Hot water production system

A hybrid hot water production system using a heat pump and steam boiler optimizes energy efficiency and reduces emissions by adjusting output sharing, addressing the inefficiencies of heat pumps at high temperatures.

JP7574903B2Active Publication Date: 2024-10-29MIURA CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2023187945
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-11-01
Publication Date
2024-10-29
Estimated Expiration
2039-02-14

AI Technical Summary

Technical Problem

Existing hot water production systems using heat pumps face reduced energy efficiency and increased emissions when producing high-temperature hot water, leading to higher running costs and lower CO2 reduction effectiveness.

Method used

A hybrid system combining a heat pump water heater and a steam boiler, where water is initially heated to a first temperature by the heat pump and then further heated to a higher temperature using steam, with a control mechanism to adjust the output sharing between the two systems based on target hot water temperature.

Benefits of technology

The system effectively reduces CO2 emissions and running costs while maintaining high energy efficiency by optimizing the use of both heat pump and steam boiler, even when producing high-temperature hot water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007574903000001
    Figure 0007574903000001
  • Figure 0007574903000002
    Figure 0007574903000002
  • Figure 0007574903000003
    Figure 0007574903000003
Patent Text Reader

Abstract

To provide a hot water producing system which has increased reduction effect of a CO2 emission amount and reduces running cost, even when an output hot water temperature is high.SOLUTION: A hot water producing system 1 includes first heating means 2 which heats service water W1 to a first temperature while the service water is made to flow through a condenser 92 of a heat pump type water heater of a heat pump type hot water system 10, and second heating means 3 which exchanges the heat of the service water heated by the first heating means 2 directly with steam S generated from a steam boiler device 30, so as to heat the service water to a second temperature higher than the first temperature.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a hot water producing system. [Background technology]

[0002] 2. Description of the Related Art Conventionally, hot water producing systems have been known. For example, Patent Document 1 discloses a system that produces hot water using a heat pump in order to wash or sterilize workpieces such as food with hot water. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2009-133522 A Summary of the Invention [Problem to be solved by the invention]

[0004] Currently, many factories and business establishments are working on "decarbonization" to move away from fossil fuels in order to reduce emissions of CO2, a typical greenhouse gas. As a result, as shown in Patent Document 1, systems using heat pumps are increasingly being adopted as systems for producing hot water. However, heat pumps have the characteristic that, although the COP (coefficient of performance) is high and the effect of reducing CO2 emissions is high when the hot water outlet temperature is low, the COP is low and the effect of reducing CO2 emissions is also reduced when the hot water outlet temperature is increased. In addition, when the hot water outlet temperature is increased, the running costs are also high because the COP is low.

[0005] The present invention has been made in consideration of the above-mentioned problems, and its object is to provide a hot water production system that is highly effective in reducing CO2 emissions and can reduce running costs even when the outlet hot water temperature is increased. [Means for solving the problem]

[0006] The present invention relates to a hot water production system comprising a first heating means (e.g., first heating means 2) that heats service water to a target hot water temperature while flowing it through a heat pump water heater (e.g., a water heater of a heat pump water heater system 10), a second heating means (e.g., second heating means 3) that directly exchanges heat with steam generated in a steam boiler (e.g., a steam boiler device 30) and adjusted to a target steam pressure, thereby raising the temperature of the service water to a target hot water outlet temperature that is set higher than the target hot water temperature, and a control means that controls the first heating means and the second heating means, wherein the control means adjusts the output share of the water heater and the steam boiler in accordance with the set target hot water outlet temperature.

[0007] In addition, it is preferable that the second heating means has a steam header (e.g., steam header 51) that collects steam generated in the steam boiler, and a heating steam supply valve (e.g., heating steam supply valve 54) that adjusts the amount of steam supplied from the steam header, and that the control means has a boiler control unit (e.g., boiler control unit 120) that controls the steam boiler so that the header pressure of the steam header becomes the target steam pressure, and a steam supply control unit (e.g., steam supply control unit 130) that controls the heating steam supply valve so that the hot water discharged from the second heating means becomes the set target hot water discharge temperature.

[0008] The second heating means includes a hot water tank (e.g., hot water tank 40) for storing hot water heated by the hot water heater, a first water level sensor (e.g., first water level sensor 42) for detecting a water level in the hot water tank, a heating steam supply line (e.g., heating steam supply line L2) for supplying steam generated by the steam boiler to the hot water tank, a heating steam supply valve (e.g., heating steam supply valve 54) provided in the heating steam supply line, and a hot water storage temperature sensor for detecting the temperature of the hot water in the hot water tank, and the first heating means includes a water supply line for supplying water to the hot water heater, a hot water supply line for supplying the hot water heated by the hot water heater to the hot water tank, and a hot water supply temperature sensor (e.g., , a hot water storage temperature sensor 41), and when the water level detected by the first water level sensor falls below a first set water level when the water level in the hot water tank drops, the control means executes the supply of service water via the water supply line and the supply of hot water via the hot water supply line, and when the water level detected by the first water level sensor rises above a second set water level that is higher than the first set water level, the control means stops the supply of service water via the water supply line and the supply of hot water via the hot water supply line, and when the water level detected by the first water level sensor rises above a second set water level that is higher than the first set water level, it is preferable that the control means controls the water heater so that the temperature detected by the hot water supply temperature sensor becomes the target hot water temperature when the supply of service water is being executed, and controls the opening of the heating steam supply valve so that the temperature detected by the hot water storage temperature sensor becomes the target hot water outlet temperature.

[0009] The system also includes a bypass water supply line (e.g., bypass water supply line L5) that supplies water to the hot water tank without passing through the water heater, and a bypass water supply valve (e.g., bypass water supply valve 62) provided on the bypass water supply line, and when the water level detected by the first water level sensor falls below a third set water level that is lower than the first set water level when the water level in the hot water tank drops, the control means opens the bypass water supply valve and controls the opening of the heating steam supply valve to full open, and when the water level detected by the first water level sensor rises above a fourth set water level that is higher than the third set water level when the water level in the hot water tank rises, the control means closes the bypass water supply valve, and it is preferable that the amount of steam supplied when the bypass water supply valve is open is greater than the amount of steam supplied when the bypass water supply valve is closed.

[0010] In addition, the present invention includes a bypass water supply line that supplies water to the hot water tank without passing through the water heater, a bypass water supply valve provided on the bypass water supply line, a preheating heat exchanger (e.g., preheating heat exchanger 75) that indirectly exchanges heat between the water flowing through the bypass water supply line and steam, a preheating steam supply line (e.g., preheating steam supply line L10) that supplies steam generated by the steam boiler to the preheating heat exchanger, and a preheating steam supply valve provided on the preheating steam supply line. It is preferable that the control means is provided with a steam supply valve (e.g., a preheating steam supply valve 76), and when the water level detected by the first water level sensor falls below a third set water level that is lower than the first set water level when the water level in the hot water tank drops, the control means opens the bypass water supply valve and also opens the preheating steam supply valve, and when the water level detected by the first water level sensor exceeds a fourth set water level that is higher than the third set water level when the water level in the hot water tank rises, the control means closes the bypass water supply valve.

[0011] The system also includes a temperature control heat exchanger (e.g., temperature control heat exchanger 70) that indirectly exchanges heat between the hot water discharged from the hot water tank and steam, a temperature control steam supply line (e.g., temperature control steam supply line L9) that supplies steam generated in the steam boiler to the temperature control heat exchanger, a temperature control steam supply valve (e.g., temperature control steam supply valve 72) provided in the temperature control steam supply line, and a hot water outlet temperature sensor (e.g., hot water outlet temperature sensor 71) that detects the hot water outlet temperature of the temperature control heat exchanger, and it is preferable that the control means controls the opening of the temperature control steam supply valve so that the temperature detected by the hot water outlet temperature sensor becomes the target hot water outlet temperature.

[0012] Furthermore, it is preferable that the first heating means includes multiple water heaters (e.g., water heaters 11, 12, 13), and the hot water tank has multiple water level thresholds set for changing the number of water heaters in operation, and that the control means executes number control to increase the number of water heaters in operation by one each time the water level detected by the first water level sensor falls below the water level threshold by one step when the water level in the hot water tank drops, and to execute number control to decrease the number of water heaters in operation by one each time the water level detected by the first water level sensor exceeds the water level threshold by one step when the water level in the hot water tank rises.

[0013] Further, the first heating means includes a plurality of the water heaters (e.g., water heaters 11, 12, 13), and the hot water tank is set with a plurality of water level thresholds for changing the number of the water heaters in operation and / or the target hot water temperature, and the water heaters are capable of switching between a plurality of target hot water temperatures in a temperature range higher than a first temperature and lower than the target hot water outlet temperature, and the control means executes control to raise the target hot water temperature of the water heater by one step while maintaining the number of the water heaters in operation when the water level detected by the first water level sensor exceeds the water level threshold by one step during operation with the target hot water temperature of the water heater set to the first temperature, and executes control to raise the target hot water temperature of the water heater by one step while maintaining the number of the water heaters in operation, and executes control to raise the target hot water temperature of the water heater by one step when the water level detected by the first water level sensor exceeds the water level threshold by one step during operation with the target hot water temperature of the water heater increased by one step or more. When the target hot water temperature of the water heater is set to the first temperature, control is executed to reduce the number of operating water heaters by one and at the same time return the target hot water temperature to the first temperature, or control is executed to further increase the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters, and when the water level detected by the first water level sensor falls one step below the water level threshold while operating with the target hot water temperature of the water heater set to the first temperature, control is executed to increase the number of operating water heaters by one and at the same time increase the target hot water temperature of the water heater by one or more steps, and when the water level detected by the first water level sensor falls one step below the water level threshold while operating with the target hot water temperature of the water heater increased by one or more steps, control is executed to decrease the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters.

[0014] It is also preferable to provide a water supply tank (e.g., water supply tank 60) for storing water to be supplied to the water heater and / or water supply to the steam boiler, and a switching means (e.g., switching means 80) for switching the destination of hot water supplied from the water heater to the hot water tank or the water supply tank.

[0015] It is also preferable that the first heating means includes a plurality of the water heaters, and the hot water tank has a plurality of water level thresholds set for changing the number of hot water heaters, and the control means controls the switching means to increase the number of hot water heaters for the hot water tank by one each time the water level detected by the first water level sensor falls below the water level threshold by one step, while simultaneously decreasing the number of hot water heaters for the water supply tank by one, when the water level in the hot water tank drops, and to control the switching means to decrease the number of hot water heaters for the hot water tank by one each time the water level detected by the first water level sensor exceeds the water level threshold by one step, while simultaneously increasing the number of hot water heaters for the water supply tank by one, when the water level in the hot water tank rises.

[0016] It is also preferable that a second water level sensor is provided for detecting the water level in the water supply tank, and the control means stops the water heater that is supplying hot water to the water supply tank when the water level detected by the second water level sensor reaches the water supply stop water level, and operates the water heater that is stopped when the detected water level reaches the water supply start water level.

[0017] The present invention also relates to a hot water production method that includes a first heating step of heating water to a target hot water temperature while flowing it through a heat pump water heater (e.g., a water heater of a heat pump water heater system 10), and a second heating step of directly exchanging heat with steam generated in a steam boiler (e.g., a steam boiler device 30) and adjusted to a target steam pressure, to raise the temperature of the water to a target hot water outlet temperature that is set higher than the target hot water temperature, and that adjusts the output share of the water heater and the steam boiler according to the set target hot water outlet temperature when the first heating step and the second heating step are performed. Effect of the Invention

[0018] According to the present invention, it is possible to provide a hot water producing system that is highly effective in reducing CO2 emissions and is also capable of reducing running costs, even when the outlet hot water temperature is increased. [Brief description of the drawings]

[0019] [Figure 1] 1 is a schematic diagram showing a hot water producing system according to a first embodiment of the present invention. [Diagram 2] FIG. 2 is a diagram showing a heat pump circuit of the water heater of the embodiment. [Diagram 3] FIG. 2 is a functional block diagram showing a configuration of a control unit in the embodiment. [Figure 4] FIG. 4 is a schematic diagram for explaining the hot water storage control of the embodiment. [Diagram 5] A diagram showing the number of operating water heaters and the total amount of make-up water in the hot water storage control of the above embodiment. [Figure 6] FIG. 6 is a diagram showing a modified example of the hot water storage control shown in FIG. [Figure 7] FIG. 1 is a schematic diagram showing a first comparative example in which a hot water producing system is constructed using only steam from a steam boiler device as heating means. [Figure 8] FIG. 11 is a schematic diagram showing a second comparative example in which a hot water production system is constructed using only a heat pump hot water supply system as a heating means. [Figure 9] FIG. 2 is a schematic diagram showing the hot water producing system of the embodiment. [Figure 10] 6 is a graph showing the effects of the above embodiment. [Figure 11] FIG. 4 is a schematic diagram showing a hot water producing system according to a second embodiment of the present invention. [Figure 12] FIG. 11 is a schematic diagram showing a hot water producing system according to a third embodiment of the present invention. [Figure 13] FIG. 11 is a schematic diagram showing a hot water producing system according to a fourth embodiment of the present invention. [Figure 14] FIG. 4 is a schematic diagram for explaining the contents of the hot water temperature control in the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] First Embodiment Hereinafter, a hot water producing system 1 according to a first embodiment of the present invention will be described with reference to the drawings. Note that in this specification, the term "line" is a general term for a line, such as a flow path, a pathway, or a pipe, through which a fluid can flow.

[0021] 1 is a schematic diagram showing a hot water production system 1 of this embodiment. The hot water production system 1 of this embodiment includes a first heating means 2 that heats service water W1 to a first temperature while passing it through (through) a condenser of a heat pump water heater, and a second heating means 3 that directly exchanges heat between the service water W1 heated by the first heating means 2 and steam S generated by a steam boiler, thereby raising the temperature to a second temperature higher than the first temperature.

[0022] The first heating means 2 is composed of a heat pump type hot water supply system 10 and includes a plurality of heat pump type hot water heaters, in this embodiment, a first heat pump type hot water heater 11, a second heat pump type hot water heater 12, and a third heat pump type hot water heater 13 (hereinafter also referred to as the first hot water heater 11, the second hot water heater 12, and the third hot water heater 13). Each of the heat pump type hot water heaters 11, 12, and 13 (hereinafter also referred to as the hot water heaters 11, 12, and 13) preferably has an electrically driven refrigerant compressor, and heats the water W1 supplied from a water supply tank 60 described later to a first temperature, for example, 50 to 70°C, by circulating it through a condenser of the heat pump type hot water supply system 10.

[0023] Here, the multiple water heaters 11, 12, and 13 all have the same configuration, and each water heater has a heat pump circuit 90. Therefore, the heat pump circuit 90 of the first water heater 11 will be described as a representative of these. As shown in Fig. 2, the heat pump circuit 90 of the first water heater 11 includes a refrigerant compressor 91, a condenser 92, an expansion valve 93, and an evaporator 94. The refrigerant compressor 91, the condenser 92, the expansion valve 93, and the evaporator 94 are connected in sequence in a ring shape by a refrigerant circulation line L7, thereby forming the heat pump circuit 90.

[0024] The electrically driven refrigerant compressor 91 has a motor 95 as a drive source, and compresses gaseous refrigerant R such as fluorocarbon gas into a high-temperature, high-pressure refrigerant. The condenser 92 condenses and liquefies the refrigerant R from the refrigerant compressor 91. The expansion valve 93 reduces the pressure and temperature of the refrigerant R by passing the refrigerant R sent from the condenser 92. The evaporator 94 evaporates the refrigerant R sent from the expansion valve 93 using heat source water W8 sent through a heat source water supply line L8 as a heat source. Note that the heat source water supply line L8 is not shown in FIG. 1.

[0025] The heat source of the heat pump circuit 90 is not limited to heat source water such as waste hot water, but various heat source gases such as exhaust gas (combustion gas, exhaust steam, etc.) from factory facilities, cooling air containing waste heat, and outside air not containing waste heat can be used. If the evaporator is structured such that the heat transfer surface is exposed to the outside, the heat source gas is supplied to the heat transfer surface by a fan (for example, atmospheric ventilation). If the evaporator is structured such that the heat transfer surface is present within a closed space (for example, a shell), the heat source gas is supplied to the heat transfer surface by a blower.

[0026] Thus, in the heat pump circuit 90 of the first hot water heater 11, the refrigerant R absorbs heat from the outside and vaporizes in the evaporator 94, while the refrigerant R radiates heat to the outside and condenses in the condenser 92. Using this principle, the heat pump circuit 90 of the first hot water heater 11 pumps up heat from the heat source water W8 in the evaporator 94, and heats the water W1 from the heat pump water supply line L3 in the condenser 92. The water W1, which has been heated by passing through the condenser 92 and turned into hot water, is supplied to the hot water tank 40, which will be described later, through the hot water supply line L1.

[0027] In addition, in the heat pump circuit 90 of the first hot water heater 11, the opening degree of the expansion valve 93 is adjusted so that the degree of superheating of the refrigerant R (the inlet refrigerant temperature of the refrigerant compressor 91) is constant, or so that the degree of subcooling of the refrigerant R (the inlet refrigerant temperature of the expansion valve 93) is constant.

[0028] The heat pump circuit 90 of the first hot water heater 11 may be configured to be able to change its output. For example, the rotation speed of the motor 95 of the refrigerant compressor 91 may be configured to be able to be changed by inverter control.

[0029] 1, each of water heaters 11, 12, 13 is provided with a hot water temperature sensor 14, 15, 16 that detects the hot water temperature from each of water heaters 11, 12, 13. Note that hot water temperature sensors 14, 15, 16 only need to be provided in water heaters 11, 12, 13, and may be provided within water heaters 11, 12, 13 or may be provided downstream of water heaters 11, 12, 13 in hot water supply line L1 before the junction.

[0030] Water W1 (hereinafter, also referred to as hot water W1) that has been heated by a plurality of water heaters 11, 12, 13 is joined together by a hot water supply line L1 and then supplied to a hot water tank 40, which will be described later.

[0031] Next, the second heating means 3 will be described. The second heating means 3 includes a steam boiler device 30, a hot water tank 40, and a heating steam supply line L2 that supplies steam S generated by the steam boiler device 30 to the hot water tank 40. The steam boiler device 30 is preferably a steam boiler having a gas-fired or oil-fired burner, and is composed of, for example, a plurality of once-through boilers 31 that generate steam S. The second heating means 3 uses the steam S generated by the steam boiler device 30 to heat the service water W1 heated by the first heating means 2 to a second temperature higher than the first temperature.

[0032] The temperature-raising steam supply line L2 includes a steam header 51 in which steam S generated in the multiple once-through boilers 31 is collected, a connection line 52 that connects the multiple once-through boilers 31 to the steam header 51, and a steam supply line 53 that supplies the steam S collected in the steam header 51 to the hot water tank 40. The steam supply line 53 is provided with a temperature-raising steam supply valve 54. The steam header 51 is also provided with a pressure gauge 55 for detecting the header pressure.

[0033] The hot water tank 40 stores the hot water W1 supplied from the first heating means 2. In addition, the steam S from the steam boiler device 30 is supplied to the hot water tank 40 through the heating steam supply line L2. As a result, the hot water TW (hereinafter also referred to as the stored water TW) stored in the hot water tank 40 is heated to a second temperature, for example, 75 to 95°C, which is higher than the first temperature. That is, by blowing the steam S into the hot water tank 40, direct heat exchange is performed between the hot water TW stored in the hot water tank 40 and the steam S from the steam boiler device 30, and as a result, the hot water TW stored in the hot water tank 40 is heated. At this time, the total heat of the steam S from the steam boiler device 30, that is, sensible heat and latent heat, is utilized by the direct heat exchange, and the hot water TW stored in the hot water tank 40 is quickly heated. The hot water tank 40 includes a stored hot water temperature sensor 41 that detects the temperature of the stored hot water TW, and a first water level sensor 42 that detects the water level WL of the stored hot water TW.

[0034] The hot water producing system 1 of this embodiment includes a water supply tank 60 that stores water. The water stored in the water supply tank 60 is supplied to the water heaters 11, 12, and 13 via a heat pump water supply line L3.

[0035] Each of the water heaters 11, 12, 13 is provided with a water supply pump 17, 18, 19 for supplying the water W1 to each of the water heaters 11, 12, 13. Note that the water supply pumps 17, 18, 19 only need to be provided in the water heaters 11, 12, 13, and may be provided in the water supply lines in the water heaters 11, 12, 13, or may be provided in the heat pump water supply line L3 after branching corresponding to each of the water heaters 11, 12, 13.

[0036] Water supply pumps 17, 18, 19 are each driven with their rotation speed adjusted by, for example, inverter control, thereby adjusting the amount of water supplied to water heaters 11, 12, 13. Note that a configuration may be adopted in which a flow rate adjustment valve is provided corresponding to each water heater 11, 12, 13, and the amount of water supplied to water heaters 11, 12, 13 is adjusted by controlling the opening degree of the flow rate adjustment valve. When a flow rate adjustment valve is provided, water supply pumps 17, 18, 19 are driven at a predetermined rotation rate (constant drive frequency).

[0037] The water stored in the water supply tank 60 is supplied to the steam boiler apparatus 30 as boiler feed water via a boiler feed water line L4. A boiler feed water pump 32 is provided on the boiler feed water line L4. The boiler feed water pump 32 is driven, for example, by inverter control, so as to adjust the amount of water supplied to the steam boiler apparatus 30. The boiler feed water pump 32 may be provided for each of the multiple once-through boilers 31, or may be provided within the steam boiler apparatus 30. The amount of water supplied may be adjusted by a flow control valve.

[0038] Furthermore, the hot water producing system 1 of this embodiment includes a bypass water supply line L5 for directly supplying the service water stored in the water supply tank 60 to the hot water tank 40. The bypass water supply line L5 is provided with a bypass water supply pump 61 and a bypass water supply valve 62. When the bypass water supply valve 62 is opened, the service water stored in the water supply tank 60 is replenished as make-up water to the hot water tank 40. At this time, the service water W5 (hereinafter also referred to as cold water W5) is supplied into the hot water tank 40 through the bypass water supply line L5.

[0039] The hot water producing system 1 of this embodiment includes a control unit 100 for performing various controls. Fig. 3 is a functional block diagram showing the configuration of the control unit 100. As shown in Fig. 3, the control unit 100 includes a hot water supply control unit 110, a boiler control unit 120, a steam supply control unit 130, and a hot water storage control unit 140.

[0040] As described above, the control unit 100 is composed of a plurality of functional blocks, but each block does not necessarily need to be physically separated, and the functions of the plurality of blocks may be realized by one CPU. The control unit 100 may be divided into two or more parts, taking into consideration the arrangement and wiring of the devices to be controlled. For example, from the viewpoint of independent control of water heaters and boilers, it is preferable to incorporate the function of the water heater control unit 110 into the local control unit of each water heater, and the function of the boiler control unit 120 into a unit control panel that controls a group of boilers.

[0041] The hot water supply control unit 110 controls the heat pump hot water supply system 10. More specifically, it controls the operation of the water heaters 11, 12, and 13, such as starting and stopping the operation. The hot water supply control unit 110 also controls the water supply pumps 17, 18, and 19 based on the temperatures detected by the hot water supply temperature sensors 14, 15, and 16 to adjust the amount of hot water W1 supplied from the water heaters 11, 12, and 13. For adjusting the amount of hot water, it is preferable to use feedback control using a PID algorithm. For example, focusing on the first water heater 11, the hot water supply control unit 110 controls the number of revolutions of the water supply pump 17 to adjust the amount of hot water supplied so that the temperature detected by the hot water supply temperature sensor 14 becomes a predetermined target hot water temperature. The same applies to the control of the second water heater 12 and the third water heater 13. Note that a flow rate control valve may be provided for each water heater 11, 12, 13, and the amount of hot water supplied may be adjusted by controlling the opening degree of the flow rate control valve. As a result, hot water W1 supplied from water heaters 11, 12, 13 is heated to a first temperature corresponding to the target hot water temperature so that the hot water temperature is always the target hot water temperature. Note that when the amount of heat source input to the heat pump circuit is small, the amount of hot water supplied is reduced to control the hot water temperature to be maintained at the target hot water temperature.

[0042] Here, the target hot water supply temperature is set, for example, to 50 to 85° C. More preferably, it is 50 to 70° C. This preferable target hot water supply temperature will be described later with reference to FIGS.

[0043] The boiler control unit 120 controls the number of steam boiler units 30 to be increased or decreased based on the header pressure value detected by the pressure gauge 55 provided in the steam header 51. More specifically, the amount of deviation between the header pressure value and the target steam pressure value is calculated so that the header pressure value becomes the target steam pressure value, and the number of boilers to be increased or decreased is calculated. This number increase or decrease control is publicly known, as disclosed in, for example, JP 2015-140975 A, and therefore will not be described here.

[0044] The steam supply control unit 130 controls the opening of the heating steam supply valve 54 based on the temperature detected by the hot water storage temperature sensor 41. More specifically, the steam supply control unit 130 controls the opening of the heating steam supply valve 54 to adjust the supply amount of steam S so that the temperature detected by the hot water storage temperature sensor 41 becomes a predetermined target hot water storage temperature. For adjusting the supply amount, it is preferable to use feedback control. For example, an operation amount for the heating steam supply valve 54 is calculated by a PID algorithm so that the temperature detected by the hot water storage temperature sensor 41 converges to the target hot water storage temperature, and an opening designation signal is output from the steam supply control unit 130 to the actuator circuit of the heating steam supply valve 54. By performing such steam supply control, the temperature of the hot water TW in the hot water tank 40 is heated to a second temperature corresponding to the target hot water storage temperature so that it always becomes the target hot water storage temperature.

[0045] Here, the target hot water storage temperature is a temperature higher than the target hot water supply temperature (first temperature), and is preferably set to 75 to 95° C. This preferable target hot water storage temperature will be described later with reference to FIGS.

[0046] The hot water storage control unit 140 controls the bypass water supply valve 62, the heating steam supply valve 54, and the water heaters 11, 12, and 13 based on the detection result of the first water level sensor 42. As shown in FIG. 4, the first water level sensor 42 is configured by an electrode type water level detector equipped with a plurality of electrodes, and includes a first electrode 421, a second electrode 422, a third electrode 423, a fourth electrode 424, and a fifth electrode 425. Although not shown, an electrode constituting a common electrode and an electrode for detecting an abnormal water level may be further included. Each of the electrodes 421 to 425 detects whether the water level WL of the stored water TW in the hot water tank 40 reaches the lower end of each electrode depending on whether the lower end of the electrode is immersed in water.

[0047] Here, the water level detected by the first electrode 421 is water level LL, the water level detected by the second electrode 422 is water level L, the water level detected by the third electrode 423 is water level M, the water level detected by the fourth electrode 424 is water level H, and the water level detected by the fifth electrode 425 is water level HH. As shown in Fig. 4, the electrodes are inserted into the hot water tank 40 so that the height positions of the lower ends are, in order from the lowest, the first electrode 421, the second electrode 422, the third electrode 423, the fourth electrode 424, and the fifth electrode 425. The water levels detected by these electrodes become multiple-stage water level thresholds for controlling changes in the number of operating water heaters 11, 12, and 13, etc.

[0048] In this embodiment, the hot water storage control unit 140 controls the bypass water supply valve 62, the heating steam supply valve 54, and the water heaters 11, 12, and 13 based on the detection result of the first water level sensor 42. More specifically, when the first water level sensor 42 detects that the water level has fallen below the water level LL, the hot water storage control unit 140 opens the bypass water supply valve 62. Furthermore, when the water level in the hot water tank 40 is falling, the hot water storage control unit 140 executes a unit number control to increase the number of operating water heaters by one each time the water level detected by the first water level sensor 42 falls below the water level threshold by one step, and when the water level in the hot water tank 40 is rising, the hot water storage control unit 140 executes a unit number control to decrease the number of operating water heaters by one each time the water level detected by the first water level sensor 42 rises above the water level threshold by one step. This number control is performed, for example, at water level H, water level M, and water level L when the water level is decreasing, and at water level M, water level H, and water level HH when the water level is increasing. The hot water storage control unit 140 may control the heating steam supply valve 54 via the steam supply control unit 130. The hot water storage control unit 140 may also control the water heaters 11, 12, and 13 via the hot water supply control unit 110.

[0049] Here, a specific description will be given of a case where the water level WL in the hot water tank 40 changes from a state in which it is located within the range of water level LL to water level L shown in FIG. 4. The stored water TW stored in the hot water tank 40 is supplied to a hot water demand point (not shown) through the hot water outlet line L6. When the amount of hot water W6 supplied from the hot water tank 40 to the hot water demand point exceeds the amount of hot water W1 supplied to the hot water tank 40 from the multiple water heaters 11, 12, and 13 as the first heating means 2 and the amount of moisture of the steam S supplied to the hot water tank 40 from the steam boiler device 30, the water level WL in the hot water tank 40 drops (see arrow A in FIG. 4). When the lower end of the first electrode rod 421 is exposed above the water surface at a certain timing, the first water level sensor 42 detects that the water level WL has fallen below the water level LL.

[0050] When the hot water storage control unit 140 detects that the water level WL has fallen below the water level LL, it determines that the hot water tank 40 is about to enter a state of drought, and operates all three water heaters 11, 12, and 13 to supply as much hot water W1 as possible to the hot water tank 40, while opening the bypass water supply valve 62 to directly replenish the cold water W5 stored in the water supply tank 60 to the hot water tank 40. Furthermore, taking into consideration that the temperature of the stored water TW in the hot water tank 40 drops due to the supply of cold water W5, the heating steam supply valve 54 is fully opened to supply as much steam S as possible to the hot water tank 40. At this time, the steam supply control unit 130 controls the heating steam supply valve 54 to be fully opened regardless of the temperature detected by the hot water storage temperature sensor 41.

[0051] In this way, when the water level WL falls below the water level LL, that is, when the hot water tank 40 is in a state immediately before a drought, the water level WL is quickly restored by supplying hot water W1 heated by the first heating means 2 and also supplying cold water W5 that has not passed through the first heating means 2. Also, by fully opening the heating steam supply valve 54 to supply steam S, the temperature of the stored water TW in the hot water tank 40, which has been lowered by the supply of cold water W5, is raised as quickly as possible.

[0052] By carrying out such control, the water level WL recovers (see arrow B in FIG. 4). Then, when the water surface comes into contact with the second electrode rod 422 and the tip of the second electrode rod 422 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level L. When the hot water storage control unit 140 detects that the water level WL has exceeded the water level L (entered the range between the water level L and the water level M), it determines that the hot water tank 40 has recovered from the state immediately before the drought, and closes the bypass water supply valve 62. In addition, the control of the heating steam supply valve 54 is returned to the normal temperature control based on the temperature detected by the hot water storage temperature sensor 41. At this point, the water level WL is still not high, so the operation of all three water heaters 11, 12, and 13 continues.

[0053] Next, when the water level WL rises further and the tip of the third electrode rod 423 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level M (entered the range of water level M to water level H). At this time, it is determined that there is a little extra water storage capacity, and one of the three water heaters is stopped, and only two water heaters continue to operate. For example, among the water heaters 11, 12, and 13, the third water heater 13 is stopped, and only the first and second water heaters 11 and 12 continue to operate. The bypass water supply valve 62 is maintained in a closed state. In addition, the control of the heating steam supply valve 54 is also maintained in a normal temperature control state by the steam supply control unit 130.

[0054] Next, when the water level WL rises further and the tip of the fourth electrode rod 424 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level H (entered the range of water level H to water level HH). At this time, it is determined that there is more water storage capacity, and operation of two of the three water heaters is stopped, and only operation of one water heater is continued. For example, among the water heaters 11, 12, and 13, operation of the second and third water heaters 12 and 13 is stopped, and only the first water heater 11 continues operation. Note that the bypass water supply valve 62 remains closed. In addition, the control of the heating steam supply valve 54 maintains the normal temperature control state by the steam supply control unit 130.

[0055] Next, when the water level WL rises further and the tip of the fifth electrode rod 425 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level HH. At this time, it is determined that the amount of stored water has become sufficient, and the operation of the other water heater is stopped. In other words, the operation of all the water heaters 11, 12, and 13 is stopped. The bypass water supply valve 62 remains closed. In addition, the control of the heating steam supply valve 54 maintains the normal temperature control state by the steam supply control unit 130.

[0056] Next, a case where the water level WL drops from this state will be described. When the water level WL drops (see arrow C in FIG. 4) and the lower end of the fourth electrode rod 424 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below the water level H (entered the range between water level M and water level H). When the hot water storage control unit 140 detects that the water level WL has fallen below the water level H, it resumes operation of only one of the three water heaters. For example, of the water heaters 11, 12, and 13, it resumes operation of the first water heater 11.

[0057] Here, if the water level WL rises after it falls below the water level H and the tip of the fifth electrode rod 425 is submerged in the water surface, that is, if it is detected that the water level WL has risen above the water level HH, it is determined that the amount of stored water has again become sufficient, and as described above, operation of all water heaters 11, 12, and 13 is stopped.

[0058] On the other hand, after the water level WL falls below water level H, when the water level WL falls further (see arrow D in FIG. 4) and the lower end of the third electrode rod 423 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below water level M (entered the range between water level L and water level M). When the hot water storage control unit 140 detects that the water level WL has fallen below water level M, it operates only two of the three water heaters. For example, of the water heaters 11, 12, and 13, it operates the first and second water heaters 11 and 12.

[0059] From this state, when the water level WL further drops and the lower end of the second electrode rod 422 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below the water level L (entered the range from water level LL to water level L). When the hot water storage control unit 140 detects that the water level WL has fallen below the water level L, it executes the operation of all three water heaters 11, 12, 13.

[0060] If the water level WL further drops from this state and the lower end of the first electrode rod 421 is exposed above the water surface, that is, if it is detected that the water level WL has fallen below the water level LL, the hot water storage control unit 140 determines that the hot water tank 40 is about to enter a state of drought, and as described above, it operates all three water heaters 11, 12, and 13 and opens the bypass water supply valve 62. Furthermore, it fully opens the heating steam supply valve 54.

[0061] In this way, the number of operating water heaters is increased or decreased according to the water level WL in the hot water tank 40, so it is possible to appropriately manage the water level WL in the hot water tank 40. Also, power consumption can be reduced.

[0062] As shown in Fig. 4, the hot water storage control unit 140 shifts the number of operating water heaters in a given water level range between when the water level is rising and when the water level is falling. For example, in the water level range between water level L and water level M, the number of operating units is three when the water level is rising, while the number of operating units is two when the water level is falling. This is to prevent a situation in which the water heater is frequently started and stopped when the water level WL fluctuates around the water level threshold. This reduces the risk of failure of the water heater and hot water supply control equipment (such as the water supply pump and water supply valve) for supplying hot water.

[0063] Instead of shifting the number of water heaters in operation in a predetermined water level range between when the water level rises and when the water level falls, a status check time may be provided. That is, when it is determined that the state in which the water level WL is below a predetermined water level threshold has continued for a first predetermined time, a control such as switching the number of water heaters in operation may be performed. For example, in the process of the water level WL falling as shown by the arrow C in FIG. 4, when it is determined that the state in which the water level WL is below the water level HH has continued for a predetermined time, the number of water heaters in operation is switched from 0 to 1. By providing a status check time in this way, even if the number of water heaters in operation in the water level range of H to HH as a predetermined water level range is the same between when the water level rises and when the water level falls, it is possible to prevent a situation in which the water heaters are frequently started and stopped. Note that a status check time is also provided for other water level thresholds in the same manner.

[0064] In addition, a configuration may be adopted in which, when it is determined that the state in which the water level WL exceeds a predetermined water level threshold has continued for a second predetermined time, control such as switching the number of water heaters in operation is executed. For example, in the process of the water level WL rising as shown by arrow B in Fig. 4, when it is determined that the state in which the water level WL exceeds the water level LL has continued for a predetermined time, the bypass water supply valve 62 may be closed and the control of the heating steam supply valve 54 may be returned to temperature control. Furthermore, when it is determined that the water level WL has risen and continued to exceed the water level L for a predetermined time, the number of water heaters in operation may be switched from three to two. In addition, similar state confirmation times are set for other water level thresholds as well.

[0065] By such control, it is possible to perform control such as changing the number of water heaters in operation based on the state confirmation time for the water level WL continuing to fall or the state confirmation time for the water level WL continuing to rise. The set value of the state confirmation time is preferably adjustable. By making the set value of the state confirmation time adjustable, it is possible to set a first predetermined time as a delay time corresponding to the water level width required to confirm the water level continuing to fall when the water level falls below the water level threshold, taking into account the difference in the water level fall speed due to the cross-sectional area of ​​the hot water tank 40. Alternatively, it is possible to set a second predetermined time as a delay time corresponding to the water level width required to confirm the water level continuing to rise when the water level exceeds the water level threshold, taking into account the difference in the water level rise speed due to the cross-sectional area of ​​the hot water tank 40. The set value of the state confirmation time can be adjusted manually or automatically, and can be set to a value greater than 0. The state confirmation time is measured using an internal timer of the control unit 100 or the like.

[0066] The first water level sensor 42 is not limited to an electrode-type water level detector, and various water level detectors can be used. For example, five float-type water level detectors may be provided to detect each water level threshold. Also, an electrode-type water level detector and a float-type water level detector may be used in combination. Furthermore, multiple water level thresholds may be detected using a water level detection unit such as a pressure-type water level sensor that can measure continuous water levels. The number of water level thresholds to be detected is not limited to five.

[0067] Fig. 5 is a diagram showing the number of operating water heaters 11, 12, and 13 and the total amount of make-up water when the water level is rising. The horizontal axis represents the water level WL in the hot water tank 40, and the vertical axis represents the total amount of make-up water. In Fig. 5, the amount of hot water supplied from the first heat pump water heater 11 is represented as "HP1", the amount of hot water supplied from the second heat pump water heater 12 is represented as "HP2", and the amount of hot water supplied from the third heat pump water heater 13 is represented as "HP3".

[0068] When the water level WL rises after falling below the water level LL, as shown in Fig. 5, hot water W1 is supplied from the three water heaters 11, 12, and 13, cold water W5 is supplied directly from the water supply tank 60, and steam S is supplied from the steam boiler device 30 with the heating steam supply valve 54 fully open until the water level WL exceeds the water level L. The total amount of makeup water at this time is as shown on the vertical axis of Fig. 5.

[0069] After that, when the water level WL exceeds the water level L, the bypass water supply valve 62 is closed, and the control of the heating steam supply valve 54 is returned to temperature control. Thus, the total amount of makeup water is reduced as shown in FIG. 5. Further, when the water level WL exceeds the water level M, the operation of the third water heater 13 is stopped, and only the operation of the first and second water heaters 11 and 12 is continued. Thus, the total amount of makeup water is further reduced as shown in FIG. 5. In addition, since the influence of the cold water W5 supplied directly from the water supply tank 60 is also reduced, the supply amount of steam S, which is adjusted based on the hot water storage temperature in the hot water tank, is also gradually reduced. Further, when the water level WL exceeds the water level H, the operation of the second water heater 12 is further stopped, and only the operation of the first water heater 11 is continued. Thus, the total amount of makeup water is further reduced as shown in FIG. 5. Then, when the water level WL exceeds the water level HH, the operation of the first water heater 11 is also stopped, and the operation of all three water heaters is stopped. However, even at this time, the temperature control of the heating steam supply valve 54 continues, so the supply of steam S from the steam boiler device 30 continues.

[0070] In this embodiment, the hot water temperature from water heaters 11, 12, and 13 is controlled to be constant. For example, the target hot water temperature is set to 70° C. Water heaters 11, 12, and 13 supply hot water W1 at a first temperature that corresponds to the target hot water temperature.

[0071] Note that stopping the operation of the water heaters described above also includes actions to stop the supply of hot water from the water heaters, such as stopping the operation of water supply pumps 17, 18, and 19 and closing the flow control valves corresponding to each of the water heaters 11, 12, and 13. It also includes stopping the operation of refrigerant compressor 91 to stop the circulation of refrigerant in the heat pump circuit.

[0072] In addition, a configuration may be adopted in which which of the water heaters 11, 12, and 13 is to be given priority in stopping / resuming the operation of the water heater is appropriately determined based on the state and operation history of each water heater. Also, it may be determined in advance.

[0073] In this way, since the number of operating water heaters is controlled depending on the water level WL in the hot water tank 40, it is possible to appropriately manage the water level WL in the hot water tank 40. Also, power consumption can be reduced.

[0074] FIG. 6 is a modified example of the hot water storage control shown in FIG. 5. In this modified example, as shown in FIG. 6, a configuration for detecting the water level threshold value in more detail may be adopted. Here, the water level LL, water level L, water level M1, water level M2, water level M3, water level M4, water level H, and water level HH are set as detectable water level threshold values, in order from the lowest water level. In this modified example, in addition to changing the number of operating water heaters, control is performed to change the target hot water supply temperature of the water heater. Specifically, the water heater is capable of switching between multiple target hot water supply temperatures in a temperature range higher than a first temperature and lower than a second temperature.

[0075] More specifically, in this modified example, when the water heater is operating with its target hot water temperature set to a first temperature, if the water level detected by first water level sensor 42 exceeds the water level threshold by one step, control is executed to increase the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters, and when the water heater is operating with its target hot water temperature increased by one step, control is executed to reduce the number of operating water heaters by one and at the same time return the target hot water temperature to the first temperature. In addition, when the water heater is operating with the target hot water temperature set to the first temperature, if the water level detected by the first water level sensor 42 falls one step below the water level threshold, control is executed to increase the number of operating water heaters by one and at the same time raise the target hot water temperature of the water heater by one step, and when the water heater is operating with the target hot water temperature raised by one step, control is executed to lower the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters.

[0076] FIG. 6 is a diagram showing the number of operating water heaters 11, 12, and 13, the hot water supply temperature, and the total amount of makeup water when the water level rises. For example, consider a case where the water level WL rises after falling below the water level LL and is between the water level L and the water level M1. At this time, the target hot water supply temperature of the three water heaters 11, 12, and 13 is set to 70° C. (first temperature). When the water level WL further rises from this state and exceeds the water level M1, control is executed to raise the target hot water supply temperature of the water heaters 11, 12, and 13 by one step to 80° C. while maintaining the number of operating water heaters 11, 12, and 13. Here, the temperature when raised by one step is set to a temperature lower than the target hot water storage temperature (second temperature) of the hot water tank 40.

[0077] Next, while water heaters 11, 12, and 13 are operating with their target hot water temperatures raised by one step to 80° C., if the water level WL rises further and exceeds water level M2, control is executed to reduce the number of operating water heaters by one and return the target hot water temperature to 70° C. (first temperature). Similarly, even if the water level WL continues to rise, control is executed alternately between raising the target hot water temperature of the water heaters by one step while maintaining the number of operating water heaters, and reducing the number of operating water heaters by one and returning the target hot water temperature to the original value.

[0078] Next, consider the case where the water level WL exceeds the water level HH, and then drops, and for example, when the water level WL is between the water level M4 and the water level H, the target hot water temperature of the water heater is set to 70°C (first temperature). Note that, here, the above-mentioned method of state confirmation time is used to explain the case where the number of operating water heaters in a specified water level range is the same when the water level is rising and when the water level is falling. Therefore, the case where the water level is falling will also be explained using FIG. 6. When the water level WL further drops from the situation where the water level WL is between the water level M4 and the water level H, and falls below the water level M4, the number of operating water heaters is increased by one to operate two water heaters, and at the same time, the target hot water temperature of the water heater is increased by one step to 80°C.

[0079] Next, when the water level WL falls below water level M3 while the water heater is operating with its target hot water temperature set to 80°C, control is executed to lower the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters, and return it to 70°C. Similarly, even if the water level WL continues to drop, control is executed alternately between increasing the number of operating water heaters by one and raising the target hot water temperature of the water heater by one step, and returning the target hot water temperature while maintaining the number of operating water heaters.

[0080] In this modified example, the method of status confirmation time is used, but this is not limited to this. As described in Figure 4, a method of shifting the number of operating water heaters in a specified water level range when the water level is rising and when the water level is falling may also be used.

[0081] In addition, when the water level rises, the target hot water temperature of the water heater may be increased by one step while maintaining the number of operating water heaters, and then when the water level further rises, the target hot water temperature of the water heater may be increased by another step while maintaining the number of operating water heaters. For example, when the water level exceeds M1, the target hot water temperature of the water heaters 11, 12, and 13 is increased by one step to 75°C while maintaining the number of operating water heaters 11, 12, and 13. Then, when the water level WL further rises during operation in this state and exceeds water level M2, the target hot water temperature of the water heaters 11, 12, and 13 is increased by another step to 80°C while maintaining the number of operating water heaters 11, 12, and 13. When the water level WL further rises during operation in this state and exceeds water level M3, the number of operating water heaters is reduced by one, and the target hot water temperature is returned to 70°C (first temperature). When the water level is decreasing, the control is executed so as to perform the opposite operation.

[0082] In other words, when the water heater is operating with its target hot water temperature set to a first temperature, and the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, control is executed to increase the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters, and when the water heater is operating with its target hot water temperature increased by one or more steps, and the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, control is executed to reduce the number of operating water heaters by one and at the same time return the target hot water temperature to the first temperature, or control is executed to increase the target hot water temperature of the water heater by another step while maintaining the number of operating water heaters. In addition, when the water heater is operating with the target hot water temperature set to the first temperature, if the water level detected by the first water level sensor 42 falls one step below the water level threshold, control may be executed to increase the number of operating water heaters by one and at the same time raise the target hot water temperature of the water heater by one or more steps (e.g., two steps), and when the water heater is operating with the target hot water temperature raised by one or more steps (e.g., two steps), control may be executed to lower the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters.

[0083] Generally, raising the target hot water supply temperature of the water heater reduces the amount of hot water that can be supplied, and lowering the target temperature of the water heater increases the amount of hot water that can be supplied. Taking this into consideration, by adopting the control shown in this modified example, it becomes possible to finely adjust the total amount of make-up water while maintaining the same number of operating heat pumps as much as possible. This makes it possible to appropriately manage the water level in the hot water tank. In addition, because it is possible to continue operating the heat pump as much as possible, it is possible to solve the problem of low-temperature water supply at the initial stage of restarting the operation of the heat pump.

[0084] As described above, the hot water producing system 1 of this embodiment includes the first heating means 2 that heats the service water W1 to a first temperature while circulating the water W1 through the condenser of the heat pump hot water supply system 10, and the second heating means 3 that raises the temperature of the service water W1 heated by the first heating means 2 to a second temperature higher than the first temperature by utilizing the steam S generated by the steam boiler device 30. The effects of adopting this configuration will be described in detail with reference to Figures 7 to 10.

[0085] 7 shows a first comparative example in which a hot water production system is constructed using only steam S from a steam boiler device 30 as heating means. The temperature of hot water required by the hot water demand point varies depending on the application, but for example, when washing bottles for food or medicine, or pasteurizing (sterilizing bottles), hot water in the high temperature range of about 75°C to 95°C may be required. Therefore, a case will be described in which the hot water production system supplies hot water in the high temperature range, for example, hot water at 90°C, to the hot water demand point.

[0086] The hot water production system 5 in Fig. 7 uses only steam S from a steam boiler device 30 as a heating means. Here, the steam boiler has a gas-fired or oil-fired burner and generates steam using fossil fuels. Therefore, the CO2 emissions and running costs of this hot water production system 5 are relatively high, and there is a demand for significant reductions.

[0087] Therefore, it is conceivable to adopt a hot water production system using an electrically driven heat pump hot water supply system 10 with a high COP (coefficient of performance) without using fossil fuel as a heating means. FIG. 8 shows a second comparative example in which a hot water production system 6 is constructed using only a heat pump hot water supply system 10 as a heating means. The CO2 emission coefficient of electricity (0.51 kg CO2 / kWh) is larger than the CO2 emission coefficient of city gas 13A (0.18 kg CO2 / kWh), but when comparing the CO2 emission per output, the heat pump with a high COP has less CO2 emission than the steam boiler. In addition, the unit price of electricity (about 15 yen / kWh) is higher than the fuel unit price of city gas 13A (about 6.2 yen / kWh), but when comparing the running cost per output, the heat pump with a high COP has a lower CO2 emission and running cost than the steam boiler. Therefore, the hot water production system 6 has lower CO2 emission and running cost than the hot water production system 5 of FIG. 7.

[0088] However, while a heat pump has a relatively high COP and is highly effective in reducing CO2 emissions when the hot water temperature is low, when the hot water temperature is increased, the COP becomes relatively low and the effect of reducing CO2 emissions decreases. For example, the COP of a heat pump when supplying hot water at 90°C is equivalent to 2.8. Therefore, the effect of reducing CO2 emissions (CO2 emission reduction ratio) is only about 10% compared to hot water production system 5 that uses only steam from a steam boiler as a heating means. In addition, the effect of reducing running costs (running cost reduction ratio) is also only about 20%.

[0089] Next, we will consider the hot water production system 1 of this embodiment, i.e., a hybrid hot water production system equipped with a first heating means 2 that heats the service water W1 to a first temperature while circulating it through a condenser of a heat pump type hot water supply system 10, and a second heating means 3 that heats the service water W1 heated by the first heating means 2 to a second temperature higher than the first temperature by using steam S generated by a steam boiler device 30.

[0090] In such a hot water production system 1, the heat pump type hot water supply system 10 as the first heating means 2 heats the water W1 to a temperature range where it can be operated with high efficiency, for example to 70°C, and this heated hot water W1 can be heated to a high temperature range, for example to 90°C, using steam S from the steam boiler device 30, making it possible to produce hot water in the high temperature range with high efficiency.

[0091] Here, the COP of the heat pump when the hot water supply temperature is 70°C is, for example, equivalent to 4.2, which is very high. In the hot water production system 1 of this embodiment, the heat pump is responsible for heating up to a temperature range where such a high COP can be maintained. For example, when the hot water production system 1 is to produce hot water of 90°C, the heat pump is responsible for heating up to 70°C. At this time, the heat pump is responsible for about 60% to 80% (load factor 60% to 80%) of the total thermal output required to produce hot water of 90°C. Then, the steam boiler is responsible for raising the temperature from 70°C to 90°C. At this time, the steam boiler is responsible for about 20% to 40% (load factor 20% to 40%) of the total thermal output required to produce hot water of 90°C.

[0092] When the heat pump and steam boiler are used in this combination, the hot water production system 1 reduces CO2 emissions by about 30%, which is very effective, compared to the hot water production system 5 that uses only steam from a steam boiler as a heating means. In addition, the running costs are also reduced by about 35%, which is very effective.

[0093] In this way, by using the hot water production system 1 of this embodiment, even if the hot water outlet temperature is increased, it is possible to reduce CO2 emissions and running costs extremely effectively. Furthermore, with the hot water production system 1 of this embodiment, it is possible to appropriately adjust the load factors of the heat pump and the steam boiler, i.e., the share of heat output (output allocation) of each, according to the target hot water outlet temperature, thereby extremely effectively reducing CO2 emissions and running costs. The relationship between the output ratio of the heat pump and the steam boiler according to the target hot water outlet temperature of the hot water production system 1 is preferably stored in a table or a formula. For example, a configuration is provided in which the target hot water outlet temperature can be set, and an appropriate output ratio of the heat pump and the steam boiler is set according to the set target hot water outlet temperature.

[0094] FIG. 10 is a graph showing the CO2 emission reduction ratio and the running cost reduction ratio when hot water of, for example, 90° C. is produced and dispensed using the hot water producing system 1 of this embodiment.

[0095] The horizontal axis of the graph in FIG. 10 is the hot water supply temperature of the heat pump. The vertical axis of the line graph in FIG. 10 is the CO2 emission reduction ratio and the running cost reduction ratio. Here, the CO2 emission reduction ratio indicates the ratio of CO2 emission that can be reduced by the hot water production system 1 of this embodiment when the CO2 emission of the hot water production system 5 using only steam from a steam boiler as a heating means is set to 100%. That is, if the CO2 emission reduction ratio is 25%, it means that 100% CO2 emission can be reduced to 75% by converting to the hot water production system 1. On the other hand, the running cost reduction ratio indicates the ratio of running cost that can be reduced by the hot water production system 1 of this embodiment when the running cost of the hot water production system 5 using only steam from a steam boiler as a heating means is set to 100%. That is, if the running cost reduction ratio is 30%, it means that 100% running cost can be reduced to 70% by converting to the hot water production system 1. The vertical axis of the bar graph in Fig. 10 shows the output ratio of the heat pump and the steam boiler, that is, the share of the thermal output (output sharing) of each. The bar graph showing the heat pump output ratio is accompanied by the COP at the hot water supply temperature of the heat pump. The higher the hot water supply temperature, the lower the COP.

[0096] In the line graph of FIG. 10, when comparing the data of the heat pump hot water supply temperature = 90 ° C. with the data of the heat pump hot water supply temperature = 50 ° C. to 80 ° C., it can be seen that compared with the case of producing hot water of 90 ° C. using only a heat pump (data of heat pump hot water supply temperature = 90 ° C.), the effect of reducing CO2 and the effect of reducing running costs are clearly higher when heating to 50 to 80 ° C. with a heat pump and then heating to 90 ° C. using steam. For example, if heating to 50 to 70 ° C. with a heat pump and then heating to 90 ° C. using steam, the effect of reducing CO2 and the effect of reducing running costs are high. Furthermore, from the trend of the line graph, it can be seen that the effect of the present invention can be obtained even when, for example, heating to 85 ° C. with a heat pump and then heating to 90 ° C. using steam.

[0097] In this way, by using the hot water production system 1 of this embodiment, i.e., a hybrid hot water production system equipped with a first heating means 2 that heats the service water W1 to a first temperature while circulating it through the condenser of the heat pump hot water supply system 10, and a second heating means that uses steam S generated by the steam boiler device 30 to raise the temperature of the service water W1 heated by the first heating means 2 to a second temperature higher than the first temperature, it is possible to extremely effectively reduce CO2 emissions and running costs even when the outlet hot water temperature of the system is increased.

[0098] The first heating means 2 of the hot water production system 1 of this embodiment heats the water W1 to the first temperature while passing it through the condenser of the heat pump water heater. By adopting a configuration in which the hot water heated by the second heating means 3 passes through the condenser without returning it again, that is, a configuration in which the hot water W1 of the first temperature heated by the first heating means 2 is always additionally supplied, and this is heated by the second heating means 3. Therefore, even when the hot water demand point requires a large amount of hot water, it is easy to always supply hot water of a stable temperature. In addition, when the hot water tank 40 is provided, even if the water level WL in the hot water tank 40 drops, the hot water W1 of the first temperature heated by the first heating means 2 is always additionally supplied into the hot water tank 40 according to the level of the drop. Therefore, with this configuration, the frequency of occurrence of a situation in which cold water W5 must be supplied into the hot water tank 40 is reduced. Therefore, the supply of the cold water W5 rarely causes the temperature of the water TW stored in the hot water tank 40 to drop excessively.

[0099] The second heating means 3 of the hot water producing system 1 of this embodiment heats the water W1 heated by the first heating means 2 directly with the steam S generated by the steam boiler device 30 to a second temperature higher than the first temperature. In this way, by directly exchanging heat between the water W1 heated by the first heating means 2 and the steam S generated by the steam boiler device 30, the water W1 heated by the first heating means 2 is quickly heated. In other words, the total heat (sensible heat and latent heat) of the steam S is utilized, so that the water W1 heated by the first heating means 2 is quickly heated. This also improves the control responsiveness of the outlet hot water temperature.

[0100] In order to obtain such an effect, it is particularly preferable to use a heat pump water heater having an electrically driven refrigerant compressor as the water heater, and a steam boiler having a gas-fired or oil-fired burner as the steam boiler. The effect of the present invention can be obtained appropriately by setting the first temperature to 50 to 85°C and the second temperature to a temperature higher than the first temperature, 75 to 95°C. Preferably, the first temperature is set to 50 to 80°C, and the second temperature is set to a temperature higher than the first temperature, 75 to 95°C. More preferably, the first temperature is set to 50 to 70°C, and the second temperature is set to 75 to 95°C. In this way, by combining a heat pump water heater having an electrically driven refrigerant compressor and a steam boiler having a burner that burns fossil fuel, and appropriately setting the temperature ranges for heating by each, a high reduction effect in CO2 emissions and a high reduction effect in running costs can be obtained compared to the case of producing high-temperature water by a heat pump water heater alone or a steam boiler alone.

[0101] In addition, it is preferable that the hot water producing system 1 of this embodiment is equipped with a hot water tank 40 as the second heating means 3, but a configuration may be adopted in which steam is directly supplied to the hot water W1 flowing through the hot water supply line L1 without providing the hot water tank 40.

[0102] In order to perform appropriate hot water storage control, it is preferable that the heat pump hot water supply system 10 has multiple water heaters, but it may also have only one. In the case of one water heater, the control by multiple water heaters described in this embodiment is not performed, and the amount of hot water supply is controlled based on the water level WL of the hot water tank 40, and the hot water supply is controlled on and off. In the case of using multiple water heaters, any number of units equal to or greater than two may be used.

[0103] Although it is preferable that the steam boiler device 30 has a plurality of boilers, it may have only one boiler. In the case of one boiler, the combustion rate may be controlled based on the measured steam pressure value and the target steam pressure value. In the case of using a plurality of boilers, any number of boilers equal to or greater than two may be used. In addition, the boiler constituting the steam boiler device 30 may be a boiler other than a once-through boiler.

[0104] The produced hot water can be used for various purposes, including but not limited to washing bottles for food and medicine and pasteurizer sterilization. For example, in the food and beverage field, hot water can be used for heating raw materials and processed products, washing bottles, cleaning in place (CIP) of manufacturing equipment, and the like. In the food and beverage field, steam S generated by the steam boiler device 30 can be used for high-temperature cooking (fried foods, steamed foods, stir-fried foods), retort pot sterilization (sterilization of pouches and cans), stationary sterilization (SIP) of manufacturing equipment, and backup of hot water production. In the machinery field, hot water can be used for washing and degreasing. In these applications, hot water in a high temperature range of about 75°C to 95°C may be required, and in cases where hot water in such a high temperature range is required, the hot water production system 1 of this embodiment can be particularly suitably used.

[0105] According to the hot water producing system 1 of the present embodiment described above, the following effects are achieved.

[0106] (1) The hot water production system 1 of this embodiment includes a first heating means 2 for heating the water W1 to a first temperature while passing it through the condenser 92 of the heat pump water heaters 11, 12, and 13 of the heat pump water supply system 10, and a second heating means 3 for directly exchanging heat with the water heated by the first heating means 2 and the steam S generated by the steam boiler device 30 to raise the temperature to a second temperature higher than the first temperature. In this way, the water is heated by the first heating means 2 up to a temperature at which the water can be heated efficiently by the heat pump water heaters 11, 12, and 13, and further heating is performed by directly exchanging heat with the steam S. Therefore, even if the outlet temperature is increased, a hot water production system having a high effect of reducing CO2 emissions and running costs can be provided. In addition, since the steam S is used for heating and direct heat exchange is performed, the temperature control responsiveness is extremely good.

[0107] (2) The water heaters 11, 12, and 13 of the hot water production system 1 of this embodiment have an electrically driven refrigerant compressor 91, and the steam boiler device 30 has a gas-fired or oil-fired burner, with the first temperature being 50 to 70° C. and the second temperature being 75 to 95° C. In this way, by combining a heat pump water heater having an electrically driven refrigerant compressor with a steam boiler having a burner that burns fossil fuel and appropriately setting the heating temperature range of each, it is possible to obtain a high reduction in CO2 emissions and a high reduction in running costs compared to producing high-temperature water using only a heat pump water heater or only a steam boiler.

[0108] (3) The second heating means 3 of the hot water producing system 1 of this embodiment includes a hot water tank 40 that stores hot water W1 heated by the water heaters 11, 12, and 13, a heating steam supply line L2 that supplies steam S generated by the steam boiler device 30 to the hot water tank 40, and a heating steam supply valve 54 provided on the heating steam supply line L2. In this manner, by supplying steam S into the hot water tank 40, it is possible to effectively perform direct heat exchange between the hot water in the hot water tank 40 and the steam S.

[0109] (4) The second heating means 3 of the hot water production system 1 of this embodiment includes a hot water temperature sensor 41 that detects the temperature of the hot water in the hot water tank 40, and controls the opening of the heating steam supply valve 54 so that the temperature detected by the hot water temperature sensor 41 becomes the target hot water temperature. This makes it possible to appropriately control the temperature of the hot water in the hot water tank 40.

[0110] (5) The hot water producing system 1 of this embodiment includes a first water level sensor 42 that detects the water level in the hot water tank 40, a bypass water supply line L5 that supplies water to the hot water tank 40 without going through a water heater, and a bypass water supply valve 62 provided in the bypass water supply line L5, and opens the bypass water supply valve 62 when the water level detected by the first water level sensor 42 falls below a set water level. This allows water to be replenished from the bypass water supply line L5 at an appropriate time when the hot water in the hot water tank 40 is low.

[0111] (6) The hot water production system 1 of this embodiment includes a first water level sensor 42 that detects the water level in the hot water tank 40, the first heating means 2 includes multiple water heaters 11, 12, 13, multiple water level thresholds are set in the hot water tank 40 to change the number of water heaters 11, 12, 13 in operation, and when the water level in the hot water tank 40 falls, the number of water heaters 11, 12, 13 in operation is increased by one each time the water level detected by the first water level sensor 42 falls below the water level threshold by one step, and when the water level in the hot water tank 40 rises, the number of water heaters 11, 12, 13 in operation is decreased by one each time the water level detected by the first water level sensor 42 exceeds the water level threshold by one step. In this way, the number of water heaters 11, 12, 13 in operation is increased or decreased depending on the water level in the hot water tank 40, so that the water level in the hot water tank 40 can be appropriately managed. In addition, power consumption can be reduced.

[0112] (7) The hot water production system 1 of this embodiment is equipped with a first water level sensor 42 that detects the water level in the hot water tank 40, and the first heating means 2 includes multiple water heaters 11, 12, 13. Multiple water level thresholds are set in the hot water tank 40 for changing the number of operating water heaters 11, 12, 13 and / or the target hot water temperature. The water heaters 11, 12, 13 are capable of switching between multiple target hot water temperatures within a temperature range higher than a first temperature and lower than a second temperature. During operation with the target hot water temperature of the water heater set to the first temperature, when the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, control is executed to increase the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters, and the system is operated with the target hot water temperature of the water heater increased by one or more steps. During operation, when the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, the number of operating water heaters is decreased by one and the target hot water temperature is returned to the first temperature, or the target hot water temperature of the water heater is increased by one step while maintaining the number of operating water heaters. During operation with the target hot water temperature of the water heater set to the first temperature, when the water level detected by the first water level sensor 42 falls below the water level threshold by one step, the number of operating water heaters is increased by one and the target hot water temperature of the water heater is increased by one or more steps. During operation with the target hot water temperature of the water heater increased by one or more steps, when the water level detected by the first water level sensor 42 falls below the water level threshold by one step, the target hot water temperature of the water heater is decreased by one step while maintaining the number of operating water heaters. This allows the water level in the hot water tank 40 to be appropriately managed. In addition, it is possible to continue operation of the heat pump as long as possible, and the problem of low-temperature water supply in the initial stage of restarting the operation of the heat pump can be eliminated.

[0113] (8) Water heaters 11, 12, 13 of hot water production system 1 of this embodiment include a water line that circulates water to condenser 92, flow rate adjustment valves or water supply pumps 17, 18, 19 provided on the water line, and water supply temperature sensors 14, 15, 16 that detect the hot water temperatures of water heaters 11, 12, 13, and control the opening of the flow rate adjustment valves or the rotation speed of water supply pumps 17, 18, 19 so that the detected temperatures of hot water temperature sensors 14, 15, 16 become the target hot water temperatures. This allows the hot water temperatures of water heaters 11, 12, 13 to be appropriately controlled.

[0114] (9) The hot water production method of this embodiment includes a first heating step in which the water W1 is heated to a first temperature while passing through the condenser 92 of the heat pump water heaters 11, 12, and 13 of the heat pump water supply system 10, and a second heating step in which the water heated in the first heating step is heated to a second temperature higher than the first temperature by directly exchanging heat with the steam S generated by the steam boiler device 30. In this way, the water is heated in the first heating step up to a temperature at which the water can be heated efficiently by the heat pump water heaters 11, 12, and 13, and further heated by directly exchanging heat with the steam S. Therefore, even if the outlet temperature is increased, a hot water production system having a high effect of reducing CO2 emissions and running costs can be provided. In addition, since the steam S is used for heating and direct heat exchange is performed, the temperature control responsiveness is extremely good.

[0115] <Second embodiment> Next, a second embodiment will be described with reference to Fig. 11. Note that a description of the same configuration as in the first embodiment will be omitted. The hot water producing system 1 of the second embodiment further includes a temperature adjustment heat exchanger 70 that indirectly exchanges heat between hot water W6 delivered from the hot water tank 40 and steam S from the steam boiler device 30. Fig. 11 is a diagram showing the hot water producing system 1 according to the second embodiment of the present invention.

[0116] As shown in FIG. 11, in this embodiment, a temperature adjustment heat exchanger 70 is provided in a hot water outlet line L6 that supplies hot water W6 from the hot water tank 40 to a hot water demand point. The temperature adjustment heat exchanger 70 is an indirect heat exchanger that performs indirect heat exchange between the hot water W6 delivered from the hot water tank 40 and the steam S from the steam boiler device 30. This heats the hot water W6 delivered from the hot water tank 40. The hot water W6 heated by the temperature adjustment heat exchanger 70 is supplied to the hot water demand point through the hot water outlet line L6. A hot water outlet temperature sensor 71 that detects the temperature of hot water delivered from the temperature adjustment heat exchanger 70 is provided downstream of the temperature adjustment heat exchanger 70.

[0117] The steam supply line 53 (temperature-raising steam supply line L2) in this embodiment branches midway, with one branch connected to the hot water tank 40 and the other branch connected to the temperature control heat exchanger 70. The line connected to the hot water tank 40 is provided with a temperature-raising steam supply valve 54 similar to that in the first embodiment. On the other hand, the line connected to the temperature control heat exchanger 70 constitutes a temperature control steam supply line L9, and this temperature control steam supply line L9 is provided with a temperature control steam supply valve 72.

[0118] These temperature control heat exchanger 70, temperature control steam supply line L9, temperature control steam supply valve 72, and outlet water temperature sensor 71 constitute additional heating means and have the function of adjusting the final terminal outlet water temperature using steam from the steam boiler equipment 30.

[0119] In this embodiment, the steam supply control unit 130 controls the temperature adjustment steam supply valve 72 in addition to the steam supply control described in the first embodiment. Specifically, the opening degree of the temperature adjustment steam supply valve 72 is controlled so that the temperature detected by the outlet hot water temperature sensor 71 becomes the target outlet hot water temperature. For example, when the target outlet hot water temperature is 90°C, the operation amount for the temperature adjustment steam supply valve 72 is calculated by a PID algorithm so that the temperature detected by the outlet hot water temperature sensor 71 converges to the target outlet hot water temperature of 90°C, and an opening degree designation signal is output from the steam supply control unit 130 to the actuator circuit of the temperature adjustment steam supply valve 72.

[0120] In this embodiment, the purpose is to stabilize the supply of hot heat to the hot water demand points. Therefore, the temperature detection by the outlet hot water temperature sensor 71 and the opening adjustment of the temperature control steam supply valve 72 are performed when hot water W6 flows through the hot water outlet line L6.

[0121] In general, it is difficult to keep the temperature distribution of the stored water TW in the hot water tank 40 constant, and some degree of temperature unevenness occurs. In particular, temperature unevenness is likely to occur when the size of the hot water tank 40 is large. Therefore, even if the heating steam supply valve 54 is controlled based on the temperature detected by the hot water temperature sensor 41, the temperature of the hot water W6 discharged from the hot water tank 40 may not be stable due to the influence of the temperature unevenness of the stored water TW in the hot water tank 40. However, as in this embodiment, by providing a temperature control heat exchanger 70 in the hot water discharge line L6, the final hot water temperature discharged from the hot water production system 1 can be appropriately controlled even if temperature unevenness occurs in the stored water TW in the hot water tank 40.

[0122] According to the hot water producing system 1 of the present embodiment described above, in addition to the effects (1) to (9), the following effects are achieved.

[0123] (10) The hot water producing system 1 of this embodiment includes a temperature control heat exchanger 70 that performs indirect heat exchange between hot water W6 discharged from the hot water tank 40 and steam S, a temperature control steam supply line L9 that supplies steam S generated by the steam boiler device 30 to the temperature control heat exchanger 70, and a temperature control steam supply valve 72 provided in the temperature control steam supply line L9. As a result, even if there is temperature unevenness in the hot water in the hot water tank 40, the final hot water outlet temperature can be increased using the temperature control heat exchanger 70.

[0124] (11) The hot water production system 1 of this embodiment includes an outlet hot water temperature sensor 71 that detects the outlet hot water temperature of the temperature adjustment heat exchanger 70, and controls the opening of the temperature adjustment steam supply valve 72 so that the temperature detected by the outlet hot water temperature sensor 71 becomes the target outlet hot water temperature. This allows the final outlet hot water temperature to be appropriately controlled.

[0125] <Third embodiment> Next, a third embodiment will be described with reference to Fig. 12. Note that a description of the same configuration as in the first embodiment will be omitted. The hot water producing system 1 of the third embodiment further includes a preheating heat exchanger 75 that performs indirect heat exchange between the service water W5 flowing through the bypass water supply line L5 and the steam S from the steam boiler device 30. Fig. 12 is a diagram showing the hot water producing system 1 according to the third embodiment of the present invention.

[0126] 12, in this embodiment, a preheating heat exchanger 75 is provided in the bypass water supply line L5. The preheating heat exchanger 75 is an indirect heat exchanger, and performs indirect heat exchange between the service water (cold water) W5 from the water supply tank 60 supplied through the bypass water supply line L5 and the steam from the steam boiler device 30. The preheating heat exchanger 75 is provided downstream of the bypass water supply valve 62.

[0127] The steam supply line 53 (heating steam supply line L2) in this embodiment is branched midway, one of which is connected to the hot water tank 40 and the other of which is connected to the preheating heat exchanger 75. The line connected to the hot water tank 40 is provided with a heating steam supply valve 54 similar to that in the first embodiment. On the other hand, the line connected to the preheating heat exchanger 75 constitutes the preheating steam supply line L10, and this preheating steam supply line L10 is provided with a preheating steam supply valve 76.

[0128] The preheating heat exchanger 75, the preheating steam supply line L10, and the preheating steam supply valve 76 constitute additional heating means and have the function of heating the water W5 supplied through the bypass water supply line L5.

[0129] In this embodiment, the hot water storage control unit 140 controls the preheating steam supply valve 76 in addition to the hot water storage control described in the first embodiment. Specifically, when the bypass water supply valve 62 is opened, the preheating steam supply valve 76 is also opened. This makes it possible to prevent a sudden drop in the temperature of the stored water TW in the hot water tank 40 due to the service water W5 supplied through the bypass water supply line L5.

[0130] As in the first embodiment, the bypass water supply valve 62 is opened when it is detected that the water level WL in the hot water tank 40 has fallen below the water level LL, that is, when the hot water tank 40 is about to run out of water. As a result, the cold water W5 stored in the water supply tank 60 is directly supplied to the hot water tank 40, preventing the hot water tank 40 from running out of water; however, the temperature of the water TW stored in the hot water tank 40 naturally drops.

[0131] The preheating heat exchanger 75 in this embodiment is provided to prevent as much as possible a decrease in the temperature of the stored water TW in the hot water tank 40 due to the replenishment of the water W5 through such bypass water supply. That is, when the bypass water supply valve 62 is opened, the preheating steam supply valve 76 is also opened, thereby heating the water W5 supplied into the hot water tank 40 through the bypass water supply line L5. This makes it possible to increase the temperature of the water W5 when the water W5 is replenished to the hot water tank 40 from the bypass water supply line L5.

[0132] According to the hot water producing system 1 of the present embodiment described above, in addition to the effects (1) to (9), the following effects are achieved.

[0133] (12) The hot water producing system 1 of this embodiment includes a preheating heat exchanger 75 that performs indirect heat exchange between the service water W5 flowing through the bypass water supply line L5 and steam, a preheating steam supply line L10 that supplies the steam S generated by the steam boiler device 30 to the preheating heat exchanger 75, and a preheating steam supply valve 76 provided on the preheating steam supply line L10, and opens the preheating steam supply valve 76 when the bypass water supply valve 62 is opened. This makes it possible to increase the temperature of the make-up water when supplying service water from the bypass water supply line L5 to the hot water tank 40.

[0134] <Fourth embodiment> Next, a fourth embodiment will be described with reference to Figs. 13-14. Description of configurations similar to those of the first embodiment will be omitted. The hot water producing system 1 of the fourth embodiment further includes a switching means 80 for switching the supply destination of the hot water W1 supplied from the water heaters 11, 12, and 13 to the hot water tank 40 or the water supply tank 60. Fig. 13 is a diagram showing the hot water producing system 1 according to the fourth embodiment of the present invention.

[0135] 13, in this embodiment, the hot water supply line L1 branches midway, one end being connected to the hot water tank 40 and the other being connected to the water supply tank 60. The hot water supply line connected to the water supply tank 60 constitutes the water supply tank hot water supply line L11.

[0136] Switching valves 81, 82, and 83 are provided as switching means 80 at the branching portion of the hot water supply line L1 connected to each of the water heaters 11, 12, and 13. These switching valves 81, 82, and 83 function as switching means for switching the supply destination of the hot water supplied from each of the water heaters 11, 12, and 13 to the hot water tank 40 side or the water supply tank 60 side. By providing such switching means, the supply direction of the hot water from each of the water heaters 11, 12, and 13 can be switched between the hot water tank 40 side and the water supply tank 60 side as necessary. This also makes it possible to continue the operation of the water heaters 11, 12, and 13 as much as possible, and solves the problem of low-temperature water supply at the initial stage of restarting the operation of the heat pump water heaters 11, 12, and 13.

[0137] In this embodiment, a second water supply tank 65 that supplies water to the heat pump water heaters 11, 12, and 13 is provided separately from the water supply tank 60. Water W1 from the second water supply tank 65 is supplied to the water heaters 11, 12, and 13 via a heat pump water supply line L3.

[0138] Next, a description will be given of the specific control of the switching valve 81. The hot water storage control unit 140 controls the bypass water supply valve 62, the heating steam supply valve 54, and the switching valves 81, 82, and 83 based on the detection result of the first water level sensor 42. The hot water tank 40 includes the first water level sensor 42 shown in FIG. 4, similar to the first embodiment.

[0139] In this embodiment, the hot water storage control unit 140 opens the bypass water supply valve 62 when the first water level sensor 42 detects that the water level has fallen below the water level LL. In addition, when the water level in the hot water tank 40 drops, the hot water storage control unit 140 controls the switching valves 81, 82, 83 to increase the number of hot water heaters 11, 12, 13 for the hot water tank 40 by one each time the water level detected by the first water level sensor 42 falls one step below the water level threshold, and at the same time to decrease the number of hot water heaters 11, 12, 13 for the water supply tank 60 by one; and when the water level in the hot water tank 40 rises, the hot water storage control unit 140 controls the switching valves 81, 82, 83 to decrease the number of hot water heaters 11, 12, 13 for the hot water tank 40 by one each time the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, and at the same time to increase the number of hot water heaters 11, 12, 13 for the water supply tank 60 by one. This control is performed, for example, at water level H, water level M, and water level L when the water level is decreasing, and at water level M, water level H, and water level HH when the water level is increasing. The hot water storage control unit 140 may control the heating steam supply valve 54 via the steam supply control unit 130. The hot water storage control unit 140 may also control the water heaters 11, 12, and 13 and the switching valves 81, 82, and 83 via the hot water supply control unit 110.

[0140] Here, for example, a case where the water level WL in the hot water tank 40 fluctuates will be described with reference to Fig. 14. Note that a description of the same control as that in Fig. 4 of the first embodiment will be omitted.

[0141] First, the control in the case where the water level WL is recovering (see arrow B in FIG. 4) will be described. When the water level WL rises and the tip of the third electrode rod 423 is submerged in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level M. At this time, it is determined that there is a little room left in the amount of water stored in the hot water tank 40, and only one of the three switching valves is switched to the water supply tank 60 side. For example, of the switching valves 81, 82, and 83, only the switching valve 83 is switched to the water supply tank 60 side. In other words, the switching means 80 is controlled so as to decrease the number of hot water supply units for the hot water tank 40 by one and at the same time increase the number of hot water supply units for the water supply tank 60 by one.

[0142] Next, when the water level WL rises further and the tip of the fourth electrode rod 424 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level H. At this time, it is determined that there is more water stored in the hot water tank 40, and two of the three switching valves are switched to the water supply tank 60 side. For example, of the switching valves 81, 82, and 83, the switching valves 82 and 83 are switched to the water supply tank 60 side.

[0143] Next, when the water level WL rises further and the tip of the fifth electrode 425 is immersed in the water surface, the first water level sensor 42 detects that the water level WL has exceeded the water level HH. At this time, it is determined that the amount of water stored in the hot water tank 40 is sufficient, and all three switching valves 81, 82, and 83 are switched to the water supply tank 60 side.

[0144] Next, a case where the water level WL drops from this state will be described. When the water level WL drops (see arrow A in FIG. 4) and the lower end of the fourth electrode rod 424 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below the water level H. When the hot water storage control unit 140 detects that the water level WL has fallen below the water level H, it switches one of the three switching valves to the hot water tank 40 side. For example, of switching valves 81, 82, and 83, switching valve 81 is switched to the hot water tank 40 side.

[0145] Here, if the water level WL rises after falling below the water level H and the tip of the fifth electrode rod 425 is submerged in the water surface, it is determined that the amount of water stored in the hot water tank 40 is sufficient again, and all of the switching valves 81, 82, 83 are switched to the water supply tank 60 side, as described above.

[0146] On the other hand, after the water level WL falls below water level H, when the water level WL falls further (see arrow A in FIG. 4) and the lower end of the third electrode rod 423 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below water level M. When the hot water storage control unit 140 detects that the water level WL has fallen below water level H, it switches two of the three switching valves to the hot water tank 40 side. For example, of the switching valves 81, 82, and 83, the switching valves 81 and 82 are switched to the hot water tank 40 side.

[0147] From this state, when the water level WL further drops and the lower end of the second electrode rod 422 is exposed above the water surface, the first water level sensor 42 detects that the water level WL has fallen below the water level L. When the hot water storage control unit 140 detects that the water level WL has fallen below the water level L, it switches all three switching valves 81, 82, 83 to the hot water tank 40 side.

[0148] As a result, the hot water W1 heated by the first heating means 2 can be switched to the hot water tank 40 or the water supply tank 60 depending on the need and supplied as hot water. That is, the hot water W1 heated by the first heating means 2 that does not need to be supplied to the hot water tank 40 can be supplied to the water supply tank 60 that stores water for boiler supply or bypass supply. Therefore, the hot water W1 heated by the first heating means 2 can be used effectively. In addition, by controlling the switching means 80, it is possible to continue the operation of the heat pump water heaters 11, 12, 13 as much as possible, and the problem of low-temperature water supply at the initial stage of restarting the operation of the heat pump can be solved.

[0149] In order to effectively heat the water for the boiler feed water and the bypass feed water, it is preferable to divide the water supply tank into a water supply tank 60 for storing the water for the boiler feed water and the bypass feed water and a second water supply tank 65 for storing the water for supply to the heat pump hot water supply system 10, and to supply the hot water W1 heated by the first heating means 2 to the water supply tank 60. However, as shown in the first embodiment, the second water supply tank 65 may be shared with the water supply tank 60. In this case, the water supplied to the heat pump hot water supply system 10 is also heated. The switching means 80 may be configured to be capable of switching the supply destination of the hot water W1 from the water heaters 11, 12, and 13 to the hot water tank 40 or the second water supply tank 65.

[0150] 10, the hot water storage control unit 140 shifts the number of operating water heaters in a predetermined water level band (for example, a water level band between water level L and water level M) between when the water level is rising and when the water level is falling, but instead of shifting the number of operating water heaters in a predetermined water level band between when the water level is rising and when the water level is falling, a status confirmation time may be provided, as in the first embodiment. In other words, the configuration may be such that control such as switching the switching valves 81, 82, 83 is executed when it is determined that the water level WL has remained above / below a predetermined water level threshold for a predetermined time.

[0151] Further, in this embodiment, a second water level sensor (not shown) for detecting the water level of the water supply tank 60 may be provided in the water supply tank 60, and when the water level detected by the second water level sensor reaches the water supply stop water level, one of the water heaters 11, 12, and 13 that is supplying hot water to the water supply tank 60 may be stopped, and when the detected water level reaches the water supply start water level, the water heater that is stopped may be operated. For example, when the water level WL is rising and exceeds the water level M, and one of the three water heaters, for example, the water heater 13, is supplying hot water to the water supply tank 60 side, when the water level detected by the second water level sensor of the water supply tank 60 reaches the water supply stop water level, the operation of the water heater 13 is stopped. Then, when the water level detected by the second water level sensor reaches the water supply start water level, the operation of the water heater 13 that has been stopped is resumed. This allows the water level in the water supply tank 60 to be appropriately managed.

[0152] According to the hot water producing system 1 of the present embodiment described above, in addition to the effects (1) to (9), the following effects are achieved.

[0153] (13) The hot water producing system 1 of this embodiment includes a water supply tank 60 that stores water to be supplied to the water heaters 11, 12, 13 and / or feed water to be supplied to the steam boiler device 30, and a switching means for switching the supply destination of the hot water W1 supplied from the water heaters 11, 12, 13 to the hot water tank 40 or the water supply tank 60. This allows the hot water W1 supplied from the water heaters 11, 12, 13 to be supplied by switching to the hot water tank 40 or the water supply tank 60 as needed. Furthermore, by being able to switch, it is possible to continue operation of the heat pump as long as possible, and the problem of low-temperature water supply at the initial stage of restarting the operation of the heat pump can be eliminated. (14) The hot water producing system 1 of this embodiment includes a first water level sensor 42 that detects the water level in the hot water tank 40, and the first heating means 2 includes a plurality of water heaters 11, 12, and 13. The hot water tank 40 has a plurality of water level thresholds set therein for changing the number of hot water heaters 11, 12, and 13. When the water level in the hot water tank 40 drops, the number of hot water heaters 11, 12, and 13 for the hot water tank 40 is reduced by one each time the water level detected by the first water level sensor 42 falls below the water level threshold by one step. When the water level in the hot water tank 40 rises, the switching means 80 is controlled so that the number of hot water heaters 11, 12, 13 for the hot water tank 40 is decreased by one each time the water level detected by the first water level sensor 42 exceeds the water level threshold by one step, and the switching means 80 is controlled so that the number of hot water heaters 11, 12, 13 for the hot water tank 40 is increased by one each time the water level detected by the first water level sensor 42 exceeds the water level threshold by one step. This allows water to be supplied by switching between the hot water tank 40 and the water supply tank 60 as necessary. Also, by controlling the switching means 80, it is possible to continue operation of the heat pump as long as possible, and the problem of low-temperature water supply at the initial stage of restarting operation of the heat pump can be eliminated. (15) The hot water producing system 1 of this embodiment includes a second water level sensor that detects the water level in the water supply tank 60, and when the water level detected by the second water level sensor reaches the water supply stop water level, the water heater that is supplying hot water to the water supply tank 60 is stopped, and when the detected water level reaches the water supply start water level, the water heater that is stopped is operated. This allows the water level in the water supply tank 60 to be appropriately managed.

[0154] Although the preferred embodiments of the hot water producing system of the present invention have been described above, the present invention is not limited to the above-mentioned embodiments and can be modified as appropriate. In addition, a plurality of embodiments can be combined. [Explanation of symbols]

[0155] 1. Hot water production system 2...First heating means 3...Second heating means 10. Heat pump hot water system 11…First heat pump water heater 12…Second heat pump water heater 13…Third heat pump water heater 14, 15, 16...Hot water temperature sensor 17, 18, 19…Water supply pump 30...Steam boiler equipment 31...Once-through boiler 40…Hot water tank 41…Hot water temperature sensor 42…First water level sensor 421...1st electrode rod 422...Second electrode rod 423...Third electrode rod 424…4th electrode rod 425...5th electrode rod 51…Steam header 52…Connecting line 53…Steam supply line 54... Steam supply valve for heating 55…Pressure gauge 60…Water tank 62...Bypass water supply valve 70...Heat exchanger for temperature control 71...Outlet water temperature sensor 72…Temperature control steam supply valve 75…Preheating heat exchanger 76…Preheating steam supply valve 80...Switching means 81, 82, 83...Switching valve 90…Heat pump circuit 91...Refrigerant compressor 92…Condenser 93…Expansion valve 94…Evaporator 100...Control unit 110...Hot water supply control unit 120...Boiler control unit 130...Steam supply control unit 140...Hot water storage control unit L1…Hot water supply line L2: Steam supply line for heating L3…Heat pump water supply line L4…Boiler feed water line L5…Bypass water supply line L6…Hot water outlet line L7…Refrigerant circulation line L8…Heat source water supply line L9…Temperature control steam supply line L10: Preheating steam supply line W1…Water (warm water) W5…Water (cold water) W6…Hot water S: Steam R…Refrigerant TW: Hot water, stored water WL…Water level

Claims

1. A first heating means for heating the water to a target hot water temperature while passing the water through the heat pump type hot water heater; a second heating means for directly exchanging heat with the water heated to the target hot water supply temperature by the first heating means, the second heating means heating the water to a target hot water outlet temperature set higher than the target hot water supply temperature, the second heating means heating the water to a target hot water outlet temperature set higher than the target hot water supply temperature, the second heating means directly exchanging heat with the water heated to the target hot water supply temperature by the first heating means and the steam adjusted to a target steam pressure; A control means for controlling the first heating means and the second heating means, The control means adjusts the output sharing between the water heater and the steam boiler in accordance with the set target hot water outlet temperature.

2. The second heating means is a steam header that collects steam generated in the steam boiler; a heating steam supply valve for adjusting the amount of steam supplied from the steam header, The control means a boiler control unit that controls the steam boiler so that a header pressure of the steam header becomes the target steam pressure; 2. The hot water producing system according to claim 1, further comprising: a steam supply control unit that controls the heating steam supply valve so that the hot water discharged from the second heating means has the set target hot water discharge temperature.

3. The second heating means is A hot water tank for storing hot water heated by the water heater; a first water level sensor for detecting a water level in the hot water tank; a heating steam supply line for supplying steam generated by the steam boiler to the hot water tank; A heating steam supply valve provided in the heating steam supply line; a hot water temperature sensor for detecting the temperature of the hot water in the hot water tank; The first heating means is A water supply line for supplying water to the water heater; a hot water supply line that supplies hot water heated by the hot water heater to the hot water tank; a hot water temperature sensor for detecting a hot water temperature of the hot water flowing through the hot water supply line; The control means When the water level in the hot water tank drops and the detected water level of the first water level sensor falls below a first set water level, the supply of water through the water supply line and the supply of hot water through the hot water supply line are executed; when the water level detected by the first water level sensor exceeds a second set water level that is higher than the first set water level during a water level rise in the hot water tank, the supply of water through the water supply line and the supply of hot water through the hot water supply line are stopped; When the water supply is in progress, Controlling the water heater so that the temperature detected by the hot water temperature sensor becomes the target hot water temperature; 2. The hot water producing system according to claim 1, wherein an opening degree of the heating steam supply valve is controlled so that the temperature detected by the hot water storage temperature sensor becomes the target hot water outlet temperature.

4. a bypass water supply line for supplying water to the hot water tank without passing through the water heater; a bypass water supply valve provided in the bypass water supply line, The control means When the water level in the hot water tank drops and the detected water level of the first water level sensor falls below a third set water level that is lower than the first set water level, the bypass water supply valve is opened and the heating steam supply valve is controlled to be fully open, When the water level in the hot water tank rises and the detected water level of the first water level sensor exceeds a fourth set water level that is higher than the third set water level, the bypass water supply valve is closed; The hot water producing system according to claim 3 , wherein an amount of steam supplied when the bypass water supply valve is in an open state is greater than an amount of steam supplied when the bypass water supply valve is in a closed state.

5. a bypass water supply line for supplying water to the hot water tank without passing through the water heater; A bypass water supply valve provided in the bypass water supply line; a preheating heat exchanger for indirectly exchanging heat between the water flowing through the bypass water supply line and steam; a preheating steam supply line for supplying steam generated in the steam boiler to the preheating heat exchanger; A preheating steam supply valve provided in the preheating steam supply line, The control means When the water level in the hot water tank drops, if the detected water level of the first water level sensor falls below a third set water level that is lower than the first set water level, the bypass water supply valve is opened and the pre-heating steam supply valve is opened.

4. The hot water producing system according to claim 3, wherein when the water level in the hot water tank rises and the detected water level of the first water level sensor exceeds a fourth set water level that is higher than the third set water level, the bypass water supply valve is closed.

6. a temperature control heat exchanger for indirectly exchanging heat between the hot water discharged from the hot water tank and steam; a temperature control steam supply line for supplying steam generated in the steam boiler to the temperature control heat exchanger; A temperature control steam supply valve provided in the temperature control steam supply line; a hot water outlet temperature sensor for detecting a hot water outlet temperature of the temperature adjustment heat exchanger; The control means The hot water producing system according to any one of claims 3 to 5, wherein the opening degree of the temperature adjusting steam supply valve is controlled so that the detected temperature of the outlet hot water temperature sensor becomes the target outlet hot water temperature.

7. The first heating means includes a plurality of the water heaters, A plurality of water level thresholds are set in the hot water tank for changing the number of the water heaters in operation; The control means When the water level in the hot water tank is decreasing, a number control is executed to increase the number of the water heaters in operation by one each time the water level detected by the first water level sensor falls below the water level threshold by one level; A hot water producing system as described in any one of claims 3 to 6, wherein when the water level in the hot water tank rises, a number control is performed to reduce the number of operating water heaters by one each time the detected water level of the first water level sensor exceeds the water level threshold by one step.

8. The first heating means includes a plurality of the water heaters, A plurality of water level thresholds are set in the hot water tank for changing the number of the hot water heaters in operation and / or the target hot water temperature; The water heater is capable of switching a target hot water supply temperature among a plurality of stages within a temperature range higher than a first temperature and lower than the target hot water outlet temperature, The control means When the target hot water temperature of the water heater is set to the first temperature and the detected water level of the first water level sensor exceeds the water level threshold by one step, control is executed to increase the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters; when the target hot water temperature of the water heater is increased by one step or more and the detected water level of the first water level sensor exceeds the water level threshold by one step, control is executed to reduce the number of operating water heaters by one and at the same time return the target hot water temperature to the first temperature, or control is executed to increase the target hot water temperature of the water heater by another step while maintaining the number of operating water heaters; A hot water production system as described in any of claims 3 to 6, wherein, during operation with the target hot water temperature of the water heater set to the first temperature, when the water level detected by the first water level sensor falls one step below the water level threshold, control is executed to increase the number of operating water heaters by one and at the same time raise the target hot water temperature of the water heater by one or more steps, and, during operation with the target hot water temperature of the water heater raised by one or more steps, when the water level detected by the first water level sensor falls one step below the water level threshold, control is executed to lower the target hot water temperature of the water heater by one step while maintaining the number of operating water heaters.

9. a water supply tank for storing water to be supplied to the water heater and / or water to be supplied to the steam boiler; The hot water producing system according to any one of claims 3 to 8, further comprising a switching means for switching a supply destination of the hot water supplied from the water heater to the hot water tank or the water supply tank.

10. The first heating means includes a plurality of the water heaters, The hot water tank is provided with a plurality of water level thresholds for changing the number of hot water heaters; The control means When the water level in the hot water tank is decreasing, the switching means is controlled so that the number of hot water heaters for the hot water tank is increased by one each time the water level detected by the first water level sensor falls below the water level threshold by one step, and at the same time, the number of hot water heaters for the water supply tank is decreased by one each time; The hot water producing system of claim 9, wherein when the water level in the hot water tank rises, the switching means controls so as to reduce the number of hot water heaters for the hot water tank by one each time the detected water level of the first water level sensor exceeds the water level threshold by one step, while at the same time increasing the number of hot water heaters for the water supply tank by one.

11. a second water level sensor for detecting a water level in the water supply tank; The control means The hot water producing system according to claim 9 or claim 10, wherein when the detected water level of the second water level sensor reaches a water supply stop water level, the water heater that is supplying hot water to the water tank is stopped, and when the detected water level reaches a water supply start water level, the water heater that is stopped is operated.

12. A first heating step of heating the water to a target hot water temperature while passing the water through the heat pump water heater; a second heating step of directly exchanging heat with steam generated by a steam boiler and adjusted to a target steam pressure, thereby raising the temperature of the water heated to the target hot water supply temperature in the first heating step to a target hot water outlet temperature set higher than the target hot water supply temperature; A hot water producing method comprising: adjusting an output share between the water heater and the steam boiler in accordance with the set target hot water outlet temperature during execution of the first heating step and the second heating step.

Citation Information

Patent Citations

  • Hydraulic system and food processing apparatus

    JP2009133522A

  • Heat supply system

    JP2010286135A

  • Heated water manufacturing system

    JP2017032224A