Electric vehicle management device and electric vehicle management system
The electric vehicle management device addresses user anxiety by adjusting SOC based on predicted electricity prices, optimizing charging costs through threshold-based strategies.
Patent Information
- Application Number
- JP2022023166
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-02-17
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2042-02-17
AI Technical Summary
Existing electric vehicle management systems do not consider electricity prices when adjusting power consumption, leading to increased charging costs and user economic anxiety.
An electric vehicle management device that adjusts State of Charge (SOC) based on predicted electricity market prices, using threshold comparisons to minimize economic burden on users.
Reduces user anxiety by optimizing SOC adjustments based on market price predictions, thereby minimizing charging costs and control load on the system.
Smart Images

Figure 0007601027000001 
Figure 0007601027000002 
Figure 0007601027000003
Abstract
Description
[Technical field]
[0001] The present disclosure relates to an electric vehicle management device and an electric vehicle management system. [Background technology]
[0002] For example, Patent Publication No. 2020-150717 (Patent Document 1) discloses a supply and demand management server that adjusts the power consumption (generated power) of an electric vehicle based on a power supply and demand forecast value, which is the difference between the forecasted power demand and forecasted power supply of a power grid. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2020-150717 A Summary of the Invention [Problem to be solved by the invention]
[0004] As described above, the supply and demand management server described in Patent Document 1 adjusts the power consumption (power generation) of an electric vehicle based on a predicted value of power supply and demand in the power grid. However, the supply and demand management server does not make the above adjustments taking into account the price of electricity. Therefore, for example, if the power consumption of an electric vehicle is adjusted to be high when the price of electricity is high, the cost of charging the electric vehicle the next time will be high. For this reason, it is thought that control by the supply and demand management server may cause users of electric vehicles to feel financial anxiety (dissatisfaction) about charging their electric vehicles.
[0005] The present disclosure has been made to solve the above-mentioned problems, and its purpose is to provide an electric vehicle management device and an electric vehicle management system that are capable of reducing the financial anxiety (dissatisfaction) felt by users of electric vehicles regarding charging their electric vehicles. [Means for solving the problem]
[0006] An electric vehicle management device according to a first aspect of the present disclosure is an electric vehicle management device that manages electric vehicles that can be charged from a power grid, and is equipped with: a communication unit that acquires information on the market price of electricity through communication and communicates with the electric vehicle; and a control unit that calculates a predicted value of the market price based on the market price information acquired by the communication unit, and the control unit performs a SOC adjustment process to adjust the SOC of the electric vehicle while it is in motion based on the calculated predicted value.
[0007] In the electric vehicle management device according to the first aspect, as described above, a SOC adjustment process is performed to adjust the SOC of the electric vehicle while traveling based on the calculated predicted value of the market price of electricity. This makes it possible to adjust the SOC of the electric vehicle while traveling based on the predicted value of the market price of electricity. As a result, the SOC can be easily adjusted based on the predicted value of the market price so that the economic damage to the user caused by charging the electric vehicle is reduced. This makes it possible to suppress the user of the electric vehicle from feeling economic anxiety (dissatisfaction).
[0008] In the electric vehicle management device according to the first aspect, the control unit preferably performs the SOC adjustment process based on the magnitude relationship between the predicted value and the predetermined threshold price. This allows the SOC adjustment process to be performed simply by comparing the predicted value of the market price with the predetermined threshold price (without performing complex calculations). As a result, the control load on the control unit due to the SOC adjustment process can be reduced.
[0009] In this case, preferably, the predetermined threshold price includes a first threshold price, the SOC adjustment process includes an SOC suppression process for suppressing a decrease in the SOC of the electric vehicle during running, and the control unit performs the SOC suppression process when the predicted value is equal to or greater than the first threshold price. This allows the SOC suppression process to be performed simply by comparing the predicted value of the market price with the first threshold price (without performing complex calculations). As a result, the control load on the control unit due to the SOC suppression process can be reduced.
[0010] In addition, in an electric vehicle management device in which an SOC suppression process is performed when the predicted value is equal to or greater than a first threshold price, the SOC suppression process preferably includes a first process for lowering an output upper limit value of a temperature regulator of the electric vehicle compared to when the predicted value is less than the first threshold price, thereby making it possible to further suppress a decrease in SOC caused by a lower output upper limit value of the temperature regulator of the electric vehicle compared to when the predicted value is less than the first threshold price.
[0011] In addition, in an electric vehicle management device in which an SOC suppression process is performed when the predicted value is equal to or greater than the first threshold price, the SOC suppression process preferably includes a second process for limiting the output of the motor generator of the electric vehicle without lowering the output upper limit of the temperature regulator of the electric vehicle. This makes it possible to easily suppress a drop in SOC by limiting the output of the motor generator while preventing the user of the electric vehicle from feeling uncomfortable due to the lowering of the output upper limit of the temperature regulator.
[0012] In addition, in an electric vehicle management device in which an SOC suppression process is performed when the predicted value is equal to or greater than a first threshold price, the predetermined threshold price preferably includes a second threshold price smaller than the first threshold price, the SOC adjustment process includes an SOC promotion process for promoting a decrease in the SOC of the electric vehicle during travel, and the control unit performs the SOC promotion process when the predicted value is equal to or less than the second threshold price. This allows the SOC promotion process to be performed simply by comparing the predicted market price value with the second threshold price (without performing complex calculations). As a result, the control load on the control unit due to the SOC promotion process can be reduced.
[0013] In the electric vehicle management device according to the first aspect, the control unit preferably detects a scheduled time when the next charging will be performed, calculates a predicted value at the scheduled time, and performs an SOC adjustment process based on the predicted value. This makes it possible to adjust the SOC based on the market price at the time when charging is actually performed. As a result, it is possible to more reliably suppress financial anxiety (dissatisfaction) felt by users of electric vehicles.
[0014] In the electric vehicle management device according to the first aspect, the control unit preferably detects a scheduled time for the next charging and performs SOC adjustment processing based on the detection of the scheduled time, thereby making it possible to exclude an electric vehicle that is not scheduled for the next charging from being a target for the SOC adjustment processing.
[0015] In the electric vehicle management device according to the first aspect, the control unit preferably calculates the predicted value before a gate closure of the electricity trading market. This makes it possible to calculate the predicted value of the electricity market before a gate closure at which electricity market trading is possible.
[0016] An electric vehicle management system according to a second aspect of the present disclosure includes an electric vehicle capable of being charged from a power grid, and an electric vehicle management device that manages the electric vehicle, the electric vehicle management device including a communication unit that acquires information on the market price of electricity through communication and communicates with the electric vehicle, and a control unit that calculates a predicted value of the market price based on the market price information acquired by the communication unit, and the control unit performs processing to adjust the SOC of the electric vehicle while in motion based on the calculated predicted value.
[0017] In the electric vehicle management system according to the second aspect, as described above, a SOC adjustment process is performed to adjust the SOC of the electric vehicle while traveling based on the calculated predicted value of the market price of electricity. This makes it possible to adjust the SOC of the electric vehicle while traveling based on the predicted value of the market price of electricity. As a result, the SOC can be easily adjusted based on the predicted value of the market price so that economic damage to the user caused by charging the electric vehicle is reduced. This makes it possible to provide an electric vehicle management system that can suppress economic anxiety (dissatisfaction) felt by the user of the electric vehicle. Effect of the Invention
[0018] According to the present disclosure, it is possible to suppress financial anxiety (dissatisfaction) felt by users of electric vehicles regarding charging of their electric vehicles. [Brief description of the drawings]
[0019] [Figure 1] 1 is a diagram showing a schematic configuration of an electric vehicle management system according to an embodiment of the present disclosure; [Diagram 2] FIG. 1 is a diagram illustrating an example of a configuration of an electric vehicle. [Diagram 3] 1 is a diagram illustrating a detailed configuration of an electric vehicle management device according to an embodiment of the present disclosure. [Figure 4] FIG. 13 is a diagram showing the transition of the predicted value of the market price. [Diagram 5] FIG. 11 illustrates an example of an SOC suppression process. [Figure 6] FIG. 11 illustrates an example of a SOC promotion process. [Figure 7] FIG. 4 is a flow chart showing the processing of the electric vehicle management device. [Figure 8] FIG. 11 is a diagram illustrating an example of an SOC suppression process according to a modified example of the present disclosure. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0020] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present disclosure will now be described in detail with reference to the accompanying drawings, in which the same or corresponding parts are designated by the same reference characters and will not be described repeatedly.
[0021] Fig. 1 is a diagram showing a schematic configuration of an electric vehicle management system 1 according to an embodiment of the present disclosure. As shown in Fig. 1, the electric vehicle management system 1 includes a vehicle group VG (electric vehicles 100), a server 700, and an electric vehicle management device 1000. The electric vehicle management device 1000 includes a server 300 and a server 600. Each of the server 300 and the server 600 corresponds to a management computer.
[0022] The power system PG is a power grid constructed by power transmission and distribution facilities. A plurality of power plants are connected to the power system PG. The power system PG receives power supply from these power plants. In this embodiment, a power company maintains and manages the power system PG (commercial power source). The power company corresponds to a TSO (system operator) described later. The power system PG supplies AC power (for example, three-phase AC power). The server 700 corresponds to a computer belonging to the TSO (hereinafter, may be referred to as a "TSO server"). The servers 600 and 700 are configured to be able to communicate with each other.
[0023] The server 300 manages the vehicle group VG. The server 300 periodically communicates with each electric vehicle 100 included in the vehicle group VG. The number of electric vehicles 100 included in the vehicle group VG may be 5 or more and less than 30, 30 or more and less than 100, or 100 or more.
[0024] Each of the electric vehicles 100 included in the vehicle group VG is configured to be able to operate as a regulating power for the power system PG. FIG.
[0025] As shown in Fig. 2, the electric vehicle 100 includes a battery 130 that stores electric power for traveling. The electric vehicle 100 is an electric vehicle (BEV (Battery Electric Vehicle)) that does not include an engine (internal combustion engine). The battery 130 includes a known vehicle power storage device (for example, a liquid type secondary battery, an all-solid-state secondary battery, or a battery pack). Examples of the vehicle secondary battery include a lithium ion battery and a nickel metal hydride battery. The electric vehicle 100 may be a PHEV (Plug-in Hybrid electric Vehicle).
[0026] The electric vehicle 100 includes an electronic control unit (hereinafter referred to as an “ECU (Electronic Control Unit)”) 150. The ECU 150 controls charging and discharging of the battery 130.
[0027] Electric vehicle 100 is configured to be electrically connectable to, for example, electric vehicle supply equipment (EVSE) 200 shown in Fig. 2. EVSE 200 corresponds to a power supply facility outside the vehicle. EVSE 200 is electrically connected to a power system PG and configured to receive power from power system PG and supply power. A charging cable 210 is connected to a main body of EVSE 200.
[0028] The electric vehicle 100 includes an inlet 110 and a charger / discharger 120. When a charging cable 210 of the EVSE 200 is connected to the inlet 110 of the electric vehicle 100, the electric vehicle 100 is electrically connected to the power grid PG via the EVSE 200 (hereinafter also referred to as a “plugged-in state”). The charger / discharger 120 is controlled by the ECU 150.
[0029] In the plugged-in state, the electric vehicle 100 is capable of external charging (charging the battery 130 with electric power from outside the vehicle) and external power supply (power supply from the battery 130 to the outside of the vehicle). The electric vehicle 100 is capable of adjusting the power of the power system PG by external charging and external power supply.
[0030] The ECU 150 includes a processor 151, a random access memory (RAM) 152, a storage device 153, and a timer 154. The ECU 150 may be a computer or a central processing unit (CPU). The RAM 152 functions as a working memory that temporarily stores data processed by the processor 151. The storage device 153 is configured to be able to save stored information. In addition to programs, the storage device 153 stores information used by the programs (for example, maps, formulas, and various parameters). The processor 151 executes the programs stored in the storage device 153, thereby executing various controls in the ECU 150. The timer 154 is configured to notify the processor 151 of the arrival of a set time. The ECU 150 can obtain the current time by using a real-time clock (RTC) circuit (not shown) built into the ECU 150.
[0031] The electric vehicle 100 further includes a traveling drive unit 140, an HMI (Human Machine Interface) 160, a position sensor 170, a communication device 180, a temperature regulator 190, and drive wheels W. The HMI 160 includes an input device and a display device. The HMI 160 may include a touch panel display. The HMI 160 may include a smart speaker that accepts voice input. The position sensor 170 is configured to detect the position of the electric vehicle 100 and output the detection result to the ECU 150. The position sensor 170 may be a sensor that utilizes a GPS (Global Positioning System).
[0032] The traveling drive unit 140 includes a PCU (Power Control Unit) 141 and a MG (Motor Generator) 142, and is configured to travel the electric vehicle 100 using the electric power stored in the battery 130. The PCU 141 is controlled by the ECU 150.
[0033] The MG 142 is, for example, a three-phase AC motor generator. The MG is configured to be driven by the PCU 141 and to rotate the drive wheels W. The PCU 141 drives the MG using electric power supplied from the battery 130. The MG 142 is also configured to perform regenerative power generation and supply the generated electric power to the battery 130.
[0034] The communication device 180 includes various communication I / Fs (interfaces). The ECU 150 is configured to communicate with devices external to the electric vehicle 100 through the communication device 180. The communication device 180 includes a wireless communication device (e.g., a DCM (Data Communication Module)) that can access a mobile communication network (telematics). The wireless communication device may include a communication I / F compatible with 5G (fifth generation mobile communication system). The electric vehicle 100 may wirelessly communicate with the server 300 in both a plugged-in state and a plugged-out state (a state in which the electric vehicle 100 and the power system PG are electrically disconnected).
[0035] The temperature regulator 190, which adjusts the temperature inside the vehicle cabin of the electric vehicle 100, includes a cooling device 191 and a heater 192. For example, the cooling device 191 may be an air conditioner equipped with an electric compressor, and the heater 192 may be an electric water heater. Each of the cooling device 191 and the heater 192 is controlled by the ECU 150 and consumes power from the battery 130. Note that the configuration of the electric vehicle 100 described above is merely an example.
[0036] The mobile terminal UT is a terminal carried by a user of the electric vehicle 100. The mobile terminal UT includes, for example, a smartphone equipped with a touch panel display. However, the mobile terminal UT is not limited to this, and any mobile terminal can be adopted, and may include a laptop, a tablet terminal, a wearable device (for example, a smart watch or smart glasses), an electronic key, or the like.
[0037] The mobile terminal UT is registered in advance with the server 300 and configured to be capable of wireless communication with the server 300 .
[0038] In this embodiment, the mobile terminal UT includes a location sensor. The location sensor may be a sensor using a GPS. The mobile terminal UT transmits information indicating the user's location (hereinafter also referred to as "user location information") to the server 300 periodically or in response to a request from the server 300.
[0039] The mobile terminal UT predicts a driving plan for the electric vehicle 100 using the user position information. Examples of the driving plan include a boarding time (or departure time), a home time, and a destination (or a driving route to the destination). For example, the mobile terminal UT may predict the time when the user will board the electric vehicle 100 based on a change in the position of the user who has exited the electric vehicle 100. The mobile terminal UT may function as an electronic key for the electric vehicle 100. When the user locks the door of the electric vehicle 100 using the mobile terminal UT after exiting the electric vehicle 100, the position of the mobile terminal UT at the time of exiting the vehicle may be registered in the mobile terminal UT as the parking position of the electric vehicle 100, and the mobile terminal UT may start tracking the user's position (detecting the position using a position sensor and recording the user's position). The mobile terminal UT may learn the user's behavior pattern from history data (for example, weather information, traffic congestion information, and past position data managed separately according to the day of the week).
[0040] The mobile terminal UT transmits the driving plan to the server 300. Furthermore, a driving plan set by the user in the mobile terminal UT may be transmitted from the mobile terminal UT to the server 300. A schedule set in a scheduler application or an alarm application installed in the mobile terminal UT may be automatically transmitted to the server 300. Furthermore, a driving plan set by the user in a navigation system (not shown) of the electric vehicle 100 may be transmitted to the server 300. When the driving plan for the electric vehicle 100 is changed, the latest driving plan may be transmitted from the mobile terminal UT of the user of the electric vehicle 100 (or from the electric vehicle 100) to the server 300.
[0041] A vehicle system (a system that controls the electric vehicle 100) including the ECU 150 is switched on (operated) / off (stopped) by a user operating a start switch (not shown). In general, the start switch is called a "power switch" or an "ignition switch".
[0042] Referring again to FIG. 1, the server 600 corresponds to a computer belonging to an aggregator. The aggregator is an electric utility that provides an energy management service by aggregating a plurality of distributed energy resources (hereinafter also referred to as "DERs (Distributed Energy Resources)"). Each electric vehicle 100 included in the vehicle group VG can function as a DER. The server 600 may cause a plurality of DERs (including the vehicle group VG) to function as a VPP (Virtual Power Plant) by remotely and integrally controlling these DERs. The server 600 may implement DR (Demand Response) for each DER.
[0043] The server 600 can remotely control a DER (for example, the battery 130 shown in FIG. 2) to charge or discharge for power adjustment of the power grid PG. For example, when an imbalance occurs, the server 600 controls a DER (for example, the charger / discharger 120 shown in FIG. 2) to eliminate the imbalance.
[0044] Fig. 3 is a diagram showing a detailed configuration of the server 300 and the server 600. Referring to Fig. 3, the servers 300 and 600 each include a processor 310, 610, a storage device 320, 620, a communication device 330, 630, and an HMI 340, 640. The communication device 630 acquires information on the market price of electricity through communication. The communication device 330 and the communication device 630 communicate with each other. The communication device 630 and the communication device 330 are an example of a "communication unit" in the present disclosure. The processor 310 and the processor 610 are an example of a "control unit" in the present disclosure.
[0045] Each of the storage devices 320 and 620 is configured to be capable of storing various types of information. In addition to the programs executed by the processors 310 and 610, the storage devices 320 and 620 store information used in the programs (e.g., maps, formulas, and various parameters). Each of the communication devices 330 and 630 includes various communication I / Fs (interfaces). Each of the HMIs 340 and 640 includes an input device and a display device.
[0046] The server 300 is configured to manage information (hereinafter, also referred to as "vehicle information") related to each electric vehicle 100 included in the vehicle group VG. The vehicle information is stored in a storage device 320 of the server 300. Specifically, identification information (vehicle ID) for identifying the electric vehicle 100 is given to each electric vehicle 100, and the server 300 manages the vehicle information by distinguishing it by the vehicle ID. The vehicle ID may be a number unique to each electric vehicle 100 (for example, a vehicle identification number (VIN)) or may be a communication address of the electric vehicle 100. The vehicle information includes, for example, the position of the electric vehicle 100, a state of charge (SOC) of a battery 130 included in the electric vehicle 100, a travel plan for the electric vehicle 100, a grid connection state (plugged-in state / plugged-out state), and a state of the vehicle system (on / off). In addition, specifications of the electric vehicle 100 (for example, specifications related to charging and discharging) may be registered in advance in the server 300.
[0047] Furthermore, the server 300 periodically communicates with each of the electric vehicles 100. Specifically, the server 300 repeatedly executes the process shown in Fig. 7, which will be described below.
[0048] The server 600 also includes a vehicle management unit 611, a selection unit 612, a supply and demand management unit 613, a trading unit 614, an adjustment capacity calculation unit 615, and a market price prediction unit 616. Each of these units is embodied, for example, by a processor 610 and a program executed by the processor 610. However, without being limited thereto, each of the above units may be embodied by dedicated hardware (electronic circuits).
[0049] The vehicle management unit 611 acquires data managed by the server 300 as necessary. Furthermore, the vehicle management unit 611 predicts future behavior of the electric vehicle 100 based on the data acquired from the server 300.
[0050] The vehicle management unit 611 operates the vehicle selected by the selection unit 612 as the adjusting power of the power system PG by remote control.
[0051] The supply and demand management unit 613 acquires supply and demand information of the power system PG from the server 700. The supply and demand management unit 613 also monitors the actual supply and demand of the power system PG. When an imbalance occurs in the simultaneous balancing amount of the power system PG, the supply and demand management unit 613 generates an adjustment power request to eliminate the imbalance.
[0052] The trading unit 614 performs trading in the electricity market. The trading unit 614 executes bidding in the electricity market and notifies the bidding result to the supply and demand management unit 613. When the trading unit 614 wins a bid in the electricity market, the trading unit 614 generates an adjustment power request.
[0053] The regulation capability calculation unit 615 calculates a target regulation capability for the regulation capability request. In response to the adjustment capability request, the selection unit 612 selects an electric vehicle 100 to be operated as an adjustment capability from among the multiple electric vehicles 100 included in the vehicle group VG. The selection unit 612 notifies the vehicle management unit 611 of the selected electric vehicle 100.
[0054] The market price prediction unit 616 calculates a predicted value of the market price based on the market price information acquired by the communication device 630. Specifically, the market price prediction unit 616 (processor 610) detects (calculates) the scheduled time when the next charging of the traveling electric vehicle 100 will be performed, and calculates a predicted value of the market price at the detected (calculated) scheduled time. The graph shown in Fig. 4 shows the relationship between the predicted value on an annual basis predicted by the market price prediction unit 616 and time. The process of detecting (calculating) the scheduled time when the next charging will be performed may be performed by the processor 310 of the server 300.
[0055] The market price prediction unit 616 (processor 610) detects (calculates) a scheduled time for the next charging to be performed, based on the future behavior of the electric vehicle 100 predicted by the vehicle management unit 611. In addition, the market price prediction unit 616 (processor 610) may detect (calculate) a scheduled time for the next charging to be performed for the electric vehicle 100 selected by the selection unit 612.
[0056] The server 300 also includes a SOC adjustment processing unit 311. The SOC adjustment processing unit 311 is embodied, for example, by the processor 310 and a program executed by the processor 310. However, without being limited thereto, the SOC adjustment processing unit 311 may be embodied by dedicated hardware (electronic circuitry).
[0057] The SOC adjustment processing unit 311 performs an SOC adjustment process to adjust the SOC of the electric vehicle 100 while it is running. If the SOC is adjusted without considering the market price of electricity, for example, when the price of electricity is high, the SOC of the electric vehicle is adjusted to be lowered, and the cost of the next charge increases. For this reason, it is considered that the user of the electric vehicle 100 may feel financial anxiety (dissatisfaction) about charging.
[0058] Therefore, in this embodiment, the processor 310 (SOC adjustment processing unit 311) performs the SOC adjustment process based on the predicted value of the market price of electricity calculated by the market price prediction unit 616. Specifically, the processor 310 (SOC adjustment processing unit 311) transmits a command signal to the electrically powered vehicle 100 to perform the SOC adjustment process based on the predicted value of the market price of electricity. Note that the SOC of the electrically powered vehicle 100 is adjusted during the period from when the SOC adjustment process is started until the next charging.
[0059] Furthermore, the processor 310 compares the predicted value of the power market price calculated by the market price prediction unit 616 with a predetermined threshold price. Then, the SOC adjustment processing unit 311 (processor 310) performs the above SOC adjustment process based on the magnitude relationship between the predicted value of the market price and the predetermined threshold price. Note that the comparison of the predicted value of the market price with the predetermined threshold price may be performed by the processor 610.
[0060] The above-mentioned predetermined threshold prices include threshold price A and threshold price B. FIG. 4 shows a graph illustrating the relationship between the predicted value of the market price and time. As shown in FIG. 4, threshold price B is smaller than threshold price A. Each of threshold price A and threshold price B is stored in advance in storage device 320 (or storage device 620). Furthermore, each of threshold price A and threshold price B may be calculated appropriately based on predetermined information (e.g., the trend of the market price of electricity, etc.) instead of being a fixed value as described above. Note that threshold price A and threshold price B are examples of the "first threshold price" and "second threshold price" of the present disclosure, respectively.
[0061] In this embodiment, when the predicted value of the market price of electricity is equal to or higher than the threshold price A, the SOC adjustment processing unit 311 (processor 310) performs an SOC suppression process for suppressing a decrease in the SOC of the traveling electric vehicle 100. This makes it possible to suppress the SOC from becoming relatively low at a time when the market price is predicted to be relatively high. As a result, it is possible to suppress the cost of charging the electric vehicle 100 from becoming high, so that it is possible to easily suppress the user from feeling financial anxiety (dissatisfaction). Also, as shown in FIG. 4, the threshold price A is smaller than, for example, ½ of the maximum value of the predicted market price in one year. Note that the magnitude of the threshold price A is not limited to this example.
[0062] Fig. 5 shows a graph illustrating the relationship between the outside air temperature and the output upper limit value of the temperature regulator 190 (cooling device 191 and heater 192). As shown in Fig. 5, the SOC suppression process includes a process (an example of the "first process" of the present disclosure) for lowering the output upper limit value of the temperature regulator 190 of the electric vehicle 100, for example, compared to the case where the predicted value of the market price of electricity is less than threshold price A (the case where the predicted value is greater than threshold price B and less than threshold price A). Note that in Fig. 5, the change in the output upper limit value after the SOC suppression process is illustrated by a solid line, and the change in the output upper limit value before the SOC suppression process is illustrated by a dashed line.
[0063] Specifically, the SOC suppression process includes a process of lowering the output upper limit value of each of the cooling device 191 and the heater 192. The output upper limit value of the cooling device 191 may be controlled by the evaporator outlet temperature, and the output upper limit value of the heater 192 may be controlled by the supplied power. The amount of reduction in the output upper limit value due to the SOC suppression process is, for example, a fixed value set in advance. Note that the amount of reduction may be calculated based on, for example, the magnitude of the difference between the predicted value of the market price of electricity and the threshold price A.
[0064] Moreover, the output upper limit value of each of the cooling device 191 and the heater 192 changes depending on the outside air temperature. Specifically, the higher the outside air temperature, the higher the output upper limit value of the cooling device 191. The lower the outside air temperature, the higher the output upper limit value of the heater 192. Here, the rate of change of the output upper limit value with respect to the outside air temperature may be the same or different before and after the SOC suppression process is performed. Also, the amount of reduction in the output upper limit value of each of the cooling device 191 and the heater 192 due to the SOC suppression process may be the same or different. Also, only the output upper limit value of either the cooling device 191 or the heater 192 may be reduced by the SOC suppression process.
[0065] The SOC suppression process is not limited to the above example. For example, the decrease in SOC may be suppressed by increasing the regeneration strength by braking.
[0066] Furthermore, the SOC adjustment process performs an SOC promotion process for promoting a decrease in the SOC of the traveling electric vehicle 100 when the predicted value of the market price of electricity is equal to or lower than the threshold price B (see the dashed line in FIG. 5). For example, the threshold price B is smaller than 1 / 2 of the threshold price A. Note that the magnitude of the threshold price B is not limited to this example.
[0067] Fig. 6 shows a graph illustrating the relationship between the outside air temperature and the output upper limit value of the temperature regulator 190 (cooling device 191 and heater 192). As shown in Fig. 6, the SOC acceleration process includes a process for increasing the output upper limit value of the temperature regulator 190 of the electric vehicle 100, for example, compared to a case in which the predicted value of the market price of electricity is higher than threshold price B (a case in which the predicted value is higher than threshold price B and lower than threshold price A). Note that in Fig. 6, the change in the output upper limit value after the SOC acceleration process is indicated by a solid line, and the change in the output upper limit value before the SOC acceleration process is indicated by a dashed line.
[0068] Specifically, the SOC promotion process includes a process of increasing the output upper limit value of each of the cooling device 191 and the heater 192. The increase amount of the output upper limit value by the SOC promotion process is, for example, a preset fixed value. Note that the increase amount may be calculated based on, for example, the magnitude of the difference between the predicted value of the market price of electricity and the threshold price B.
[0069] The rate of change of the output upper limit value with respect to the outside air temperature may be the same or different before and after the SOC promotion process. The amount of increase in the output upper limit value of each of the cooling device 191 and the heater 192 due to the SOC promotion process may be the same or different. Only the output upper limit value of either the cooling device 191 or the heater 192 may be increased by the SOC promotion process.
[0070] The SOC promotion process is not limited to the above example. For example, in a PHEV vehicle, the decrease in SOC may be promoted by actively using EV driving rather than HV driving. In a BEV vehicle, the decrease in SOC may be promoted by switching to a power mode that prioritizes the output of MG142. This allows the user to enjoy driving more, and since the market price is relatively low when charging after driving, it is possible to reduce the economic damage to the user. (Control flow of electric vehicle management device) Next, the control flow of the electric vehicle control device 1000 will be described with reference to FIG.
[0071] First, in step S1, it is determined whether or not the electric vehicle 100 is traveling. Specifically, the processor 310 determines that the electric vehicle 100 is traveling based on vehicle information of the electric vehicle 100 (such as the position of the electric vehicle 100 and the traveling plan of the electric vehicle 100) acquired by the communication device 330 of the server 300. In detail, the processor 310 determines that the electric vehicle 100 is traveling when the start switch is turned on. If it is determined that the electric vehicle 100 is traveling (Yes in S1), the process proceeds to step S2. If it is determined that the electric vehicle 100 is not traveling (No in S1), the process proceeds to return. The above determination in step S1 may be performed by the processor 610 of the server 600.
[0072] Next, in step S2, the next charging schedule for the electric vehicle 100 is detected. Specifically, the above determination is made by the processor 610 based on vehicle information of the electric vehicle 100 (such as the position of the electric vehicle 100, the driving plan of the electric vehicle 100, and past driving data) or information transmitted from the mobile terminal UT. If it is determined that the next charging is scheduled (Yes in S2), the process proceeds to step S3. If it is determined that the next charging is not scheduled (undecided) (No in S2), the process of step S2 is repeated. The above determination in step S2 may be made by the processor 310 of the server 300.
[0073] Next, in step S3, the scheduled time for the next charge of the electric vehicle 100 is detected. Specifically, the scheduled time is calculated based on vehicle information of the electric vehicle 100 (such as the position of the electric vehicle 100, the driving plan of the electric vehicle 100, and past driving data) or information transmitted from the mobile terminal UT. The scheduled time may also be calculated based on traffic congestion information, a personal schedule stored in the mobile terminal UT, or the like. The process in step S3 may be performed by the processor 310 of the server 300.
[0074] Next, in step S4, a predicted value of the market price of electricity at the scheduled time detected in step S3 is calculated. Specifically, the predicted value of the market price is calculated by the processor 610 (market price prediction unit 616) of the server 600.
[0075] Next, in step S5, it is determined whether the predicted value of the electricity market price calculated in step S4 is equal to or less than threshold price B (see FIG. 4). If the predicted value is equal to or less than threshold price B (Yes in S5), the process proceeds to step S6. If the predicted value is greater than threshold price B (No in S5), the process proceeds to step S7.
[0076] In step S6, the SOC promotion process is performed. The details of the SOC promotion process are as described above.
[0077] Also, in step S7, it is determined whether the predicted value of the electricity market price calculated in step S4 is equal to or greater than the threshold price A. If the predicted value is equal to or greater than the threshold price A (Yes in S7), the process proceeds to step S8. If the predicted value is smaller than the threshold price A (No in S7), the process proceeds to RETURN.
[0078] In step S8, the SOC suppression process is performed as described above.
[0079] The order of steps S5 and S7 may be reversed. Furthermore, the processor 610 (market price prediction unit 616) of the server 600 calculates a predicted value of the market price of electricity before the gate closure of the electricity trading market.
[0080] As described above, in this embodiment, the processor 310 (SOC adjustment processing unit 311) performs an SOC adjustment process for adjusting the SOC of the traveling electric vehicle 100 based on the calculated predicted value of the market price of electricity. This adjusts the SOC of the traveling electric vehicle 100 based on the predicted value of the market price of electricity. As a result, it is possible to adjust the SOC based on the predicted value of the market price so as to reduce the economic burden on the user. This makes it possible to suppress economic anxiety (dissatisfaction) felt by the user of the electric vehicle 100.
[0081] In the above embodiment, the output upper limit value of the temperature regulator 190 is reduced in the SOC suppression process, but the present disclosure is not limited to this. The output of other devices may be changed without reducing the output upper limit value of the temperature regulator 190.
[0082] In the above embodiment, the server 300 transmits a command signal to the electric vehicle 100 to perform the SOC adjustment process, but the present disclosure is not limited to this. The server 300 may transmit only the comparison result between the predicted value of the electricity market price and the threshold price A (B) to the electric vehicle 100. In this case, the electric vehicle 100 executes the SOC suppression process (SOC promotion process) based on the comparison result transmitted from the server 300.
[0083] In the above embodiment, an example has been shown in which the SOC adjustment process is performed by adjusting the output upper limit value of the temperature regulator 190, but the present disclosure is not limited to this. For example, the server 300 may set a target SOC when the traveling electric vehicle 100 arrives at the destination. In this case, the server 300 may adjust the SOC when the electric vehicle 100 arrives at the destination to be the target SOC by changing (adjusting) the travel route, constants (suitable values / threshold values), various maps, power consumption, regeneration amount, and the like of the electric vehicle 100. In this case, for example, the target SOC may be set to 80% in the SOC suppression process and to 20% in the SOC promotion process, so that the SOC when charging is performed at the destination can be adjusted based on the market value of electricity.
[0084] For example, as shown in FIG. 8, the SOC suppression process may include a process for limiting the output of the MG 142 of the electric vehicle 100 without performing a process for lowering the output upper limit value of the temperature regulator 190 of the electric vehicle 100 (an example of the “second process” of the present disclosure).
[0085] In the example shown in FIG. 8, the output upper limit value of MG 142 is maximum when the outside air temperature is a predetermined temperature T. Furthermore, in a range where the outside air temperature is equal to or higher than the predetermined temperature T, the higher the outside air temperature, the lower the output upper limit value of MG 142. Furthermore, in a range where the outside air temperature is equal to or lower than the predetermined temperature T, the lower the outside air temperature, the higher the output upper limit value of MG 142. This makes it possible to suppress the output (power consumption) of MG 142 when the power consumption of cooling device 191 is large due to a high outside air temperature. Furthermore, it is possible to suppress the output (power consumption) of MG 142 when the power consumption of heater 192 is large due to a low outside air temperature. As a result, a decrease in the SOC of electric vehicle 100 is suppressed.
[0086] In the above embodiment, the electric vehicle management device 1000 includes the server 300 and the server 600, but the present disclosure is not limited to this. The electric vehicle management device 1000 may include only one server having the functions of both the server 300 and the server 600.
[0087] The above-described various modifications may be implemented in any combination. The embodiments disclosed herein should be considered to be illustrative and not restrictive in all respects. The scope of the present disclosure is defined by the claims, not by the description of the embodiments described above, and is intended to include all modifications within the meaning and scope of the claims. [Explanation of symbols]
[0088] 100 electric vehicle, 142 MG (motor generator), 190 temperature regulator, 330, 630 communication device (communication unit), 310, 610 processor (control unit), 1000 electric vehicle management device, A threshold price (first threshold price), B threshold price (second threshold price), PG power system.
Claims
1. An electric vehicle management device that manages electric vehicles that can be charged from a power grid, a communication unit that acquires information on a market price of electricity through communication and communicates with the electric vehicle; a control unit that calculates a predicted value of the market price based on the market price information acquired by the communication unit, The control unit performs an SOC adjustment process for adjusting the SOC of the electric vehicle during travel based on the calculated predicted value.
2. The electric vehicle management device according to claim 1 , wherein the control unit performs the SOC adjustment process based on a magnitude relationship between the predicted value and a predetermined threshold price.
3. the predetermined threshold price includes a first threshold price; the SOC adjustment process includes an SOC suppression process for suppressing a decrease in the SOC of the electric vehicle during traveling, The electric vehicle management device according to claim 2 , wherein the control unit performs the SOC suppression process when the predicted value is equal to or greater than the first threshold price.
4. The electric vehicle management device according to claim 3 , wherein the SOC suppression process includes a first process for lowering an output upper limit value of a temperature regulator of the electric vehicle compared to a case where the predicted value is less than the first threshold price.
5. The electric vehicle management device according to claim 3 , wherein the SOC suppression process includes a second process for limiting an output of a motor generator of the electric vehicle without performing a process for lowering an output upper limit value of a temperature regulator of the electric vehicle.
6. the predetermined threshold price includes a second threshold price that is less than the first threshold price; The SOC adjustment process includes an SOC promotion process for promoting a reduction in the SOC of the electric vehicle during running, The electric vehicle management device according to any one of claims 3 to 5, wherein the control unit performs the SOC promotion process when the predicted value is equal to or less than the second threshold price.
7. The control unit detects a scheduled time for the next charging, calculates the predicted value at the scheduled time, and performs the SOC adjustment process based on the predicted value. The electric vehicle management device according to any one of claims 1 to 6.
8. The control unit detects a scheduled time for the next charging, and performs the SOC adjustment process based on the detection of the scheduled time. The electric vehicle management device according to any one of claims 1 to 7.
9. The electric vehicle management device according to any one of claims 1 to 8, wherein the control unit calculates the predicted value before a gate close of an electricity trading market.
10. An electric vehicle that can be charged from a power grid; an electric vehicle management device for managing the electric vehicle, The electric vehicle management device includes a communication unit that acquires information on a market price of electricity through communication and communicates with the electric vehicle, and a control unit that calculates a predicted value of the market price based on the market price information acquired by the communication unit, The control unit performs processing to adjust the SOC of the electric vehicle while the vehicle is traveling based on the calculated predicted value.
Citation Information
Patent Citations
Hybrid vehicle, charging device and hybrid vehicle operation system
JP2008308030A
Charging / discharging apparatus and charging / discharging method
JP2012016271A
Vehicle charging control method and vehicle charging control system
JP2013215084A
Apparatus and method for controlling energy navigation
JP2014056589A
Vehicle controller and vehicle
JP2019158484A