Distributed energy resource management device, distributed energy resource management system, and distributed energy resource management program

The distributed energy resource management device optimizes DER power output to balance supply and demand, addressing voltage and current constraints, thereby reducing the need for additional infrastructure and enhancing system stability.

JP7577050B2Active Publication Date: 2024-11-01MITSUBISHI ELECTRIC CORP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2021202850
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-12-14
Publication Date
2024-11-01
Estimated Expiration
2041-12-14

AI Technical Summary

Technical Problem

Existing technologies for managing distributed energy resources (DERs) struggle to balance power supply and demand while adhering to voltage and current constraints, leading to potential violations and the need for additional capital investments in voltage regulation equipment.

Method used

A distributed energy resource management device that calculates and controls the active and reactive power output of DERs to match supply and demand, ensuring compliance with voltage and current constraints, using an optimal power flow calculation and communication system to adjust the power control ranges of individual DERs.

Benefits of technology

This approach enables effective power supply and demand management, reducing the risk of voltage and current violations and minimizing capital investments by optimizing the control of DERs within the power distribution system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007577050000001
    Figure 0007577050000001
  • Figure 0007577050000002
    Figure 0007577050000002
  • Figure 0007577050000003
    Figure 0007577050000003
Patent Text Reader

Abstract

To obtain a DER management device that can provide a VPP aggregator with a range of effective power control quantities for each DER while meeting grid voltage and current constraints for grid supply and demand coordination.SOLUTION: A DER management device 2 includes an optimum tidal current calculation unit 24, a control command value calculation unit, and a communication unit 21. The optimum tidal current calculation unit 24 calculates the maximum values of the charge and discharge quantities that can be output in the range of a controllable first amount of power of a first DER in a period to be controlled, provided that the constraints on the voltage and current of a distribution system are observed from voltage and current distributions of the distribution system based on supply and demand forecasts, and determines an effective power control range defined by the maximum values of the charge and discharge quantities. The control command value calculation unit generates first control command information in which each of the plurality of first DERs is associated with the effective power control range. The communication unit 21 transmits the first control command information to a VPP aggregator that determines the effective power amount to be commanded to the plurality of first DERs.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a distributed energy resource management device, a distributed energy resource management system, and a distributed energy resource management program that manage the amount of charged and discharged power in accordance with supply and demand adjustment of distributed energy resources such as storage batteries. [Background technology]

[0002] Currently, distributed energy resources (DER), which include solar power generation facilities, storage batteries, electric vehicles, etc. as energy facilities, are becoming widespread. Technologies for supply and demand control using DER are being considered for the time when DER will become widespread in large quantities. One of these technologies is the Virtual Power Plant (VPP), which bundles together a number of DERs connected to the power distribution system and regards them as a single virtual substation.

[0003] On the other hand, when a large number of DERs are connected to the grid, there is a possibility that a current violation, in which the current deviates from a specified range, or a voltage violation, in which the voltage deviates from a specified range, may occur in the distribution system. In order to prepare for current or voltage violations, further capital investment in voltage regulators and other equipment will be required. Therefore, in order to reduce capital investment when DERs are widely adopted, there is a technology called a DER management device that appropriately controls DERs.

[0004] Furthermore, Patent Document 1 discloses a technology for predicting the range of voltage fluctuations in a power grid and performing proactive voltage control of the power grid so that the voltage does not violate the voltage regulation of the power grid when the output of a DER fluctuates significantly. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2017-108489 A Summary of the Invention [Problem to be solved by the invention]

[0006] However, in the technology described in the above Patent Document 1, the control amount for controlling the voltage of the power system is determined only for the purpose of eliminating the voltage violation in the power system, and matching the demand and supply of power is not taken into consideration. In addition, when adjusting the supply and demand of power, the VPP aggregator does not have system information indicating the distribution of voltage and current in the power distribution system, and therefore cannot adjust the supply and demand taking into account the system status. As a result, the control of the active power amount for adjusting the supply and demand of power by the VPP aggregator may cause a voltage and current violation in the power distribution system. For this reason, a technology has been desired that allows the VPP aggregator to control the active power amount of each DER while taking into account the voltage and current constraints in order to adjust the supply and demand of the system.

[0007] The present disclosure has been made in consideration of the above, and aims to provide a distributed energy resource management device that can provide a range of active power control amount of each DER to a VPP aggregator while satisfying the voltage and current constraints of the grid, for adjusting supply and demand in the grid. [Means for solving the problem]

[0008] In order to solve the above-mentioned problems and achieve the object, the present disclosure provides a distributed energy resource management device that calculates an output of a distributed energy resource including a plurality of first distributed energy resources that are connected to a power distribution system and whose output active power is controlled. The distributed energy resource management device includes an optimal power flow calculation unit, a control command value calculation unit, and a communication unit. The optimal power flow calculation unit calculates a maximum value of a charge amount and a discharge amount that can be output within a range of a first amount of power that can be controlled by the first distributed energy resource during a control target period while observing constraints on the voltage and current of the power distribution system from a voltage and current distribution of the power distribution system based on a supply and demand forecast, and determines an active power control range that is determined by the maximum value of the charge amount and the discharge amount. The control command value calculation unit generates first control command information that associates each of the plurality of first distributed energy resources with the active power control range. The communication unit transmits the first control command information to a virtual substation aggregator that determines an active power amount to be commanded to the plurality of first distributed energy resources. The active power control range is the control range of the active power output from the first distributed energy resource. Effect of the Invention

[0009] According to the present disclosure, it is possible to provide a VPP aggregator with a range of active power control amount of each DER while satisfying the constraints of the voltage and current of the grid in order to adjust supply and demand in the grid. [Brief description of the drawings]

[0010] [Figure 1] FIG. 1 is a diagram illustrating an example of a configuration of a distributed energy resource management system and a power system to be controlled according to a first embodiment. [Diagram 2] FIG. 1 is a diagram illustrating an example of a configuration of a DER provided in a DER management system according to a first embodiment; [Diagram 3] FIG. 1 is a diagram illustrating an example of a configuration of a DER management device provided in a DER management system according to a first embodiment; [Figure 4] FIG. 1 is a diagram illustrating an example of a configuration of a VPP aggregator provided in a DER management system according to a first embodiment; [Diagram 5] FIG. 1 is a diagram illustrating an example of a configuration of a power distribution automation system provided in a DER management system according to a first embodiment. [Figure 6] A flowchart showing an example of a procedure of a DER management method according to the first embodiment. [Figure 7] A flowchart showing an example of a procedure of a DER management method according to the first embodiment. [Figure 8] FIG. 1 is a schematic diagram showing an example of a configuration of a power distribution system. [Figure 9] FIG. 9 is a diagram showing an example of voltage distribution in the power distribution system shown in FIG. 8. [Figure 10] FIG. 9 is a diagram showing an example of the charge / discharge amount in each DER in the power distribution system shown in FIG. 8. [Figure 11] A diagram showing an example of voltage control in the second DER. [Figure 12] A flowchart showing an example of a procedure for a command value calculation process for a VPP aggregator in a DER management system according to the first embodiment. [Figure 13] A flowchart showing an example of a procedure for setting a parameter of a power distribution automation system in a DER management system according to the first embodiment. [Figure 14] FIG. 1 is a diagram showing an example of the configuration of a computer system that realizes a DER management device, a VPP aggregator, and a power distribution automation system used in a DER management system according to a first embodiment. [Figure 15] A flowchart showing an example of a procedure of a DER management method according to the second embodiment. [Figure 16] FIG. 9 is a diagram showing an example of voltage distribution in the power distribution system shown in FIG. 8. [Figure 17] FIG. 11 is a diagram illustrating an example of a configuration of a DER management system according to a third embodiment. [Figure 18] FIG. 11 is a diagram illustrating an example of the configuration of a DER management device according to a third embodiment. [Figure 19] A flowchart showing an example of a procedure of a DER management method according to a third embodiment. [Figure 20] A flowchart showing an example of a procedure of a DER management method according to a fourth embodiment. [Figure 21]FIG. 13 is a diagram illustrating an example of the configuration of a DER management device according to a fifth embodiment. [Figure 22] FIG. 13 is a diagram illustrating an example of a configuration of a power distribution automation system according to a fifth embodiment. [Figure 23] FIG. 13 is a diagram illustrating an example of a configuration of a DER management system according to a fifth embodiment. [Figure 24] FIG. 13 is a schematic diagram illustrating another example of the configuration of a DER management system according to the fifth embodiment. [Diagram 25] FIG. 13 is a diagram illustrating another example of the configuration of a DER management device according to the fifth embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A distributed energy resource management device, a distributed energy resource management system, and a distributed energy resource management program according to embodiments of the present disclosure will be described below in detail with reference to the accompanying drawings.

[0012] Embodiment 1 FIG. 1 is a diagram showing an example of a configuration of a distributed energy resource management system according to a first embodiment and a power system to be controlled. In the first embodiment, a distributed energy resource management system 1 including a distributed energy resource management device 2, a virtual substation aggregator 3, a power distribution automation system 4, a load 5, and a first distributed energy resource 6a controls an active power control amount of the first distributed energy resource 6a so that the demand and supply of the power system match within a range that satisfies a power system constraint in the power system to be controlled. The power system constraint includes constraints that the voltage and current in the power system to be controlled should satisfy. Hereinafter, the distributed energy resource management system 1 is referred to as a DER management system 1, the distributed energy resource management device 2 is referred to as a DER management device 2, and the distributed energy resource is referred to as a DER. In addition, the virtual substation aggregator 3 is referred to as a VPP aggregator 3.

[0013] In addition, in embodiment 1, the DER management system 1, which further has a second DER 6b, controls the active power control amount of the first DER 6a and determines the reactive power control amount and setting value of the second DER 6b so that the demand and supply of the power system are matched within a range that satisfies the power system constraints in the power system to be controlled.

[0014] In the following, a case where the power system to be controlled is a power distribution system 100 will be taken as an example. In the power distribution system 100 of the DER management system 1, a power distribution line 103 is connected to a power distribution transformer 101 via a bus 102. The power distribution line 103 is, for example, a high-voltage power distribution line of 6600V or the like. Although not shown, a pole transformer or the like may be connected to the power distribution line 103. The pole transformer is a transformer that converts high-voltage power such as 6600V into low-voltage power such as 100V or 200V and outputs the power to a low-voltage power distribution line. In addition, although not shown, the power distribution line 103 may be provided with a voltage regulator. An example of the voltage regulator is an SVR (Step Voltage Regulator). The SVR is a voltage control device that controls the voltage in the power distribution line 103 so that the voltage in the power distribution line 103 is within an appropriate range determined by the power system constraint.

[0015] A load 5 and a first DER 6a or a second DER 6b are connected to the distribution line 103. The load 5 is a device owned by a consumer 7 that consumes power. The consumer 7 receives power from the distribution line 103. The first DER 6a and the second DER 6b are facilities owned by the consumer 7 that can be charged and discharged or facilities that can generate power. Facilities that can be charged and discharged may include facilities that can only be charged. In the following, the charging amount indicates the amount of stored electric charge when the first DER 6a and the second DER 6b are facilities that can be charged and discharged, but when the first DER 6a and the second DER 6b include facilities that can generate power as well as facilities that can be charged and discharged, it also includes the amount of suppression of the amount of power generation in facilities that can generate power. Furthermore, when the first DER 6a and the second DER 6b are facilities capable of charging and discharging, the discharge amount indicates the amount of charge discharged, but when the first DER 6a and the second DER 6b include not only facilities capable of charging and discharging but also facilities capable of generating electricity, it also includes the amount of electricity generated by facilities capable of generating electricity. However, when the first DER 6a or the second DER 6b indicates facilities capable of generating electricity, i.e., when facilities capable of charging and discharging are not included, the amount of electricity generated is expressed as the amount of electricity generated.

[0016] The first DER 6a is a DER in which power supply and demand control is performed by active power. The second DER 6b is a DER that has a voltage control function and performs voltage control by reactive power. The first DER 6a is also a DER that does not have a voltage control function. In the following description, when the first DER 6a and the second DER 6b are not distinguished from each other, the first DER 6a and the second DER 6b are referred to as DER 6.

[0017] In the example of FIG. 1, all the consumers 7 have the first DER 6a or the second DER 6b, but not all the consumers 7 may have the DER 6. The first DER 6a transmits the first controllable amount of power, which is the controllable amount of power for each determined period to be controlled, to the VPP aggregator 3 via the communication network 71. The first DER 6a controls the charge / discharge amount or the power generation amount according to a command from the VPP aggregator 3. Hereinafter, the determined period to be controlled is referred to as the controlled period. The second DER 6b transmits the second controllable amount of power, which is the controllable amount of power for each determined period to the distribution automation system 4 via the communication network 72. The second DER 6b controls the reactive power amount according to a command from the distribution automation system 4. The first controllable amount of power corresponds to the first amount of power, and the second controllable amount of power corresponds to the second amount of power. The communication networks 71 and 72 may be the Internet or a dedicated line. Furthermore, the communication networks 71 and 72 may be wired networks, wireless networks, or may include both.

[0018] The DER management device 2 is a device that calculates the control range of the output of the DER 6 including a plurality of first DER 6a connected to the power distribution system 100. The DER management device 2 uses information from the VPP aggregator 3 connected to the communication network 73 to determine an active power control range, which is a range of the control amount that can be charged and discharged of the first DER 6a of each distribution line 103 of the power distribution system 100 while satisfying the power system constraints of the power distribution system 100. In addition, when the DER management system 1 includes a second DER 6b, the DER management device 2 uses information from the power distribution automation system 4 connected to the communication network 73 to determine a reactive power control amount of the second DER 6b of each distribution line 103 of the power distribution system 100 while satisfying the power system constraints of the power distribution system 100, and determines a setting value that specifies the range in which the control of the reactive power amount is executed. The DER management device 2 transmits the active power control range to the VPP aggregator 3 via the communication network 73, and transmits the reactive power control amount and the setting value to the power distribution automation system 4 via the communication network 73.

[0019] The VPP aggregator 3 is a device that manages the amount of charge or discharge of the DER 6 owned by the consumer 7. The VPP aggregator 3 is a device provided in a business that manages the amount of charge or discharge of the DER 6 of the consumer 7. In the first embodiment, the VPP aggregator 3 is a device that determines the amount of active power to be commanded to a plurality of first DERs 6a for supply and demand adjustment. The VPP aggregator 3 collects the first controllable power amount from the first DER 6a and transmits the first controllable power amount to the DER management device 2 via the communication network 73. In addition, when the VPP aggregator 3 receives the active power control range from the DER management device 2, it determines the active power control amount for each first DER 6a that minimizes the operation cost for adjusting the supply and demand of power within the active power control range, and output plan information that specifies the timing of outputting the active power control amount for each first DER 6a. The VPP aggregator 3 transmits the output plan information as a first control command value to each first DER 6a via the communication network 71. The output plan information, for example, is information that specifies the timing and extent of the active power control amount that each first DER 6a outputs within a control target period. Note that, although FIG. 1 illustrates a case in which the VPP aggregator 3 determines the control amount for supply and demand control for the DER 6 connected to the distribution system 100, it also manages the charge or discharge amount for the DER 6 connected to other distribution systems (not shown) other than the distribution system 100 in its own system.

[0020] The power distribution automation system 4 collects the second controllable power amount from the second DER 6b and transmits the second controllable power amount to the DER management device 2 via the communication network 73. Furthermore, when the power distribution automation system 4 receives the reactive power control amount and setting value for each second DER 6b from the DER management device 2, it transmits the reactive power control amount and setting value as second control command values ​​to each second DER 6b via the communication network 72.

[0021] Next, the configurations of the DER 6, DER management device 2, VPP aggregator 3, and distribution automation system 4 will be described in detail. FIG. 2 is a diagram showing a schematic example of the configuration of a DER provided in the DER management system according to the first embodiment. Since the basic configuration is the same for the first DER 6a and the second DER 6b, they will be described together in FIG. 2. The DER 6 includes a distributed energy device 61 and a power control device 62.

[0022] The distributed energy device 61 includes energy equipment (not shown) that performs charging / discharging or generating power, a PCS (Power Conditioning Subsystem: power conditioner) that is disposed between the power distribution system 100 and the energy equipment and controls the power in the energy equipment, and an energy control unit (not shown) such as an inverter. Examples of energy equipment include charging / discharging equipment that is a device capable of charging / discharging such as an electric vehicle or a storage battery, and power generation equipment that is a device capable of generating power such as a solar power generation equipment. When the energy equipment is an electric vehicle, the energy control unit is a charging / discharging device that controls charging / discharging of a storage battery mounted on the electric vehicle. When the energy equipment is a storage battery, the energy control unit is a PCS that controls charging / discharging of the storage battery. When the energy equipment is a solar power generation equipment, the energy control unit is a PCS that converts the generated power of the solar power generation equipment into AC power and controls the output power of the solar power generation equipment.

[0023] When the DER 6 is the first DER 6a, the distributed energy device 61 is a device in which the active power outputted is controlled. When the DER 6 is the first DER 6a, the distributed energy device 61 does not have a voltage control function. When the DER 6 is the second DER 6b, the distributed energy device 61 is a device in which the voltage control function is performed and the reactive power outputted is controlled. The voltage control function is a function that outputs reactive power and controls the voltage of the second DER 6b so that the interconnection point voltage falls within the dead zone when the interconnection point voltage with the power distribution system 100 deviates from a dead zone determined by a specified setting value.

[0024] The power control device 62 acquires the controllable power amount of the DER 6 for each control target period and transmits it to the VPP aggregator 3 or the distribution automation system 4. The controllable power amount includes a first controllable power amount in the case of the first DER 6a and a second controllable power amount in the case of the second DER 6b. The power control device 62 also controls the power of the distributed energy device 61 according to the first control command value or the second control command value acquired from the VPP aggregator 3 or the distribution automation system 4. An example of the control target period is a period during which the DER management device 2 and the VPP aggregator 3 perform power supply and demand prediction, and is 30 minutes, 1 hour, etc. The power control device 62 includes a communication unit 621, a controllable power calculation unit 622, a storage unit 623, and a control unit 624.

[0025] The communication unit 621 communicates with the VPP aggregator 3 or the distribution automation system 4 via the communication networks 71, 72. In one example, the communication unit 621 transmits the controllable power amount of the distributed energy device 61 calculated by the controllable power calculation unit 622 to the VPP aggregator 3 in the case of the first DER 6a, and transmits it to the distribution automation system 4 in the case of the second DER 6b. Furthermore, in the case of the first DER 6a, the communication unit 621 receives a first control command value for the first DER 6a received from the VPP aggregator 3 and stores it in the storage unit 623. In the case of the second DER 6b, the communication unit 621 receives a second control command value for the second DER 6b received from the distribution automation system 4 and stores it in the storage unit 623.

[0026] The controllable power calculation unit 622 calculates the controllable power amount, which is the amount of power that can be controlled by the distributed energy device 61 during the control target period, and outputs it to the communication unit 621. The control target period is 30 minutes, 1 hour, etc., as described above. When the distributed energy device 61 has a photovoltaic power generation facility as an energy facility, the controllable power amount is the amount by which the power generation capacity of the photovoltaic power generation facility at the time of calculation can be suppressed during the control target period. When the distributed energy device 61 has a storage battery as an energy facility, the controllable power amount is the amount by which the storage battery can continue to discharge or charge during the control target period based on the energy (State of Charge: SoC) stored in the storage battery. Since the SoC of the storage battery changes from moment to moment, the amount that can be discharged or charged also changes at the time of calculation. When the distributed energy device 61 has an electric vehicle as an energy facility, it is the same as when the distributed energy device 61 has a storage battery as an energy facility.

[0027] The storage unit 623 stores a first control command value received from the VPP aggregator 3 via the communication unit 621 when the DER 6 is the first DER 6a, and stores a second control command value received from the power distribution automation system 4 via the communication unit 621 when the DER 6 is the second DER 6b. When the DER 6 is the first DER 6a, the first control command value is output plan information, and when the DER 6 is the second DER 6b, the second control command value is a reactive power control amount and a setting value. Hereinafter, when the first control command value and the second control command value are not distinguished from each other, the first control command value and the second control command value are simply referred to as control command values.

[0028] The control unit 624 uses the control command value to control the distributed energy equipment 61. In the case of the first DER 6a, the control unit 624 refers to the output plan information, which is the first control command value stored in the memory unit 623, and outputs a command to the distributed energy equipment 61 so that a specified amount of output is performed at a time specified in the output plan information, thereby controlling the distributed energy equipment 61. In the case of the second DER 6b, the control unit 624 sets the setting value stored in the memory unit 623 to the distributed energy equipment 61.

[0029] 3 is a diagram illustrating an example of a configuration of a DER management device provided in the DER management system according to Embodiment 1. The DER management device 2 includes a communication unit 21, a storage unit 22, a prediction unit 23, an optimal power flow calculation unit 24, and a DER control command value calculation unit 25.

[0030] The communication unit 21 communicates with the VPP aggregator 3 and the distribution automation system 4 via the communication network 73. In one example, the communication unit 21 receives a first controllable amount of power of the first DER 6a from the VPP aggregator 3 and stores it in the storage unit 22. The communication unit 21 receives a second controllable amount of power of the second DER 6b from the distribution automation system 4 and stores it in the storage unit 22. In addition, the communication unit 21 transmits first control command information for the first DER 6a calculated by the DER control command value calculation unit 25 to the VPP aggregator 3, and transmits second control command information for the second DER 6b to the distribution automation system 4.

[0031] The storage unit 22 stores the first controllable power amount of the first DER 6a received from the VPP aggregator 3 and the second controllable power amount of the second DER 6b received from the power distribution automation system 4. The storage unit 22 also stores load power generation result information including a result value of the load demand in the power distribution system 100 and a result value of the power generation profile. The result value of the load demand is past data of the amount of power requested by the load 5 connected to the power distribution system 100 in each time period of the day. The result value of the power generation profile is past data of the amount of power generated by the DER capable of generating power connected to the power distribution system 100 in each time period of the day. In one example, the result value of the load demand and the result value of the power generation profile are data collected from measuring devices (not shown) installed in the load 5 and the DER 6, respectively. In one example, the load power generation result information is desirably information in which the result value of the load demand and the result value of the power generation profile are associated with at least one of the day type and the weather condition. The day type is information indicating the type of day, such as a weekday or a holiday, and the weather conditions are information on the weather, temperature, and the like.

[0032] The prediction unit 23 predicts the load demand of the load 5 connected to the power distribution system 100 and the power generation amount of the DER capable of generating power during the control period based on the load power generation result information, and estimates the voltage and current distribution in the distribution line 103 of the power distribution system 100 during the control period based on the prediction result. The control period is a period during which the DER management device 2 predicts supply and demand, and is 30 minutes, 1 hour, etc. Specifically, the prediction unit 23 obtains the actual value of the load demand during the period corresponding to the control period from the load power generation result information, and predicts the load demand during the control period by performing statistical processing. In addition, the prediction unit 23 obtains the actual value of the power generation profile during the period corresponding to the control period from the load power generation result information, and predicts the power generation amount during the control period by performing statistical processing, etc. Hereinafter, the predicted load demand and power generation amount during the control period are referred to as a load demand forecast value and a power generation forecast value, respectively. In this case, if the load power generation result information includes at least one of information on the day type and weather conditions, the load demand forecast value and the power generation forecast value can be predicted using the load demand result value and the power generation profile result value of a day with similar conditions to the day on which the prediction is made using this information. As a result, it is possible to improve the prediction accuracy of the load demand and power generation amount during the control target period.

[0033] Furthermore, the prediction unit 23 calculates the voltage at the interconnection point between each distribution line 103 of the distribution system 100 and the DER 6, and the current flowing through the line between the interconnection points, using the load demand forecast value and the power generation forecast value for the control period. This makes it possible to estimate the voltage distribution, which is the distribution of voltages in the distribution line 103, and the current distribution, which is the distribution of currents. Hereinafter, the combination of the voltage distribution and the current distribution will be referred to as the voltage / current distribution.

[0034] The optimal power flow calculation unit 24 uses the controllable power amount of the DER 6 obtained from the VPP aggregator 3 and the distribution automation system 4 as a variable, and solves an optimization problem to maximize the discharge and charge amounts of the first DER 6a and minimize the reactive power control amount of the second DER 6b for the estimated voltage and current distribution so that the power system constraints of the distribution system 100 are observed.

[0035] Specifically, the optimal power flow calculation unit 24 uses the first controllable power amount and the second controllable power amount as variables, and solves a first optimization problem for maximizing the discharge amount of the first DER 6a and minimizing the reactive power amount of the second DER 6b that has the effect of lowering the voltage, under the constraint condition that the power system constraint is observed for the estimated voltage-current distribution. The optimal power flow calculation unit 24 also uses the first controllable power amount and the second controllable power amount as variables, and solves a second optimization problem for maximizing the charge amount of the first DER 6a and minimizing the reactive power amount of the second DER 6b that has the effect of raising the voltage, for the estimated voltage-current distribution. Note that here, when the DER 6 is a DER capable of generating electricity, the calculation is performed assuming that lowering the generating capacity from the generating capacity at the time of calculation, i.e., suppressing the generating capacity, is charging.

[0036] By solving the first optimization problem, the maximized discharge amount of each first DER6a and the minimized first reactive power amount of each second DER6b having the effect of dropping the voltage are obtained. By using the maximized discharge amount of each first DER6a in the distribution line 103, a voltage-current distribution when the discharge amount is maximized is obtained. By solving the second optimization problem, the maximized charge amount of each first DER6a and the minimized second reactive power amount of each second DER6b having the effect of raising the voltage are obtained. By using the maximized charge amount of each first DER6a in the distribution line 103, a voltage-current distribution when the charge amount is maximized is obtained.

[0037] The optimal power flow calculation unit 24 determines an active power control range for each first DER 6a, which is a range of active power with the maximum discharge amount as the lower limit and the maximum charge amount as the upper limit. The optimal power flow calculation unit 24 determines the first reactive power amount and the second reactive power amount as reactive power control amounts for each second DER 6b.

[0038] In one example, in a system state in which the amount of power generation by the DER that can generate power during the control period is large, voltage violations and current violations due to voltage rise are likely to occur in the distribution line 103. In such a situation, when the DER 6 discharges, the voltage further rises, and voltage violations and current violations due to voltage rise are likely to occur. Therefore, in the distribution line 103 of FIG. 1, a discharge amount that maximizes the amount discharged by the first DER 6a is calculated, and a first reactive power amount that minimizes the reactive power amount is calculated for the second DER 6b, so that the voltage and current of the interconnection point connected to the consumer 7 comply with the power system constraints. This makes it possible to obtain a voltage and current distribution when the discharge amount that satisfies the power system constraints is maximized while adjusting the supply and demand of power in the distribution line 103.

[0039] In addition, in a system state where the amount of power generation by the DER that can generate power during the control period is small, voltage violations and current violations due to voltage drop are likely to occur in the distribution line 103. In such a situation, when the DER 6 charges, the voltage drops further, and voltage violations and current violations due to voltage drop are likely to occur. In the distribution line 103 of FIG. 1, a charge amount that maximizes the amount charged by the first DER 6a is calculated for the first DER 6a, and a second reactive power amount that minimizes the reactive power amount is calculated for the second DER 6b, so that the voltage and current at the interconnection point connected to the consumer 7 comply with the power system constraints. This allows a voltage and current distribution to be obtained when the charge amount that satisfies the power system constraints is maximized while adjusting the supply and demand of power in the distribution line 103.

[0040] When the second DER 6b does not exist in the power distribution system 100, the optimal power flow calculation unit 24 uses the first controllable power amount acquired from the VPP aggregator 3 as a variable and solves an optimization problem to maximize the discharge amount and charge amount of the first DER 6a under the constraint condition that the power system constraint is observed for the estimated voltage and current distribution. As a result, the maximized discharge amount and maximized charge amount of each first DER 6a are acquired.

[0041] As described above, when the second DER 6b is not present in the power distribution system 100, the optimal power flow calculation unit 24 calculates the maximum amount of charge and discharge that can be output within the range of the first controllable amount of power that can be controlled by the first DER 6a during the control period while observing the power system constraints on the voltage and current of the power distribution system 100 from the voltage and current distribution of the power distribution system 100 based on the supply and demand forecast, and determines an active power control range determined by the maximum amount of discharge and charge. Also, when the second DER 6b is present in the power distribution system 100, the optimal power flow calculation unit 24 calculates, in addition to the active power control range, from the voltage and current distribution, a reactive power control amount that is the minimum amount of reactive power that can be output within the range of the second controllable amount of power that can be controlled by the second DER 6b during the control period while observing the power system constraints of the power distribution system 100.

[0042] When maximizing the charge amount and discharge amount, a priority or weight may be set for the first DER 6a. In this case, a priority or weight is set for the first DER 6a in advance in the DER management device 2, and the optimal power flow calculation unit 24 solves the optimization problem according to the set priority or weight. This makes it possible to maximize the charge amount and discharge amount of the first DER 6a to be prioritized under the constraint condition that the power system constraint is observed. A priority or weight may be set for the second DER 6b in a similar manner.

[0043] The DER control command value calculation unit 25 generates control command information for each DER 6 from the active power control range of the first DER 6a and the reactive power control amount of the second DER 6b calculated by the optimal power flow calculation unit 24. Specifically, for the first DER 6a, the DER control command value calculation unit 25 generates first control command information in which each first DER 6a corresponds to the active power control range calculated by the optimal power flow calculation unit 24. For the second DER 6b, the DER control command value calculation unit 25 calculates a setting value to be used for voltage control by reactive power in the second DER 6b using the reactive power control amount, the voltage-current distribution when the discharge amount is maximized, and the voltage-current distribution when the charge amount is maximized. The DER control command value calculation unit 25 generates second control command information in which each second DER 6b corresponds to the reactive power control amount and the setting value. The calculation of the setting value will be described later. The first control command information for the first DER 6a is transmitted to the VPP aggregator 3 via the communication unit 21, and the second control command information for the second DER 6b is transmitted to the power distribution automation system 4 via the communication unit 21. The DER control command value calculation unit 25 corresponds to the control command value calculation unit.

[0044] 4 is a diagram illustrating an example of a configuration of a VPP aggregator provided in the DER management system according to embodiment 1. The VPP aggregator 3 includes a communication unit 31, a DER controllable amount collection unit 32, a storage unit 33, a demand forecasting unit 34, a required adjustment capacity estimation unit 35, and a DER control command value determination unit 36.

[0045] The communication unit 31 communicates with the first DER 6a and the DER management device 2 via the communication networks 71, 73. In one example, the communication unit 31 transmits the first controllable power amount of each first DER 6a collected by the DER controllable amount collection unit 32 to the DER management device 2. The communication unit 31 also receives first control command information for each first DER 6a received from the DER management device 2, and transmits output plan information determined by the DER control command value determination unit 36 ​​to the first DER 6a as a first control command value.

[0046] The DER controllable amount collecting unit 32 collects the first controllable amount of power from the first DER 6a for each control target period. The DER controllable amount collecting unit 32 stores the collected first controllable amount of power in the storage unit 33.

[0047] The storage unit 33 stores the controllable power amount information collected by the DER controllable amount collection unit 32. The storage unit 33 also stores supply and demand record information used for forecasting supply and demand of power in the power distribution system 100. The supply and demand record information is, for example, information that associates a past demand power amount record value in the load 5, a renewable energy output record value which is the amount of power output by a DER capable of generating power, an other system interconnection flow record value which is the amount of power flowing through an interconnection line with another system, and a local system generator output record value which is the actual value of the amount of power output by a thermal power generator or the like in the local system, with power generation status information including a day type, weather conditions, and a time period. The day type is information indicating a type by day such as a weekday or holiday, the weather conditions are information such as weather, temperature, and the like, and the time period is information indicating a time of day such as morning, afternoon, evening, or night. Here, the amount of power output by a DER capable of generating power is referred to as a renewable energy output in order to distinguish it from the amount of power output by a thermal power generator or the like.

[0048] The demand forecasting unit 34 forecasts the load demand, renewable energy output, cross-system interconnection current flow, and generator output of thermal power generators and the like in the local system during a control period in the local system to be controlled, and stores them in the storage unit 33. In one example, the demand forecasting unit 34 acquires past supply and demand actual information for the same or similar day type, weather condition, and time period as the control period, and performs statistical processing on the acquired supply and demand actual information to obtain supply and demand forecast information. Specifically, the demand forecasting unit 34 performs statistical processing on the past actual values ​​of demand energy demand during the control period to obtain a load demand forecast value for the control period. The demand forecasting unit 34 performs statistical processing on the past actual values ​​of renewable energy output during the control period to obtain a renewable energy output forecast value for the control period. The demand forecasting unit 34 performs statistical processing on the past actual values ​​of cross-system interconnection current flow during the control period to obtain a cross-system interconnection current forecast value for the control period. The demand forecasting unit 34 performs statistical processing of the past generator output actual values ​​during the control period to obtain a generator output forecast value within the own system during the control period. The renewable energy output forecast value is the amount of power generated by the DER capable of generating power that is connected to the power distribution system 100. The other system interconnection flow is the net amount of power lent between the own system and other systems in which the VPP aggregator 3 performs supply and demand control.

[0049] The required adjustment capacity estimation unit 35 estimates adjustment capacity, which is the amount of power required for supply and demand control and is to be commanded to all the first DERs 6a under its management, based on supply and demand prediction within the own system during the control period using the load demand prediction value, renewable energy output prediction value, other system interconnection flow prediction value, and own system generator output prediction value predicted by the demand prediction unit 34. Specifically, the required adjustment capacity estimation unit 35 expresses the adjustment capacity as shown in the following formula (1) when the load demand prediction value, renewable energy output prediction value, other system interconnection flow prediction value, and own system generator output prediction value are all expressed as absolute values ​​and the other system interconnection flow going out from the own system to the other system is taken as positive. Adjustment capacity = Load demand - Renewable energy output + Power flow from other grids - Power output of generators in the grid (1)

[0050] The DER control command value determination unit 36 ​​allocates the adjustment power for supply and demand control in the power distribution system 100 during the control period to each of the first DERs 6a so that the operation cost is minimized within the active power control range of the first control command information, and generates a first control command value that specifies the active power control amount, which is the allocated adjustment power, and the output timing for each of the first DERs 6a. Specifically, the DER control command value determination unit 36 ​​determines the active power control amount, which is the amount of power allocated to each of the first DERs 6a, to be commanded to the first DERs 6a by solving an optimization problem that minimizes the operation cost represented by the objective function under the constraint condition that the active power control amount of each of the first DERs 6a falls within the active power control range. When the first DERs 6a include a storage battery or an electric vehicle, the active power control amount is the charge amount or discharge amount, and when the first DERs 6a include a photovoltaic power generation facility, the active power control amount is the power generation suppression amount. In one example, the DER control command value determiner 36 solves an optimization problem to minimize the operating cost by using information that associates the operating cost with the charge amount and discharge amount in each first DER 6a. The DER control command value determiner 36 also determines output plan information that specifies how much active power is to be output from which first DER 6a at what timing during the control target period. The output plan information is information that specifies the control timing for outputting the determined active power amount for each first DER 6a, and in one example, is generated for each first DER 6a. The DER control command value determiner 36 sets the output plan information generated for each first DER 6a as the first control command value. The DER control command value determiner 36 corresponds to the control command value determiner.

[0051] 5 is a diagram illustrating an example of a configuration of a power distribution automation system provided in the DER management system according to Embodiment 1. In one example, the power distribution automation system 4 is a device that manages the voltage and current in a power company's system, and manages the voltage and current of a second DER 6b connected to the power distribution system 100. The power distribution automation system 4 includes a communication unit 41, a DER controllable amount collection unit 42, a storage unit 43, and a DER control command value setting unit 44.

[0052] The communication unit 41 communicates with the second DER 6b and the DER management device 2 via the communication networks 72 and 73. In one example, the communication unit 41 receives the second controllable power amount from each second DER 6b. The communication unit 41 transmits the second controllable power amount of each second DER 6b collected by the DER controllable amount collection unit 42 to the DER management device 2. The communication unit 41 also receives second control command information for each second DER 6b from the DER management device 2. In accordance with an instruction from the DER control command value setting unit 44, the communication unit 41 transmits a second control command value including a reactive power control amount and a setting value included in the second control command information to each second DER 6b.

[0053] The DER controllable amount collecting unit 42 collects the second controllable amount of power from the second DER 6b for each control period. The DER controllable amount collecting unit 42 stores the collected second controllable amount of power in the storage unit 43.

[0054] The storage unit 43 stores the second controllable power amount collected by the DER controllable amount collection unit 42. The storage unit 43 also stores system information of the power distribution system 100 and load power generation record information. The system information is information indicating how the voltage and current in the system are distributed. The load power generation record information is information indicating the load demand amount and the record value of the power generation amount of the consumer 7 having the second DER 6b. In one example, the load power generation record information is information that associates power record information including the record value of the demand amount of the load 5 in the past and the record value of the amount of power output by the DER capable of generating power with power generation status information including the day type, weather conditions, and time period. In one example, the load power generation record information is acquired from the DER management device 2.

[0055] The DER control command value setting unit 44 generates a second control command value including a reactive power control amount and a setting value to be set for each second DER 6b from the second control command information received from the DER management device 2. The DER control command value setting unit 44 sets the second control command value for each second DER 6b via the communication unit 41.

[0056] Next, details of the processing in the DER management device 2 will be described. Fig. 6 and Fig. 7 are flowcharts showing an example of the procedure of a DER management method according to the first embodiment. The DER management method includes a calculation method of control command information executed by the DER management device 2. First, the communication unit 21 receives a first controllable amount of power for the first DER 6a from the VPP aggregator 3 (step S11), and receives a second controllable amount of power for the second DER 6b from the power distribution automation system 4 (step S12).

[0057] Next, the prediction unit 23 predicts a load demand prediction value of the load 5 connected to the power distribution system 100 and a power generation prediction value of the DER capable of generating power during the control period (step S13). The prediction unit 23 predicts a load demand prediction value and a power generation prediction value during the control period using the actual load demand value and the actual power generation profile value stored in the storage unit 22. Thereafter, the prediction unit 23 estimates a voltage / current distribution in the distribution line 103 of the power distribution system 100 using the load demand prediction value and the power generation prediction value (step S14).

[0058] Next, the optimal power flow calculation unit 24 sets the distribution line 103 where no violation of the power system constraint occurs as a control target, and calculates an active power control range for the first DER 6a and calculates a reactive power control amount for the second DER 6b so that the power system constraint is observed for the estimated voltage / current distribution. Specifically, the optimal power flow calculation unit 24 uses the first controllable power amount and the second controllable power amount as variables, and solves a first optimization problem that maximizes the discharge amount of the first DER 6a and minimizes the reactive power amount of the second DER 6b that has the effect of dropping the voltage, under the constraint condition that the power system constraint is observed for the estimated voltage / current distribution (step S15). In addition, the optimal power flow calculation unit 24 uses the first controllable power amount and the second controllable power amount as variables and solves a second optimization problem that maximizes the charge amount of the first DER 6a and minimizes the reactive power amount of the second DER 6b, which has the effect of raising the voltage, for the estimated voltage and current distribution, under the constraint that power system constraints are observed (step S16).

[0059] 8 is a diagram showing a schematic diagram of an example of the configuration of a power distribution system. Here, a case is shown in which two voltage regulating devices, SVRs 91a and 91b, are connected to a power distribution line 103, and two DERs 6c and 6d are provided on the power distribution line 103 between the SVRs 91a and 91b.

[0060] FIG. 9 is a diagram showing an example of voltage distribution in the power distribution system shown in FIG. 8. The horizontal axis of FIG. 9 indicates the position on the power distribution line 103 shown in FIG. 8, and the vertical axis indicates voltage. Here, the position of DER 6c is set to Pc, and the position of DER 6d is set to Pd. In FIG. 9, a graph G11 shows, in one example, the voltage distribution of the power distribution system 100 estimated by the prediction unit 23 in step S12, and is assumed to be in a state before control. The interconnection point voltage at the point where each of DER 6c, 6d is interconnected with the system, i.e., the power distribution line 103, needs to fall within a range determined by the power system constraint. The lower limit of this determined range is V1, and the upper limit is V2. The charge / discharge amounts of DER 6c and DER 6d are controlled so that the graph G11 exists between the lower limit V1 and the upper limit V2. Regarding the current distribution in the power distribution system, the control amount of each DER including the first DER 6a and the second DER 6b is determined so that the current flowing through each line is smaller than the allowable maximum value.

[0061] In steps S15 and S16, the discharge and charge amounts that can be output within a range in which the power system constraints are observed, for the voltage and current distributions before control, are calculated by solving a first optimization problem and a second optimization problem, respectively. Fig. 10 is a diagram showing an example of the charge and discharge amounts at each DER in the power distribution system shown in Fig. 8. In Fig. 10, the horizontal axis indicates the position on the power distribution line 103 shown in Fig. 8, and the vertical axis indicates active power. When the active power is positive, it indicates charging, and when it is negative, it indicates discharging.

[0062] The maximum value of the discharge amount of the first DER6a and the minimum value of the first reactive power amount of the second DER6b, which has the effect of lowering the voltage, are obtained by solving a first optimization problem. In the example of FIG. 10, the maximum value of the discharge amount of the DER6c is PC1, and the maximum value of the discharge amount of the DER6d is PC2. In addition, the maximum value of the charge amount of the first DER6a and the minimum value of the second reactive power amount of the second DER6b, which has the effect of raising the voltage, are obtained by solving a second optimization problem. In the example of FIG. 10, the maximum value of the charge amount of the DER6c is PD1, and the maximum value of the charge amount of the DER6d is PD2.

[0063] 7, the optimal power flow calculation unit 24 determines an active power control range for each first DER 6a, with the maximum discharge amount as the lower limit and the maximum charge amount as the upper limit (step S17). The optimal power flow calculation unit 24 determines a reactive power control amount including a first reactive power amount and a second reactive power amount for each second DER 6b (step S18).

[0064] The optimal power flow calculation unit 24 calculates the voltage distribution when the discharge amount in the distribution line 103 is maximized from the calculated maximum value of the discharge amount of each first DER 6a (step S19), and calculates the voltage distribution when the charge amount in the distribution line 103 is maximized from the calculated maximum value of the charge amount of each first DER 6a (step S20).

[0065] Thereafter, the DER control command value calculation unit 25 calculates a set value for the second DER 6b using the voltage distribution when the discharge amount is maximized and the voltage distribution when the charge amount is maximized, and the reactive power control amount (step S21).

[0066] Here, a specific example of calculation of the set value will be described. FIG. 11 is a diagram showing an example of voltage control in the second DER. In this diagram, the horizontal axis indicates the voltage of the second DER 6b in one example, and the vertical axis indicates the reactive power output Q. The dead band is a voltage range between the lower limit voltage value VL and the upper limit voltage value VU, and when the voltage of the second DER 6b exists in this range, the reactive power control is not performed. When the voltage of the second DER 6b is smaller than the lower limit voltage value VL or larger than the upper limit voltage value VU, the reactive power corresponding to the voltage of the second DER 6b is output to the second DER 6b, thereby performing the reactive power control of the second DER 6b. For this reason, the lower limit voltage value VL and the upper limit voltage value VU are also referred to as the control start voltage. Moreover, the average value of the lower limit voltage value VL and the upper limit voltage value VU, the voltage value VT through which the vertical axis passes in FIG. 11, is referred to as the control target value. The dead zone indicates a target range within which the voltage of the second DER 6b falls, centered around the control target value.

[0067] When the voltage of the second DER 6b exceeds VQ1 or falls below VQ2, the output amount of reactive power becomes a constant value. That is, there are upper and lower limits for the reactive power that the second DER 6b can output. The upper and lower limits may use the first reactive power amount and the second reactive power amount calculated by the optimal power flow calculation unit 24, or the upper and lower limits of the second controllable power amount of the second DER 6b. Note that the method of determining the slope and gain may use various known methods and is not limited to these.

[0068] In FIG. 8, DER 6c is the second DER 6b, that is, a DER having a voltage adjustment function. When control by the DER management device 2 is not performed, the distribution line 103 has a voltage distribution as shown in graph G11 of FIG. 9. Also, as described above, when the charge amount of each DER 6c, 6d is controlled to be the maximum value, the voltage distribution is as shown in graph G12, and when the discharge amount of each DER 6c, 6d is controlled to be the maximum value, the voltage distribution is as shown in graph G13. At this time, the voltage value of graph G12 at the position Pc of DER 6c, that is, the interconnection point voltage at the interconnection point between DER 6c and the distribution system 100 is set as the lower limit voltage value VL of the dead zone, and the voltage value of graph G13, that is, the interconnection point voltage at the interconnection point between DER 6c and the distribution system 100 is set as the upper limit voltage value VU of the dead zone. In other words, the area between the lower limit voltage value VL and the upper limit voltage value VU is the dead zone. Moreover, the average value of the lower limit voltage value VL and the upper limit voltage value VU is set as the target voltage VT. The DER control command value calculation unit 25 calculates the lower limit voltage value VL, the upper limit voltage value VU, and the target voltage VT as described above, and sets these as the set values.

[0069] 7, the DER control command value calculation unit 25 generates first control command information that associates the first DER 6a with the active power control range, and generates second control command information that associates the second DER 6b with the reactive power control amount and setting value (step S22). Then, the communication unit 21 transmits the first control command information to the VPP aggregator 3 (step S23), and transmits the second control command information to the power distribution automation system 4 (step S24). This ends the process.

[0070] In the above description, the process proceeds to step S15 after step S14. However, there may be cases where the voltage-current distribution of the distribution line 103 of the power distribution system 100 estimated in step S14 violates the power system constraint. In this case, the process from step S15 onward is performed for the distribution line 103 whose voltage-current distribution satisfies the power system constraint, and the process ends for the distribution line 103 whose voltage-current distribution does not satisfy the power system constraint, because the control amount for eliminating the violation is not secured for the distribution line 103 in the first embodiment. In other words, between steps S14 and S15, a process may be included in which the optimal power flow calculation unit 24 determines whether the distribution line 103 has a voltage-current distribution that satisfies the power system constraint.

[0071] Next, the processing in the VPP aggregator 3 and the power distribution automation system 4 will be described. Fig. 12 is a flowchart showing an example of a procedure for a command value calculation process for the VPP aggregator in the DER management system according to embodiment 1. First, the communication unit 31 receives first control command information that associates the first DER 6a with an active power control range from the DER management device 2 (step S31).

[0072] Next, the demand forecasting unit 34 forecasts the load demand forecast value, the renewable energy output forecast value, the other system interconnection power flow forecast value, and the own system generator output forecast value for the control target period (step S32). After that, the necessary adjustment capacity estimating unit 35 estimates adjustment capacity, which is the amount of power that needs to be commanded to all the first DERs 6a under its management for supply and demand control in the power distribution system 100, using the load demand forecast value, the renewable energy output forecast value, the other system interconnection power flow forecast value, and the own system generator output forecast value (step S33).

[0073] Next, the active power control amount, which is the amount of power obtained by allocating the adjustment capability to each first DER 6a, is determined within the active power control range of the first DER 6a with the aim of minimizing the overall operation cost within the system. Specifically, the DER control command value determiner 36 solves an optimization problem that minimizes the operation cost represented by the objective function under the constraint that the active power control amount of each first DER 6a falls within the active power control range. In this way, the DER control command value determiner 36 determines the active power control amount to be commanded to the first DER 6a, which is the amount of power obtained by allocating the adjustment capability to each first DER 6a (step S34).

[0074] In addition, the DER control command value determination unit 36 ​​determines output plan information that specifies how much active power should be output from which first DER 6a and at what timing during the control period, and generates a first control command value that corresponds to the output plan information for each first DER 6a (step S35).

[0075] Thereafter, the communication unit 31 transmits the first control command value to each first DER 6a (step S36). The power control device 62 of each first DER 6a controls the distributed energy device 61 based on the first control command value, i.e., the output plan information, from the VPP aggregator 3. This ends the process.

[0076] 13 is a flowchart showing an example of a procedure of a setpoint setting process of the power distribution automation system in the DER management system according to embodiment 1. First, the communication unit 41 receives second control command information from the DER management device 2 (step S51). The second control command information is information that associates the second DER 6b with a reactive power control amount and a setpoint.

[0077] Next, the DER control command value setting unit 44 generates a second control command value including a reactive power control amount and a setting value to be set for each second DER 6b from the received second control command information (step S52). Then, the communication unit 41 transmits the second control command value to each second DER 6b (step S53). The power control device 62 of each second DER 6b controls the distributed energy device 61 based on the reactive power control amount and the setting value included in the second control command value received from the distribution automation system 4. This ends the process.

[0078] Next, a hardware configuration example of the DER management device 2, the VPP aggregator 3, and the distribution automation system 4 according to the first embodiment will be described. Fig. 14 is a diagram showing an example of the configuration of a computer system that realizes the DER management device, the VPP aggregator, and the distribution automation system used in the DER management system according to the first embodiment. The DER management device 2, the VPP aggregator 3, and the distribution automation system 4 are each realized by, for example, a computer system 200 illustrated in Fig. 14.

[0079] As shown in FIG. 14, the computer system 200 includes a control unit 201, an input unit 202, a storage unit 203, a display unit 204, a communication unit 205, and an output unit 206, which are connected via a system bus 207. In FIG. 14, the control unit 201 is, for example, a CPU (Central Processing Unit) or the like, and executes a program in which the processing in the DER management device 2, the VPP aggregator 3, and the power distribution automation system 4 of the first embodiment is described. The input unit 202 is, for example, composed of a keyboard, a mouse, and the like, and is used by a user of the computer system 200 to input various information. The storage unit 203 includes various memories such as a RAM (Random Access Memory) and a ROM (Read Only Memory) and a storage device such as a hard disk, and stores the program to be executed by the control unit 201, necessary data obtained in the process of processing, and the like. The storage unit 203 is also used as a temporary storage area for the program. The display unit 204 is composed of a liquid crystal display (LCD) or the like, and displays various screens to the user of the computer system 200. The communication unit 205 is a receiver and a transmitter that executes communication processing. The output unit 206 is a printer or the like.

[0080] Here, an example of the operation of the computer system 200 until the programs for realizing the DER management device 2, the VPP aggregator 3, and the power distribution automation system 4 of the first embodiment are in an executable state will be described. In the computer system 200 having the above-mentioned configuration, for example, a program is installed in the storage unit 203 from a CD-ROM or DVD-ROM set in a CD (Compact Disc)-ROM drive or a DVD (Digital Versatile Disc)-ROM drive (not shown). Then, when the program is executed, the program read from the storage unit 203 is stored in the storage unit 203. In this state, the control unit 201 executes the processes as the DER management device 2, the VPP aggregator 3, and the power distribution automation system 4 of the first embodiment according to the program stored in the storage unit 203.

[0081] In the above explanation, the program describing the processing is provided on a CD-ROM or DVD-ROM as a recording medium. However, this is not limited to this, and depending on the configuration of computer system 200 and the capacity of the program to be provided, for example, a program provided via a transmission medium such as the Internet via communication unit 205 may be used.

[0082] The communication unit 21 shown in FIG. 3 is realized by, for example, the communication unit 205 shown in FIG. 14. The communication unit 31 shown in FIG. 4 is realized by, for example, the communication unit 205 shown in FIG. 14. The communication unit 41 shown in FIG. 5 is realized by, for example, the communication unit 205 shown in FIG. 14. The prediction unit 23, the optimal power flow calculation unit 24, and the DER control command value calculation unit 25 shown in FIG. 3 are realized by the control unit 201 executing the corresponding programs. The DER controllable amount collection unit 32, the demand forecasting unit 34, the required adjustment power estimation unit 35, and the DER control command value determination unit 36 ​​shown in FIG. 4 are realized by the control unit 201 executing the corresponding programs. The DER controllable amount collection unit 42 and the DER control command value setting unit 44 shown in FIG. 5 are realized by the control unit 201 executing the corresponding programs. In addition, when the control unit 201 executes the programs, the storage unit 203 is also used.

[0083] The storage unit 22 shown in Fig. 3 is realized by the storage unit 203 shown in Fig. 14. The storage unit 33 shown in Fig. 4 is realized by the storage unit 203 shown in Fig. 14. The storage unit 43 shown in Fig. 5 is realized by the storage unit 203 shown in Fig. 14.

[0084] Furthermore, each of the DER management device 2, the VPP aggregator 3, and the power distribution automation system 4 in the first embodiment may be realized by one computer system 200, or may be realized by a plurality of computer systems 200. For example, the DER management device 2 may be realized by a cloud system. Furthermore, the DER management device 2 may be realized by one computer system 200.

[0085] The DER management program of the first embodiment, for example, causes the computer system 200 to execute the steps of: calculating, from the voltage and current distribution of the power distribution system 100 based on supply and demand forecasts, an active power control range that is determined by the maximum amount of charging and discharging that can be output within the range of the first controllable amount of power that can be controlled by the first DER 6a during the control period while observing the constraints on the voltage and current of the power distribution system 100; generating first control command information that associates each of the multiple first DERs 6a with the active power control range; and transmitting the first control command information to the VPP aggregator 3 that determines the amount of active power to be commanded to the multiple first DERs 6a for supply and demand adjustment.

[0086] In the first embodiment, the DER management device 2 uses the first controllable power amount in the first DER 6a as a variable, and outputs an active power control range having a lower limit and an upper limit of the maximum discharge amount obtained by solving a first optimization problem whose objective function maximizes the discharge amount of the first DER 6a and a second optimization problem whose objective function maximizes the charge amount of the first DER 6a so that the power system constraints of the power distribution system 100 are observed for the voltage and current distribution obtained by supply and demand forecast of the power distribution system 100, as first control command information to the VPP aggregator 3. This has the effect of being able to provide the VPP aggregator 3 with the range of the active power control amount of each first DER 6a, i.e., the charge and discharge range allowed for each first DER 6a, while satisfying the constraints on the voltage and current of the power distribution system 100, for supply and demand adjustment of the power distribution system 100. This allows the VPP aggregator 3 to determine the allocation of active power control amounts to be commanded to each first DER 6a for supply and demand control in the power distribution system 100, with the aim of minimizing operation costs within the allowable charge and discharge range of each first DER 6a. By controlling the first DER 6a with the active power control amount determined in this manner, the VPP aggregator 3 can adjust power supply and demand and suppress the occurrence of voltage and current violations in the power distribution system 100.

[0087] Furthermore, when a second DER 6b that is a DER having a voltage adjustment function is further provided in the power distribution system 100, the DER management device 2 solves a first optimization problem in which the objective function maximizes the discharge amount of the first DER 6a and minimizes the reactive power amount of the second DER 6b that has the effect of dropping the voltage, and a second optimization problem in which the objective function maximizes the charge amount of the first DER 6a and minimizes the reactive power amount of the second DER 6b that has the effect of raising the voltage, so that the power system constraints of the power distribution system 100 are observed for the voltage and current distribution obtained by the supply and demand forecast of the power distribution system 100. Then, the DER management device 2 transmits an active power control range with the maximum discharge amount as the lower limit and the maximum charge amount as the upper limit to the VPP aggregator 3 as first control command information. Furthermore, the DER management device 2 calculates a first reactive power amount which is the minimum value of the reactive power amount of each second DER 6b having the effect of dropping a voltage, a second reactive power amount which is the minimum value of the reactive power amount of each second DER 6b having the effect of raising a voltage, and a setting value for controlling the power output by the second DER 6b with reactive power, and outputs these as second control command information to the distribution automation system 4. This makes it possible to adjust supply and demand in the power distribution system 100 while satisfying constraints on the voltage and current of the power distribution system 100, even when the second DER 6b is provided in the system.

[0088] Embodiment 2 In the first embodiment, the prediction unit 23 of the DER management device 2 predicts one predicted power generation amount value in a control period of the DER 6 connected to the power distribution system 100. In the second embodiment, a case will be described in which the prediction unit 23 of the DER management device 2 predicts two predicted power generation amount values ​​in a control period of the DER 6 connected to the power distribution system 100.

[0089] The configurations of the DER management system 1, DER 6, DER management device 2, VPP aggregator 3, and power distribution automation system 4 according to the second embodiment are similar to those described in the first embodiment, and therefore will not be described. However, the function of the DER management device 2 differs from that of the first embodiment. The following describes the parts that differ from the first embodiment.

[0090] In the second embodiment, the prediction unit 23 of the DER management device 2 predicts the demand of the load 5 connected to the distribution system 100 during the control period, and predicts the maximum and minimum values ​​of the power generation amount of a DER capable of generating power connected to the distribution system 100 during the control period, based on the load power generation performance information. Hereinafter, the maximum and minimum values ​​of the power generation amount during the control period are referred to as the maximum predicted power generation amount value and the minimum predicted power generation amount value, respectively. In the first embodiment, one value was predicted as the predicted power generation amount value for a DER capable of generating power, but in the second embodiment, two values ​​are predicted.

[0091] In the second embodiment, the prediction unit 23 also predicts the load demand forecast value, the maximum power generation forecast value, and the minimum power generation forecast value using the actual value of the load demand and the actual value of the power generation profile. Since the prediction of the load demand forecast value has been described in the first embodiment, the description will be omitted here, and a specific example of the prediction of the maximum power generation forecast value and the minimum power generation forecast value will be described. The prediction unit 23 acquires the actual values ​​of the power generation profile for the period corresponding to the control target period from the load power generation actual information, and sets the power generation profile with the largest power generation amount among them as the maximum power generation forecast value. Similarly, the prediction unit 23 sets the power generation profile with the smallest power generation amount among the acquired actual values ​​of the power generation profiles as the minimum power generation forecast value. Alternatively, the prediction unit 23 may set the maximum power generation forecast value to the power generation amount with the largest output among the power generation amounts assumed based on the weather conditions such as solar radiation and wind volume that are the same as or similar to the predicted control target period and the actual values ​​of the power generation profiles of the DERs capable of generating power in the past, and set the minimum power generation forecast value to the power generation amount with the smallest output.

[0092] In addition, the prediction unit 23 uses the load demand forecast value for the control period and the maximum forecast value and minimum forecast value of the power generation amount of the power generation-capable DER to estimate the voltage and current distribution of the power distribution system 100 when the power generation-capable DER is at maximum output and when it is at minimum output.

[0093] The optimal power flow calculation unit 24 of the DER management device 2 calculates the maximum discharge amount that can be output within the range of the first controllable power amount of the first DER 6a during the control period from the voltage / current distribution of the distribution system 100 based on a supply and demand forecast where the power system constraints of the distribution system 100 are observed and the power generation capable DER during the control period has the maximum output, and the maximum charge amount that can be output within the range of the first controllable power amount during the control period from the voltage / current distribution of the distribution system 100 based on a supply and demand forecast where the power generation capable DER during the control period has the minimum output, and determines the active power control range determined by the maximum discharge amount and charge amount.

[0094] Specifically, the third optimization problem is solved using the first controllable power amount and the second controllable power amount as variables to maximize the discharge amount of the first DER 6a and minimize the reactive power amount of the second DER 6b that has the effect of dropping the voltage under the constraint condition that the power system constraint is observed for the voltage-current distribution when the power generating DER has the maximum output. The optimal power flow calculation unit 24 also solves a fourth optimization problem using the first controllable power amount and the second controllable power amount as variables to maximize the charge amount of the first DER 6a and minimize the reactive power amount of the second DER 6b that has the effect of raising the voltage under the constraint condition that the power system constraint is observed for the voltage-current distribution when the power generating DER has the minimum output.

[0095] By solving the third optimization problem, the maximized discharge amount of each first DER 6a and the minimized first reactive power amount of each second DER 6b having the effect of dropping the voltage are obtained. By using the maximized discharge amount of each first DER 6a in the distribution line 103, a voltage-current distribution when the discharge amount is maximized is obtained. By solving the fourth optimization problem, the maximized charge amount of each first DER 6a and the minimized second reactive power amount of each second DER 6b having the effect of raising the voltage are obtained. By using the maximized charge amount of each first DER 6a in the distribution line 103, a voltage-current distribution when the charge amount is maximized is obtained.

[0096] Next, a detailed description will be given of the processing in the DER management device 2. Fig. 15 is a flowchart showing an example of the procedure of the DER management method according to the second embodiment. First, the communication unit 21 receives a first controllable amount of power for the first DER 6a from the VPP aggregator 3 (step S71), and receives a second controllable amount of power for the second DER 6b from the power distribution automation system 4 (step S72).

[0097] Next, the prediction unit 23 predicts a load demand prediction value of the load 5 connected to the distribution system 100 during the control period using the actual value of the load demand (step S73). The prediction unit 23 also predicts a maximum predicted value of power generation and a minimum predicted value of power generation of the DER capable of power generation connected to the distribution system 100 during the control period using the actual value of the power generation profile (step S74). Here, the maximum predicted value of power generation of the DER capable of power generation refers to the maximum of the power generation of the DER capable of power generation predicted from the actual value of the power generation profile during the control period. The minimum predicted value of power generation of the DER capable of power generation refers to the minimum of the power generation of the DER capable of power generation predicted from the actual value of the power generation profile during the control period.

[0098] Thereafter, the prediction unit 23 estimates a voltage-current distribution at maximum power generation, which is a voltage-current distribution in the distribution line 103 of the power distribution system 100, using the load demand predicted value and the maximum power generation predicted value (step S75). The voltage-current distribution at maximum power generation corresponds to the first voltage-current distribution. Furthermore, the prediction unit 23 estimates a voltage-current distribution at minimum power generation, which is a voltage-current distribution in the distribution line 103 of the power distribution system 100, using the load demand predicted value and the minimum power generation predicted value (step S76). The voltage-current distribution at minimum power generation corresponds to the second voltage-current distribution.

[0099] Fig. 16 is a diagram showing an example of voltage distribution in the power distribution system shown in Fig. 8. The horizontal axis of Fig. 16 indicates the position on the power distribution line 103 of the power distribution system 100 shown in Fig. 8, and the vertical axis indicates voltage. In Fig. 16, graph G21 shows the voltage distribution at maximum power generation estimated in step S75, which is assumed to be in the state before control. Graph G22 shows the voltage distribution at minimum power generation estimated in step S76, which is assumed to be in the state before control.

[0100] 15, the optimal power flow calculation unit 24 solves a third optimization problem of maximizing the discharge amount of the first DER 6a and minimizing the reactive power amount of the second DER 6b that has the effect of lowering the voltage under the constraint condition that the power system constraint is observed for the estimated maximum power generation voltage-current distribution with the distribution line 103 that does not violate the power system constraint as the control object and the first controllable power amount and the second controllable power amount as variables (step S77). The optimal power flow calculation unit 24 also solves a fourth optimization problem of maximizing the charge amount of the first DER 6a and minimizing the reactive power amount of the second DER 6b that has the effect of raising the voltage under the constraint condition that the power system constraint is observed for the estimated minimum power generation voltage-current distribution with the distribution line 103 that does not violate the power system constraint as the control object and the first controllable power amount and the second controllable power amount as variables (step S78).

[0101] Thereafter, the same procedures as those shown in steps S17 to S24 in FIG. 7 of the first embodiment are executed. That is, the optimal power flow calculation unit 24 determines an active power control range for the first DER 6a, and calculates a reactive power control amount and a set value including the first reactive power amount and the second reactive power amount for the second DER 6b. The DER control command value calculation unit 25 generates first control command information that associates the first DER 6a with the active power control range, and generates second control command information that associates the second DER 6b with the reactive power control amount and the set value. Then, the communication unit 21 transmits the first control command information and the second control command information to the VPP aggregator 3 and the power distribution automation system 4, respectively.

[0102] The voltage distribution at maximum power generation calculated in step S75 is shown in graph G23 of FIG. 16, and the voltage distribution at minimum power generation calculated in step S76 is shown in graph G24 of FIG. 16. If DER 6c in FIG. 8 is the second DER 6b, that is, a DER having a voltage adjustment function, the set value of DER 6c is calculated in the same manner as in the first embodiment. That is, the voltage value of graph G24 at position Pc of DER 6c is set as the lower limit voltage value VL of the dead zone, and the voltage value of graph G23 is set as the upper limit voltage value VU of the dead zone. The average value of the lower limit voltage value VL and the upper limit voltage value VU is set as the target voltage VT. Then, DER control command value calculation unit 25 sets the lower limit voltage value VL, the upper limit voltage value VU, and the target voltage VT as set values.

[0103] In the second embodiment, the same effects as those in the first embodiment can be obtained.

[0104] Embodiment 3 In the first and second embodiments, the DER management device 2 acquires actual values, which are past data of the load demand and power generation profile in the power distribution system 100, from the storage unit 22 to estimate the voltage-current distribution of the power distribution system 100. However, the estimation of the voltage-current distribution of the power distribution system 100 is not limited to that shown in the first and second embodiments. In the third embodiment, a case will be described in which the voltage-current distribution of the power distribution system 100 is estimated by another method.

[0105] FIG. 17 is a diagram showing a schematic diagram of an example of the configuration of a DER management system according to the third embodiment. The same components as those in the first embodiment are given the same reference numerals, and the description thereof will be omitted. The DER management system 1a according to the third embodiment further includes a measuring device 8 on each distribution line 103. The measuring device 8 is a device for measuring a state quantity of the distribution system 100. The state quantity of the distribution system 100 may be any quantity capable of calculating the voltage and current distribution of the distribution line 103. Examples of the state quantity of the distribution system 100 are line voltage, phase voltage, line current, power factor, passing active power, and passing reactive power. The measuring device 8 transmits the measured state quantity of the distribution quantity as distribution system state quantity information to the DER management device 2a via the communication network 81. In one example, the measuring device 8 is provided on the distribution line 103 on the distribution transformer 101 side.

[0106] In the third embodiment, the configurations of the DER 6, the VPP aggregator 3, and the power distribution automation system 4 are the same as those described in the first embodiment, and the configuration of the DER management device 2a is different from that of the first embodiment. FIG. 18 is a diagram showing an example of the configuration of a DER management device according to the third embodiment. The same components as those in the first embodiment are given the same reference numerals and their description is omitted, and only the parts different from the first embodiment are described. The DER management device 2a includes a measurement information collection unit 26 instead of the prediction unit 23 in the configuration of the first embodiment. The communication unit 21 also has a function of communicating with the measurement device 8. The communication unit 21 receives power distribution system state quantity information from the measurement device 8.

[0107] The measurement information collecting unit 26 collects distribution system state quantity information from the measuring device 8 via the communication unit 21, and stores the collected distribution system state quantity information in the storage unit 22 together with the time of collection. The measurement information collecting unit 26 also estimates a voltage / current distribution of the distribution line 103 of the distribution system 100 during the control target period, using the distribution system state quantity information stored in the storage unit 22. That is, in the third embodiment, the distribution system state quantity information measured by the measuring device 8 is used to estimate the voltage / current distribution of the distribution system 100. In one example, the measurement information collecting unit 26 estimates the voltage / current distribution of the distribution system 100 during the control target period, using past data obtained by measuring state quantities related to the voltage / current distribution of the distribution system 100.

[0108] Next, the details of the processing in the DER management device 2a will be described. Fig. 19 is a flowchart showing an example of the procedure of the DER management method according to the third embodiment. In Fig. 19, the same processing as in Fig. 6 of the first embodiment is given the same step numbers, and the description thereof will be omitted. Below, the parts different from Fig. 6 will be described.

[0109] In addition to receiving the first controllable power amount and the second controllable power amount in steps S11 and S12, the measurement information collector 26 collects power distribution system state quantity information from the measurement device 8 via the communication unit 21 (step S91). The collected power distribution system state quantity information is stored in the memory unit 22 together with the time of collection.

[0110] Next, the measurement information collector 26 estimates the voltage and current distribution during the control period using the power distribution system state quantity information during the period corresponding to the control period (step S92). After that, the process proceeds to step S15 and subsequent steps in FIG.

[0111] In the third embodiment, the DER management device 2a collects, from the measurement device 8, distribution system state quantity information capable of calculating the voltage-current distribution of the distribution line 103, and estimates the voltage-current distribution of the distribution line 103 during a control target period using the distribution system state quantity information. In the first embodiment, a load demand forecast value and a power generation forecast value are predicted from an actual value of a load demand and an actual value of a power generation profile, and the voltage-current distribution in the distribution line 103 is estimated from the load demand forecast value and the power generation forecast value. However, in the third embodiment, the voltage-current distribution of the distribution line 103 is estimated from the distribution system state quantity information, and therefore, an effect is achieved in that the number of processing steps required to estimate the voltage-current distribution can be reduced compared to the first embodiment.

[0112] Embodiment 4 In the third embodiment, an example in which the voltage and current distribution of the power distribution system 100 is calculated using the power distribution system state quantity information measured by the measuring device 8 is applied to the first embodiment. In the fourth embodiment, an example in which the voltage and current distribution of the power distribution system 100 is calculated using the past power distribution system state quantity information measured by the measuring device 8 is applied to the second embodiment.

[0113] The configurations of the DER management system 1a, DER 6, DER management device 2a, VPP aggregator 3, and power distribution automation system 4 according to the fourth embodiment are similar to those described in the first to third embodiments, and therefore will not be described below. The following describes the parts that differ from the first to third embodiments.

[0114] In the fourth embodiment, the measurement information collecting unit 26 of the DER management device 2a uses the past distribution system state quantity information stored in the storage unit 22 to calculate a voltage-current distribution at maximum power generation when the power generation-capable DER in the control target period is estimated to have a maximum output, and a voltage-current distribution at minimum power generation when the power generation-capable DER is estimated to have a minimum output. Specifically, the measurement information collecting unit 26 extracts data of maximum output and data of minimum output from the past distribution system state quantity information for the period corresponding to the control target period for the power generation-capable DER. In addition, for the chargeable / dischargeable DER, output is predicted using the past distribution system state quantity information for the period corresponding to the control target period. When extracting data of maximum output and minimum output for the power generation-capable DER and predicting the output of the chargeable / dischargeable DER, the past distribution system state quantity information may be narrowed down using weather conditions that are the same as or similar to those of the control target period. In this case, the distribution system state quantity information includes a day type, weather conditions, and a time period. Then, using the extracted data showing the maximum and minimum output of the power generating DER and the output of the chargeable and dischargeable DER, the voltage-current distribution at maximum power generation and the voltage-current distribution at minimum power generation of the distribution line 103 are calculated.

[0115] Next, the details of the processing in the DER management device 2a will be explained. Fig. 20 is a flowchart showing an example of the procedure of the DER management method according to the fourth embodiment. In Fig. 20, the same processing as in Fig. 15 of the second embodiment is given the same step number, and the explanation thereof will be omitted. Below, the parts different from Fig. 15 will be explained.

[0116] In addition to receiving the first controllable power amount and the second controllable power amount in steps S71 and S72, the measurement information collector 26 collects power distribution system state quantity information from the measurement device 8 via the communication unit 21 (step S111). The collected power distribution system state quantity information is stored in the storage unit 22 together with the time of collection.

[0117] Next, the measurement information collector 26 predicts the maximum and minimum outputs of the DERs capable of generating electricity and the output of the DERs capable of charging and discharging during the period corresponding to the control target period using past distribution system state quantity information (step S112). After that, the measurement information collector 26 estimates the voltage-current distribution at maximum power generation in the distribution system 100 using the predicted maximum outputs of the DERs capable of generating electricity and the output of the DERs capable of charging and discharging (step S113). In addition, the measurement information collector 26 estimates the voltage-current distribution at minimum power generation in the distribution system 100 using the predicted minimum outputs of the DERs capable of generating electricity and the output of the DERs capable of charging and discharging (step S114). After that, the process proceeds to step S77 and subsequent steps in FIG. 15.

[0118] In the fourth embodiment, the same effects as those in the third embodiment can be obtained.

[0119] Embodiment 5. In the fifth embodiment, a modified example of the first to fourth embodiments will be described. In the following, the same components as those described above will be denoted by the same reference numerals, and the description thereof will be omitted, and only the differences will be described.

[0120] In the first to fourth embodiments, the DER management device 2, 2a transmits the reactive power control amount and the setting value to the power distribution automation system 4, and the power distribution automation system 4 sets the reactive power control amount and the setting value in the second DER 6b. The DER management device 2 may execute a process of setting the reactive power control amount and the setting value in the second DER 6b.

[0121] Fig. 21 is a diagram illustrating an example of the configuration of a DER management device according to the fifth embodiment. The DER management device 2b further includes a DER control command value setting unit 27 in Fig. 3 of the first embodiment. The DER control command value setting unit 27 generates a second control command value in which a reactive power control amount and a setting value are associated with each second DER 6b from the second control command information, and sets the second control command value in the second DER 6b. The DER control command value setting unit 27 corresponds to the control command value setting unit.

[0122] Fig. 22 is a diagram illustrating an example of the configuration of a power distribution automation system according to embodiment 5. As illustrated in Fig. 22, the power distribution automation system 4a has a configuration in which the DER control command value setting unit 44 is removed from Fig. 5 of embodiment 1. This is because the power distribution automation system 4a does not set the reactive power control amount and setting value for the second DER 6b.

[0123] 21 and 22 show an example in which the distribution automation system 4a does not set the reactive power control amount and the set value for the second DER 6b, but the distribution automation system 4 may be removed from the DER management systems 1 and 1a. FIG. 23 is a diagram showing an example of a configuration of a DER management system according to a fifth embodiment. The DER management system 1b in FIG. 23 has a configuration in which the distribution automation system 4 is removed from FIG. 1 in the first embodiment. In this case, the DER controllable amount collection unit 32 of the VPP aggregator 3 further has a function of collecting the second controllable power amount from the second DER 6b and transmitting it to the DER management device 2. The communication unit 21 of the DER management device 2 further has a function of transmitting second control command information indicating the reactive power control amount and the set value for each second DER 6b to the VPP aggregator 3. The DER control command value determination unit 36 ​​of the VPP aggregator 3 further has a function of generating a second control command value in which a reactive power control amount and a setting value are associated with each second DER 6b from the second control command information, and setting the second control command value to the second DER 6b. In this way, when the power distribution automation system 4 is not present, it is possible to have the VPP aggregator 3 perform the function of the power distribution automation system 4 instead. In addition, the DER management system 1b of FIG. 23 may be provided with the DER management device 2b described in FIG. 21. That is, the communication unit 21 of the DER management device 2b may not transmit the second control command information to the VPP aggregator 3, and the DER control command value setting unit 27 may set the second control command value generated from the second control command information to each second DER 6b.

[0124] In the above description, the configuration of the first embodiment has been taken as an example, but similar modifications can also be applied to the configurations of the second to fourth embodiments.

[0125] In the above description, the prediction unit 23 or the measurement information collecting unit 26 of the DER management devices 2, 2a, and 2b estimates the voltage-current distribution, but the DER management devices 2, 2a, and 2b may not have the prediction unit 23 or the measurement information collecting unit 26 and may acquire the estimated voltage-current distribution from outside. FIG. 24 is a diagram showing a schematic diagram of another example of the configuration of a DER management system according to the fifth embodiment. The DER management system 1c in FIG. 24 further includes a prediction system 9 connected to a communication network 73. The prediction system 9 is a device having the function of the prediction unit 23 of the DER management device 2 in the first and second embodiments. That is, the prediction system 9 holds load power generation performance information including the actual value of the load demand connected to the distribution system 100 and the actual value of the power generation profile, predicts the load demand forecast value and the power generation forecast value of the distribution system 100 during the control target period based on the load power generation performance information, and estimates the voltage-current distribution in the distribution line 103 of the distribution system 100 during the control target period based on the result of the prediction. Then, the prediction system 9 transmits the voltage and current distribution to the DER management device 2c.

[0126] Fig. 25 is a diagram illustrating another example of the configuration of a DER management device according to embodiment 5. As illustrated in Fig. 25, a DER management device 2c has a configuration obtained by removing the prediction unit 23 from Fig. 3 of embodiment 1. An optimal power flow calculation unit 24 performs a process of determining an active power control range and a reactive power control amount by using the voltage and current distribution acquired from the prediction system 9.

[0127] The prediction system 9 may have the function of the measurement information collector 26 described in the third and fourth embodiments. In this case, the prediction system 9 collects power distribution system state quantity information from the measurement device 8 via the communication unit, and stores the collected power distribution system state quantity information in the storage unit together with the collection time. The prediction system 9 also estimates a voltage-current distribution in the distribution line 103 of the power distribution system 100 during the control target period, using the power distribution system state quantity information stored in the storage unit. Then, the prediction system 9 transmits the voltage-current distribution to the DER management device 2c. By having the prediction system 9 estimate the voltage-current distribution in this manner, it is possible to reduce the processing load on the DER management device 2c.

[0128] The configurations shown in the above embodiments are merely examples, and may be combined with other known technologies, or the embodiments may be combined with each other. Also, parts of the configurations may be omitted or modified without departing from the spirit of the invention. [Explanation of symbols]

[0129] 1,1a,1b,1c DER management system, 2,2a,2b,2c DER management device, 3 VPP aggregator, 4,4a power distribution automation system, 5 load, 6 DER, 6a first DER, 6b second DER, 7 consumer, 8 measurement device, 9 forecasting system, 21,31,41,621 communication unit, 22,33,43,623 memory unit, 23 forecasting unit, 24 optimal power flow calculation unit, 25 DER control command value calculation unit, 26 measurement information collection unit, 27,44 DER control command value setting unit, 32,42 DER controllable amount collection unit, 34 demand forecasting unit, 35 required adjustment capacity estimation unit, 36 DER control command value determination unit, 61 distributed energy device, 62 power control device, 71,72,73,81 communication network, 100 power distribution system, 101 Distribution transformer, 102 busbar, 103 distribution line, 622 controllable power calculation unit, 624 control unit.

Claims

1. A distributed energy resource management device that calculates output of distributed energy resources including a plurality of first distributed energy resources that are connected to a power distribution system and control active power output, comprising: an optimal power flow calculation unit that calculates maximum values ​​of charge and discharge amounts that can be output within a range of a first amount of power that is controllable by the first distributed energy resource during a control period, from a voltage and current distribution of the power distribution system based on a supply and demand forecast, while observing constraints on the voltage and current of the power distribution system, and determines an active power control range that is determined by the maximum values ​​of the charge and discharge amounts; a control command value calculation unit that generates first control command information in which each of the plurality of first distributed energy resources is associated with the active power control range; a communication unit that transmits the first control command information to a virtual substation aggregator that determines an amount of active power to be commanded to the plurality of first distributed energy resources; Equipped with A distributed energy resource management device, characterized in that the active power control range is a control range of the active power output from the first distributed energy resource.

2. The distributed energy resource further includes a plurality of second distributed energy resources connected to the power grid and having a voltage regulation function; the optimal power flow calculation unit calculates, from the voltage and current distribution in addition to the active power control range, a reactive power control amount that is a minimum value of an amount of reactive power that can be output within a controllable second amount of power of the plurality of second distributed energy resources during the control period while the constraints of the power distribution system are observed; The distributed energy resource management device according to claim 1, characterized in that the control command value calculation unit further generates second control command information that associates a setting value used for voltage control by reactive power in the plurality of second distributed energy resources and the reactive power control amount with each of the plurality of second distributed energy resources.

3. 3. The distributed energy resource management device according to claim 1, further comprising a prediction unit that estimates the voltage and current distribution during the control period using an actual value of load demand in the power distribution system and an actual value of power generation in a distributed energy resource capable of generating power.

4. The distributed energy resource management device according to claim 1 or 2, further comprising a measurement information collection unit that collects state quantities of the power distribution system from a measurement device and estimates the voltage and current distribution during the control period using the state quantities of the power distribution system.

5. A distributed energy resource management device that calculates output of distributed energy resources including a plurality of first distributed energy resources that are connected to a power distribution system and control active power output, comprising: an optimal power flow calculation unit that calculates a maximum discharge amount that can be output within a first controllable amount of power of the first distributed energy resource during the control period from a first voltage / current distribution of the distribution system based on a supply / demand forecast in which constraints on the voltage and current of the distribution system are observed during a control period and a power generating distributed energy resource during the control period has a maximum output, and a maximum charge amount that can be output within the first amount of power during the control period from a second voltage / current distribution of the distribution system based on a supply / demand forecast in which the power generating distributed energy resource during the control period has a minimum output, and determines an active power control range determined by the discharge amount and the maximum charge amount; a control command value calculation unit that generates first control command information in which each of the plurality of first distributed energy resources is associated with the active power control range; a communication unit that transmits the first control command information to a virtual substation aggregator that determines an amount of active power to be commanded to the plurality of first distributed energy resources; Equipped with A distributed energy resource management device, characterized in that the active power control range is a control range of the active power output from the first distributed energy resource.

6. The distributed energy resource further includes a plurality of second distributed energy resources connected to the power grid and having a voltage regulation function; the optimal power flow calculation unit calculates, from the first voltage / current distribution and the second voltage / current distribution in addition to the active power control range, a reactive power control amount that is a minimum value of an amount of reactive power that can be output within a controllable second amount of power of the plurality of second distributed energy resources during the control period while the constraints of the power distribution system are observed; The distributed energy resource management device according to claim 5, characterized in that the control command value calculation unit further generates second control command information that associates a setting value used for voltage control by reactive power in the plurality of second distributed energy resources and the reactive power control amount with the plurality of second distributed energy resources.

7. 7. The distributed energy resource management device according to claim 5, further comprising a prediction unit that estimates the first voltage-current distribution and the second voltage-current distribution during the control period using an actual value of load demand in the power distribution system and an actual value of power generation in the distributed energy resource capable of generating power.

8. The distributed energy resource management device according to claim 5 or 6, further comprising a measurement information collection unit that collects state quantities of the power distribution system from a measurement device and estimates the first voltage current distribution and the second voltage current distribution during the control period using the state quantities of the power distribution system.

9. A distributed energy resource including a plurality of first distributed energy resources connected to a power distribution system and having an output controlled by active power; A distributed energy resource management device according to claim 1; A virtual substation aggregator that determines an amount of active power to be commanded to the first plurality of distributed energy resources for supply and demand adjustment; A distributed energy resource management system comprising: The virtual substation aggregator comprises: a communication unit that receives the first control command information from the distributed energy resource management apparatus; a required adjustment capacity estimation unit that estimates an adjustment capacity, which is an amount of power required for supply and demand control, based on a supply and demand forecast in the power distribution system during the control target period; a control command value determination unit that allocates the adjustment capability to each of the plurality of first distributed energy resources within the active power control range of the first control command information so as to minimize an operation cost, and determines a first control command value including an active power control amount, which is the allocated adjustment capability to be commanded to each of the plurality of first distributed energy resources, and an output timing; Equipped with The distributed energy resource management system according to claim 1, wherein the communication unit transmits the first control command value to each of the plurality of first distributed energy resources.

10. The distributed energy resource further includes a plurality of second distributed energy resources connected to the power grid and having a voltage regulation function; the optimal power flow calculation unit of the distributed energy resource management apparatus calculates, from the voltage and current distribution in addition to the active power control range, a reactive power control amount that is a minimum value of an amount of reactive power that can be output within a controllable second amount of power of the plurality of second distributed energy resources during the control target period while the constraints of the power distribution system are observed; The distributed energy resource management system according to claim 9, characterized in that the control command value calculation unit of the distributed energy resource management device further generates second control command information that associates a setting value used for voltage control by reactive power in the plurality of second distributed energy resources and the reactive power control amount with each of the plurality of second distributed energy resources.

11. A distributed energy resource including a plurality of first distributed energy resources connected to a power distribution system and having an output controlled by active power; A distributed energy resource management device according to claim 5; A virtual substation aggregator that determines an amount of active power to be commanded to the first plurality of distributed energy resources for supply and demand adjustment; A distributed energy resource management system comprising: The virtual substation aggregator comprises: a communication unit that receives the first control command information from the distributed energy resource management apparatus; a required adjustment capacity estimation unit that estimates an adjustment capacity, which is an amount of power required for supply and demand control, based on a supply and demand forecast in the power distribution system during the control target period; a control command value determination unit that allocates the adjustment capability to each of the plurality of first distributed energy resources within the active power control range of the first control command information so as to minimize an operation cost, and determines a first control command value including an active power control amount, which is the allocated adjustment capability to be commanded to each of the plurality of first distributed energy resources, and an output timing; Equipped with The distributed energy resource management system according to claim 1, wherein the communication unit transmits the first control command value to each of the plurality of first distributed energy resources.

12. The distributed energy resource further includes a plurality of second distributed energy resources connected to the power grid and having a voltage regulation function; the optimal power flow calculation unit of the distributed energy resource management apparatus calculates, from the first voltage / current distribution and the second voltage / current distribution in addition to the active power control range, a reactive power control amount that is a minimum value of an amount of reactive power that can be output within a controllable second amount of power of the plurality of second distributed energy resources during the control period while the constraints of the power distribution system are observed; The distributed energy resource management system according to claim 11, characterized in that the control command value calculation unit of the distributed energy resource management device further generates second control command information that associates a setting value used for voltage control by reactive power in the multiple second distributed energy resources and the reactive power control amount with each of the multiple second distributed energy resources.

13. The communication unit of the distributed energy resource management apparatus transmits the second control command information to the virtual substation aggregator, 13. The distributed energy resource management system according to claim 10 or 12, characterized in that the communication unit of the virtual substation aggregator transmits the first amount of power collected from the plurality of first distributed energy resources and the second amount of power collected from the plurality of second distributed energy resources to the distributed energy resource management device, and transmits to each of the plurality of second distributed energy resources a second control command value that commands the setting value and the reactive power control amount included in the second control command information to each of the plurality of second distributed energy resources.

14. a distribution automation system for managing voltage and current of the second distributed energy resource; the power distribution automation system includes a communication unit configured to transmit the second amount of power collected from the plurality of second distributed energy resources to the distributed energy resource management device; The communication unit of the virtual substation aggregator transmits the first amount of power collected from the plurality of first distributed energy resources to the distributed energy resource management device; The communication unit of the distributed energy resource management apparatus transmits the second control command information to the power distribution automation system, 13. The distributed energy resource management system according to claim 10 or 12, characterized in that the communication unit of the power distribution automation system transmits, to each of the plurality of second distributed energy resources, a second control command value that commands the setting value and the reactive power control amount included in the second control command information.

15. a distribution automation system for managing voltage and current of the second distributed energy resource; the power distribution automation system includes a communication unit configured to transmit the second amount of power collected from the plurality of second distributed energy resources to the distributed energy resource management device; The distributed energy resource management system according to claim 10 or 12, characterized in that the communication unit of the virtual substation aggregator transmits the first amount of power collected from the plurality of first distributed energy resources to the distributed energy resource management device.

16. The communication unit of the distributed energy resource management apparatus transmits the second control command information to the power distribution automation system, The distributed energy resource management system according to claim 15, characterized in that the communication unit of the power distribution automation system transmits, to each of the plurality of second distributed energy resources, a second control command value that commands the setting value and the reactive power control amount included in the second control command information.

17. The distributed energy resource management system according to claim 15, characterized in that the communication unit of the distributed energy resource management device transmits, to each of the plurality of second distributed energy resources, a second control command value that commands the setting value and the reactive power control amount included in the second control command information.

18. 10. The distributed energy resource management system according to claim 9, further comprising a prediction system that predicts the voltage and current distribution during the control period using an actual value of load demand in the power distribution system and an actual value of power generation in a distributed energy resource capable of generating power, and transmits the voltage and current distribution to the distributed energy resource management device.

19. 12. The distributed energy resource management system according to claim 11, further comprising a prediction system that predicts the first voltage current distribution and the second voltage current distribution during the control period using an actual value of load demand in the power distribution system and an actual value of power generation in a distributed energy resource capable of generating power, and transmits the prediction results to the distributed energy resource management device.

20. A distributed energy resource management program for calculating an output of a distributed energy resource including a plurality of first distributed energy resources that are connected to a power distribution system and control an effective power output, the program comprising: On the computer, calculating maximum values ​​of charge and discharge amounts that can be output within a range of a first amount of power that is controllable by the first distributed energy resource during a control period from a voltage and current distribution of the power distribution system based on a supply and demand forecast, while observing constraints on the voltage and current of the power distribution system; and calculating an active power control range determined by the maximum values ​​of the charge and discharge amounts; generating first control command information in which each of the plurality of first distributed energy resources is associated with the active power control range; transmitting the first control command information to a virtual substation aggregator that determines an amount of active power to be commanded to the first plurality of distributed energy resources; Run the command, A distributed energy resource management program, characterized in that the active power control range is a control range of the active power output from the first distributed energy resource.

21. A distributed energy resource management program for calculating an output of a distributed energy resource including a plurality of first distributed energy resources that are connected to a power distribution system and control an effective power output, the program comprising: On the computer, a step of calculating a maximum discharge amount that can be output within a first controllable amount of power of the first distributed energy resource during the control period from a first voltage / current distribution of the distribution system based on a supply / demand forecast in which constraints on the voltage and current of the distribution system are observed during a control period and a power generating distributed energy resource during the control period has a maximum output, and a maximum charge amount that can be output within the first amount of power during the control period from a second voltage / current distribution of the distribution system based on a supply / demand forecast in which the power generating distributed energy resource during the control period has a minimum output, and determining an active power control range determined by the discharge amount and the maximum charge amount; generating first control command information in which each of the plurality of first distributed energy resources is associated with the active power control range; transmitting the first control command information to a virtual substation aggregator that determines an amount of active power to be commanded to the first plurality of distributed energy resources; Run the command, A distributed energy resource management program, characterized in that the active power control range is a control range of the active power output from the first distributed energy resource.

Citation Information

Patent Citations

  • Preceding control determination device, preceding control device, and preceding control determination program

    JP2017108489A

  • Distributed energy resource management apparatus, power control system, distributed energy resource, central feeding command office computer system, and power control method

    JP2021019486A

  • Electric power distribution device, electric power distribution method, and program

    JP2022077459A