Transport system and control method thereof

The conveyance system optimizes power distribution and vehicle allocation by using a track-based power supply and controller to manage battery charge levels, addressing inefficiencies in existing systems and ensuring continuous operation.

JP7595629B2Active Publication Date: 2024-12-06SYSTEM ENGINEERING MEGA SOLUTION CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2022188869
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2022-04-11
Filing Date
2022-11-28
Publication Date
2024-12-06
Estimated Expiration
2042-11-28

AI Technical Summary

Technical Problem

Existing conveyance systems face challenges in efficiently allocating work to a large number of conveyance vehicles that operate using electric power provided through trucks, necessitating a method for controlling the transport system to optimize power usage and vehicle allocation.

Method used

A conveyance system with a first track and power supply installed on a rail, along with a controller that allocates work to multiple transport vehicles, including moving vehicles between tracks based on battery charge levels and power availability to optimize power usage and vehicle operation.

Benefits of technology

The system efficiently manages power distribution and vehicle allocation, preventing overload and ensuring continuous operation by reallocating vehicles and adjusting charging speeds, thereby optimizing the use of electric power and battery resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007595629000001
    Figure 0007595629000001
  • Figure 0007595629000002
    Figure 0007595629000002
  • Figure 0007595629000003
    Figure 0007595629000003
Patent Text Reader

Abstract

To provide a conveyance system of efficiently allocating operations to a number of conveying carriages operated by receiving power supply via a track.SOLUTION: A conveyance system comprises: a first track installed on a rail; a first power feeder for feeding power to the first track; a number of conveying carriages each moving along the rail and provided with a battery therein, for charging the battery by receiving power supply from the first track; and a controller for allocating operations of a number of the conveying carriages based on a first allowable power in the first track.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a transport system and a control method thereof. [Background technology]

[0002] In the manufacturing process of semiconductor devices, substrates may be transported by an automated guided transport system. In particular, the automated guided transport system may include a transport vehicle (e.g., an overhead hoist transport (OHT), a rail guided vehicle (RGV), etc.) configured to be movable along rails installed on the ceiling or floor of a clean room. A track that supplies power is installed on the rails, and the transport vehicle operates by receiving power from the track in a non-contact manner. Summary of the Invention [Problem to be solved by the invention]

[0003] An object of the present invention is to provide a transport system that efficiently allocates work to a large number of transport vehicles that operate by receiving power via a track.

[0004] Another object of the present invention is to provide a method for controlling the above-mentioned transport system.

[0005] The object of the present invention is not limited to the above-mentioned objects, and other objects not mentioned herein will be clearly understood by those skilled in the art from the following description. [Means for solving the problem]

[0006] One aspect of the transport system of the present invention for achieving the above object includes a first track installed on a rail, a first power supplier that supplies power to the first track, a number of transport vehicles that move along the rail, have batteries installed therein, and receive power from the first track to charge the batteries, and a controller that allocates work to the multiple transport vehicles based on a first allowable power on the first track.

[0007] Another aspect of the transport system of the present invention for achieving the above object includes a track mounted on rails, a power supplier for supplying power to the track, a number of transport vehicles that move along the rails and have batteries installed therein, receiving power from the track to charge the batteries, and a controller for allocating work to the multiple transport vehicles, wherein when the number of transport vehicles located on the track is the maximum number to be charged, the controller controls a first transport vehicle among the multiple transport vehicles located on the track to operate only on battery power, enters a second transport vehicle into the track, and moves a third transport vehicle among the multiple transport vehicles located on the track to another track, thereby ending the first transport vehicle from operating only on battery power.

[0008] In one aspect of a manufacturing method for a conveying system of the present invention to achieve the other object, a conveying system is provided including a first track installed on a rail, a first power supplier supplying power to the first track, and a number of conveying carts moving along the rail and having batteries installed therein, and when a first allowable power of the first track is greater than the first reference power, a conveying cart having a charge amount smaller than a second reference charge amount is caused to enter the first track, and when the first allowable power of the first track is smaller than the second reference power, a conveying cart positioned on the first track and having a charge amount smaller than the second reference charge amount is caused to move to another track.

[0009] Specific details of other embodiments are included in the detailed description and drawings. [Brief description of the drawings]

[0010] [Figure 1] FIG. 1 is a block diagram illustrating a transport system according to some embodiments of the present invention. [Diagram 2] FIG. 2 is a schematic diagram illustrating the transport system of FIG. [Diagram 3] FIG. 1 is a conceptual diagram for explaining a track installed on a rail. [Figure 4] FIG. 2 is a block diagram for explaining the structure of the transport platform vehicle shown in FIG. [Diagram 5] 4 is a flowchart for explaining a control method of the transport system according to the embodiment of the present invention. [Figure 6] FIG. 4 is a diagram for explaining a method for calculating the first allowable power. [Figure 7] FIG. 4 is a diagram for explaining a section to which the first allowable power belongs. [Figure 8] FIG. 13 is a diagram for explaining a section to which the charge amount of the transporting platform vehicle belongs. [Figure 9] 11 is a diagram for explaining a work allocation method when the first allowable power falls within the power sufficient section EPS. FIG. [Figure 10] 11 is a diagram for explaining a work allocation method when the first allowable power falls within the power sufficient section EPS. FIG. [Figure 11] 11 is a diagram for explaining a work allocation method when the first allowable power belongs to a power shortage section SPS. FIG. [Figure 12] 11 is a diagram for explaining a work allocation method when the first allowable power belongs to a power shortage section SPS. FIG. [Figure 13] 11 is a diagram for explaining a work allocation method when the first allowable power belongs to a power shortage section SPS. FIG. [Figure 14] 13 is a diagram for explaining a work allocation method when the first allowable power belongs to the maximum power usage section FPS. FIG. [Figure 15] FIG. 11 is a diagram for explaining a control method of a conveyance system according to another embodiment of the present invention. [Figure 16]FIG. 11 is a diagram for explaining a control method of a conveyance system according to another embodiment of the present invention. [Figure 17] 11 is a flowchart illustrating a method of controlling a transport system according to still another embodiment of the present invention. [Figure 18] 11 is a flowchart illustrating a method of controlling a transport system according to still another embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. Advantages and features of the present invention, as well as methods for achieving the same, will become apparent from the following detailed embodiments in conjunction with the accompanying drawings. However, the present invention is not limited to the embodiments disclosed below, and may be realized in various different forms. The present embodiments are provided merely to complete the disclosure of the present invention and to fully inform those skilled in the art of the present invention of the scope of the invention, and the present invention is defined only by the scope of the claims. The same reference symbols refer to the same elements throughout the specification.

[0012] Spatially relative terms such as "below," "beneath," "lower," "above," "upper," and the like, are used to facilitate describing the relationship of one element or component to another element or component as depicted in the drawings. Spatially relative terms should be understood to include different orientations of the elements in use or operation in addition to the orientation depicted in the drawings. For example, if an element depicted in the drawings is flipped over, an element described as "below" or "beneath" another element may be placed "above" the other element. Thus, the exemplary term "below" can include both an orientation of below and above. Elements may be oriented in other directions, so the spatially relative terms can be interpreted according to the orientation.

[0013] Although the terms "first" and "second" are used to describe various elements, components, and / or sections, it is understood that these elements, components, and / or sections are not limited by these terms. These terms are used merely to distinguish one element, component, or section from another element, component, or section. Thus, it is understood that a first element, first component, or first section referred to below may be a second element, second component, or second section within the technical spirit of the present invention.

[0014] Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings. In the description with reference to the accompanying drawings, the same reference numbers will be given to the same or corresponding components regardless of the drawing numbers, and duplicate descriptions related thereto will be omitted.

[0015] Fig. 1 is a block diagram for explaining a conveying system according to some embodiments of the present invention. Fig. 2 is a schematic diagram showing the conveying system of Fig. 1. Fig. 3 is a conceptual diagram for explaining tracks installed on rails. Fig. 4 is a block diagram for explaining the structure of the conveying platform shown in Fig. 1.

[0016] First, referring to FIG. 1 and FIG. 2, a transport system according to some embodiments of the present invention includes a controller (or OHT Control System, 10), a number of transport vehicles 20, and rails 40.

[0017] The rail 40 is installed in a semiconductor manufacturing line. The rail 40 is installed on the ceiling of the semiconductor manufacturing line, but is not limited to this.

[0018] The transport vehicle 20 moves along the rail 40 to carry a container in which substrates are stored. The transport vehicle 20 may be, for example, an overhead hoist transport (OHT), but is not limited thereto. The container to be transported may be, for example, a front opening unified pod (FOUP), but is not limited thereto.

[0019] The transport vehicle 20 and the controller 10 can interface with each other by wireless communication. The controller 10 provides instructions according to the work process to the transport vehicle 20. Specifically, the controller 10 searches for the shortest route from the starting point to the destination so that the transport work can be completed efficiently, selects the transport vehicle 20 in the optimal position for performing the transport work, and provides the transport command.

[0020] Now, referring to FIG. 3, a rail 40 is provided with a number of tracks T1, T2.

[0021] The multiple tracks T1, T2 include a first track T1 and a second track T2. The first track T1 and the second track T2 may be physically separated from each other. A first power supply PSU1 is connected to the first track T1 and supplies power PW1 to the first track T1. A second power supply PSU2 is connected to the second track T2 and supplies power PW2 to the second track T2.

[0022] The transport vehicle 20 receives power PW1, PW2 from the first truck T1 and / or the second truck T2 in a non-contact manner. The transport vehicle 20 can use the supplied power PW1, PW2 to perform loading / unloading operations, traveling operations, accelerating operations, standby operations, etc., and can charge the internal battery.

[0023] FIG. 3 illustrates an example in which two trucks T1 and T2 are installed, but the present invention is not limited to this.

[0024] The unit length of the track T1 can be determined taking into consideration the capacity of the power supply PSU1 that supplies power to the track (e.g., T1), the number of transport vehicles 20 that can simultaneously receive power from the track T1, the arrangement and structure of the rail 40, etc. As the overall length of the rail 40 increases, the number of tracks to be installed also increases. For example, assume that the unit length of the track is 50 m. If the rail 40 is 100 m, two tracks can be installed, if the rail 40 is 150 m, three tracks can be installed, and if the rail 40 is 200 m, four tracks can be installed.

[0025] Now referring to FIG. 4, the transport vehicle 20 includes a microcontroller 22, a gripping unit 23, a communication unit 24, a traveling unit 25, a power receiving unit 26, a battery 28, and the like.

[0026] The gripping unit 23 is for gripping the container, and the traveling unit 25 is for moving the transport vehicle 20 along the rail 40. The communication unit 24 is for communicating with a controller (see 10 in FIG. 1), and the power receiving unit 26 is for receiving the supply of power PW1, PW2 from the trucks T1, T2. The battery 28 is for charging the power PW1, PW2 supplied from the trucks T1, T2. The microcontroller 22 controls the gripping unit 23, the communication unit 24, the traveling unit 25, the power receiving unit 26, the battery 28, etc.

[0027] The transport vehicle 20 receives instructions from the controller 10 via the communication unit 24. The instructions may include, for example, a movement instruction, a transportation instruction, a power mode instruction, a charging method instruction, etc. The movement instruction is an instruction to move to a position specified by the controller 10, and the transportation instruction is an instruction to pick up a container at a departure point and move it to a destination. The power mode instruction may be an instruction to operate by receiving power PW1, PW2 from the trucks T1, T2, or to operate only with the power charged in the battery 28 without receiving power PW1, PW2 from the trucks T1, T2, or to use all of the power PW1, PW2 supplied from the trucks T1, T2 and the power charged in the battery 28. In addition, the charging method instruction is related to the charging speed of the battery 28, and may indicate charging the battery 28 at a reference charging speed, charging the battery 28 at a charging speed slower than the reference charging speed, or charging the battery 28 at a charging speed faster than the reference charging speed, etc. The microcontroller 22 interprets these instructions from the controller 10 and controls the other units 23, 24, 25, 26, 28 etc. in accordance with the instructions.

[0028] Furthermore, the microcontroller 22 can provide the current state of the transport vehicle 20 to the controller 10 via the communication unit 24. The current state of the transport vehicle 20 can include, for example, at least one of a loading / unloading state, a traveling state, an accelerating state, and a waiting state. Optionally, the current state of the transport vehicle 20 can further include at least one of a charge amount of the battery 28, a charging speed of the battery 28, and a discharge amount (i.e., a usage amount) of the battery 28.

[0029] 1 to 4 again, a number of transport vehicles 20 move along rails 40. In addition, among the multiple transport vehicles 20, some of the transport vehicles 20 may be positioned on a first track T1, and other some of the transport vehicles 20 may be positioned on a second track T2.

[0030] The controller 10 can allocate the work of the multiple transport vehicles 20 based on at least one of the first allowable power in the first track T1 and the second allowable power in the second track T2. The first allowable power indicates the amount of power that can be further used in the first track T1, and the second allowable power indicates the amount of power that can be further used in the second track T2. For example, the controller 10 can move the transport vehicles 20 located in the first track T1 and satisfying a preset condition to the second track T2, adjust the charging speed of the transport vehicles 20 located in the first track T1, or selectively allow the transport vehicles 20 satisfying a preset condition to enter the first track T1 based on at least one of the first allowable power and the second allowable power.

[0031] A method for allocating tasks to a large number of transport vehicles 20 will be described below with reference to FIGS.

[0032] Fig. 5 is a flow chart for explaining a method for controlling a transportation system according to an embodiment of the present invention. Fig. 6 is a diagram for explaining a method for calculating the first allowable power. Fig. 7 is a diagram for explaining a section to which the first allowable power belongs. Fig. 8 is a diagram for explaining a section to which the charge amount of the transportation vehicle belongs. Figs. 9 and 10 are diagrams for explaining a method for allocating work when the first allowable power belongs to a sufficient power section EPS. Figs. 11 to 13 are diagrams for explaining a method for allocating work when the first allowable power belongs to a power shortage section SPS. Fig. 14 is a diagram for explaining a method for allocating work when the first allowable power belongs to a maximum power usage section FPS.

[0033] First, referring to FIG. 5, a first allowable power AP1 in the first track T1 is calculated (S110 in FIG. 5).

[0034] More specifically, as shown in Fig. 6, the first allowed power AP1 means the amount of power that can be further used in the first track T1. The first allowed power AP1 may be a value obtained by subtracting the first power usage UP1 in the first track T1 from the first limit power LP1 in the first track T1. The first limit power LP1 means the power provided to the first track T1 by the first power supply PSU1. The first power usage UP1 means the power used by the multiple transport vehicles 20 located in the first track T1. In other words, the first allowed power AP1 corresponds to the remainder obtained by subtracting the power already used from the power provided to the first track T1.

[0035] For example, assume that the first power supply PSU1 supplies 30 kW to the first track T1, and the power consumed by a number of transport vehicles 20 positioned on the first track T1 is 8 kW. In this case, the first limit power LP1 is 30 kW, the first usage power UP1 is 8 kW, and therefore the first allowable power AP1 may be 22 kW.

[0036] The first power usage UP1 (i.e., power used by the multiple transport vehicles 20) can be obtained by combining the actual power usage used by each of the multiple transport vehicles 20. For example, each of the multiple transport vehicles 20 transmits actual power usage to the controller 10, and the controller 10 can obtain the combined actual power usage transmitted.

[0037] Alternatively, the first power usage UP1 can be calculated based on the number of transport vehicles 20 positioned on the first track T1. For example, assume that the first power supply PSU1 supplies 30 kW to the first track T1 and the maximum power that one transport vehicle 20 can use is 1 kW. The first power usage UP1 can be obtained by considering only the number of transport vehicles 20 positioned on the first track T1, without specifically considering how much power each of the multiple transport vehicles 20 uses. If the number of transport vehicles 20 positioned on the first track T1 is eight, the first power usage UP1 can be determined to be 8 kW.

[0038] In the above example, the maximum number of transport vehicles 20 that can be positioned on the first track T1 (i.e., the maximum number of transport vehicles 20 that can be charged on the first track T1) is 30 (∵30=30kW / 1kW). The controller 10 can see that when the first allowable power AP1 is 22kW (∵22kW=30kW-8kW), an additional 22 transport vehicles 20 can be charged on the first track T1.

[0039] Considering the above-mentioned points, the first power usage UP1, the first allowable power AP1, and the first limit power LP1 can all be expressed as the number of transport vehicles 20. In the above-mentioned example, the first limit power LP1 is 30 vehicles and the first power usage UP1 is 8 vehicles, therefore, the first allowable power AP1 can also be expressed as 22 vehicles (∵22=30-8).

[0040] When such a method is used, the amount of status data transmitted from the transport vehicle 20 to the controller 10 becomes small. In other words, the transport vehicle 20 does not transmit the actual power usage to the controller 10, but only transmits to the controller 10 information about the track on which the transport vehicle 20 is located (i.e., the position information of the transport vehicle 20). In this way, the possibility of transmission errors of the transport vehicle 20, calculation errors of the controller 10, etc. is reduced.

[0041] Alternatively, if a power sensing sensor is installed in the first power supply PSU1, the sensor can measure the power used in the first track T1 (i.e., the first power usage UP1). The first power supply PSU1 transmits the first power usage UP1 measured by the sensor to the controller 10, so that the controller 10 can grasp the first power usage UP1 without performing a separate calculation. As a result, the controller 10 can quickly calculate the first allowable power AP1 in the first track T1.

[0042] Next, the section to which the calculated first allowable power AP1 belongs is checked (S120 in FIG. 5).

[0043] More specifically, as shown in Fig. 7, a section in which the first allowable power AP1 is smaller than the third reference power SP3 is the maximum power usage section FPS. In the above example, this may be the case where 30 transport vehicles 20 are positioned on the first track T1 and there is no additional transport vehicle 20 that can be charged on the first track T1. Depending on the design, this may also be included in the maximum power usage section FPS when 29 transport vehicles 20 are positioned on the first track T1 and there is only one additional transport vehicle 20 that can be charged on the first track T1. In other words, the maximum power usage section FPS corresponds to a section in which the first allowable power AP1 is very small.

[0044] A section where the first allowable power AP1 is greater than the third reference power SP3 and less than the second reference power SP2 is a power shortage section SPS. In the above example, this may be the case where 27 to 28 transport vehicles 20 are positioned on the first track T1 and there are two to three additional transport vehicles 20 that can be charged on the first track T1. Depending on the design, the power shortage section SPS may also include a case where there is one additional transport vehicle 20 that can be charged on the first track T1.

[0045] A section where the first allowable power AP1 is greater than the first reference power SP1 is a sufficient power section EPS. In the above example, this may be the case where 15 or more additional transport vehicles 20 can be charged on the first track T1. The magnitude of the first reference power SP1 may be adjusted to be different depending on the design, and for example, the first reference power SP1 and the second reference power SP2 may be the same.

[0046] On the other hand, if the first allowable power AP1 is in the sufficient power section EPS as a result of checking the section to which the first allowable power AP1 belongs, the tasks of the transport vehicle 20 are allocated as follows (S130 in FIG. 5).

[0047] 9, a number of transport vehicles OHT1-OHT10 are positioned on a first track T1. For example, a first power supply PSU1 supplies 30 kW of power, and ten transport vehicles OHT1-OHT10 are positioned on the first track T1. Since the first allowable power AP1 of the first track T1 is greater than the first reference power SP1, the first allowable power AP1 falls within the sufficient power section EPS.

[0048] In this case, the controller 10 moves and inserts the transport vehicle OHT 10 that is sufficiently charged into another track (eg, the second track T2) (see reference symbol A1).

[0049] Furthermore, among the numerous transport vehicles OHT1 to OHT10 positioned on the first track T1, the transport vehicle OHT1 that is short of charge is preferentially charged (see reference symbol B1 in the drawing).

[0050] Here, a transport vehicle with a sufficient charge (e.g., OHT10) means that the battery (see 28 in FIG. 4) installed in the transport vehicle OHT10 has a sufficient charge. A transport vehicle with an insufficient charge (e.g., OHT1) means that the battery 28 installed in the transport vehicle OHT1 has an insufficient charge. In addition, the "sufficient" and "insufficient" charge of the battery 28 can be defined as follows. As shown in FIG. 8, when the charge of the battery 28 is smaller than the second reference charge amount CP2, the battery 28 belongs to the insufficient charge section SCP, that is, it can be determined that the charge of the battery 28 is insufficient. In addition, when the charge of the battery 28 is larger than the first reference charge amount CP1, the battery 28 belongs to the sufficient charge section ECP, that is, it can be determined that the charge of the battery 28 is sufficient.

[0051] 10, a number of transport vehicles OHT1 to OHT10 are positioned on a first track T1. A first allowable power AP1 corresponds to a sufficient power section EPS.

[0052] Several transport vehicles may be waiting to enter the first track T1. In such a case, the charge levels of the waiting transport vehicles are checked, and the transport vehicle with an insufficient charge level (e.g., OHT11) is first introduced into the first track T1 (see reference symbol D1). For example, if a transport vehicle with a charge level of 10%, a transport vehicle with a charge level of 60%, and a transport vehicle with a charge level of 80% are waiting, the transport vehicle with the lowest charge level (i.e., the transport vehicle with a charge level of 10%) is first introduced into the first track T1. In this way, the transport vehicle OHT11 with an insufficient charge level can be charged preferentially.

[0053] On the other hand, if the first allowable power AP1 is in a power shortage section SPS as a result of checking the section to which the first allowable power AP1 belongs, the tasks of the transport vehicle 20 are allocated as follows (S140 in FIG. 5).

[0054] 11 and 12, a number of transport vehicles OHT1-OHT27 are located on a first track T1. For example, a first power supply PSU1 supplies 30 kW of power, and 27 transport vehicles OHT1-OHT27 are located on the first track T1. Since the first allowable power AP1 of the first track T1 is greater than the third reference power SP3 and less than the second reference power SP2, the first allowable power AP1 corresponds to the power shortage section SPS.

[0055] In such a case, the controller 10 moves and puts the transport vehicle OHT 27 with insufficient charge into another track (that is, a track with sufficient allowable power) (see C1 in FIG. 11).

[0056] Alternatively, the controller 10 charges the transport vehicles OHT1 to OHT3 that are short of charge at a charging speed lower than the reference charging speed (see B2 in FIG. 12).

[0057] That is, the transport vehicle OHT27 arranged adjacent to another track is not charged on the first track T1, but is moved to the other track and charged there. On the other hand, the transport vehicles OHT1 to OHT3 must be located on the first track T1 before the other transport vehicles OHT4 to OHT27 located in front of them move to the other tracks. Therefore, the transport vehicles OHT1 to OHT3 are charged, but at a charging speed lower than the reference charging speed.

[0058] 13, a number of transport vehicles OHT1 to OHT27 are positioned on a first track T1. A first allowable power AP1 corresponds to a power shortage section SPS.

[0059] Several transport vehicles may be waiting to enter the first track T1. In such a case, the charge levels of the waiting transport vehicles are checked, and a transport vehicle with a sufficient charge level (e.g., OHT28) is allowed to enter the first track T1 first (see drawing reference D2). For example, if a transport vehicle with a 10% charge level, a transport vehicle with a 60% charge level, and a transport vehicle with an 80% charge level are waiting, the transport vehicle with the highest charge level (i.e., the transport vehicle with an 80% charge level) is allowed to enter the first track T1 first. In this way, the power usage load on the first track T1 can be prevented from increasing.

[0060] On the other hand, if the first allowable power AP1 is in the maximum power usage section FPS as a result of checking the section to which the first allowable power AP1 belongs, the operations of the transport vehicle 20 are allocated as follows (S150 in FIG. 5).

[0061] 14, a number of transport vehicles OHT1-OHT30 are located on a first track T1. For example, a first power supply PSU1 supplies 30 kW of power, and 30 transport vehicles OHT1-OHT30 are located on the first track T1. Because the first allowable power AP1 of the first track T1 is smaller than the third reference power SP3, the first allowable power AP1 corresponds to the maximum power usage section FPS.

[0062] Thirty transport vehicles OHT1 to OHT30 are positioned on the first track T1, and 30 may be the maximum number of transport vehicles 20 that can be supplied with power on the first track T1 (ie, the maximum number of transport vehicles that can be charged).

[0063] However, the transport vehicle OHT31 may be waiting to enter the first track T1.

[0064] In order to allow the transport vehicle OHT31 to enter, at least one of the transport vehicles OHT1 to OHT30 (for example, OHT3) is first controlled to run only on battery power (see reference symbol E1) in order to prevent the first truck T1 from being overloaded.

[0065] Thereafter, the waiting transport vehicle OHT31 is caused to enter the first track T1 (see reference symbol D3). At this time, 31 transport vehicles OHT1 to OHT31 are positioned on the first track T1. Therefore, the number of transport vehicles OHT1 to OHT31 positioned on the first track T1 (i.e., 31 vehicles) is greater than the maximum number of transport vehicles that can be charged on the first track T1 (i.e., 30 vehicles).

[0066] Also, selectively, when the charge amount of some of the multiple transport vehicles OHT1 to OHT31 (for example, OHT1) is insufficient, the transport vehicle OHT1 can be charged at a charging speed lower than the reference charging speed.

[0067] Next, at least one of the transport vehicles OHT1 to OHT30 (for example, OHT30) is moved to another track (see reference symbol C2).

[0068] Next, the transport vehicle OHT3 is caused to cease operating solely on battery power. As the transport vehicle OHT30 has left the first track T1, the number of transport vehicles OHT1-OHT29, OHT31 on the first track T1 becomes 30. In other words, the number of transport vehicles OHT1-OHT29, OHT31 located on the first track T1 (i.e., 30 vehicles) becomes the same as the maximum number of charged vehicles on the first track T1 (i.e., 30 vehicles). This is because it is no longer necessary to operate the transport vehicle OHT3 solely on battery power.

[0069] 15 and 16 are diagrams for explaining a control method of a transport system according to another embodiment of the present invention.

[0070] 15, a first power supply unit PSU1 supplies power to a first track T1, and a number of transport vehicles OHT1 to OHT10 are positioned on the first track T1. The multiple transport vehicles OHT1 to OHT10 are charged by the power supplied by the first track T1.

[0071] A second power supply unit PSU2 supplies power to a second track T2, and a large number of transport vehicles OHT11 to OHT20 are positioned on the second track T2. The large number of transport vehicles OHT11 to OHT20 are charged by the power supplied by the second track T2.

[0072] Next, referring to FIG. 16, the second power supply PSU2 suddenly stops operating. In this case, a power backup is performed. The first truck T1 and the second truck T2 are connected to each other via a connecting truck. In this case, the first power supply PSU1 can supply power to not only the first truck T1 but also the second truck T2 via the connecting truck. The first power supply PSU1 supplies power to the transport vehicles OHT11 to OHT20 on the second truck T2 to enable them to operate. Therefore, the number of transport vehicles receiving power from the first power supply PSU1 suddenly increases from 10 (i.e., OHT1 to OHT10) to 20 (i.e., OHT1 to OHT20). Here, in order to prevent a sudden increase in load, the following work allocation is performed.

[0073] First, at least one (e.g., OHT10) of the multiple transport vehicles OHT1 to OHT20 located on the first track T1 and the second track T2 is operated only by a battery (see reference symbol D2). The charge amount of the selected transport vehicle OHT10 may belong to the sufficient charge section (ECP).

[0074] Also, at least one of the multiple transport vehicles OHT1 to OHT20 (for example, OHT20) is moved to another track with sufficient allowable power (see reference symbol C3).

[0075] In addition, the multiple transport vehicles OHT1 to OHT20 can be controlled to be charged at a charging speed lower than the reference charging speed. In particular, some of the multiple transport vehicles OHT1 to OHT20 (e.g., OHT11, OHT12) are controlled to be charged at a charging speed lower than the reference charging speed (see reference symbol B3).

[0076] 17 is a flow chart for explaining a method for controlling a transport system according to still another embodiment of the present invention. For convenience of explanation, the following will mainly explain the points that are different from the contents explained using FIGS.

[0077] Referring to FIG. 17, a first allowable power AP1 for the first track and a second allowable power AP2 for the second track are calculated (S210).

[0078] The first allowable power AP1 in the first track may be a value obtained by subtracting the first power usage UP1 in the first track from the first limit power LP1 in the first track, as described with reference to FIG. 6. Here, the first power usage UP1 may be calculated as a sum of the actual power usage of a number of transport vehicles positioned on the first track. Alternatively, the first power usage UP1 may be calculated based on the number of transport vehicles positioned on the first track. Also, the first power usage UP1 may be calculated as a value measured by a power sensing sensor installed in the first power supplier.

[0079] The second allowable power AP2 in the second track can also be calculated in the same manner as described above. That is, the second allowable power AP2 can be a value obtained by subtracting the second power usage UP2 in the second track from the second limit power LP2 in the second track. Here, the second power usage UP2 can be calculated as the sum of the actual power usage of a number of transport vehicles positioned in the second track. Alternatively, the second power usage UP2 can be calculated based on the number of transport vehicles positioned in the second track. Also, the second power usage UP2 can be calculated as a value measured by a power sensing sensor installed in the second power supplier.

[0080] Next, the first allowable power AP1 and the second allowable power AP2 are compared (S220).

[0081] If the first allowable power AP1 is greater than the second allowable power (yes in S220), a transport vehicle that is sufficiently charged among the multiple transport vehicles located on the first track can be moved to the second track (S230). That is, when the second allowable power AP2 of the second track is insufficient, the transport vehicle that enters the second track first may be sufficiently charged.

[0082] In addition, among the multiple transport vehicles positioned on the second track, a transport vehicle that is insufficiently charged can be moved to the first track. The transport vehicle that is insufficiently charged is charged on the first track. That is, when the first allowable power AP1 of the first track is sufficient, the transport vehicle that enters the first track first may be insufficiently charged.

[0083] If the second allowable power AP2 is greater than the first allowable power (no in S220), then among the multiple transport vehicles positioned on the second track, a transport vehicle with a sufficient amount of charge can be moved to the first track (S240). That is, when the first allowable power AP1 of the first track is insufficient, the transport vehicle that enters the first track first may be one with a sufficient amount of charge.

[0084] In addition, among the multiple transport vehicles positioned on the first track, a transport vehicle that is insufficiently charged can be moved to the second track. The transport vehicle that is insufficiently charged is charged on the second track. That is, when the second allowable power AP2 of the second track is sufficient, the transport vehicle that enters the second track first may be insufficiently charged.

[0085] 18 is a flow chart illustrating a method for controlling a transport system according to still another embodiment of the present invention. For convenience of explanation, the following description will focus on the differences from the contents described with reference to FIGS.

[0086] 18, a transportation system is provided (S310). For example, the transportation system includes a first track installed on a rail, a first power supplier that supplies power to the first track, and a number of transportation vehicles that move along the rail and have batteries installed therein.

[0087] Next, it is checked whether the first allowable power AP1 in the first track is within the sufficient power section EPS (S320).

[0088] If the transport vehicle belongs to the sufficient power section EPS (yes in S320), the first transport vehicle having a charge amount less than the second reference charge amount CP2 is allowed to enter the first track (S322), or the transport vehicle located on the first track can be charged at a charge rate greater than the reference charge rate.

[0089] Next, it is checked whether the first allowable power AP1 in the first track belongs to the power shortage section SPS (S330).

[0090] If the transport vehicle belongs to the power shortage section SPS (yes in S330), the second transport vehicle located on the first track and having a charge amount less than the second reference charge amount CP2 is moved to another track (a track with sufficient allowable power) (S332). Also, the transport vehicle with a charge amount greater than the first reference charge amount CP1 is put into the first track first. The transport vehicle located on the first track and having insufficient battery power is charged at a reduced charge rate (i.e., at a charge rate less than the reference charge rate).

[0091] Next, it is checked whether the first allowable power AP1 in the first track belongs to the maximum power usage section FPS (S340).

[0092] If the vehicle belongs to the maximum power usage section FPS (yes in S340), at least one of the multiple transportation vehicles, the third transportation vehicle, is operated only by the battery, and the fourth transportation vehicle is caused to enter the first track (S342). In this way, the number of transportation vehicles located on the first track can be greater than the maximum number of charged vehicles on the first track. In addition, the fifth transportation vehicle, among the multiple transportation vehicles on the first track, is moved to another track, and the third transportation vehicle ceases to operate only by the battery.

[0093] Although the embodiment of the present invention has been described above with reference to the accompanying drawings, those skilled in the art will understand that the present invention can be embodied in other specific forms without changing the technical idea or essential features of the present invention. Therefore, it should be understood that the above embodiment is illustrative in all respects and is not limiting.

Claims

1. a first track mounted on the rail; a first power supply for supplying power to the first track; a number of transport vehicles that move along the rail, have batteries installed therein, and receive power from the first track to charge the batteries; a controller that allocates work among the plurality of transport vehicles based on a first allowable power in the first track; The first allowable power is greater than a first reference power, and the controller moves a transport vehicle located on the first track and having a charge amount greater than the first reference charge amount to another track having an allowable power less than the first allowable power.

2. The transportation system according to claim 1 , wherein the first allowable power comprises a value obtained by subtracting a first usage power at the first track from a first limit power at the first track.

3. The transportation system according to claim 2 , wherein the first power consumption is calculated based on the number of transportation vehicles positioned on the first track.

4. The transportation system according to claim 2 , wherein the first power usage is a total of actual power usage of a number of transportation vehicles positioned on the first track.

5. 3. The transportation system according to claim 2, wherein the first power supplier includes a sensor for sensing power used by the first track, and the first power usage is a value measured by the sensor.

6. 2. The transportation system according to claim 1, wherein the controller charges a transport vehicle having a charge amount smaller than a second reference charge amount among a plurality of transport vehicles positioned on the first track, and the second reference charge amount is smaller than the first reference charge amount.

7. a first track mounted on the rail; a first power supply for supplying power to the first track; a number of transport vehicles that move along the rail, have batteries installed therein, and receive power from the first track to charge the batteries; a controller that allocates work among the plurality of transport vehicles based on a first allowable power in the first track; The first allowable power is smaller than a second reference power, and the controller causes a transport vehicle located on the first track and having a charge amount smaller than the second reference charge amount to be put into another track having an allowable power larger than the first allowable power.

8. a first track mounted on the rail; a first power supply for supplying power to the first track; a number of transport vehicles that move along the rail, have batteries installed therein, and receive power from the first track to charge the batteries; a controller that allocates work among the plurality of transport vehicles based on a first allowable power in the first track; The first allowable power is smaller than a second reference power, and the controller charges the multiple transport vehicles located on the first track at a charging rate lower than the reference charging rate.

9. 9. The transportation system according to claim 8, wherein the first allowable power is smaller than a third reference power, and the third reference power is smaller than the second reference power, and the controller controls at least one of the plurality of transport vehicles located on the first track to operate only by battery, and then moves a waiting transport vehicle to the first track.

10. 10. The transportation system according to claim 9, wherein a first maximum charged number of the first track means a maximum number of transport vehicles that can be supplied with power by the first track, and the number of transport vehicles located on the first track after the waiting transport vehicle moves to the first track is greater than the first maximum charged number.

11. 2. The transportation system of claim 1, further comprising a second track mounted on the rail and a second power supplier supplying power to the second track, wherein when operation of the second power supplier suddenly stops, the controller controls the first power supplier to supply power to the first track and the second track.

12. 12. The transportation system according to claim 11, wherein the controller controls at least one of the multiple transport vehicles located on the first track and the second track to operate only on batteries, and charges the transport vehicles located on the first track and the second track at a charging rate lower than a reference charging rate.

13. A track installed on the rails, a power supply for supplying power to the truck; a number of transport vehicles that move along the rail, have batteries installed therein, and receive power from the track to charge the batteries; A controller for allocating work to a number of transport vehicles, When the number of transport vehicles located on the track is the maximum number of vehicles to be charged, The controller includes: A first transport vehicle among the plurality of transport vehicles located on the track is controlled so as to be operated only by the battery; A second transport vehicle is caused to enter the truck, A third transport vehicle among the multiple transport vehicles located on the track is moved to another track, and ceasing the first transport vehicle from operating solely on battery power.

14. The transport system according to claim 13, further comprising charging a transport vehicle located on the track and having a charge amount less than a reference charge amount at a charging rate lower than a reference charging rate before the third transport vehicle moves to another track after the second transport vehicle has entered the track.

15. A transport system is provided that includes a first track installed on a rail, a first power supplier that supplies power to the first track, and a number of transport vehicles that move along the rail and have batteries installed therein; When the first allowable power of the first track is greater than the first reference power, a transport vehicle having a charge amount less than a second reference charge amount is allowed to enter the first track, A method for controlling a transportation system, comprising: when the first allowable power of the first track is smaller than a second reference power, moving a transportation car located on the first track and having a charge amount smaller than the second reference charge amount to another track.

16. 16. The method for controlling a transportation system according to claim 15, further comprising charging the transportation carriage located on the first track at a charging rate higher than a reference charging rate when the first allowed power of the first track is higher than the first reference power.

17. 16. The method for controlling a transportation system according to claim 15, further comprising, when the first allowable power of the first track is smaller than the second reference power, charging the transportation car located on the first track at a charging rate that is smaller than a reference charging rate.

18. 16. The method of controlling a transportation system according to claim 15, further comprising: a second track mounted on the rail; and a second power supplier supplying power to the second track, and the first power supplier supplying power to the first track and the second track when operation of the second power supplier suddenly stops.

19. 20. The method for controlling a transportation system according to claim 18, further comprising controlling at least one of the multiple transportation vehicles located on the first track and the second track to operate only on battery power.