Recommended methods for operating and stopping workbenches, devices, electronic equipment and warehouse systems
By determining the optimal number of workbenches based on processing order information and deadlines, the method improves the efficiency of a smart warehouse system by ensuring timely processing and optimal resource utilization.
Patent Information
- Application Number
- JP2023572048
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2021-02-09
- Filing Date
- 2022-01-21
- Publication Date
- 2024-11-27
- Estimated Expiration
- 2042-01-21
AI Technical Summary
Conventional methods for adjusting the number of workbenches in a smart warehouse system based on operator experience lead to inefficiencies such as insufficient processing capacity or resource wastage, affecting overall work efficiency.
A method and system that determines the optimal number of workbenches based on processing order information and deadlines, generating recommendations for operation or pause instructions to improve timing accuracy and resource utilization.
Enhances the efficiency of the warehouse system by ensuring orders are processed on time and optimizing the use of workbenches, preventing both underutilization and overutilization.
Smart Images

Figure 0007591169000001 
Figure 0007591169000002 
Figure 0007591169000003
Abstract
Description
[Technical field]
[0001] This disclosure claims priority to a Chinese patent application entitled "Method, device, electronic device and warehouse system for recommending operation / pause of workbench" filed with the China Patent Office on February 9, 2021, application number 202110178242.X, the entire contents of which are incorporated herein by reference.
[0002] The present disclosure relates to the technical field of smart warehouses, and in particular to a method, device, electronic device, and warehouse system for recommending operation / inactivity of a workbench. [Background technology]
[0003] A smart warehouse system based on warehouse robots adopts a smart operation system, and controls the warehouse robot according to system commands to take out the goods from the corresponding storage box to the workbench, where humans or robots pick up and sort the goods, and complete the packing and shipping process of the ordered goods. Summary of the Invention [Problem to be solved by the invention]
[0004] In the conventional technology, the number of work tables is adjusted to operate or stop according to specific needs, and when the order quantity is large, the operator operates the work table to increase the order processing capacity, and in the opposite case, the work table is stopped to save the work table resources. However, in the actual operating process, relying only on the operator's experience to determine the operation and stop timing of the work table is low in accuracy, which leads to problems such as insufficient processing capacity of the work table or waste of resources, and affects the work efficiency of the entire warehouse system.
[0005] The present disclosure provides a workbench operation / halt recommendation method, device, electronic device, and warehouse system that determine a target number of work benches based on information on orders to be processed, generate workbench operation / halt information based on the target number of work benches and send it to a terminal device to prompt an operator to operate or halt the work benches, thereby increasing the rationality of the operation / halt timing of the work benches and improving the work efficiency of the entire warehouse system. [Means for solving the problem]
[0006] As a first aspect, a workbench operation / idle recommendation method provided in an embodiment of the present disclosure includes the steps of acquiring order information needing processing, which represents orders in the system that need to be processed and a deadline corresponding to each of the orders that need to be processed; determining a target number of workbenches based on the order information needing processing, which represents the number of workbenches required to finish processing the corresponding orders that need to be processed by the deadline; generating workbench operation / idle information based on the target number of workbenches, and transmitting the workbench operation / idle information to a terminal device, wherein each of the orders that need to be processed corresponds to at least one storage box.
[0007] Optionally, the step of determining a target number of work units based on the information on orders to be processed includes a step of determining a required number of storage boxes based on the information on orders to be processed, and a step of determining a target number of work units based on the required number of storage boxes and workbench consumption capacity information, wherein the required number of storage boxes represents the number of storage boxes that need to be processed within a first predetermined time, and the workbench consumption capacity information represents the number of storage boxes that one workbench consumes within a unit time.
[0008] Optionally, the method further includes the steps of obtaining ID information of the workbench; obtaining a work history record of the workbench based on the ID information of the workbench; and determining the workbench consumption capacity information based on the work history record.
[0009] Optionally, the information on orders to be processed includes at least two orders to be processed and cut-off times corresponding to the orders to be processed, each of the orders to be processed includes at least one storage box ID, the number of required storage boxes includes a first required number and a second required number, the first required number represents the number of storage boxes that need to be processed within a first predetermined time, and the second required number represents the number of storage boxes that need to be processed within a second predetermined time, and the step of determining the number of required storage boxes based on the information on orders to be processed includes the steps of identifying a first target order and a second target order based on cut-off times of each of the orders to be processed, determining the first required number based on the number of storage box IDs of the first target order, and determining the second required number based on the number of storage box IDs of the second target order. the first target order represents an order to be processed for which the interval between the deadline and the current time is equal to or less than a first predetermined time, the second target order represents an order to be processed for which the interval between the deadline and the current time is equal to or less than a second predetermined time, the second predetermined time being longer than the first predetermined time, and the step of determining a target number of work units based on the required number of storage boxes and the workbench capacity information includes a step of determining a first number of work units based on the first required number and the workbench capacity information, a step of determining a second number of work units based on the second required number and the workbench capacity information, and a step of determining the first number of work units as the target number of work units if the first number of work units is equal to or greater than the second number of work units, and determining the second number of work units as the target number of work units if the first number of work units is smaller than the second number of work units.
[0010] Optionally, the information on orders needing processing includes at least one order needing processing and a deadline corresponding to the order needing processing, each of the orders needing processing including at least one storage box ID, and the step of determining the number of storage boxes required based on the information on orders needing processing includes the steps of: identifying a closest deadline based on the deadlines of each of the orders needing processing; identifying a target order based on the closest deadline; and determining the number of storage boxes required based on the number of storage box IDs in the target order, wherein the closest deadline represents a deadline closest to a current time, the time from the current time to the closest deadline is the first predetermined time, and the target order represents an order needing processing corresponding to the closest deadline.
[0011] Optionally, the workbench capacity information includes workbench category information indicating the category to which the storage boxes processed by the workbench belong, and the workbench operation / halt recommendation method further includes a step of determining storage box category information indicating the category to which the storage boxes corresponding to each of the orders to be processed belong based on the order information to be processed, and the step of determining a target number of workbenches based on the required number of storage boxes and workbench capacity information includes a step of distributing the required number of storage boxes based on the storage box category information and the workbench category information to determine the number of storage boxes that need to be processed by each of the workbenches, and a step of determining a target number of workbenches corresponding to the category information of the workbench based on the number of storage boxes that need to be processed by each of the workbenches and the workbench capacity information corresponding to each of the workbenches, and the step of generating workbench operation / halt information based on the target number of workbenches includes a step of generating workbench operation / halt information for instructing a user to operate or halt the workbench corresponding to the category information of the workbench based on the target number of workbenches corresponding to the category information of the workbench.
[0012] Optionally, the terminal device is a workbench, the workbench operation / halt information includes operation information and halt information, the step of generating workbench operation / halt information based on the target number of workbenches includes a step of generating operation information for instructing a user to operate the workbench if the target number of workbenches is larger than the current number of workbenches, and generating halt information for instructing a user to halt the workbench if the target number of workbenches is smaller than the current number of workbenches, and the step of transmitting the workbench operation / halt information to the terminal device includes a step of transmitting the operation information or halt information to the workbench for presentation.
[0013] As a second aspect, a workbench operation / idle recommendation device provided in an embodiment of the present disclosure includes an acquisition module for acquiring order information needing processing, which represents orders in the system that need to be processed and a deadline corresponding to each of the orders that need to be processed; a determination module for determining a target number of workbenches, which represents the number of workbenches required to finish processing the corresponding orders that need to be processed by the deadline, based on the order information needing processing; and a transmission module for generating workbench operation / idle information based on the target number of workbenches and transmitting the workbench operation / idle information to a terminal device, wherein each of the orders that need to be processed corresponds to at least one storage box.
[0014] Optionally, the determination module is specifically used to determine the number of storage boxes required based on the order information to be processed, and to determine a target number of work tables based on the number of storage boxes required and work table consumption capacity information, where the number of storage boxes required represents the number of storage boxes that need to be processed within a first predetermined time, and the work table consumption capacity information represents the number of storage boxes that one work table consumes within a unit time.
[0015] Optionally, the acquisition module is further used to acquire ID information of the workbench, acquire a work history record of the workbench based on the ID information of the workbench, and determine the workbench digestion capacity information based on the work history record.
[0016] Optionally, the information on orders to be processed includes at least two orders to be processed and deadlines corresponding to the orders to be processed, each of the orders to be processed includes at least one storage box ID, the number of required storage boxes includes a first required number and a second required number, the first required number represents the number of storage boxes that need to be processed within a first predetermined time, and the second required number represents the number of storage boxes that need to be processed within a second predetermined time, and when the determination module determines the number of required storage boxes based on the information on orders to be processed, specifically, identifies a first target order and a second target order based on the deadlines of each of the orders to be processed, determines the first required number based on the number of storage box IDs of the first target order, and determines the second required number based on the number of storage box IDs of the second target order. the first target order represents an order that needs to be processed where the interval between the deadline and the current time is equal to or less than a first predetermined time, the second target order represents an order that needs to be processed where the interval between the deadline and the current time is equal to or less than a second predetermined time, the second predetermined time is longer than the first predetermined time, and the determination module is used, when determining a target number of work units based on the required number of storage boxes and the workbench capacity information, specifically, to determine a first number of work units based on the first required number and the workbench capacity information, to determine a second number of work units based on the second required number and the workbench capacity information, and, if the first number of work units is equal to or greater than the second number of work units, to determine the first number of work units as the target number of work units, and, if the first number of work units is smaller than the second number of work units, to determine the second number of work units as the target number of work units.
[0017] Optionally, the information on orders to be processed includes at least one order to be processed and a deadline corresponding to the order to be processed, each of the orders to be processed includes at least one storage box ID, and when the determination module determines the number of storage boxes required based on the information on orders to be processed, it specifically identifies a closest deadline based on the deadlines of each of the orders to be processed, identifies a target order based on the closest deadline, and determines the number of storage boxes required based on the number of storage box IDs in the target orders, the closest deadline representing the deadline closest to a current time, the time from the current time to the closest deadline is the first predetermined time, and the target order represents the order to be processed corresponding to the closest deadline.
[0018] Optionally, the workbench capacity information includes workbench category information indicating the category to which the storage box processed on the workbench belongs, and the determination module is further used to determine storage box category information indicating the category to which the storage box corresponding to each of the orders to be processed belongs based on the order information to be processed. When determining a target number of workbenches based on the required number of storage boxes and workbench capacity information, the determination module is used, specifically, to distribute the required number of storage boxes based on the storage box category information and the workbench category information to determine the number of storage boxes that need to be processed on each of the workbenches, and to determine a target number of workbenches corresponding to the category information of the workbench based on the number of storage boxes that need to be processed on each of the workbenches and the workbench capacity information corresponding to each of the workbenches. When generating workbench operation / stop information based on the target number of workbenches, specifically, the transmission module is used to generate workbench operation / stop information for instructing a user to operate or stop the workbench corresponding to the category information of the workbench based on the target number of workbenches corresponding to the category information of the workbench.
[0019] Optionally, the terminal device is a workbench, and the workbench operation / halt information includes operation information and pause information, and the transmission module is used, when generating the workbench operation / halt information based on the target number of work units, specifically, for generating operation information for instructing a user to operate the workbench if the target number of work units is greater than the current number of work units, and for generating pause information for instructing a user to pause the workbench if the target number of work units is smaller than the current number of work units, and when transmitting the workbench operation / halt information to the terminal device, specifically, for transmitting the operation information or pause information to the workbench for presentation.
[0020] As a third aspect, an electronic device provided in an embodiment of the present disclosure includes: A processor; Memory and ,and The memory includes stores program code, Processor is before The data stored in the memory Read the program code and First aspect of the disclosure Or the second aspect The worktable operation / stop recommendation method provided in the corresponding embodiment of execution vinegar do.
[0021] As a fourth aspect, a warehouse system provided in an embodiment of the present disclosure includes a workbench and an electronic device provided in an embodiment corresponding to the third aspect of the present disclosure, the workbench and the electronic device being communicatively connected.
[0022] As a fifth aspect, a computer-readable storage medium provided in an embodiment of the present disclosure stores computer-executable instructions, which, when executed by a processor, realizes a workbench operation / idle recommendation method provided in any embodiment corresponding to the first aspect of the present disclosure.
[0023] In a sixth aspect, an embodiment of the present disclosure provides a computer program product, comprising: Includes program code Computer Programs A product comprising: The computer program computer When executed by The program code The first aspect or Second Aspect and the first aspect Or the second aspect Various selectable methods for worktable operation / stop recommended methods Carry out do. Effect of the Invention
[0024] According to the worktable operation / stop recommendation method, device, electronic device, and warehouse system provided in the embodiment of the present disclosure, order information to be processed, which represents orders to be processed in the system and the deadlines corresponding to each of the orders to be processed, is acquired, and based on the order information to be processed, a target number of worktables representing the number of worktables required to finish processing the corresponding orders to be processed by the deadline is determined, and worktable operation / stop information is generated based on the target number of worktables, and the worktable operation / stop information is transmitted to a terminal device. Each order to be processed corresponds to at least one storage box. Since the order information to be processed is determined based on the order to be processed, the requirement of not allowing the order to be processed to exceed its deadline can be met by performing work on the worktables of the target number of worktables, and the worktable operation / stop information generated based on the target number of worktables can be used as recommended information for the user's worktable operation / stop operation, thereby improving the accuracy of the timing of the user's operation to operate / stop the worktable, and improving the work efficiency of the entire warehouse system. [Brief description of the drawings]
[0025] The following drawings are incorporated in and constitute a part of the specification, illustrate preferred embodiments of the disclosure, and together with the description, serve to explain the principles of the invention.
[0026] [Figure 1] FIG. 1 is a diagram illustrating an application scenario of the workbench operation / halt recommendation method provided in the embodiment of the present disclosure. [Diagram 2] FIG. 2 is a flowchart of a worktable operation / idle recommendation method provided in one embodiment of the present disclosure. [Diagram 3] FIG. 3 is a flowchart of a worktable operation / idle recommendation method provided in another embodiment of the present disclosure. [Figure 4]FIG. 4 is a flow chart of an alternative embodiment of step S202 in the embodiment shown in FIG. [Diagram 5] FIG. 5 is a flow chart of another embodiment that can be selected from step S202 in the embodiment shown in FIG. [Figure 6] FIG. 6 is a flow chart of an alternative embodiment of step S203 in the embodiment shown in FIG. [Figure 7] FIG. 7 is a schematic diagram of an example of determining a target number of work vehicles provided in an embodiment of the present disclosure. [Figure 8] FIG. 8 is a structural schematic diagram of a workbench operation / pause recommendation device provided in one embodiment of the present disclosure. [Figure 9] FIG. 9 is a schematic diagram of an electronic device provided in an embodiment of the present disclosure. [Figure 10] FIG. 10 is a structural schematic diagram of a warehouse system provided in one embodiment of the present disclosure.
[0027] The above figures show clear examples of the present disclosure, which will be described in more detail below. These figures and written description are not intended to limit the scope of the concept of the present disclosure in any way, but to explain the concept of the present disclosure to those skilled in the art by referring to specific examples. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0028] Exemplary embodiments will now be described in detail, examples of which are illustrated in the drawings. When referring to the drawings in the following description, the same reference numerals in different drawings refer to the same or similar elements unless otherwise stated. The embodiments described in the following exemplary embodiments are not representative of all embodiments consistent with the present disclosure. Rather, they are merely examples of apparatus and methods consistent with some aspects of the present disclosure, as detailed in the claims.
[0029] The following specific examples are used to describe in detail the technical means of the present disclosure and how the technical means of the present disclosure solves the above technical problems. The following specific examples can be combined with each other, and the same or similar concepts or processes may not be repeated in some examples. The following examples are described in detail in conjunction with the drawings.
[0030] First, application scenarios of the embodiments of the present disclosure will be described in detail.
[0031] FIG. 1 is a diagram of an application scene of the worktable operation / halt recommendation method provided in the embodiment of the present disclosure. As shown in FIG. 1, in the smart warehouse system 100, the warehouse robot 110 is controlled to transport the storage box 120 in the rack area, and the storage box 120 is carried to the worktable 130, and the operator or robot at the worktable 130 performs subsequent processing, such as taking out, sorting, packing, and the like, of the items in the storage box 120. In the prior art, the number of worktables 130 is adjusted to operate / halt according to specific needs, and when the order quantity is large, the operator operates the worktable 130 to increase the order processing capacity, and in the opposite case, the worktable 130 is halted to save the resources of the worktable. However, in the actual operating process, the warehouse system 100 cannot automatically identify the current optimal number of worktables, so it is difficult to determine the operation / halt timing of the worktable 130 by relying only on the operator's experience, which leads to problems such as insufficient processing capacity of the worktable or waste of resources, and affects the work efficiency of the entire warehouse system 100.
[0032] To solve this problem, the workbench operation / stop recommendation method provided in the embodiment of the present disclosure automatically determines the target number of work benches based on information on orders to be processed, generates workbench operation / stop information based on the target number of work benches and sends it to the terminal device, thereby prompting the operator to operate and stop the workbench, thereby increasing the rationality of the operation / stop timing of the workbenches and improving the work efficiency of the entire warehouse system.
[0033] 2 is a flowchart of a worktable operation / stop recommendation method provided in an embodiment of the present disclosure. Illustratively, the worktable operation / stop recommendation method can be applied to a smart warehouse system. As shown in FIG. 2, the worktable operation / stop recommendation method provided in an embodiment of the present disclosure includes the following steps:
[0034] In S101, information on orders to be processed is obtained. The information on orders to be processed is used to represent orders to be processed in the system and the deadlines corresponding to each of the orders to be processed. Each order to be processed corresponds to at least one storage box.
[0035] For example, the order information is data that records the orders in the system, and when the smart warehouse system receives information of new orders sent from the upstream device, the order information is updated accordingly, and the number of orders in the system is also increased. Furthermore, the order information includes a cut-off time corresponding to each order, and the system processes the orders according to the cut-off time, thereby ensuring that the orders are processed by the cut-off time. Here, each order includes at least one specific product, i.e., SKU, and each SKU corresponds to one or more storage boxes for storing the products. Thus, each processing order corresponds to at least one storage box.
[0036] In step S102, a target number of work units is determined based on the information on the orders to be processed. The target number of work units is used to indicate the number of work units required to process the corresponding orders to be processed by the deadline.
[0037] For example, the processing order information includes ID information of the orders to be processed and ID information of specific products included in each processing order. For example, the processing order information includes order to be processed 001 and order to be processed 002, where order to be processed 001 includes one product A1 and two products B4, and order to be processed 002 includes one product A2 and two products C1. Based on the related information in the processing order information, the ID information of the products included in each order can be identified, and further, based on the preset storage box arrangement information and the ID information of the products, the storage box corresponding to the products in each processing order can be identified.
[0038] Furthermore, the capacity of the work bench is evaluated by measuring the number of storage boxes processed, but since different orders to be processed have different corresponding deadlines, in order for all orders to be processed in the order information to be processed by the deadline, it is necessary to guarantee that the total capacity of the work bench can finish using up the storage boxes corresponding to each order by the deadline of each order.Then, the minimum number of work benches that can finish using up the storage boxes corresponding to each order by the deadline of each order is the target number of work benches.
[0039] For example, there are multiple methods for determining the target worktable, for example, the number of storage boxes that need to be processed within a certain time, i.e., the required number of storage boxes, is specified to ensure that the orders in the order information to be processed are processed by the deadline. Then, based on the processing capacity of one worktable, the number of worktables required to finish using up the required number of storage boxes, i.e., the target number of worktables, is determined. Also, for example, the average number of worktables at the current time is obtained from the operation history information recorded in the warehouse system, and the average number of worktables is determined as the target number of worktables. Here, it can be set according to specific needs.
[0040] In S103, workbench operation / stop information is generated based on the target number of workbenches, and the workbench operation / stop information is transmitted to the terminal device.
[0041] For example, the target number of work units is the number of work units that can realize that all the orders to be processed in the order information to be processed are processed by the deadline, and can be considered as the optimal number of work units. The warehouse system can obtain information on the operation and idleness of work units by comparing the target number of work units with the number of work units currently in operation.
[0042] More specifically, for example, if the target number of work units is larger than the current number of work units, operation information is generated to instruct the user to operate the work units, and if the target number of work units is smaller than the current number of work units, pause information is generated to instruct the user to pause the work units. This encourages the user to adjust the current number of work units, matches the current number of work units with the target number of work units, and achieves the optimal number of work units, thereby avoiding idle and wasting work units and further avoiding insufficient total capacity of the work units leading to overtime in order processing, thereby improving the work efficiency of the entire warehouse system.
[0043] Furthermore, optionally, the step of transmitting the workbench operation / stop information to the terminal device includes the warehouse system transmitting the operation information or stop information to the workbench and presenting the information to the operator via a presentation unit of the workbench, thereby notifying the operator to operate or stop the workbench. The presentation unit includes a display unit and / or an audio unit, and the presentation unit notifies the operator of the information in various ways, such as by displaying information and / or playing audio.
[0044] Furthermore, as an option, before operating all the work tables, the work table operation / idle information is determined, and then the system is set to operate a target number of work tables in advance based on the work table operation information (pre-operation means that the work table worker has not yet arrived at the work table), and after the pre-operation, the system transmits order information to the pre-operated work tables, and transmits a container transport task to the robot based on the transmitted order, and transports the container required for the order corresponding to the work table to the work table. The work table worker can start work immediately when he arrives at the workstation, and there is no need to wait for the container transport time, improving efficiency.
[0045] In the embodiment provided by the present disclosure, information on orders to be processed, which indicates orders to be processed in the system and the deadlines corresponding to each order to be processed, is acquired, and a target number of worktables, which indicates the number of worktables required to finish processing the corresponding orders to be processed by the deadline, is determined based on the information on orders to be processed, and worktable operation / stop information is generated based on the target number of worktables, and the worktable operation / stop information is sent to the terminal device. Here, each order to be processed corresponds to at least one storage box. Since the information on orders to be processed is determined based on the orders to be processed, the requirement of not allowing the orders to be processed to exceed their deadlines can be met by performing work on the worktables of the target number of worktables, and the worktable operation / stop information generated based on the target number of worktables can be used as recommended information for the user's worktable operation / stop operation, thereby improving the accuracy of the timing of the user's operation to operate and stop the worktables, and improving the work efficiency of the entire warehouse system.
[0046] 3 is a flowchart of a workbench operation / stop recommendation method provided in another embodiment of the present disclosure. The workbench operation / stop recommendation method provided in this embodiment is based on the embodiment shown in FIG. 2 and further subdivides step S102. As shown in FIG. 3, the workbench operation / stop recommendation method provided in this embodiment includes the following steps:
[0047] In S201, information on the order to be processed is obtained.
[0048] In S202, the number of storage boxes required is determined based on the information on the order to be processed.
[0049] In the embodiment shown in Fig. 2, a number of orders in the processing order information and the corresponding deadlines are identified based on the processing order information, and the number of storage boxes that need to be processed within a specified time, i.e., the required number of storage boxes, is determined and obtained. If the processing work for the required number of storage boxes can be completed within the specified time, it is guaranteed that the processing orders corresponding to all the processing order information will not exceed the time limit.
[0050] In an alternative embodiment, the order to be processed information includes at least two orders to be processed and deadlines corresponding to the orders to be processed, and each order to be processed includes at least one storage box ID. The storage box ID is used to distinguish and locate the storage box. The number of required storage boxes includes a first required number and a second required number, the first required number representing the number of storage boxes that need to be processed within a first predetermined time, and the second required number representing the number of storage boxes that need to be processed within a second predetermined time.
[0051] As shown in FIG. 4, the specific implementation process of step S202 may include the following steps:
[0052] At S2021, a first target order and a second target order are identified based on a cut-off time for each order to be processed. The first target order represents an order to be processed whose cut-off time and current time are separated by a first predetermined time or less, and the second target order represents an order to be processed whose cut-off time and current time are separated by a second predetermined time or less. The second predetermined time is greater than the first predetermined time.
[0053] In S2022, a first required quantity is determined based on the number of storage box IDs of the first target order, and a second required quantity is determined based on the number of storage box IDs of the second target order.
[0054] For example, the deadline of an order to be processed may refer to a specific time such as 6:00 p.m. on X / X / XX, and orders to be processed may be classified into orders with different degrees of urgency depending on the length of time from the current time to the deadline of the order to be processed. To specifically explain that the first target order refers to an order to be processed whose deadline and current time are equal to or shorter than a first predetermined time, for example, if the first predetermined time is two hours and the deadline and current time of order A are one hour apart, then order A is the first target order. Correspondingly, if the deadline and current time of order B are three hours apart, then order B is the second target order. The urgency of order B is lower than that of order A. Both the first target order and the second target order correspond to one or more orders to be processed.
[0055] Furthermore, a first required number is determined based on the orders to be processed corresponding to the first target order. The first required number is the sum of the number of storage box IDs calculated after collecting the storage box IDs in all the orders to be processed corresponding to the first target order. Note that the same storage box ID may be included in different orders to be processed. Therefore, the first required number may be less than or equal to the sum of the number of storage box IDs in each order to be processed. Correspondingly, a second required number is determined based on the orders to be processed corresponding to the second target order. The first required number and the second required number each represent the total number of storage boxes that need to be processed on the workbench within the corresponding time. In the subsequent target workbench number determination step, the corresponding first target workbench number and second target workbench number are determined for the first required number and the second required number, respectively, thereby achieving precise control of the workbench operation / stop timing, avoiding the problem of insufficient total processing capacity of the workbench due to a sudden increase in the order quantity in a certain time period, and improving the work stability and work efficiency of the workbench and warehouse system.
[0056] Optionally, in the steps of this embodiment, in addition to identifying the first and second target orders based on the deadlines of each order to be processed, multiple target orders such as a third target order and a fourth target order can be identified, thereby enabling control of the number of work tables in multiple time periods, further improving the precise control of the timing of work table operation and pause, and improving the work stability and work efficiency of the work table and warehouse system; however, examples will not be given here one by one.
[0057] In another alternative embodiment, the order to be processed information includes at least one order to be processed and a cut-off time corresponding to the order to be processed, and each order to be processed includes at least one storage box ID.
[0058] As shown in FIG. 5, the specific implementation process of step S202 may include the following steps:
[0059] In S2023, a closest deadline is identified based on the deadline of each order to be processed. The closest deadline represents the deadline closest to the current time, and the time from the current time to the closest deadline is a first predetermined time.
[0060] In S2024, a target order is identified based on the closest deadline. The target order is an order that needs to be processed and corresponds to the closest deadline.
[0061] In S2025, the number of storage boxes required is determined based on the number of storage box IDs in the target order.
[0062] For example, the closest deadline is the deadline closest to the current time. For example, suppose the interval between the deadline of order A and the current time is 1 hour, the interval between the deadline of order B and the current time is 2 hours, and the interval between the deadline of order C and the current time is 4 hours. In this case, the deadline of order A is closestIt is the deadline. Note that the closest deadline also changes constantly as time passes and orders are processed continuously. For example, the closest deadline 3 hours later is when the gap between the deadline of order C and the current time is 1 hour, and the deadline of order C is the closest to the current time among all the orders that need to be processed.
[0063] Furthermore, a target order is identified based on the order to be processed that corresponds to the closest deadline. The target order may correspond to one or more orders to be processed. The storage box IDs in all the target orders are collected, and the sum of the numbers of storage box IDs is calculated and determined as the required number of storage boxes. In the subsequent step of determining the target number of work units, if the target number of work units is determined based on the required number of storage boxes, it is guaranteed that the orders within the closest deadline will be processed on time and the deadline will not be exceeded.
[0064] In this embodiment, the steps obtain the corresponding target orders within the nearest deadline, and determine the number of storage boxes required based on the target orders, so that each order to be processed is placed in the time interval up to the nearest deadline, and the number of worktables required can be dynamically determined, thereby determining accurate recommendations for the operation and idle information of the worktable, and improving the work stability and work efficiency of the worktable and warehouse system.
[0065] In S203, a target number of work benches is determined based on the required number of storage boxes and the work bench capacity information, which indicates the number of storage boxes that one work bench can consume within a unit time.
[0066] Step S203 further includes a step of obtaining workbench digestion capacity information, specifically including the following steps:
[0067] Acquire ID information of the workbench, acquire target work history records of the workbench based on the ID information of the workbench, and determine workbench consumption capacity information based on the work history records.
[0068] For example, the workbench consumption capacity information is information representing the capacity of one workbench to process and consume storage boxes, specifically, for example, 100 boxes / hour / unit. By identifying the ID information of the workbench, it is possible to obtain the work history record of the workbench with the corresponding ID information, for example, the total amount of storage boxes consumed by the workbench per day in the past week, or the total amount of storage boxes consumed by the workbench per hour in the past day. Then, by correspondingly calculating the amount of storage boxes consumed within a unit time, the workbench consumption capacity information can be determined.
[0069] In this embodiment, the work history records of each work platform are obtained to determine the accurate firefighting capacity information of each work platform. Each work platform has different firefighting capacity depending on factors such as the level and experience of the operator, so the accuracy of the evaluation of the firefighting capacity of the work platform can be improved based on the work history records of the work platform, and the accuracy of the firefighting capacity information of the work platform can be improved by improving the accuracy of the operation and stoppage information of the work platform.
[0070] For example, different types of storage boxes processed on each work station have different corresponding work station digestion capacity information. Therefore, optionally, the work station digestion capacity information includes work station category information. The work station category information indicates a category to which the storage box processed on the work station belongs, and step S203 further includes a step of determining storage box category information based on the order information to be processed, and the storage box category information indicates a category to which the storage box corresponding to each order to be processed belongs.
[0071] Furthermore, the step of determining the target number of work tables based on the required number of storage boxes and the work table capacity information includes a step of distributing the required number of storage boxes based on the storage box category information and the work table category information to determine the number of storage boxes that need to be processed at each work table, and a step of determining the target number of work tables for the work tables corresponding to the work table category information based on the number of storage boxes that need to be processed at each work table and the work table capacity information corresponding to each work table. Furthermore, in the process of generating work table operation / stop information based on the subsequent target number of work tables, work table operation / stop information is generated for instructing the user to operate or stop the work table corresponding to the work table category information, thereby achieving accurate recommendation of operation / stop of work tables of different categories and improving the work efficiency of the entire warehouse system.
[0072] In this embodiment, the number of storage boxes that need to be processed at each workbench is determined based on the storage box category information and workbench category information, and the target number of workbenches for each workbench is determined based on the number of storage boxes that need to be processed at each workbench and the workbench capacity information corresponding to each workbench. This allows for more detailed operation / stop management of different types of workbenches, and further improves the work stability and work efficiency of the workbench and warehouse system.
[0073] Further, in an alternative embodiment, the target number of work units includes a first number of work units and a second number of work units. As shown in FIG. 6, a specific embodiment of step S203 includes the following steps:
[0074] In S2031, a first number of work tables is determined based on the first required number and the work table digestion capacity information, and a second number of work tables is determined based on the second required number and the work table digestion capacity information.
[0075] In S2032, if the first number of work units is equal to or greater than the second number of work units, the first number of work units is determined as the target number of work units, and if the first number of work units is smaller than the second number of work units, the second number of work units is determined as the target number of work units.
[0076] Illustratively, FIG. 7 is a schematic diagram of an example of determining the target number of work units provided in the embodiment of the present disclosure. As the number of orders to be processed in the system changes, the number of orders required in the corresponding time slot and the target number of work units in the corresponding time slot also change. As shown in FIG. 7, the predetermined time is set as a point of time one hour after the current time, the number of storage boxes corresponding to the orders to be processed within one hour is set as the first required number, and the number of storage boxes corresponding to the orders to be processed within three hours is set as the second required number. Correspondingly, the number of work units required within one hour is determined as the first number of work units based on the work table digestion capacity information and the first required number. Also, the number of work units required within three hours is determined as the second number of work units based on the work table digestion capacity information and the second required number. If the first number of work units is greater than the second number of work units, it means that there are many storage boxes that need to be digested one hour from the present, and the number of orders will be fewer one hour later, so the first number of work units is set as the target number of work units to ensure that orders with a deadline within one hour can be processed. In addition, since the number of first worktables is larger and the total digestion capacity of the worktables is also higher, orders within 3 hours can be digested, and there is no problem of too many orders exceeding the total digestion capacity. Conversely, if the number of second worktables is larger than the number of first worktables, it means that there are fewer storage boxes to be digested in the hour from now, and the number of orders will increase after one hour, so the second number of worktables is set as the target number of worktables to ensure that orders with a deadline of less than 3 hours can be processed. Since the number of second worktables is larger and the total digestion capacity of the worktables is also higher, orders within 1 hour can be digested. The above scheme ensures that there will be no problem of insufficient digestion capacity due to too few worktables under any circumstances, and guarantees that order processing time will not exceed the limit, thereby improving the stability of the warehouse system.
[0077] In S204, workbench operation / stop information is generated based on the target number of workbenches corresponding to the workbench category information, and the workbench operation / stop information is transmitted to the terminal device. The workbench operation / stop information is used to instruct the user to operate or stop the workbench corresponding to the workbench category information.
[0078] In the steps of this embodiment, the embodiment of step S204 is the same as the embodiment of step S103 in the embodiment shown in FIG. 2, so it will not be described again here.
[0079] 8 is a structural schematic diagram of a platform operation / pause recommendation device provided in an embodiment of the present disclosure. As shown in FIG. 8, the platform operation / pause recommendation device 3 includes an acquisition module 31, a determination module 32 and a sending module 33.
[0080] The acquisition module 31 is used for acquiring order information representing orders to be processed in the system and deadlines corresponding to each order to be processed, where each order to be processed corresponds to at least one storage box.
[0081] The determination module 32 is used to determine a target number of worktables based on the order information, where the target number of worktables represents the number of worktables required to finish processing the corresponding order by the deadline.
[0082] The transmission module 33 is used to generate workbench operation / stop information based on the target number of workbenches and to transmit the workbench operation / stop information to a terminal device.
[0083] Optionally, the determination module 32 is specifically used to determine the number of storage boxes required according to the order information to be processed, and determine the target number of work units according to the number of storage boxes required and the workbench capacity information. The number of storage boxes required represents the number of storage boxes that need to be processed within a first predetermined time, and the workbench capacity information represents the number of storage boxes that one workbench consumes within a unit time.
[0084] Optionally, the acquisition module 31 is further used for acquiring ID information of the workbench, acquiring a workbench-related work history record based on the ID information of the workbench, and determining workbench digestive capacity information based on the work history record.
[0085] Optionally, the order information includes at least two orders to be processed and deadlines corresponding to the orders to be processed, and each order to be processed includes at least one storage box ID. The number of required storage boxes includes a first required number and a second required number, the first required number representing the number of storage boxes that need to be processed within a first predetermined time, and the second required number representing the number of storage boxes that need to be processed within a second predetermined time. When the determination module 32 determines the number of required storage boxes based on the order information to be processed, specifically, the determination module 32 identifies a first target order and a second target order based on the deadlines of each order to be processed, determines the first required number based on the number of storage box IDs of the first target order, and determines the second required number based on the number of storage box IDs of the second target order. Here, the first target order represents an order to be processed whose interval between the deadline time and the current time is equal to or shorter than the first predetermined time, and the second target order represents an order to be processed whose interval between the deadline time and the current time is equal to or shorter than the second predetermined time, and the second predetermined time is longer than the first predetermined time. When the determination module 32 determines the target number of work units based on the required number of storage boxes and the workbench capacity information, specifically, it determines a first number of work units based on a first required number and the workbench capacity information, and determines a second number of work units based on a second required number and the workbench capacity information; if the first number of work units is equal to or greater than the second number of work units, it determines the first number of work units as the target number of work units; if the first number of work units is smaller than the second number of work units, it determines the second number of work units as the target number of work units.
[0086] Optionally, the information on orders to be processed includes at least one order to be processed and a cut-off time corresponding to the order to be processed, and each order to be processed includes at least one storage box ID. When the determination module 32 determines the number of storage boxes required based on the information on orders to be processed, the determination module 32 specifically identifies the closest cut-off time based on the cut-off time of each order to be processed, identifies a target order based on the closest cut-off time, and determines the number of storage boxes required based on the number of storage box IDs in the target order. Here, the closest cut-off time represents the cut-off time closest to the current time, the time from the current time to the closest cut-off time is a first predetermined time, and the target order represents the order to be processed corresponding to the closest cut-off time.
[0087] Optionally, the workbench capacity information includes workbench category information representing the category to which the storage box processed by the workbench belongs, and the determination module 32 is further used to determine storage box category information representing the category to which the storage box corresponding to each order to be processed belongs based on the order to be processed information. When the determination module 32 determines the target number of workbenches based on the required number of storage boxes and the workbench capacity information, specifically, the determination module 32 distributes the storage boxes of the required number of storage boxes based on the storage box category information and the workbench category information to determine the number of storage boxes that need to be processed by each workbench, and determines the target number of workbenches corresponding to the category information of the workbench based on the number of storage boxes that need to be processed by each workbench and the workbench capacity information corresponding to each workbench. When the transmission module 33 generates the workbench operation / stop information based on the target number of workbenches, specifically, the transmission module 33 generates workbench operation / stop information for instructing the user to operate or stop the workbench corresponding to the category information of the workbench based on the target number of workbenches corresponding to the category information of the workbench.
[0088] Optionally, the terminal device is a workbench, the workbench operation / halt information includes operation information and pause information, and when the sending module 33 generates the workbench operation / halt information based on the target number of workbenches, specifically, when the target number of workbenches is greater than the current number of workbenches, it generates operation information for instructing the user to operate the workbench, and when the target number of workbenches is less than the current number of workbenches, it generates pause information for instructing the user to pause the workbench. When the sending module sends the workbench operation / halt information to the terminal device, specifically, it sends the operation information or pause information to the workbench for presentation.
[0089] 9 is a schematic diagram of an electronic device provided in an embodiment of the present disclosure. As shown in FIG. 9, an electronic device 4 provided in this embodiment includes a memory 41, a processor 42, and a computer program.
[0090] The computer program is stored in the memory 41 and configured to be executed by the processor 42 to realize the workbench operation / idle recommendation method provided in any one of the embodiments corresponding to Figures 2 to 6 of the present disclosure.
[0091] The memory 41 and the processor 42 are connected via a bus 43 .
[0092] The relevant description can be understood by referring to the relevant descriptions and effects corresponding to the steps in the embodiments corresponding to FIGS. 2 to 7, and therefore will not be described again here.
[0093] 10 is a structural schematic diagram of a warehouse system provided in an embodiment of the present disclosure. As shown in FIG. 10, the warehouse system includes a warehouse robot 1010, a warehouse management device 1020, and a workbench 1030.
[0094] The warehouse management equipment 1020 is used to control the warehouse robot 1010 to transport the storage box to the workbench 1030 and to transmit a workbench operation / stop recommendation method to the workbench 1030. The warehouse management equipment 1020 is the electronic device 4 in the embodiment shown in FIG.
[0095] A computer-readable storage medium provided in one embodiment of the present disclosure stores a computer program, and the computer program is executed by a processor to realize a workbench operation / idle recommendation method provided in any one of the embodiments corresponding to Figures 2 to 7 of the present disclosure.
[0096] The computer readable storage medium may be a ROM, a random access memory (RAM), a CD-ROM, a magnetic tape, a floppy disk, an optical data storage device, and so on.
[0097] A computer program product provided in one embodiment of the present disclosure includes a computer program, which is executed by a processor to realize a workbench operation / idle recommendation method provided in any one of the embodiments corresponding to Figures 2 to 7 of the present disclosure.
[0098] It is understood that the devices and methods disclosed in some embodiments provided by the present disclosure can be realized in other forms. For example, the above device embodiments are merely illustrative, and the division of modules is a kind of logical functional division, and other division methods may be used in actual implementation. For example, multiple modules or assemblies may be combined or integrated into another system, or some features may be omitted or not implemented. Note that the couplings, direct couplings, or communication connections between the devices shown or discussed may be indirect couplings or communication connections via some interface, device, or module, and may be electrical, mechanical, or other forms.
[0099] The modules described as separate components may or may not be physically separate. The components shown as modules may or may not be physical units, and may be located in one place or distributed among multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of the present embodiment.
[0100] In addition, each functional module in each embodiment of the present disclosure may be integrated into one processing unit, each module may exist physically independent, or two or more modules may be integrated into one unit. The unit consisting of the above modules may be realized in the form of hardware, or may be realized using a form in which a software functional unit is added to hardware.
[0101] The integrated module realized in the form of the above software function module may be stored in a computer-readable storage medium. The above software function module is stored in a storage medium and includes some instructions for making a computer device (which may be a personal computer, a server, or a network device, etc.) or a processor execute some steps of the method of each embodiment of the present disclosure.
[0102] The processor may be a central processing unit (CPU), other general-purpose processor, digital signal processor (DSP), application specific integrated circuit (ASIC), etc. The general-purpose processor may be a microprocessor, or the processor may be any ordinary processor, etc. The steps of the combination of the method disclosed in the invention may be directly embodied and executed as a processor of hardware, or may be executed and completed using a combination of hardware and software modules in a processor.
[0103] The memory may include a high-speed RAM, and may further include a non-volatile memory NVM, such as at least one magnetic disk memory, and may further be a U disk, a mobile hard disk, a ROM, a magnetic disk, an optical disk, and so on.
[0104] The bus may be an Industry Standard Architecture (ISA) bus, a Peripheral Component Interconnect (PCI) bus, an Extended Industry Standard Architecture (EISA) bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. For convenience of illustration, the buses in the figures of this disclosure are not limited to having only one bus or one type of bus.
[0105] The memory may be implemented by any type of volatile or non-volatile storage device, such as, for example, Static Random Access Memory (SRAM), Electrically Erasable and Programmable Read Only Memory (EEPROM), Programmable Read Only Memory (PROM), Read Only Memory (ROM), magnetic memory, flash memory, magnetic disk, optical disk, or any combination thereof. The storage media may be any available media that can be accessed by a general purpose or special purpose computer.
[0106] An example storage medium may be coupled to the processor such that the processor can read information from and write information to the storage medium. Of course, the storage medium may be a component of the processor. The processor and the storage medium may be located in an Application Specific Integrated Circuit (ASIC). Of course, the processor and the storage medium may reside as separate components in an electronic device or a main control device.
[0107] Those skilled in the art can understand that all or part of the steps of each of the above method embodiments can be achieved by hardware related to program instructions. The above program may be stored in a computer-readable storage medium. When the program is executed, the steps of each of the above method embodiments are executed, and the storage medium includes various media that can store program codes, such as ROM, RAM, magnetic disk, optical disk, etc.
[0108] Finally, the above examples are used only to explain the technical scheme of the present disclosure, and are not intended to be limiting. In addition, the present disclosure has been described in detail with reference to the above examples, but those skilled in the art can understand that the technical scheme described in the above examples can be further modified or equivalently replaced with some or all of the technical features. However, these modifications or replacements do not cause the essence of the technical scheme to deviate from the scope of the technical scheme of each example of the present disclosure.
[0109] The above are merely specific embodiments of the present disclosure, and the scope of protection of the present disclosure is not limited thereto. Any modifications or replacements that a person skilled in the art can easily think of within the technical scope of the present disclosure should be included in the scope of protection of the present disclosure. Therefore, the scope of protection of the present disclosure should be equivalent to the scope of protection of the "claims".
Claims
1. A workbench operation / stop recommendation method executed by a workbench operation / stop recommendation device, comprising: obtaining order information representing orders in the system that need to be processed and a cut-off time corresponding to each of the orders that need to be processed; determining a target number of worktables based on the order-to-be-processed information, the target number of worktables representing the number of worktables required to finish processing the corresponding order-to-be-processed by the deadline; A step of comparing the target number of work platforms with the number of work platforms currently in operation to generate work platform operation / stop information, and transmitting the work platform operation / stop information to a terminal device, Each of the orders to be processed corresponds to at least one storage box; The storage box is a box in which an item is placed and which is moved to the workbench during work, Each of the orders to be processed includes at least one specific product, and the specific product corresponds to one storage box for storing the product; The step of determining a target number of work units based on the order information to be processed includes: determining a number of storage boxes required based on the order information; determining the target number of work tables based on the required number of storage boxes and work table digestion capacity information; The number of required storage boxes represents the number of storage boxes that need to be processed within a predetermined time period; The workbench consumption capacity information indicates the number of storage boxes that one workbench consumes within a unit time.
2. acquiring ID information of the workbench; obtaining a work history record of the work bench based on ID information of the work bench; and determining the workbench capacity information based on the work history record. The workbench operation / shutdown recommendation method according to claim 1.
3. The processing order information includes at least two processing orders, each of which includes at least one storage box ID, the number of required storage boxes includes a first required number and a second required number, the first required number representing the number of storage boxes that need to be processed within a first predetermined time, and the second required number representing the number of storage boxes that need to be processed within a second predetermined time, The step of determining the number of storage boxes required based on the order information to be processed includes: identifying a first target order and a second target order based on a cut-off time for each of the orders to be processed; determining the first required quantity based on the number of storage box IDs of the first target order, and determining the second required quantity based on the number of storage box IDs of the second target order; the first target order represents an order to be processed whose deadline and current time are separated by a first predetermined time or less, and the second target order represents an order to be processed whose deadline and current time are separated by a second predetermined time or less, The second predetermined time is longer than the first predetermined time, and the step of determining a target number of work benches based on the required number of storage boxes and the work bench consumption capacity information includes: determining a first number of work benches based on the first required number and the work bench capacity information; determining a second number of work benches based on the second required number and the work bench capacity information; When the first number of work platforms is equal to or greater than the second number of work platforms, the first number of work platforms is determined to be the target number of work platforms, and when the first number of work platforms is smaller than the second number of work platforms, the second number of work platforms is determined to be the target number of work platforms.
3. A method for recommending operation / stop of a workbench according to claim 1 or 2.
4. The processing order information includes at least one processing order, each of the processing orders including at least one storage box ID; The step of determining the number of storage boxes required based on the order information to be processed includes: identifying a closest deadline based on the deadlines of each of the orders to be processed; identifying a target order based on the closest cut-off time; determining the required number of storage boxes based on the number of storage box IDs in the target order; the closest deadline time represents a deadline time closest to a current time, and the time from the current time to the closest deadline time is the predetermined time; the target order represents an order to be processed that corresponds to the closest cut-off time; 3. A method for recommending operation / stop of a workbench according to claim 1 or 2.
5. The workbench digestion capacity information includes workbench category information indicating a category to which the storage box processed by the workbench belongs, and the workbench operation / suspension recommendation method further includes: determining storage box category information representing a category to which a storage box corresponding to each of the orders to be processed belongs based on the order information to be processed; The step of determining a target number of work tables based on the required number of storage boxes and work table digestion capacity information includes: A step of allocating the required number of storage boxes based on the storage box category information and the workbench category information to determine the number of storage boxes that need to be processed on each of the workbenches; A step of determining a target number of work tables corresponding to the category information of the work table based on the number of storage boxes that need to be processed on each of the work tables and the work table digestion capacity information corresponding to each of the work tables, The step of generating workbench operation / stop information based on the target number of workbenches includes: generating workbench operation / halt information for instructing a user to operate or halt the workbench corresponding to the category information of the workbench based on a target number of workbenches corresponding to the category information of the workbench, The workbench operation / stop recommendation method according to any one of claims 1 to 4.
6. The terminal device is a workbench, and the workbench operation / stop information includes operation information or stop information; The step of generating workbench operation / stop information based on the target number of workbenches includes: When the target number of work tables is greater than the current number of work tables, generating operation information for instructing a user to operate the work tables, and when the target number of work tables is less than the current number of work tables, generating suspension information for instructing a user to suspend the work tables, The step of transmitting the workbench operation / stop information to the terminal device includes: A step of transmitting the operation information or the stop information to the worktable and presenting the information, The workbench operation / stop recommendation method according to any one of claims 1 to 5.
7. A processor and a memory are included. the memory stores program code; The processor reads out the program code stored in the memory and executes the workbench operation / halt recommendation method according to any one of claims 1 to 6. electronic equipment.
8. a work table and the electronic device according to claim 7, wherein the work table and the electronic device are communicatively connected to each other; Warehouse system.
9. A computer-readable storage medium having computer-executable instructions stored thereon, the computer-executable instructions being executed by a processor to implement the workbench operation / idle recommendation method according to any one of claims 1 to 6. A computer-readable storage medium.
10. A computer program comprising a program code, the program code being executed by a computer to realize the workbench operation / stop recommendation method according to any one of claims 1 to 6. Computer program.
Citation Information
Patent Citations
Article sorting device
JP1999011616A
Inventory scheduling method and device and non-transitory computer-readable storage medium
JP2021507859A
Automated system for transporting payloads
US20190168964A1