Connected hot water system
The system quickly adjusts the number of operating water heaters in response to flow rate changes by using a flow rate detection mechanism and number determining means, enhancing efficiency and energy usage in connected hot water systems.
Patent Information
- Application Number
- JP2021090388
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-05-28
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2041-05-28
AI Technical Summary
Existing connected hot water systems take a long time to adjust the number of operating water heaters in response to significant changes in flow rate, leading to inefficiencies.
A system that includes a flow rate detection mechanism and a number determining means to quickly adjust the number of operating water heaters based on predetermined thresholds and the rate of change in flow rate, using a connection unit to control switching valves and heaters.
Enables rapid adjustment of the number of operating water heaters to match flow rate changes, improving efficiency and energy usage by ensuring an appropriate number of heaters are operational.
Smart Images

Figure 0007579754000001 
Figure 0007579754000002 
Figure 0007579754000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a linked hot water system. [Background technology]
[0002] Patent Document 1 discloses a linked hot water supply system including a plurality of hot water supply devices provided in parallel in a hot water supply circuit, and a number determination means for determining the number of the plurality of hot water supply devices in operation. Each of the plurality of hot water supply devices includes a heat source for heating hot water flowing through the hot water supply circuit, a flow rate detection means for detecting the flow rate of hot water flowing through the heat source, a switching valve for switching between a state permitting the flow of hot water to the heat source and a state prohibiting the flow of hot water to the heat source, and a control device for controlling the operation of the heat source and the switching valve. The number determination means is configured to determine whether to change the number of the plurality of hot water supply devices in operation one by one according to the flow rate detected by the flow rate detection means of each of the plurality of hot water supply devices. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2007-315645 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the above-mentioned linked hot water supply system, even if the flow rate of hot water flowing through the hot water supply circuit changes significantly, the number of operating hot water supply devices is changed one by one, so it takes a long time until the appropriate number of operating hot water supply devices is realized. This specification provides a technology that can quickly realize the appropriate number of operating hot water supply devices even if the flow rate of hot water flowing through the hot water supply circuit changes significantly. [Means for solving the problem]
[0005] This specification discloses a linked hot water supply system. The linked hot water supply system may include a plurality of hot water supply devices provided in parallel in a hot water supply circuit, a flow rate detection means for detecting the flow rate of hot water flowing through the hot water supply circuit, and a number determination means for determining the number of operation units of the plurality of hot water supply devices. Each of the plurality of hot water supply devices may include a heat source for heating the hot water flowing through the hot water supply circuit, a switching valve for switching between a state for allowing the flow of hot water to the heat source and a state for prohibiting the flow of hot water to the heat source, and a control device for controlling the operation of the heat source and the switching valve. The number of units determination means may determine to increase the number of operating units of the plurality of hot water heating apparatuses when a first predetermined condition is satisfied that the flow rate detected by the flow rate detection means exceeds an upper threshold. The upper threshold may be a value that increases as the number of operating units increases. The number of units determination means may determine to decrease the number of operating units of the plurality of hot water heating apparatuses when a second predetermined condition is satisfied that the flow rate detected by the flow rate detection means falls below a lower threshold. The lower threshold may be a value that increases as the number of operating units increases. In at least one of the cases where the number of units determination means determines to increase the number of operating units and where the number of units determination means determines to decrease the number of operating units, the number of units determination means may be configured to determine to change the number of operating units by a number change amount that is set according to a rate of change of the flow rate detected by the flow rate detection means.
[0006] In the above linked hot water supply system, when determining the number of operating hot water supply devices, the number of operating hot water supply devices is changed by an amount of change in the number of devices that is set according to the rate of change in the flow rate of hot water flowing through the hot water supply circuit. With this configuration, even if the flow rate of hot water flowing through the hot water supply circuit changes significantly, an appropriate number of operating hot water supply devices can be quickly achieved. Furthermore, in the above configuration, when the flow rate of hot water flowing through the hot water supply circuit increases and it is determined that the capacity of the hot water supply devices in operation alone is insufficient, a decision can be made to increase the number of operating hot water supply devices. At this time, when the flow rate of hot water flowing through the hot water supply circuit increases suddenly, the number of operating hot water supply devices is increased significantly, while when the flow rate of hot water flowing through the hot water supply circuit increases only slightly, the number of operating hot water supply devices is increased slightly. Therefore, an appropriate number of operating hot water supply devices can be quickly achieved according to the degree of change in the flow rate of hot water flowing through the hot water supply circuit. Furthermore, in the above configuration, when the flow rate of hot water flowing through the hot water supply circuit decreases and it is determined that the energy efficiency of the hot water supply circuit as a whole is better if the number of operating hot water supply devices is reduced, a decision can be made to reduce the number of operating hot water supply devices. At this time, when the flow rate of hot water flowing through the hot water supply circuit decreases suddenly, the number of operating hot water supply devices is reduced significantly, while when the flow rate of hot water flowing through the hot water supply circuit decreases only slightly, the number of operating hot water supply devices is reduced slightly. Therefore, an appropriate number of operating water heating devices can be quickly achieved depending on the degree of change in the flow rate of hot and cold water flowing through the hot water circuit.
[0011] The number determination means When a decision is made to increase the number of operating units, the flow rate is The flow rate may be calculated based on the elapsed time from when the flow rate exceeds a value smaller than the upper threshold by a predetermined flow rate until when the flow rate exceeds the upper threshold.
[0012] According to the above configuration, the amount of change in the number of operating hot water heaters can be set according to the rate of change in the flow rate of hot water flowing through the hot water supply circuit immediately before the decision to change the number of operating hot water heaters is made. Therefore, even if the flow rate of hot water flowing through the hot water supply circuit suddenly changes, an appropriate number of operating hot water heaters can be quickly achieved.
[0013] The number determination means When the decision is made to reduce the number of operating vehicles, the flow rate is The flow rate change rate may be calculated based on the elapsed time from when the flow rate falls below a value that is greater than the lower threshold by a predetermined flow rate until the flow rate falls below the lower threshold.
[0014] According to the above configuration, the amount of change in the number of operating hot water heaters can be set according to the rate of change in the flow rate of hot water flowing through the hot water supply circuit immediately before the decision to change the number of operating hot water heaters is made. Therefore, even if the flow rate of hot water flowing through the hot water supply circuit suddenly changes, an appropriate number of operating hot water heaters can be quickly achieved.
[0015] The number determination means In the case of deciding to increase the number of operating vehicles, After detecting a change in the flow rate detected by the flow rate detection means The first predetermined condition and / or the second predetermined condition is satisfied. The flow rate change rate may be calculated based on an elapsed time between when the flow rate changes and when the flow rate changes.
[0016] With the above configuration, the amount of change in the number of units can be set according to the rate of change in the hot and cold water flow rate from immediately after the hot and cold water flow rate change begins until immediately before the decision to change the number of operating hot water heaters is made. Therefore, an appropriate number of operating hot water heaters can be achieved without being affected by short-term fluctuations in flow rate. [Brief description of the drawings]
[0017] [Figure 1] FIG. 1 is a diagram showing a configuration of a linked hot water supply system according to a first embodiment and a second embodiment. [Diagram 2] FIG. 1 is a diagram showing a configuration of a water heater 1 according to a first and second embodiment. [Diagram 3] 5 is a flowchart showing a process for increasing the number of operating water heaters 1, which is executed by a connection unit 2 in the connected hot water supply system according to the first embodiment. [Figure 4] 10A to 10C are diagrams showing the gradient measurement periods for the total flow rate of hot and cold water that changes at different flow rate change rates in the first embodiment. [Diagram 5] 5 is a flowchart showing a process of reducing the number of operating water heaters 1, which is executed by the connection unit 2 in the connected hot water supply system according to the first embodiment. [Figure 6] 10 is a flowchart showing a process for increasing the number of operating water heaters 1, which is executed by a connection unit 2 in a connected hot water supply system according to Example 2. [Figure 7] 13A and 13B are diagrams showing the gradient measurement periods for the total flow rate of hot and cold water that changes at different flow rate change rates in the second embodiment. [Figure 8] 10 is a flowchart showing a process of reducing the number of operating water heaters 1, which is executed by a connection unit 2 in a connected hot water supply system according to Example 2. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0018] Example 1 As shown in FIG. 1, the connected hot water supply system of this embodiment includes a plurality of hot water heaters 1, a connection unit 2, a water supply pipe 3a, a hot water supply pipe 3b, and a plurality of faucets 5.
[0019] Each water heater 1 is connected in parallel to the water supply pipe 3a and the hot water supply pipe 3b so as to receive water from the water supply pipe 3a and deliver hot water to the hot water supply pipe 3b. Each faucet 5 is connected to the hot water supply pipe 3b, and each faucet 5 is configured to deliver the hot water supplied from the hot water supply pipe 3b to the outside.
[0020] The connection unit 2 is composed of a CPU, memory, etc. The connection unit 2 is capable of communicating with the electrical unit 9 of each water heater 1 (details will be described later), and transmits the target hot water temperature to each water heater 1. The connection unit 2 also determines the number of water heaters 1 in operation based on the water supply information and flow rate information transmitted from the electrical unit 9 of each water heater 1, and transmits an operation start signal or an operation stop signal to each water heater 1. The connection unit 2 is configured not to transmit an operation stop signal when there is only one water heater 1 in a water supply possible state, so that all water heaters 1 do not stop operating. The connection unit 2 has a built-in timer, which can measure time and record the measured time.
[0021] As shown in Figure 2, each water heater 1 is equipped with a water supply pipe 3c that connects the water supply pipe 3a and the hot water supply pipe 3b to enable water to flow therethrough, a switching valve 7 that switches between an open state that allows water to be supplied to the water supply pipe 3c and a closed state that blocks the supply of water to the water supply pipe 3c, a flow rate sensor 6 that detects the flow rate of water flowing through the water supply pipe 3c, a heat exchanger 10 provided in the water supply pipe 3c, a gas burner 11 that heats the water flowing through the heat exchanger 10, a temperature sensor 8 that detects the temperature of the hot water heated by the heat exchanger 10, and an electrical unit 9 that has the function of controlling the operation of the gas burner 11 and the switching valve 7.
[0022] The electrical equipment unit 9 is composed of a CPU, a memory, etc. The electrical equipment unit 9 controls the heat of the gas burner 11 so that the temperature of the hot water detected by the temperature sensor 8 becomes the hot water supply target temperature instructed by the connection unit 2. The electrical equipment unit 9 can communicate with the connection unit 2, and transmits to the connection unit 2 water supply information indicating the operating state of the switching valve 7 and flow rate information indicating the flow rate of water flowing through the water pipe 3c detected by the flow rate sensor 6. The water supply information is indicated by either a "water supply possible state" indicating that the switching valve 7 can supply water to the water pipe 3c, or a "water supply cut off state" indicating that the switching valve 7 has cut off the supply of water to the water pipe 3c.
[0023] The connection unit 2 calculates the sum of the flow rates of hot and cold water in each water heater 1 (total flow rate) based on the flow rate information transmitted from the electrical unit 9 of each water heater 1. The total flow rate is equal to the flow rate of hot and cold water flowing through the water supply pipe 3a and the hot water supply pipe 3b.
[0024] Next, the process of increasing the number of operating water heaters 1, which is executed in the linked hot water supply system according to this embodiment, will be described with reference to FIG.
[0025] In step 100, the connection unit 2 determines whether the total flow rate exceeds a preset gradient measurement start flow rate Q1. If the determination as to whether the total flow rate exceeds the gradient measurement start flow rate Q1 is negative, the process returns to step 100. If the determination as to whether the total flow rate exceeds the gradient measurement start flow rate Q1 is positive, the process proceeds to step 101. Note that the gradient measurement start flow rate Q1 is smaller than the gradient measurement end flow rate Q2 described below. For example, the gradient measurement start flow rate Q1 is a flow rate that is smaller than the gradient measurement end flow rate Q2 by a predetermined flow rate (e.g., 10 L / min).
[0026] In step 101, the connection unit 2 starts measuring time t of a timer built into the connection unit 2, setting t=0, and then proceeds to step .
[0027] In step 102, the connection unit 2 determines whether the total flow rate exceeds a preset gradient measurement end flow rate Q2. If the determination as to whether the total flow rate exceeds the gradient measurement end flow rate Q2 is negative, the process returns to step 102. If the determination as to whether the total flow rate exceeds the gradient measurement end flow rate Q2 is positive, the process proceeds to step 103. Note that the gradient measurement end flow rate Q2 is, for example, a flow rate that is 2 L / min smaller than the boundary flow rate between "medium" and "large" described below, multiplied by the number of water heaters 1 that are ready to supply water.
[0028] In step 103, the connection unit 2 stops the time measurement in the timer built into the connection unit 2, records the time t=T1, and proceeds to step 104.
[0029] In step 104, the connection unit 2 provisionally determines the number of water heaters 1 to be increased in relation to the number of operating units. Specifically, the connection unit 2 provisionally determines the number of water heaters 1 to be increased based on the flow rate of each water heater 1 that is in a water supply possible state. In this embodiment, the connection unit 2 classifies the flow rate of each water heater 1 into one of the preset stages of "large", "medium", or "small" based on the value of the flow rate of each water heater 1 that is in a water supply possible state. For example, when the flow rate of a certain water heater 1 is 14 L / min or more, the connection unit 2 classifies the flow rate of the water heater 1 into "large", when the flow rate of the certain water heater 1 is 6 L / min or more and less than 14 L / min, the connection unit 2 classifies the flow rate of the water heater 1 into "medium", and when the flow rate of the certain water heater 1 is 6 L / min or more and less than 14 L / min, the connection unit 2 classifies the flow rate of the water heater 1 into "small". Then, connection unit 2 outputs the difference between the number of water heaters 1 classified as having a flow rate of "large" and the number of water heaters 1 classified as having a flow rate of "small" among the water heaters 1 that are in a state where water can be supplied. If this difference is 3 or more, connection unit 2 provisionally determines the increased number of water heaters 1 to be 3, if this difference is 2, it provisionally determines the increased number of water heaters 1 to be 2, and if this difference is 1, it provisionally determines the increased number of water heaters 1 to be 1.
[0030] In step 105a, the connection unit 2 determines whether the elapsed time T1 from the start of the gradient measurement to the end of the gradient measurement is less than the flow rate change speed determination index n1. If the determination of whether the elapsed time T1 is less than the flow rate change speed determination index n1 is affirmative, the process proceeds to step 106a.
[0031] In step 106a, connection unit 2 corrects the increased number of water heaters 1 provisionally determined in step 104 by increasing it by one, and confirms the increased number of water heaters 1.
[0032] In step 105a, if the determination as to whether the elapsed time T1 is less than the flow rate change speed determination index n1 is negative, the process proceeds to step 105b. In step 105b, the connection unit 2 determines whether the elapsed time T1 is equal to or greater than the flow rate change speed determination index n1 and less than the flow rate change speed determination index n2. In the case where the determination as to whether the elapsed time T1 is equal to or greater than the flow rate change speed determination index n1 and less than the flow rate change speed determination index n2 is positive, the process proceeds to step 106b. Note that the value of the flow rate change speed determination index n2 is greater than the value of the flow rate change speed determination index n1.
[0033] In step 106b, connection unit 2 confirms the increased number of water heaters 1 without making any correction to the increased number of water heaters 1 provisionally determined in step 104.
[0034] In step 105b, if the determination as to whether the elapsed time T1 is equal to or greater than the flow rate change speed determination index n1 and less than the flow rate change speed determination index n2 is negative, the process proceeds to step 105c. In step 105c, the connection unit 2 determines that the elapsed time T1 is equal to or greater than the flow rate change speed determination index n2, and the process proceeds to step 106c.
[0035] In step 106c, connection unit 2 corrects the increased number of water heaters 1 provisionally determined in step 104 by decreasing it by one, and finalizes the increased number of water heaters 1.
[0036] After steps 106a, 106b, and 106c, the process proceeds to step 107. In step 107, the connection unit 2 transmits an operation start signal to the electrical units 9 of the water heaters 1 that are in a water supply cut-off state, for the confirmed number of additional water heaters 1, to open the switching valves 7.
[0037] As shown in FIG. 4, when the rate of change of the flow rate of the total flow rate is large (see the solid line in the figure), the time T11 that elapses from when the flow rate exceeds the gradient measurement start flow rate Q1 until when the flow rate exceeds the gradient measurement end flow rate Q2 is short. In such a case, since the total flow rate increases sharply, the appropriate number of water heaters 1 in operation can be realized by significantly increasing the number of water heaters 1 in operation. In contrast, when the rate of change of the flow rate of the total flow rate is small (see the dashed line in the figure), the time T12 that elapses from when the flow rate exceeds the gradient measurement start flow rate Q1 until when the flow rate exceeds the gradient measurement end flow rate Q2 is long. In such a case, since the total flow rate has only increased slightly, the appropriate number of water heaters 1 in operation can be realized by slightly increasing the number of water heaters 1 in operation. According to the processing shown in FIG. 3, in the processing of steps 105a, 105b, 105c, 106a, 106b, and 106c, if the elapsed time T1 from exceeding the gradient measurement start flow rate Q1 to exceeding the gradient measurement end flow rate Q2 is short (if it is less than the flow rate change rate judgment index n1), the number of water heaters 1 increased is increased, and if the elapsed time T1 is long (if it is equal to or greater than the flow rate change rate judgment index n2), the number of water heaters 1 increased is decreased, thereby enabling an appropriate number of water heaters 1 in operation to be quickly achieved.
[0038] Next, the process of reducing the number of operating water heaters 1 executed in the linked hot water supply system according to this embodiment will be described with reference to FIG.
[0039] In step 150, the connection unit 2 determines whether the total flow rate is below a preset gradient measurement start flow rate Q3. If the determination as to whether the total flow rate is below the gradient measurement start flow rate Q3 is negative, the process returns to step 150. If the determination as to whether the total flow rate is below the gradient measurement start flow rate Q3 is positive, the process proceeds to step 151. Note that the gradient measurement start flow rate Q3 is smaller than the gradient measurement start flow rate Q1 and larger than the gradient measurement end flow rate Q4 described below. For example, the gradient measurement start flow rate Q3 is a flow rate that is larger than the gradient measurement end flow rate Q4 by a predetermined flow rate (e.g., 10 L / min).
[0040] In step 151 , the connection unit 2 starts measuring time t of a timer built into the connection unit 2 by setting t=0, and then proceeds to step 152 .
[0041] In step 152, the connection unit 2 determines whether the total flow rate is below a preset gradient measurement end flow rate Q4. If the determination as to whether the total flow rate is below the gradient measurement end flow rate Q4 is negative, the process returns to step 152. If the determination as to whether the total flow rate is below the gradient measurement end flow rate Q4 is positive, the process proceeds to step 153. Note that the gradient measurement end flow rate Q4 is, for example, a flow rate that is 2 L / min greater than the boundary flow rate between "small" and "medium" multiplied by the number of water heaters 1 that are ready to supply water.
[0042] In step 153, the connection unit 2 stops the time measurement in the timer built into the connection unit 2, records the time t=T10, and proceeds to step 154.
[0043] In step 154, the connection unit 2 provisionally determines the number of operating water heaters 1 to be reduced. Specifically, the connection unit 2 provisionally determines the number of water heaters 1 to be reduced based on the flow rate of each of the water heaters 1 that are in a state where water can be supplied. In this embodiment as well, the connection unit 2 outputs the difference between the number of water heaters 1 that are in a state where water can be supplied and that are classified as having a flow rate of "small" and the number of water heaters 1 that are classified as having a flow rate of "large". If this difference is 3 or more, the connection unit 2 provisionally determines the number of water heaters 1 to be reduced to 3, if this difference is 2, the connection unit 2 provisionally determines the number of water heaters 1 to be reduced to 2, and if this difference is 1, the connection unit 2 provisionally determines the number of water heaters 1 to be reduced to 1.
[0044] In step 155a, the connection unit 2 determines whether the elapsed time T10 from the start of the gradient measurement to the end of the gradient measurement is less than the flow rate change speed determination index n3. If the determination of whether the elapsed time T10 is less than the flow rate change speed determination index n3 is affirmative, the process proceeds to step 156a.
[0045] In step 156a, the connection unit 2 corrects the number of water heaters 1 tentatively determined in step 154 to be reduced by one, and confirms the number of water heaters 1 to be reduced.
[0046] In step 155a, if the determination as to whether the elapsed time T10 is less than the flow rate change speed determination index n3 is negative, the process proceeds to step 155b. In step 155b, the connection unit 2 determines whether the elapsed time T10 is equal to or greater than the flow rate change speed determination index n3 and less than the flow rate change speed determination index n4. In the case where the determination as to whether the elapsed time T10 is equal to or greater than the flow rate change speed determination index n3 and less than the flow rate change speed determination index n4 is positive, the process proceeds to step 156b. Note that the value of the flow rate change speed determination index n4 is greater than the value of the flow rate change speed determination index n3.
[0047] In step 156b, the connection unit 2 confirms the reduced number of water heaters 1 without making any correction to the reduced number of water heaters 1 provisionally determined in step 154.
[0048] In step 155b, if the determination as to whether the elapsed time T10 is equal to or greater than the flow rate change speed determination index n3 and less than the flow rate change speed determination index n4 is negative, the process proceeds to step 155c. In step 155c, the connection unit 2 determines that the elapsed time T10 is equal to or greater than the flow rate change speed determination index n4, and the process proceeds to step 156c.
[0049] In step 156c, the connection unit 2 corrects the number of water heaters 1 tentatively determined in step 154 to be reduced by one, and confirms the number of water heaters 1 to be reduced.
[0050] After steps 156a, 156b, and 156c, the process proceeds to step 157. In step 157, the connection unit 2 transmits an operation stop signal to close the switching valve 7 of each of the electrical units 9 of the water heaters 1 that are in a state where they can supply water, for the determined number of reduced water heaters 1.
[0051] According to the processing shown in FIG. 5, in the processing of steps 155a, 155b, 155c, 156a, 156b, and 156c, if the elapsed time T10 from when the flow rate falls below the gradient measurement start flow rate Q3 to when the flow rate falls below the gradient measurement end flow rate Q4 is short (less than the flow rate change rate judgment index n3), the number of water heaters 1 reduced is increased, and if the elapsed time T10 is long (greater than or equal to the flow rate change rate judgment index n4), the number of water heaters 1 reduced is decreased, thereby enabling the appropriate number of water heaters 1 in operation to be quickly achieved.
[0052] Example 2 The linked hot water supply system according to this embodiment has a similar configuration to the linked hot water supply system according to the first embodiment shown in Figs.
[0053] Next, the process of increasing the number of operating water heaters 1 executed in the linked hot water supply system according to this embodiment will be described with reference to FIG.
[0054] In step 200, the connection unit 2 determines whether a change in the total flow rate is detected. In the process of increasing the number of operating water heaters 1 executed in the connected hot water supply system of this embodiment, the connection unit 2 determines whether the total flow rate has started to rise (the total flow rate has transitioned from a steady state to a state of transient increase). If the determination as to whether a change in flow rate is detected is negative, the process returns to step 200. If the determination as to whether a change in flow rate is detected is positive, the process proceeds to step 201. Note that the steady state referred to here is, for example, a state in which the difference between the total flow rate immediately after a very short period of time and the total flow rate immediately before, and the difference between the total flow rate immediately before and immediately after a very short period of time are Predefined value In other words, the connection unit 2 is in a state where the difference between the total flow rate immediately after the short period and the total flow rate immediately before is Predefined value By judging whether the total flow rate exceeds the threshold value, it is judged whether the total flow rate has started to rise. Predefined value is, for example, 10% of the total flow rate immediately before the short period.
[0055] In step 201 , the connection unit 2 starts measuring time t of a timer built into the connection unit 2 by setting t=0, and then proceeds to step 202 .
[0056] In step 202, the connection unit 2 records the total flow rate at t=0 (the rising start flow rate Q21), and then proceeds to step 203.
[0057] In step 203, the connection unit 2 determines whether the total flow rate exceeds a preset gradient measurement end flow rate Q22. If the determination as to whether the total flow rate exceeds the gradient measurement end flow rate Q22 is negative, the process returns to step 203. If the determination as to whether the total flow rate exceeds the gradient measurement end flow rate Q22 is positive, the process proceeds to step 204. Note that the gradient measurement end flow rate Q22 is, for example, a flow rate that is 2 L / min smaller than the boundary flow rate between "medium" and "large," which will be described later, multiplied by the number of water heaters 1 that are ready to supply water.
[0058] In step 204 , the connection unit 2 stops the time measurement in the timer built into the connection unit 2 , records the time t=T 2 , and proceeds to step 205 .
[0059] In step 205, the connection unit 2 provisionally determines the number of operating water heaters 1 to be increased. The connection unit 2 provisionally determines the number of operating water heaters 1 to be increased in the same manner as in the first embodiment (see step 104 in FIG. 3).
[0060] In step 206, the connection unit 2 calculates the flow rate change rate X of the total flow rate from the rise start flow rate Q21 and the gradient measurement end flow rate Q22 recorded in step 202, and the elapsed time T2 from the rise start to the gradient measurement end recorded in step 204. Specifically, the connection unit 2 calculates the flow rate change rate X of the total flow rate as X=(Q22-Q21) / T2.
[0061] In step 207a, the connection unit 2 determines whether the flow rate change speed X of the total flow rate obtained in step 206 is less than the flow rate change speed judgment index n21. If the determination of whether the flow rate change speed X of the total flow rate is less than the flow rate change speed judgment index n21 is affirmative, the process proceeds to step 208a.
[0062] In step 208a, the connection unit 2 corrects the increased number of water heaters 1 tentatively determined in step 205 by decreasing it by one, and confirms the increased number of water heaters 1.
[0063] In step 207a, if the determination as to whether the flow rate change speed X of the total flow rate is less than the flow rate change speed determination index n21 is negative, the process proceeds to step 207b. In step 207b, the connection unit 2 determines whether the flow rate change speed X of the total flow rate is equal to or greater than the flow rate change speed determination index n21 and less than the flow rate change speed determination index n22. If the determination as to whether the flow rate change speed X of the total flow rate is equal to or greater than the flow rate change speed determination index n21 and less than the flow rate change speed determination index n22 is positive, the process proceeds to step 208b. The value of the flow rate change speed determination index n22 is greater than the flow rate change speed determination index n21.
[0064] In step 208b, connection unit 2 confirms the increased number of water heaters 1 without making any correction to the increased number of water heaters 1 provisionally determined in step 205.
[0065] In step 207b, if the determination as to whether the flow rate change speed X of the total flow rate is equal to or greater than the flow rate change speed determination index n21 and less than the flow rate change speed determination index n22 is negative, the process proceeds to step 207c. In step 207c, the connection unit 2 determines that the flow rate change speed X of the total flow rate is equal to or greater than the flow rate change speed determination index n22, and the process proceeds to step 208c.
[0066] In step 208c, the connection unit 2 corrects the increased number of water heaters 1 provisionally determined in step 205 by increasing it by one, and confirms the increased number of water heaters 1.
[0067] After steps 208a, 208b, and 208c, the process proceeds to step 209. In step 209, the connection unit 2 transmits an operation start signal to the electrical units 9 of the water heaters 1 that are in a water supply cut-off state, for the confirmed number of additional water heaters 1, to open the switching valves 7.
[0068] As shown in FIG. 7, when the flow rate change rate X of the total flow rate is large (see the solid line in the figure), the elapsed time T21 from when the total flow rate starts to rise until it exceeds the gradient measurement end flow rate Q22 is short. In such a case, since the total flow rate has increased sharply from the steady state, the appropriate number of operating water heaters 1 can be realized by significantly increasing the number of operating water heaters 1. In contrast, when the flow rate change rate X of the total flow rate is small (see the dashed line in the figure), the elapsed time T22 from when the total flow rate starts to rise until it exceeds the gradient measurement end flow rate Q22 is long. In such a case, since the total flow rate has only increased slightly from the steady state, the appropriate number of operating water heaters 1 can be realized by slightly increasing the number of operating water heaters 1. According to the process shown in FIG. 6, in the processes of steps 207a, 207b, 207c, 208a, 208b, and 208c, when the flow rate change rate X of the total flow is small (when it is less than the flow rate change rate judgment index n21), the increased number of water heaters 1 is reduced, and when the flow rate change rate X of the total flow is large (when it is equal to or greater than the flow rate change rate judgment index n22), the increased number of water heaters 1 is increased, thereby making it possible to quickly achieve an appropriate number of operating water heaters 1.
[0069] Next, the process of reducing the number of operating water heaters 1 executed in the linked hot water supply system according to this embodiment will be described with reference to FIG.
[0070] In step 250, the connection unit 2 determines whether a change in the total flow rate is detected. In the process of reducing the number of operating water heaters 1 executed in the connected hot water supply system of this embodiment, the connection unit 2 determines whether the total flow rate has started to fall (the total flow rate has transitioned from a steady state to a state of transient decrease). If the determination as to whether a change in flow rate is detected is negative, the process returns to step 250. If the determination as to whether a change in flow rate is detected is positive, the process proceeds to step 251. A steady state is, for example, a state in which the difference between the total flow rate immediately after a very short period of time and the total flow rate immediately before, and the difference between the total flow rate immediately before and immediately after a very short period of time are Predefined value In other words, the connection unit 2 is in a state where the difference between the total flow rate just before the short period and the total flow rate just after the short period is Predefined value By judging whether the total flow rate exceeds the threshold value, it is judged whether the total flow rate has started to fall. Predefined value is, for example, 10% of the total flow rate immediately before the short period.
[0071] In step 251 , the connection unit 2 starts measuring time t of a timer built into the connection unit 2 by setting t=0, and then proceeds to step 252 .
[0072] In step 252, the connection unit 2 records the total flow rate at t=0 (the falling start flow rate Q23) and proceeds to step 253.
[0073] In step 253, the connection unit 2 determines whether the total flow rate is below a preset gradient measurement end flow rate Q24. If the determination as to whether the total flow rate is below the gradient measurement end flow rate Q24 is negative, the process returns to step 253. If the determination as to whether the total flow rate is below the gradient measurement end flow rate Q24 is positive, the process proceeds to step 254. Note that the gradient measurement end flow rate Q24 is, for example, a flow rate that is 2 L / min greater than the boundary flow rate between "small" and "medium" multiplied by the number of water heaters 1 that are ready to supply water.
[0074] In step 254, the connection unit 2 stops the time measurement in the timer built into the connection unit 2, records the time t=T20, and proceeds to step 255.
[0075] In step 255, the connection unit 2 provisionally determines the number of operating water heaters 1 to be reduced. The connection unit 2 provisionally determines the number of operating water heaters 1 to be reduced in the same manner as in Example 1 (see step 154 in FIG. 5).
[0076] In step 256, the connection unit 2 calculates the flow rate change rate X0 of the total flow rate from the fall start flow rate Q23 and the gradient measurement end flow rate Q24 recorded in step 252, and the elapsed time T20 from the fall start to the gradient measurement end recorded in step 254. Specifically, the connection unit 2 calculates the flow rate change rate X0 of the total flow rate as X0=(Q23-Q24) / T20.
[0077] In step 257a, the connection unit 2 determines whether the flow rate change rate X0 of the total flow rate obtained in step 256 is less than the flow rate change rate judgment index n23. If the determination of whether the flow rate change rate X0 of the total flow rate is less than the flow rate change rate judgment index n23 is affirmative, the process proceeds to step 258a.
[0078] In step 258a, connection unit 2 corrects the number of water heaters 1 tentatively determined in step 255 to be reduced by one, and confirms the number of water heaters 1 to be reduced.
[0079] In step 257a, if the determination as to whether the flow rate change speed X0 of the total flow rate is less than the flow rate change speed determination index n23 is negative, the process proceeds to step 257b. In step 257b, the connection unit 2 determines whether the flow rate change speed X0 of the total flow rate is equal to or greater than the flow rate change speed determination index n23 and less than the flow rate change speed determination index n24. If the determination as to whether the flow rate change speed X0 of the total flow rate is equal to or greater than the flow rate change speed determination index n23 and less than the flow rate change speed determination index n24 is positive, the process proceeds to step 258b. The value of the flow rate change speed determination index n24 is greater than the flow rate change speed determination index n23.
[0080] In step 258b, connection unit 2 confirms the reduced number of water heaters 1 without making any correction to the reduced number of water heaters 1 provisionally determined in step 255.
[0081] In step 257b, if the determination as to whether the flow rate change speed X0 of the total flow rate is equal to or greater than the flow rate change speed determination index n23 and less than the flow rate change speed determination index n24 is negative, the process proceeds to step 257c. In step 257c, the connection unit 2 determines that the flow rate change speed X0 of the total flow rate is equal to or greater than the flow rate change speed determination index n24, and the process proceeds to step 258c.
[0082] In step 258c, connection unit 2 corrects the number of reduced water heaters 1 provisionally determined in step 255 by increasing it by one, and confirms the number of reduced water heaters 1.
[0083] After steps 258a, 258b, and 258c, the process proceeds to step 259. In step 259, the connection unit 2 transmits an operation stop signal to close the switching valve 7 to the electrical units 9 of the water heaters 1 that are in a state where they can supply water, for the determined number of reduced water heaters 1.
[0084] According to the processing shown in FIG. 8, in the processing of steps 257a, 257b, 257c, 258a, 258b, and 258c, when the flow rate change rate X0 of the total flow is small (when it is less than the flow rate change rate judgment index n23), the number of water heaters 1 to be reduced is reduced, and when the flow rate change rate X0 of the total flow is large (when it is equal to or greater than the flow rate change rate judgment index n24), the number of water heaters 1 to be reduced is increased, thereby enabling an appropriate number of water heaters 1 in operation to be quickly achieved.
[0085] (Modification) The values of the gradient measurement start flow rate Q1, the gradient measurement end flow rate Q2, the gradient measurement start flow rate Q3, the gradient measurement end flow rate Q4, the gradient measurement end flow rate Q22, and the gradient measurement end flow rate Q24 may be changed as appropriate.
[0086] The values of flow rate change rate determination index n1, flow rate change rate determination index n2, flow rate change rate determination index n3, flow rate change rate determination index n4, flow rate change rate determination index n21, flow rate change rate determination index n22, flow rate change rate determination index n23, and flow rate change rate determination index n24 may be changed as appropriate.
[0087] The flow rate ranges of "large", "medium" and "small" may be changed as appropriate.
[0088] The water supply pipe 3a or the hot water supply pipe 3b may be provided with a flow rate sensor, and the connection unit 2 may use the flow rate detected by this flow rate sensor as the total flow rate.
[0089] As described above, in one or more embodiments, the linked hot water supply system is a linked hot water supply system comprising a plurality of water heaters 1 arranged in parallel to the water supply pipe 3a and the hot water pipe 3b, a flow sensor 6 and a connection unit 2 (or a flow sensor provided on the water supply pipe 3a or the hot water pipe 3b) in each water heater 1 that detects the total flow rate of hot water flowing through the water supply pipe 3a and the hot water pipe 3b, and a connection unit 2 that determines the number of operating water heaters 1, wherein each of the plurality of water heaters 1 is provided with a gas burner 11 that heats the water flowing through the water supply pipe 3a and the hot water pipe 3b, a switching valve 7 that switches between an open state that allows water to flow to the gas burner 11 and a closed state that prohibits it, and an electrical unit 9 that controls the operation of the gas burner 11 and the switching valve 7, and the connection unit 2 is configured to determine, when a specified condition is satisfied, to change the number of operating water heaters 1 by an amount of change in the number that is set according to the rate of change in the total flow rate of hot water flowing through the water supply pipe 3a and the hot water pipe 3b.
[0090] In the above-mentioned linked hot water supply system, when determining the number of operating water heaters 1, a decision is made to change the number of operating water heaters 1 by an amount of change in the number that is set according to the rate of change in the total flow rate, so that an appropriate number of operating water heaters 1 can be quickly achieved even if the total flow rate changes significantly.
[0091] In one or more embodiments, the specified condition includes a condition that the total flow rate detected by the flow sensor 6 in each water heater 1 and the connecting unit 2 (or the flow sensor provided in the water supply pipe 3a or the hot water supply pipe 3b) exceeds the gradient measurement end flow rate Q2 (or the gradient measurement end flow rate Q22), and the connecting unit 2 is configured to decide to increase the number of operating water heaters 1 when the total flow rate exceeds the gradient measurement end flow rate Q2 (or the gradient measurement end flow rate Q22).
[0092] In the above configuration, when the total flow rate increases and it is determined that the capacity of the operating water heaters 1 alone is insufficient, a decision can be made to increase the number of operating water heaters 1. At this time, if the total flow rate increases sharply, the number of operating water heaters 1 is increased significantly, whereas if the total flow rate has only increased slightly, the number of operating water heaters 1 is increased slightly. Therefore, an appropriate number of operating water heaters 1 can be quickly achieved depending on the degree of change in the total flow rate.
[0093] In one or more embodiments, the specified condition includes a condition that the total flow rate detected by the flow sensor 6 in each water heater 1 and the connecting unit 2 (or the flow sensor provided in the water supply pipe 3a or the hot water supply pipe 3b) falls below the gradient measurement end flow rate Q4 (gradient measurement end flow rate Q24), and the connecting unit 2 is configured to decide to reduce the number of operating water heaters 1 when the total flow rate falls below the gradient measurement end flow rate Q4 (gradient measurement end flow rate Q24).
[0094] In the above configuration, when the total flow rate decreases and it is determined that reducing the number of operating water heaters 1 will improve the energy efficiency of the hot water circuit as a whole, a decision can be made to reduce the number of operating water heaters 1. At this time, if the total flow rate decreases suddenly, the number of operating water heaters 1 will be reduced significantly, whereas if the total flow rate has only decreased slightly, the number of operating water heaters 1 will be reduced slightly. Therefore, an appropriate number of operating water heaters 1 can be quickly achieved depending on the degree of change in the total flow rate.
[0095] In one or more embodiments, the connection unit 2 is configured to calculate the rate of flow change of the total flow based on the elapsed time T1 between exceeding the gradient measurement start flow rate Q1 and exceeding the gradient measurement end flow rate Q2.
[0096] According to the above configuration, the amount of change in the number of operating water heaters 1 can be set according to the rate of change in the total flow rate immediately before a decision is made to change the number of operating water heaters 1. Therefore, even if the total flow rate changes suddenly, an appropriate number of operating water heaters 1 can be quickly achieved.
[0097] In one or more embodiments, the connection unit 2 is configured to calculate the rate of flow change of the total flow based on the elapsed time T10 between falling below the gradient measurement start flow rate Q3 and falling below the gradient measurement end flow rate Q4.
[0098] According to the above configuration, the amount of change in the number of operating water heaters 1 can be set according to the rate of change in the total flow rate immediately before a decision is made to change the number of operating water heaters 1. Therefore, even if the total flow rate changes suddenly, an appropriate number of operating water heaters 1 can be quickly achieved.
[0099] In one or more embodiments, the connecting unit 2 is configured to calculate the flow rate change rate X (or X0) of the total flow rate based on the elapsed time T2 (or T20) from when a change in the total flow rate detected by the flow sensor 6 in each water heater 1 and the connecting unit 2 (or a flow sensor provided in the water supply pipe 3a or the hot water supply pipe 3b) is detected until the total flow rate exceeds the slope measurement end flow rate Q22 (or falls below the slope measurement end flow rate Q24) and the difference between the slope measurement end flow rate Q22 (or the slope measurement end flow rate Q24) and the rise start flow rate Q21 (or the fall start flow rate Q23).
[0100] According to the above configuration, the amount of change in the number of water heaters 1 can be set according to the rate of change X (or X0) of the total flow rate from immediately after the total flow rate starts to change until immediately before a decision is made to change the number of operating water heaters 1. Therefore, an appropriate number of operating water heaters 1 can be achieved without being affected by short-term fluctuations in the flow rate.
[0101] Although the embodiments have been described in detail above, they are merely examples and do not limit the scope of the claims. The technology described in the claims includes various modifications and variations of the specific examples exemplified above. The technical elements described in this specification or drawings exhibit technical utility alone or in various combinations, and are not limited to the combinations described in the claims at the time of filing. In addition, the technology exemplified in this specification or drawings can achieve multiple objectives simultaneously, and achieving one of these objectives is itself technically useful. [Explanation of symbols]
[0102] 1: Water heater 2: Connection unit 3a: Water supply pipe 3b:Hot water pipe 3c: Water pipe 5: Faucet 6: Flow rate detection means 7: Switching valve 8: Temperature sensor 9: Electrical unit 10: Heat exchanger 11: Gas burner Q1: Incline measurement start flow rate Q2: Flow rate at the end of gradient measurement Q21: Start flow rate Q22: Gradient measurement end flow rate Q23: Falling start flow rate Q24: Gradient measurement end flow rate Q3: Incline measurement start flow rate Q4: Gradient measurement end flow rate X: Rate of change of total flow rate X0: Rate of change of total flow rate n1: Flow rate change rate determination index n2: Flow rate change rate determination index n3: Flow rate change rate judgment index n4: Flow rate change rate judgment index n21: Flow rate change rate judgment index n22: Flow rate change rate judgment index n23: Flow rate change rate judgment index n24: Flow rate change rate judgment index
Claims
1. A plurality of hot water supply devices provided in parallel in a hot water supply circuit; A flow rate detection means for detecting a flow rate of hot water flowing through the hot water supply circuit; A connected hot water supply system including a number determination means for determining the number of operation of the plurality of hot water supply devices, Each of the plurality of hot water supply devices is A heat source that heats the hot water flowing through the hot water supply circuit; a switching valve that switches between a state in which hot water is permitted to flow to the heating source and a state in which hot water is prohibited to flow to the heating source; A control device is provided for controlling the operation of the heat source and the switching valve, the number determination means determines to increase the number of the hot water heating apparatuses in operation when a first predetermined condition is satisfied, that is, the flow rate detected by the flow rate detection means exceeds an upper threshold value; The upper threshold value is a value that increases as the number of operating vehicles increases, the number determination means determines to reduce the number of the hot water heating apparatuses in operation when a second predetermined condition is satisfied, that is, the flow rate detected by the flow rate detection means is lower than a lower threshold value; The lower threshold value is a value that increases as the number of operating vehicles increases, A linked hot water supply system, wherein in at least one of the cases where the number of units determination means decides to increase the number of operating units and where the number of units determination means decides to decrease the number of operating units, the number of units determination means is configured to determine to change the number of operating units by an amount of change in the number of units that is set in accordance with the rate of change of the flow rate detected by the flow rate detection means.
2. The connected hot water supply system of claim 1, wherein the number determination means is configured to, when deciding to increase the number of operating units, calculate the rate of change of the flow rate based on the elapsed time between when the flow rate exceeds a value that is a predetermined flow rate smaller than the upper threshold value and when the flow rate exceeds the upper threshold value.
3. The connected hot water supply system of claim 1, wherein the number determination means is configured to, when deciding to reduce the number of operating units, calculate the rate of change of the flow rate based on the elapsed time between when the flow rate falls below a value that is a predetermined flow rate greater than the lower threshold value and when the flow rate falls below the lower threshold value.
4. The connected hot water supply system of claim 1, wherein the number determination means is configured to, when deciding to increase the number of operating units, calculate the rate of change of the flow rate based on the elapsed time between when the change in the flow rate detected by the flow detection means is detected and when the first specified condition is satisfied and the amount of change in the flow rate.
5. The connected hot water supply system of claim 1, wherein the number determination means is configured to, when deciding to reduce the number of operating units, calculate the rate of change of the flow rate based on the elapsed time between when the change in the flow rate detected by the flow detection means is detected and when the second specified condition is satisfied and the amount of change in the flow rate.
Citation Information
Patent Citations
Hot water supplying device
JP1995133957A
Connected hot water supply system
JP2007315645A
Control method for parallel operation of multi-type water heaters
JP2013501208A
Hot water supply system
JP2017078518A
Hot water supply system
US20150114313A1