted into the anchor holes.

[0003] As an installation method for such post-installed anchors, Patent Document 1 discloses a method in which an anchor material covered with an expansion sleeve is inserted into an anchor hole and the rear end of the anchor material is struck to expand the expansion sleeve, thereby fixing the expansion sleeve to the inner wall of the anchor hole.

[0004] Furthermore, Patent Document 2 discloses a method for installing a post-installed anchor in which an anchor hole formed in a concrete member is filled with a filler, an anchor bar is inserted into the anchor hole, and the anchor bar is fixed by allowing the filler to solidify.

[0005] Furthermore, Patent Document 3 discloses a method for installing a post-installed anchor in which an anchor material is inserted into an anchor hole formed in a concrete member, and then a filler material is filled into the anchor hole. In the method for installing a post-installed anchor in Patent Document 3, an exhaust pipe is installed in the anchor hole so as to abut against the upper surface of the anchor hole, and the filler material is injected while the air in the anchor hole is exhausted by this exhaust pipe. [Prior art documents] [Patent documents]

[0006] [Patent Document 1] JP 2019-127733 A [Patent Document 2] JP 2019-163668 A [Patent Document 3] JP 2014-001495 A Summary of the Invention [Problem to be solved by the invention]

[0007] In the post-installed anchor of Patent Document 1, although the expanded portion of the expansion sleeve is engaged with the wall of the anchor hole, a gap is formed between the anchor material and the anchor hole in other areas, which may cause the anchor material to become loose due to vibrations or other factors.

[0008] Furthermore, the post-installed anchors of Patent Document 2 must be installed carefully in anchor holes facing upward or sideways, as there is a risk of the filler material flowing out of the anchor hole between the time the filler is injected into the anchor hole and the time the anchor bar is inserted.

[0009] Furthermore, in the post-installed anchor of Patent Document 3, in order to install an injection pipe for injecting a filler material in addition to the anchor material in the anchor hole, it is necessary to form the anchor hole larger than the anchor material. Therefore, drilling the anchor hole and injecting the filler material are time-consuming.

[0010] An object of the present invention is to provide an anchor material and a method of installing a post-installed anchor that can be installed relatively easily and enables filling material to be filled more reliably. [Means for solving the problem]

[0011] The present invention provides an anchor material for solving the above problems, which is inserted into an anchor hole formed in a concrete member and fixed in the anchor hole by a filler material filled in the anchor hole with a tip surface abutting against a bottom surface of the anchor hole, and has a length greater than a depth of the anchor hole, The outer and inner diameters are constant Both ends open circleIt consists of a cylindrical steel pipe, and an injection port is formed at the tip thereof, penetrating the inside and outside of the steel pipe in the diametrical direction.

[0012] The method for installing a post-installed anchor of the present invention uses the anchor material and includes a hole drilling step of drilling a concrete member to form an anchor hole, an anchor material disposing step of inserting the anchor material into the anchor hole, and an injection step of injecting a filler material into the anchor hole. In the injection step, the filler material is pumped through the anchor material and injected into the anchor hole from the injection port while the tip face of the anchor material is in contact with the bottom face of the anchor hole.

[0013] According to the anchor material and the installation method of the post-installed anchor of the present invention, since the anchor material is formed of a steel pipe, the anchor material can be used as an injection pipe for the filler. In addition, since there is no need to install a separate injection pipe, the anchor hole can be formed to a size according to the shape of the anchor material, and the workability is excellent. In addition, since an injection port is formed at the tip of the anchor material, the filler can be injected from the tip of the anchor material while the tip of the anchor material is in contact with the bottom surface of the anchor hole. In other words, by injecting the filler from the bottom of the anchor hole, the filler can be filled more reliably.

[0014] If the injection port is a groove that opens at the end face, the filler can be injected from the bottom face of the anchor hole, which further improves the filling efficiency of the filler. Furthermore, if a male thread is formed at the base end of the anchor material, it becomes easier to attach the new member to the anchor material. Furthermore, if the outer surface of the anchor material is uneven, the anchor material will be more firmly fixed to the filler.

[0015] Furthermore, in the anchor material placement step, an exhaust pipe is inserted so that its tip is positioned at the bottom of the anchor hole, and in the injection step, the air in the anchor hole is sucked in by the exhaust pipe, and the injection of the filler material is stopped at the stage when the filler material has been sucked in by the exhaust pipe, thereby further improving the fillability of the filler material. Furthermore, in the anchor material disposing step, if the opening of the anchor hole is covered with a cover material, outflow of the filler material can be suppressed. Effect of the Invention

[0016] According to the anchor material and the installation method of the post-installed anchor of the present invention, workability is improved and it is possible to more reliably fill the filler material. [Brief description of the drawings]

[0017] [Figure 1] FIG. 1 is a schematic diagram showing a usage situation of a post-installed anchor according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a cross-sectional view showing a post-installed anchor. [Diagram 3] FIG. [Figure 4] FIG. 1 shows a method for installing a post-installed anchor, where (a) is the hole drilling process, (b) is the anchor material installation process, and (c) is the injection process. [Diagram 5] 13(a) and 13(b) are perspective views showing anchor materials according to other embodiments. [Figure 6] 13(a) and 13(b) are perspective views showing anchor materials according to other embodiments. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] In this embodiment, a case where a bridge fall prevention member 3 is installed on a concrete bridge girder (concrete member) 2 of an existing bridge 20 as part of seismic reinforcement of the concrete bridge girder 2 will be described. As shown in FIG. 1, the bridge fall prevention member 3 is fixed to the concrete bridge girder 2 by a post-installed anchor 1. The bridge fall prevention member 3 of this embodiment is a so-called steel bracket, and includes a mounting plate 31 affixed to the underside of the concrete bridge girder 2 at the corner between the concrete bridge girder 2 and the pier 21, a vertical plate 32 extending downward from the end of the mounting plate 31, and a rib member 33 fixed to the mounting plate 31 and the vertical plate 32 so as to be perpendicular to the mounting plate 31 and the vertical plate 32. The bridge fall prevention member 3 is fixed to the underside of the concrete bridge girder 2 by fixing the mounting plate 31 to the base end of the post-installed anchor 1 protruding from the underside of the concrete bridge girder 2.

[0019] First, the post-installed anchor 1 of this embodiment will be described. As shown in Fig. 2, the post-installed anchor 1 is installed upward (for example, vertically) from the underside of a concrete bridge girder (concrete member) 2. The direction of the post-installed anchor 1 may be appropriately determined according to the purpose of use and the installation location, and is not limited to upward (vertical direction).

[0020] The post-installed anchor 1 is composed of an anchor material 5 inserted into an anchor hole 4 formed in a concrete bridge girder 2, and a filler material 6 filled in the gap between the anchor hole 4 and the anchor material 5. Non-shrink mortar is used for the filler material 6. Note that the material constituting the filler material 6 is not limited to non-shrink mortar as long as it is capable of fixing the anchor material 5 in the anchor hole 4, and may be, for example, concrete or a resin hardening material.

[0021] The anchor material 5 is made of a steel pipe having a length greater than the depth of the anchor hole 4. As shown in FIG. 2, the steel pipe constituting the anchor material 5 is cylindrical and has sufficient strength as a fixing member for the bridge fall prevention member 3. The cross-sectional shape of the steel pipe constituting the anchor material 5 is not limited to a circle, and may be, for example, a square or other polygon. As shown in FIG. 3, a male thread 52 for attaching the bridge fall prevention member 3 is formed at the base end of the anchor material 5 (the lower end in FIG. 2). The male thread 52 is formed at the portion (base end of the anchor material 5) that protrudes from the anchor hole 4 when the anchor material 5 is disposed in the anchor hole 4. The male thread 52 may be formed as necessary.

[0022] A groove 51 having a rectangular cross section is formed on the tip surface (the upper end surface in FIG. 2 ) of the anchor material 5, penetrating (diametrically) the inside and outside of the steel pipe. In this embodiment, four grooves 51 are formed at equal intervals in the circumferential direction of the steel pipe. The grooves 51 function as injection ports 51 when injecting the filler material 6 into the anchor hole 4. The cross-sectional shape, width, and depth of the grooves 51 are not limited as long as they are shapes that do not hinder the flow of the filler material 6, and may be, for example, U-shaped, semicircular, or triangular. The number and arrangement of the grooves 51 are not limited, and may be appropriately determined depending on the size and shape of the steel pipe (anchor material 5).

[0023] Next, we will explain the installation method of the post-installed anchor 1. The installation of the post-installed anchor 1 is performed by a hole drilling step, an anchor material disposing step, an injection step, and a cap removal step. The drilling step is a step of drilling a hole in the concrete bridge girder 2 to form an anchor hole 4, as shown in FIG. 4(a). The anchor hole 4 in this embodiment is formed upward from the lower surface of the concrete bridge girder 2. The anchor hole 4 has a cylindrical shape with an inner diameter larger than the outer diameter of the anchor material 5. The depth of the anchor hole 4 is a length that ensures the fixing length of the anchor material 5. The shape of the anchor hole 4 is not limited to a cylindrical shape, and may be, for example, a polygonal shape or may have an enlarged diameter portion at the tip or the like. After the anchor hole 4 is formed, it is desirable to clean the inside of the anchor hole 4 and remove concrete pieces remaining in the anchor hole 4.

[0024] 4(b), the anchor material disposing step is a step of inserting the anchor material 5 into the anchor hole 4. The tip surface of the anchor material 5 is brought into contact with the bottom surface (upper end) of the anchor hole 4. At this time, the base end portion (male thread 52) of the anchor material 5 protrudes from the opening of the anchor hole 4.

[0025] In the anchor material disposing step, the exhaust pipe 7 is inserted into the anchor hole 4 together with the anchor material 5. The exhaust pipe 7 is piped so that its tip is located at the bottom surface (upper end) of the anchor hole 4. At this time, it is preferable to pipe the exhaust pipe 7 so that its tip abuts against the bottom surface (upper end) of the anchor hole 4. The exhaust pipe 7 is made of a resin tube and has an outer diameter smaller than that of the anchor material 5. In addition, the length of the exhaust pipe 7 is greater than the depth of the anchor hole 4, and the base end of the exhaust pipe 7 is extended from the opening of the anchor hole 4 and connected to the vacuum pump P1. The material constituting the exhaust pipe 7 is not limited, and may be, for example, a polyvinyl chloride pipe or a steel pipe. The anchor material 5 and the exhaust pipe 7 may be inserted into the anchor hole 4 individually, or the exhaust pipe 7 may be attached to the anchor material 5 and inserted into the anchor hole 4.

[0026] After the anchor material 5 and the exhaust pipe 7 are inserted into the anchor hole 4, the opening of the anchor hole 4 is covered by the cover material 8. The cover material 8 is formed with a through hole 81 for inserting the anchor material 5 and the exhaust pipe 7, and is temporarily fixed to the underside of the concrete bridge girder 2 with the anchor material 5 and the exhaust pipe 7 inserted into the through hole 81. The method of fixing the cover material 8 to the concrete bridge girder 2 is not limited, and for example, a screw 82 that penetrates the cover material 8 may be fastened to the periphery of the anchor hole 4. The cover material 8 functions as a formwork when filling the filling material 6. The cover material 8 also functions as a temporary fixing member for the anchor material 5 and the exhaust pipe 7. The anchor material 5 and the exhaust pipe 7 may be temporarily fixed by a jig provided separately from the cover material 8.

[0027] The injection step is a step of injecting the filler 6 into the anchor hole 4, as shown in FIG. 4(c). The anchor material 5 is used to inject the filler 6 into the anchor hole 4. That is, a transport pipe 61 extending from the injection pump P2 is connected to the anchor material 5, and the filler 6 pumped by the injection pump P2 through the transport pipe 61 is injected from the anchor material 5 into the anchor hole 4. The filler 6 pumped through the anchor material 5 is discharged from the groove (injection port) 51 into the anchor hole 4. In the anchor hole 4, the filler 6 falls to the hole mouth side (on the cover material 8) and rises from the lower side (hole mouth side) of the anchor hole 4. When the post-installed anchor 1 is oriented horizontally or downward, the filler 6 is filled from the bottom of the anchor hole 4.

[0028] In the injection process, as the filler 6 is injected, the air in the anchor hole 4 is sucked in by the exhaust pipe 7. By sucking the air into the anchor hole 4 by the exhaust pipe 7, air is less likely to remain at the upper end of the anchor hole 4, and the formation of an air pocket (unfilled area) at the upper end of the anchor hole 4 is suppressed or the formation of an air pocket at the upper end of the anchor hole 4 is minimized.

[0029] When the top surface of the injected filler material 6 rises to the upper end of the anchor hole 4 and the filler material 6 is sucked in by the exhaust pipe 7 (when the filler material 6 is discharged from the base end of the exhaust pipe 7), the injection of the filler material 6 is stopped. As the injection of the filler material 6 stops, the suction of air by the exhaust pipe 7 is stopped. The exhaust pipe 7 is shielded to prevent air from flowing back and being sent into the anchor hole 4. The base end of the anchor material 5 is also shielded as necessary.

[0030] The lid removal process is a process of removing the lid material 8 after the filling material 6 has been cured. When the lid material 8 is removed, the exhaust pipe 7 is cut on the surface of the concrete bridge girder 2. After removing the cover material 8, the bridge fall prevention member 3 is installed using the anchor material 5. The bridge fall prevention member 3 is fixed by screwing a nut onto the male thread 52 of the anchor material 5 with the anchor material 5 inserted into the through hole formed in the mounting plate 31.

[0031] According to the post-installed anchor 1 (anchor material 5) and the installation method of the post-installed anchor 1 of this embodiment, the anchor material 5 is formed of a steel pipe, so the anchor material 5 can be used as an injection pipe for the filler material 6. Therefore, there is no need to install an injection pipe separate from the anchor material 5 in the anchor hole 4, and workability is excellent. In addition, since there is no need to install an injection pipe separate from the anchor material 5 in the anchor hole 4, the anchor hole 4 can be formed to a size according to the shape of the anchor material 5.

[0032] Furthermore, because groove 51 is formed on the tip surface of anchor material 5, filler material 6 can be injected with the tip of anchor material 5 in contact with the bottom surface of anchor hole 4. Injecting filler material 6 from the bottom of anchor hole 4 makes it possible to more reliably fill filler material 6. That is, by injecting filler material 6 along the bottom surface of anchor hole 4 from groove 51 formed on the tip of anchor material 5 without providing a gap between the tip of anchor material 5 (injection pipe) and the bottom surface of anchor hole 4, the formation of an unfilled portion at the bottom (upper end) of anchor hole 4 is suppressed.

[0033] Furthermore, since the filler 6 is injected while exhausting air from the top of the anchor hole 4 through the exhaust pipe 7, air is less likely to remain in the anchor hole 4. Therefore, gaps are less likely to form between the post-installed anchor 1 and the concrete member, enabling high-quality construction.

[0034] The embodiment of the present invention has been described above. However, the present invention is not limited to the above embodiment, and each of the above components can be appropriately modified without departing from the spirit of the present invention. For example, in the above embodiment, the case where the post-installed anchor 1 is used to fix the bridge fall prevention member 3 to the existing bridge 20 has been described, but the use of the post-installed anchor 1 is not limited. In addition, the concrete member in which the post-installed anchor 1 is installed is not limited to the concrete bridge girder 2.

[0035] In the above embodiment, the male thread 52 is formed at the base end of the anchor material 5, but the male thread 52 may be formed as necessary. For example, in cases where a newly constructed concrete member is spliced ​​to an existing concrete member, or in other cases where the base end of the anchor material 5 is embedded in the concrete member with a predetermined fixing length secured, the male thread 52 does not need to be formed.

[0036] Furthermore, as shown in Figures 5(a) and (b), unevenness may be formed on the outer surface of the anchor material 5. If unevenness is formed on the outer surface of the anchor material 5, pull-out resistance is improved. As the unevenness of the anchor material 5, for example, as shown in Figure 5(a), knots 53 like those of a deformed bar may be formed, or as shown in Figure 5(b), a spiral ridge 54 may be formed.

[0037] In the above embodiment, the anchor material 5 has a groove-shaped injection port (groove) 51 that opens at the end face. However, the shape of the injection port 51 is not limited, and may be, for example, a through hole formed at the tip of the anchor material 5 so as to penetrate the inside and outside of the anchor material 5, as shown in FIG. 6(a). In this case, the shape of the injection port 51 is not limited, and may be a rectangle, a circle, an ellipse, or the like. The injection port 51 may be formed in multiple stages at the tip of the anchor material 5. In this case, the injection port 51 may include a groove 51 formed at the end face of the anchor material 5 and a through hole formed at the end of the anchor material 5 (see FIG. 6(b)).

[0038] Moreover, the exhaust pipe 7 may be installed as required. Furthermore, the lid material 8 may be used as necessary. For example, when the viscosity of the filler 6 is high and the filler 6 does not flow out of the anchor hole 4, the lid material 8 may be omitted. [Explanation of symbols]

[0039] 1 Post-installed anchors 2. Concrete bridge girders (concrete components) 4 Anchor holes 5 Anchor material 51 Groove (inlet) 52 Male thread 6 Filling material 7. Exhaust pipe 8 Lid material

Claims

1. An anchor material that is inserted into an anchor hole formed in a concrete member and is fixed in the anchor hole by a filler material filled in the anchor hole with a tip surface abutting against a bottom surface of the anchor hole, The anchor hole is formed of a cylindrical steel pipe having a length greater than the depth of the anchor hole, a constant outer diameter and an inner diameter, and open at both ends. An anchor material characterized in that an injection port is formed at the tip portion, penetrating the inside and outside of the steel pipe in the diameter direction.

2. 2. The anchor material according to claim 1, wherein the injection port is a groove that opens at an end face.

3. 3. The anchor material according to claim 1, further comprising a male thread formed at a base end portion.

4. 4. The anchor material according to claim 1, wherein the outer surface of the anchor material is uneven.

5. A method for installing a post-installed anchor using the anchor material according to any one of claims 1 to 4, A drilling step of drilling a concrete member to form an anchor hole; an anchor material disposing step of inserting the anchor material into the anchor hole; and an injection step of injecting a filler material into the anchor hole, a filler material pressure-fed through the anchor material and injected into the anchor hole from the injection port while a tip surface of the anchor material is brought into contact with a bottom surface of the anchor hole, the filler material being pressure-fed through the anchor material.

Citation Information

Patent Citations

  • JP1982041999U

  • Anchoring material filling method and seal unit

    JP1998077800A

  • Mechanical anchor for injecting adhesive, and steel plate bonding device for concrete structure

    JP2004316286A

  • Method for fixing hole-in anchor bolt device and hole-in anchor bolt device for use therein

    JP2011247049A

  • Anchor member anchorage method of existing concrete structure

    JP2014001495A