Recommendation method, recommendation program, and recommendation device

The recommendation method and system address inefficiencies in maintenance plan selection by prioritizing plans based on defect similarity and additional context, enhancing user efficiency in industrial settings.

WO2024203726A1PCT designated stage expired Publication Date: 2024-10-03YOKOGAWA ELECTRIC CORP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2024/011036
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-31
Filing Date
2024-03-21
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

Conventional recommendation technologies for maintenance plans in industrial settings often fail to improve user efficiency, as they either recommend impractical plans or require unnecessary work in filtering through multiple options, leading to inefficiencies in decision-making.

Method used

A recommendation method and system that acquires defect information and additional context, specifies maintenance plans associated with similar defects, determines priority based on this information, and presents plans accordingly, thereby streamlining the selection process.

Benefits of technology

This approach enhances user efficiency by prioritizing practical maintenance plans, reducing unnecessary work and improving decision-making speed and accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024011036_03102024_PF_FP_ABST
    Figure JP2024011036_03102024_PF_FP_ABST
Patent Text Reader

Abstract

A recommendation device includes an acquisition unit, a specification unit, a determination unit, and a presentation unit. The acquisition unit acquires defect information that is information of a defect that has occurred in a plant and additional information different from the defect information. The specification unit specifies, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information. The determination unit determines the degree of priority of each of the specified maintenance plans on the basis of the additional information. The presentation unit presents the maintenance plans according to the degree of priority.
Need to check novelty before this filing date? Find Prior Art

Description

RECOMMENDATION METHOD, RECOMMENDATION PROGRAM, AND RECOMMENDATION DEVICE

[0001] The present invention relates to a recommendation method, a recommendation program, and a recommendation device.

[0002] A technology that supports user's decision making on the basis of a history is known. For example, in the field of content distribution via the Internet, a technology in which content expected to be preferred by a user is recommended on the basis of a viewing history of the user is used. Further, in the field of retail, a technology in which a product highly likely to be purchased by a user is recommended on the basis of a purchase history of the user is used.

[0003] Such technology that supports user's decision making on the basis of a history is useful also in the field of industry. For example, a technology in which a maintenance plan of industrial machinery in a plant is automatically generated on the basis of a result of inspection performed in the past is known. The plant is an oil plant, a petrochemical plant, a chemical plant, a gas plant, or the like. In the plant, installations including industrial machinery, etc. operate, and chemical products, etc. are generated.

[0004] Japanese Laid-open Patent Publication No. 2022-19230

[0005] However, the conventional technology has a problem that the efficiency of user's work cannot be improved in some cases.

[0006] For example, among a plurality of maintenance plans effective for a defect, maintenance plans that can be practically chosen by a user are preferentially recommended; thereby, the user can make a quick decision on which maintenance plan to choose.

[0007] Conversely, when maintenance plans that are, although effective for a defect, practically difficult to implement are recommended, the user needs to perform unnecessary work such as narrowing down the recommended maintenance plans.

[0008] In an aspect, an object is to provide a recommendation method, a recommendation program, and a recommendation device capable of improving the efficiency of user's work.

[0009] According to one aspect of embodiments, a recommendation method includes a computer's executing: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority.

[0010] According to one aspect of embodiments, a recommendation program causes a computer to execute: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority.

[0011] According to one aspect of embodiments, a recommendation device includes: an acquisition unit that acquires defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; a specification unit that specifies, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; a determination unit that determines a degree of priority of each of the specified maintenance plans on the basis of the additional information; and a presentation unit that presents the maintenance plans according to the degree of priority.

[0012] According to an embodiment, the efficiency of user's work can be improved.

[0013] Fig. 1 is a diagram illustrating a configuration example of a recommendation system according to a first embodiment.Fig. 2 is a diagram illustrating a flow of processing of the recommendation system.Fig. 3 is a diagram illustrating a configuration example of a recommendation device.Fig. 4 is a diagram illustrating an example of a defect DB.Fig. 5 is a diagram illustrating an example of a maintenance plan DB.Fig. 6 is a diagram illustrating an example of a danger information DB.Fig. 7 is a diagram illustrating an example of a selection history DB.Fig. 8 is a diagram illustrating an example of a defect report screen.Fig. 9 is a diagram illustrating an example of a maintenance plan search screen.Fig. 10 is a diagram illustrating an example of a rating table.Fig. 11 is a diagram illustrating an example of a rating table.Fig. 12 is a diagram illustrating an example of the maintenance plan search screen.Fig. 13 is a diagram illustrating an example of the maintenance plan search screen.Fig. 14 is a diagram illustrating an example of a graph display screen.Fig. 15 is a flowchart illustrating a flow of processing of the recommendation device.Fig. 16 is a diagram describing a hardware configuration example.

[0014] Hereinbelow, embodiments of a recommendation method, a recommendation program, and a recommendation device disclosed by the present application are described in detail based on the drawings. Note that the invention of the present application is not limited by the embodiments described here. Further, the same elements are denoted by the same reference signs, and a repeated description is omitted as appropriate. Further, the embodiments can be combined to the extent that there is no inconsistency, as appropriate.

[0015] A configuration of a recommendation system of a first embodiment will now be described using Fig. 1. Fig. 1 is a diagram illustrating a configuration example of a recommendation system according to the first embodiment.

[0016] As illustrated in Fig. 1, a recommendation system 1 includes a recommendation device 10, a manager terminal device 20, an engineer terminal device 30, and an information provision server 40. Each of the recommendation device 10 and the information provision server 40 is, for example, a server device. Each of the manager terminal device 20 and the engineer terminal device 30 is, for example, a stationary or portable terminal device such as a personal computer or a smartphone.

[0017] The recommendation device 10, the manager terminal device 20, the engineer terminal device 30, and the information provision server 40 are connected to each other via a network N. For example, the network N is the Internet. The network N may also be a LAN (local area network) constructed in a facility such as a plant.

[0018] Here, the recommendation system 1 is a system for recommending maintenance plans regarding a plant. For example, the recommendation system 1 presents a plurality of maintenance plans for defects related to a plant. At this time, a manager of the plant can actually choose any of the presented plurality of maintenance plans. Thereby, the recommendation system 1 can support decision making of the manager of the plant, and can improve the efficiency of manager's work.

[0019] The plant in the present embodiment is, for example, an oil plant, a petrochemical plant, a chemical plant, or a gas plant. By the plant operating, products such as LNG (liquefied natural gas), resins (plastics, nylon, etc.), and chemical products are obtained.

[0020] The plant includes a factory facility, a machine facility, a production facility, a power generation facility, a storage facility, a facility at a well source for mining oil, natural gas, or the like, etc. In the plant, field equipment for acquiring information regarding the state of the plant is provided in addition to installation equipment for generating products.

[0021] The field equipment includes sensor equipment, operating equipment, and alarm equipment. For example, the sensor equipment is a pressure sensor, a temperature sensor, a pH sensor, a speed sensor, an acceleration sensor, or the like. For example, the operating equipment is a valve, a pump, a fan, or the like, and is driven by a motor, an actuator, or the like. For example, the alarm equipment is a lamp, a speaker, or the like.

[0022] Here, various defects will occur in the plant. The defect is an abnormality of a facility, installation equipment, field equipment, or the like, and is an event that adversely affects the plant. The adverse effect includes a stop and a delay of production of products, an increase in cost (for example, monetary cost, human cost, or temporal cost), and the like.

[0023] When a defect occurs, the manager of the plant prepares a maintenance plan for solving the defect. The maintenance plan is, for example, repair, cleaning, parts replacement, etc. of the installation equipment in which the defect has occurred. Note that, regardless of whether a defect has occurred or not, the maintenance plan may be implemented to prevent a defect.

[0024] Fig. 2 is a diagram illustrating a flow of processing of the recommendation system. A manager U2 and an engineer U3 illustrated in Fig. 2 are users. The manager U2 prepares a maintenance plan for a defect of the plant. The engineer U3 operates installations of the plant. Further, the engineer U3 reports a defect of the plant found.

[0025] The recommendation system 1 accepts the report of the defect by the engineer U3. Further, the recommendation system 1 presents candidates for the maintenance plan to the manager U2 according to the direction of the defect.

[0026] As illustrated in Fig. 2, the engineer U3 reports the defect of the plant to the recommendation device 10 via the engineer terminal device 30 (Step S1). For example, the engineer terminal device 30 transmits, to the recommendation device 10, information regarding the defect inputted by the engineer U3.

[0027] The report of a defect is not limited to being performed by the engineer U3, and may be performed by other users including the manager U2. For example, the manager U2 can report a defect of the plant to the recommendation device 10 via the manager terminal device 20.

[0028] When the defect is reported, the manager U2 inputs additional information via the manager terminal device 20 (Step S2). The additional information is information for determining the degrees of priority of candidates for the maintenance plan presented by the recommendation device 10.

[0029] Further, when the defect is reported, the information provision server 40 provides additional information to the recommendation device 10 (Step S3). For example, the information provision server 40 provides additional information in response to a request from the recommendation device 10.

[0030] For example, the additional information provided by the manager U2 is information indicating what kind of information regarding the maintenance plan to place emphasis on. For example, the additional information provided by the manager U2 is information such as whether or not or how much to place emphasis on the expense for the maintenance plan.

[0031] On the other hand, the additional information provided by the information provision server 40 includes information of the outside not directly related to the maintenance plan. For example, the additional information provided by the information provision server 40 includes information of weather, information regarding an operation plan of the plant, etc.

[0032] Subsequently, the recommendation device 10 specifies maintenance plans similar to the reported defect (Step S4). First, the recommendation device 10 extracts defects similar to the reported defect from previously accumulated information in which information of defects and maintenance plans are associated with each other. Further, the recommendation device 10 specifies maintenance plans associated with the extracted defects.

[0033] The information in which information of defects and maintenance plans are associated with each other may be accumulated in the recommendation device 10 in advance, or may be inputted to the recommendation device 10 when Step S4 is executed.

[0034] Here, the recommendation device 10 determines the degrees of priority of the specified maintenance plans on the basis of additional information acquired from the manager U2 and the information provision server 40 (Step S5). Then, the recommendation device 10 presents the maintenance plans according to the degree of priority (Step S6).

[0035] (Functional configuration) A configuration of the recommendation device 10 will now be described using Fig. 3. Fig. 3 is a diagram illustrating a configuration example of the recommendation device. As illustrated in Fig. 3, the recommendation device 10 includes a communication unit 11, a storage unit 12, and a control unit 13. The functional units included in the recommendation device 10 are not limited to those illustrated in the drawing, and the recommendation device 10 may include, for example, a functional unit such as an interface on which transmission and reception of data are performed with output devices such as a display and a speaker, or the like.

[0036] The communication unit 11 is a processing unit that controls communication with other devices, and is obtained by using, for example, a communication interface or the like. For example, the communication unit 11 controls communication with the manager terminal device 20, the engineer terminal device 30, and the information provision server 40.

[0037] The storage unit 12 is a processing unit that stores various pieces of data, various programs to be executed by the control unit 13, etc. The storage unit 12 is obtained by using, for example, a memory, a hard disk, or the like. The storage unit 12 stores various pieces of data generated in processing executed by the recommendation device 10, such as data obtained in the course of execution of various pieces of processing by the control unit 13 and processing results obtained by execution of various pieces of processing.

[0038] The storage unit 12 stores a defect DB 121, a maintenance plan DB 122, a danger information DB 123, and a selection history DB 124.

[0039] The defect DB 121 accumulates information of defects that have occurred. Fig. 4 is a diagram illustrating an example of the defect DB. As illustrated in Fig. 4, the defect DB 121 includes items of "defect ID", "date and time", "position", "team", "degree of importance", "problem", and "detailed information".

[0040] The item "defect ID" is information for identifying the defect. The item "date and time" is the date and time when the defect occurred or the date and time when information of the defect was registered in the defect DB 121. The item "position" is information indicating a position in the plant where the defect has occurred. The item "team" is information indicating a team tied as an entity in charge of a facility, an installation, or equipment of a defect object.

[0041] The item "degree of importance" is information indicating the degree of importance of the defect. For example, the "degree of importance" is any of "very high", "high", "medium", and "low".

[0042] The item "problem" is information indicating an outline of the defect, and is described by a user who registers (or reports) the defect. The item "detailed information" is detailed information of the defect, and is described by a user who registers (or reports) the defect.

[0043] For example, Fig. 4 indicates that the defect identified by "DF0151" is one that occurred in a position of "Area_1" on the date and time "2022 / 9 / 1, 13:01" and of which the team in charge of the defect object is "Team_1" and the degree of importance is "low". Further, Fig. 4 indicates that the outline of the defect identified by "DF0151" is "gas leakage" and the detailed information is "gas leakage in Area_1".

[0044] The maintenance plan DB 122 accumulates information of implemented maintenance plans. Fig. 5 is a diagram illustrating an example of the maintenance plan DB. As illustrated in Fig. 5, the maintenance plan DB 122 includes items of "maintenance plan ID", "date and time", "type of defect", "factor of occurrence", "solution", "component", "necessary preparation", "safety requirements", "number of personnel", "required time", "expense", and "defect ID".

[0045] The item "maintenance plan ID" is information for identifying the maintenance plan. The item "date and time" is the date and time when the maintenance plan was implemented (the date and time of the start or completion of implementation) or the date and time when information of the maintenance plan was registered in the maintenance plan DB 122.

[0046] The item "type of defect" is information indicating the type of the defect corresponding to the maintenance plan. For example, the defect corresponding to the maintenance plan is a defect to be solved by the maintenance plan or a defect expected to be prevented from occurring by the maintenance plan. The item "factor of occurrence" is information indicating the factor of the occurrence of the defect corresponding to the maintenance plan. The item "solution" is information indicating a specific solution to the defect corresponding to the maintenance plan. The item "component" is a component having close connection with the maintenance plan or the defect corresponding to the maintenance plan.

[0047] The item "necessary preparation" is information of articles, skills, procedures, etc. necessary for the maintenance plan. The item "safety requirements" is requirements regarding safety required in the maintenance plan. The item "number of personnel" is the number of personnel (human cost) required to implement the maintenance plan. The item "required time" is the time (temporal cost) required to implement the maintenance plan. The item "expense" is the expense (monetary cost) required to implement the maintenance plan. The item "defect ID" is information for associating the maintenance plan and the defect with each other.

[0048] For example, Fig. 5 indicates that the maintenance plan identified by "MT0211" is one that was implemented on the date and time "2022 / 9 / 1, 14:21". Further, Fig. 5 indicates that the defect identified by "DF0151" corresponds to the maintenance plan identified by "MT0211".

[0049] Further, Fig. 5 indicates that the type of the defect corresponding to the maintenance plan identified by "MT0211" is "leakage", the factor of occurrence is "aging degradation", the solution is "repair and improvement", and the component is a "valve".

[0050] Further, Fig. 5 indicates that the preparation necessary for the maintenance plan identified by "MT0211" is "scaffolding installation and a container" and the safety requirements are "gas detection and wearing a harness".

[0051] Further, Fig. 5 indicates that the number of personnel required for the maintenance plan identified by "MT0211" was "five", the required time was "six hours", and the expense was "¥1,500,000".

[0052] The danger information DB 123 accumulates information regarding danger for objects related to maintenance plans. Fig. 6 is a diagram illustrating an example of the danger information DB. As illustrated in Fig. 6, the danger information DB 123 includes items of "object", "degree of danger", "type of danger", and "safety requirements".

[0053] The item "object" is information for identifying the object indicating danger. For example, the item "object" is information that identifies a position, a facility, an installation, equipment, a component, or the like in the plant.

[0054] The item "degree of danger" is information indicating the magnitude of the danger of the object. For example, the "degree of danger" is any of "high", "medium", and "low".

[0055] The item "type of danger" is information regarding the type of danger that can occur in the object. The item "safety requirements" is requirements regarding safety required according to the type of danger.

[0056] For example, Fig. 6 indicates that the degree of danger of "Area_1" is "medium", the type of danger that can occur is one related to a "high place", and "wearing a harness" is required as a safety requirement.

[0057] The selection history DB 124 accumulates information indicating the number of times that the maintenance plan was selected for actual implementation, according to the level of skill of the user who selected the maintenance plan. Fig. 7 is a diagram illustrating an example of the selection history DB. As illustrated in Fig. 7, the selection history DB 124 includes items of "maintenance plan ID" and "number of times of selection".

[0058] The item "maintenance plan ID" is information for identifying the maintenance plan. The item "number of times of selection" is the number of times of selection according to the user's level of skill.

[0059] For example, Fig. 7 indicates that the number of times that the maintenance plan identified by "MT0211" was selected by the user having a "high" level of skill is "0", the number of times that the maintenance plan was selected by the user having a "medium" level of skill is "2", and the number of times that the maintenance plan was selected by the user having a "low" level of skill is "3".

[0060] Returning to Fig. 3, the control unit 13 is a processing unit that governs the entire recommendation device 10. The control unit 13 is obtained by using, for example, a processor or the like. The control unit 13 includes a display control unit 131, an acquisition unit 132, a specification unit 133, and a determination unit 134.

[0061] The display control unit 131 controls displaying of screens. The display control unit 131 can cause the manager terminal device 20 and the engineer terminal device 30 to display screens.

[0062] For example, the display control unit 131 functions as a web server. That is, the display control unit 131 generates data (for example, an HTML file) for displaying a screen. Then, the display control unit 131 transmits the generated data to the manager terminal device 20 and the engineer terminal device 30.

[0063] Each of the manager terminal device 20 and the engineer terminal device 30 causes a web browser or the like to display a screen based on the data received from the display control unit 131.

[0064] Each of the manager terminal device 20 and the engineer terminal device 30 may cause screens to be displayed by a dedicated application of the recommendation system 1 instead of a web browser. At this time, the display control unit 131 transmits data in a format adapted to the application.

[0065] The acquisition unit 132 acquires defect information that is information of a defect that has occurred in the plant and additional information different from the defect information.

[0066] The defect information is information of a defect reported to the recommendation system 1. For example, the defect information is inputted via a defect report screen that the display control unit 131 causes the engineer terminal device 30 to display.

[0067] The defect report screen will now be described using Fig. 8. Fig. 8 is a diagram illustrating an example of the defect report screen.

[0068] As illustrated in Fig. 8, pull-down list 61a, pull-down list 61b, pull-down list 61c, text box 61d, text box 61e, and button 61f are displayed on a defect report screen 61.

[0069] The pull-down list displays one or more options. One of candidates displayed by the pull-down list is selected by the user.

[0070] Pull-down list 61a displays "Area_1", "Area_2", "Area_3", and Area_4" as candidates for predetermined positions in the plant.

[0071] Pull-down list 61b displays "Team_1", "Team_2", "Team_3", and "Team_4" as candidates for predetermined teams.

[0072] Pull-down list 61c displays "very high", "high", "medium", and "low" as candidates for predetermined degrees of importance.

[0073] Text box 61d and text box 61e accept input of text by the user. However, it is assumed that the number of characters that can be inputted to text box 61d is set smaller than the number of characters that can be inputted to text box 61e.

[0074] When button 61f is pressed, the contents inputted to the objects (the pull-down lists and the text boxes) of the defect report screen 61 are transmitted to the recommendation device 10. Thereby, the acquisition unit 132 can acquire defect information.

[0075] For example, when button 61f is pressed in the state illustrated in Fig. 8, the acquisition unit 132 acquires defect information in which the position is "Area_2", the team is "Team_3", the degree of importance is "medium", the problem is "gas leakage", and the detailed information is "carbon dioxide leaks from a tank".

[0076] When the defect is reported, the acquisition unit 132 acquires additional information. The additional information is information for determining the degrees of priority of candidates for the maintenance plan presented by the recommendation device 10. For example, the additional information is inputted via a maintenance plan search screen that the display control unit 131 causes the manager terminal device 20 to display.

[0077] The maintenance plan search screen will now be described using Fig. 9. Fig. 9 is a diagram illustrating an example of the maintenance plan search screen.

[0078] As illustrated in Fig. 9, a display area 62a, text box 621b, seek bar 622b, text box 621c, seek bar 622c, text box 621d, seek bar 622d, check box 62e, check box 62f, check box 62g, and button 62h are displayed on a maintenance plan search screen 62.

[0079] The seek bar specifies a parameter according to the position of the box on the bar. The user can adjust the position of the box on the bar.

[0080] In text box 621b, a specified value of the additional information "number of personnel" is inputted. Seek bar 622b specifies the degree of emphasis on the additional information "number of personnel".

[0081] In text box 621c, a specified value of the additional information "allowable time" is inputted. Seek bar 622c specifies the degree of emphasis on the additional information "allowable time".

[0082] In text box 621d, a specified value of the additional information "expense" is inputted. Seek bar 622d specifies the degree of emphasis on the additional information "expense".

[0083] Check box 62g specifies whether or not to take into account the additional information "danger information". Check box 62f specifies whether or not to take into account the additional information "outside information". Check box 62e specifies whether or not to take into account the additional information "past-selection history".

[0084] When button 61h is pressed, processing of specifying maintenance plans and processing of presenting maintenance plans are started on the basis of the defect information and the additional information inputted to the maintenance plan search screen 62.

[0085] For example, when button 62h is pressed in the state illustrated in Fig. 9, the acquisition unit 132 acquires information that the specified values of the pieces of additional information "number of personnel", "allowable time", and "expense" are unspecified, the degrees of emphasis on these are a predetermined value (100%), and the pieces of additional information "danger information", "outside information", and "past-selection history" are not taken into account.

[0086] From information of maintenance plans accumulated in advance in association with defects, the specification unit 133 specifies maintenance plans associated with defects similar to the defect indicated by the defect information.

[0087] First, the specification unit 133 transforms the defect information and the defect DB 121 into rating tables. The rating tables will now be described using Figs. 10 and 11. Figs. 10 and 11 are diagrams illustrating examples of rating tables.

[0088] Herein, it is assumed that the position of the defect information is "Area_2", the team is "Team_3", the degree of importance is "medium", the problem is "gas leakage", and the detailed information is "carbon dioxide leaks from a tank".

[0089] The specification unit 133 transforms the defect information to obtain the rating table illustrated in Fig. 10. As illustrated in Fig. 10, the "place", the "team", and the "degree of importance" included in the defect information are reflected in the rating table.

[0090] In the rating table, the value of an item included in the defect information is "5", and the value of an item not included in the defect information is "1".

[0091] Since the position of the defect information is "Area_2", the values of "Area_1", "Area_3", and "Area_4" in the rating table are "1", and the value of "Area_2" is "5".

[0092] The rating table is represented as a vector. For example, the rating table illustrated in Fig. 10 corresponds to a vector (1, 5, 1, 1, 1, 1, 5, 1, 1, 1, 5, 1).

[0093] Further, the specification unit 133 transforms the defect DB 121 to obtain the rating tables illustrated in Fig. 11. Fig. 11 illustrates rating tables of the defects "DF0151" and "DF0152".

[0094] The rating table of the defect "DF0151" corresponds to a vector (5, 1, 1, 1, 5, 1, 1, 1, 1, 1, 1, 5). The rating table of the defect "DF0152" corresponds to a vector (5, 1, 1, 1, 1, 1, 5, 1, 1, 1, 1, 5).

[0095] The specification unit 133 calculates the degree of similarity between the rating table obtained by transforming the defect information and each of the rating tables obtained by transforming the defect DB 121. At this time, the specification unit 133 regards the rating table as a vector, and calculates the degree of cosine similarity between vectors by Formula (1).

[0096]

[0097] Here, A and B are vectors for which the degree of similarity is to be calculated. Further, for example, Aiis the i-th element of the vector A. n is the number of elements of the vector. In the examples of Figs. 10 and 11, n = 12.

[0098] Further, the specification unit 133 uses TF-IDF as in Formula (2) to calculate the degree of similarity between defects in the "problem" and the "detailed information", which are, of the defect information and the information included in the defect DB 121, pieces of information of text that have not been transformed into rating tables. Herein, the "problem" and the "detailed information" of each defect are regarded as a document.

[0099]

[0100] Here, t is the number of appearances of the target word in the "problem" and the "detailed information" of the defect information. n is the number of documents accumulated in the defect DB 121. df is the number of documents including the target word among the documents accumulated in the defect DB 121.

[0101] The degree of similarity calculated by Formula (1) is denoted by Sim1, and the degree of similarity calculated by Formula (2) is denoted by Sim2; the specification unit 133 calculates the final degree of similarity as in Formula (3).

[0102]

[0103] Here, w is a weight set in advance. w is a value not less than 0 and not more than 1, and may be, for example, 0.5.

[0104] The method for calculating the degree of similarity between defects is not limited to the method described here. The specification unit 133 can calculate the degree of similarity between defects by a known arbitrary method for calculating the degree of similarity between pieces of data.

[0105] The specification unit 133 extracts a certain number of defects from the defect DB 121 in descending order of the degree of similarity to the defect information. For example, the specification unit 133 extracts about three to twenty defects.

[0106] Further, the specification unit 133 specifies maintenance plans corresponding to the extracted defects from among the maintenance plans accumulated in the maintenance plan DB 122. For example, the specification unit 133 specifies maintenance plans corresponding to the defects on the basis of the item "defect ID" of the maintenance plan DB 122.

[0107] On the basis of additional information, the determination unit 134 determines the degree of priority of each of the maintenance plans specified by the specification unit 133. The display control unit 131 presents the maintenance plans according to the degree of priority.

[0108] When the degree of priority is determined by the determination unit 134, as illustrated in Fig. 12, the display control unit 131 causes the maintenance plan search screen 62 to display button 62i and a search result 62j. Fig. 12 is a diagram illustrating an example of the maintenance plan search screen.

[0109] In the search result 62j, the maintenance plans specified by the specification unit 133 are displayed in descending order of the degree of priority determined by the determination unit 134. In the example of Fig. 12, the specification unit 133 has specified the maintenance plans "MT0213", "MT0211", and "MT0215". Further, the determination unit 134 has determined the highest degree of priority for "MT0213", and has determined the subsequent highest degrees of priority in the order of "MT0211" and "MT0215".

[0110] The acquisition unit 132 performs acquisition processing of acquiring, as additional information, a demand inputted by the user or a constraint condition generated on the basis of a demand. The user can input a demand via the maintenance plan search screen 62. The acquisition unit 132 generates a constraint condition on the basis of the input contents of the maintenance plan search screen 62.

[0111] For example, the acquisition unit 132 acquires, as additional information, the degree of emphasis on each of the number of personnel, the allowable time, and the expense associated with the maintenance plan. It is assumed that all of the number of personnel, the allowable time, and the expense are desirably smaller.

[0112] For example, in the case where a value (the number of personnel, the allowable time, or the expense) of a maintenance plan exceeds a specified value inputted on the maintenance plan search screen 62, the determination unit 134 reduces the degree of priority of the maintenance plan. At this time, as the value indicated by the seek bar becomes larger, the determination unit 134 reduces the degree of priority more.

[0113] Here, the number of personnel of a maintenance plan is denoted by a1, the required time is denoted by a2, and the expense is denoted by a3. The determination unit 134 calculates the degree of priority of the maintenance plan as 1 / ((w1× a1) × (w2× a2) × (w3× a3)).

[0114] The seek bar displays values from 0% to 200% (from 0 to 2). The determination unit 134 sets the weights w1, w2, and w3to values equal to the values indicated by the seek bars. However, in the case where a1, a2, or a3does not exceed the specified value, the determination unit 134 may limit the weight w1, w2, or w3to 1 or less; and in the case where a1, a2, or a3exceeds the specified value, the determination unit 134 may further increase the weight w1, w2, or w3. That is, the determination unit 134 regards the specified value as the upper limit value, and in the case where the value of the item exceeds the upper limit value, gives a penalty to the weight (for example, increases the degree of increase).

[0115] That is, in the case where a specified value is specified, the determination unit 134 suppresses a reduction in the degree of priority for, among the number of personnel, the allowable time, and the expense of the maintenance plan, an item that does not exceed the specified value, and more considerably reduces the degree of priority for an item that exceeds the specified value.

[0116] In the example of Fig. 12, a specified value of the expense, "1000000", is inputted. The values of the seek bars of the number of personnel and the allowable time are "100%". Further, the value of the seek bar of the expense is "200%".

[0117] For example, the values of the items of the maintenance plan "MT0213" are (a1, a2, a3) = (4, 8, 800000). Therefore, in the example of Fig. 12, the determination unit 134 sets (w1, w2, w3) = (1, 1, 1) and calculates the degree of priority. In this case, since the expense does not exceed the specified value, the determination unit 134 sets the weight w3of the expense to the upper limit value, "1".

[0118] For example, the values of the items of the maintenance plan "MT0211" are (a1, a2, a3) = (5, 6, 1500000). Therefore, in the example of Fig. 12, the determination unit 134 sets (w1, w2, w3) = (1, 1, 4) and calculates the degree of priority. In this case, since the expense exceeds the specified value, the determination unit 134 sets the weight w3of the expense to "4", which is twice "2".

[0119] Further, in the case where a specified value is inputted, the determination unit 134 may change the upper limit value according to the degree of emphasis of the user (the value of the seek bar). For example, in the case where the value of the seek bar is "100%", the determination unit 134 uses the specified value as it is as the upper limit value, as described hereinabove.

[0120] On the other hand, the determination unit 134 may change the upper limit value according to the value of the seek bar. For example, as the value of the seek bar becomes larger, the determination unit 134 reduces the upper limit value (increases the penalty). For example, when the value of the seek bar is denoted by r (0 <= r <= 2), the determination unit 134 calculates the upper limit value as "specified value × (1 + 0.2 × (1 - r))". In this case, the upper limit value changes between 0.8 times and 1.2 times the specified value.

[0121] For example, when the specified value of the required time is "10 hours" and the value of the seek bar is "0%", since r = 0, the determination unit 134 calculates the upper limit value as "10 hours × (1 + (0.2 × (1 - 0%))) = 12 hours".

[0122] For example, when the specified value of the expense is "1000000" and the value of the seek bar is "200%", since r = 2, the determination unit 134 calculates the upper limit value as "1000000 × (1 + (0.2 × (1 -2))) = 800000".

[0123] The determination unit 134 can determine the degree of priority while taking into account information regarding danger. The acquisition unit 132 acquires, as additional information, information regarding danger associated with the maintenance plan.

[0124] In the case where check box 62e is checked, the acquisition unit 132 refers to the danger information DB 123, and acquires the degree of danger corresponding to the maintenance plan. For example, the position of the defect "DF0151" corresponding to the maintenance plan "MT0213" is "Area_1". Thus, the determination unit 134 acquires, from the danger information DB 123, "medium" as the degree of danger of the maintenance plan "MT0213". As the acquired degree of danger becomes higher, the determination unit 134 reduces the degree of priority of the maintenance plan.

[0125] The determination unit 134 can determine the degree of priority on the basis of, for each maintenance plan, the number of times that the maintenance plan was chosen in the past and the level of skill of the user who chose the maintenance plan. In this case, the acquisition unit 132 acquires, as additional information, information based on, for each maintenance plan, the number of times that the maintenance plan was chosen in the past and the level of skill of the user who chose the maintenance plan.

[0126] In the case where check box 62g is checked, the acquisition unit 132 acquires a selection history for each maintenance plan from the selection history DB 124.

[0127] The determination unit 134 sets a larger degree of priority for a maintenance plan that was selection by the user having a "high" level of skill a larger number of times or at a higher rate.

[0128] Further, the determination unit 134 can acquire additional information not only from the user but also from the outside. For example, the acquisition unit 132 acquires, from the information provision server 40, information regarding weather or an operation plan of the plant as additional information.

[0129] For example, when information regarding weather indicates that it will rain or be a typhoon, the determination unit 134 reduces the degree of priority of a maintenance plan involving outdoor work. In this case, the determination unit 134 may increase the degree of priority of a maintenance plan that will be completed before rain or a typhoon starts.

[0130] Further, for example, when an operation plan of the plant indicates that a maintenance plan of the entire plant is to be performed within a certain number of days, the determination unit 134 reduces the degree of priority of a maintenance plan similar to contents included in the overall maintenance plan.

[0131] Further, for example, the determination unit 134 decides whether a shrinking operation of the plant in a certain period should be permitted or not according to an operation plan of the plant and the inventory status of the replacement parts. Further, the determination unit 134 may acquire, from the information provision server 40, a period in which a shrinking operation of the plant is permitted and a period in which a shrinking operation of the plant is not permitted. Then, for the period in which a shrinking operation is not permitted, the determination unit 134 reduces the degree of priority of a maintenance plan involving a shrinking operation.

[0132] Further, for example, when an operation plan of the plant indicates that the production of products cannot be stopped, the determination unit 134 increases the degree of priority of a maintenance plan in which there is no need to stop the operation of the plant. The determination unit 134 decides whether there is a need to stop the operation of the plant or not from items such as "necessary preparation" and "safety requirements" of the maintenance plan.

[0133] Further, for example, for a period in which neither a stop nor a shrinking operation of the plant is permitted, the determination unit 134 increases the degree of priority of a stopgap maintenance plan. For example, the determination unit 134 increases the degree of priority of a stopgap maintenance plan by, regardless of the user's input, determining the degree of priority with emphasis on the required time.

[0134] Thus, the determination unit 134 acquires a demand of the user via the maintenance plan search screen 62. A value of the seek bar and a specified value are acquired as demanded by the user. Further, the determination unit 134 generates a constraint condition on the basis of the acquired demand of the user. The constraint condition is a condition for determining the degree of priority according to the demand of the user.

[0135] Fig. 13 is a diagram illustrating an example of the maintenance plan search screen. As illustrated in Fig. 13, in the case where additional information different from that of Fig. 12 is inputted, the degree of priority calculated by the determination unit 134 is changed, and the display order of maintenance plans in the search result 62j is changed.

[0136] Thus, the display control unit 131 presents maintenance plans according to the degree of priority. The display control unit 131 displays a maintenance plan having a larger degree of priority on a higher side of the list. Further, the display control unit 131 may hide a maintenance plan having a degree of priority not more than a standard value. Further, the display control unit 131 may display a certain number of maintenance plans having higher degrees of priority in a highlighted manner by differentiating the font and the style.

[0137] When button 62i illustrated in Figs. 12 and 13 is pressed, the display control unit 131 causes the manager terminal device 20 to display a graph display screen. Fig. 14 is a diagram illustrating an example of the graph display screen.

[0138] As illustrated in Fig. 14, on a graph display screen 63, figures representing maintenance plans such as "MT0211", "MT0213", and "MT0215" are arranged on a coordinate plane represented by two axes.

[0139] The horizontal axis on the graph display screen 63 represents the expense of the maintenance plan. The vertical axis on the graph display screen 63 represents man-hours obtained by multiplying the number of personnel and the required time of the maintenance plan together. The allowable value is a value calculated on the basis of additional information. The display control unit 131 may set, as an allowable value, a specified value inputted to the maintenance plan search screen 62, or may set, as an allowable value, a value calculated from a specified value.

[0140] The density of the pattern of each figure representing the maintenance plan indicates the degree of danger. The display control unit 131 displays a pattern with a higher density for a maintenance plan having a larger degree of danger based on the danger information DB 123.

[0141] By using the graph display screen 63, the user can, regardless of the degree of priority, grasp a maintenance plan having the smallest value of an item such as the number of personnel, the required time, or the expense. Further, the display control unit 131 may display, on the maintenance plan search screen 62, a maintenance plan having the smallest value of an item such as the number of personnel, the required time, or the expense, separately from the search result 62j.

[0142] (Flow of processing) Fig. 15 is a flowchart illustrating a flow of processing of the recommendation device. As illustrated in Fig. 15, first, the recommendation device 10 acquires defect information (Step S101). The defect information is inputted via, for example, the engineer terminal device 30.

[0143] Next, the recommendation device 10 acquires additional information (Step S102). For example, the processing of and after Step S102 is started in response to a request from the manager terminal device 20.

[0144] The recommendation device 10 transforms the acquired defect and a history of accumulated maintenance plans into rating tables (Step S103). Then, on the basis of the rating tables, the recommendation device 10 extracts defects similar to the defect indicated by the defect information (Step S104). Subsequently, the recommendation device 10 specifies maintenance plans associated with the extracted defects (Step S105).

[0145] Here, the recommendation device 10 determines the degree of priority of each of the specified maintenance plans on the basis of additional information (Step S106). For example, the recommendation device 10 determines the degree of priority on the basis of the number of personnel, the required time, and the expense of the maintenance plan.

[0146] Then, the recommendation device 10 presents the specified maintenance plans according to the degree of priority (Step S107). For example, the recommendation device 10 puts a maintenance plan having a larger degree of priority on a higher side of a list displayed on a screen.

[0147] (Effects) As described hereinabove, the recommendation device 10 of the embodiment includes an acquisition unit 132, a specification unit 133, and a determination unit 134. The acquisition unit 132 acquires defect information that is information of a defect that has occurred in the plant and additional information different from the defect information. From information of maintenance plans accumulated in advance in association with defects, the specification unit 133 specifies maintenance plans associated with defects similar to the defect indicated by the defect information. The determination unit 134 determines the degree of priority of each of the specified maintenance plans on the basis of additional information.

[0148] Thus, the recommendation device 10 can preferentially recommend, among a plurality of maintenance plans, maintenance plans that can be practically chosen by the user. As a result, according to the present embodiment, the efficiency of user's work is improved.

[0149] Further, the acquisition unit 132 performs acquisition processing of acquiring additional information that is a demand inputted by the user or a constraint condition generated on the basis of a demand. Thereby, the recommendation device 10 can cause the user's intention to be reflected in maintenance plans presented.

[0150] The acquisition unit 132 acquires, as additional information, the degree of emphasis on each of the number of personnel, the allowable time, and the expense associated with the maintenance plan. Thereby, the recommendation device 10 can present maintenance plans advantageous to the user from the viewpoint of human cost, temporal cost, and monetary cost.

[0151] The acquisition unit 132 acquires, as additional information, information regarding danger associated with the maintenance plan. Thereby, the recommendation device 10 can preferentially present maintenance plans capable of avoiding danger.

[0152] The acquisition unit 132 acquires, as additional information, information based on, for each maintenance plan, the number of times that the maintenance plan was chosen in the past and the level of skill of the user who chose the maintenance plan. Thereby, the recommendation device 10 can propose maintenance plans having actual results in which they were selected in the past by users having a high level of skill.

[0153] The acquisition unit 132 acquires information regarding weather as additional information. Thereby, the recommendation device 10 can prevent an event where a maintenance plan cannot be implemented due to the influence of weather.

[0154] The acquisition unit 132 acquires an operation plan of the plant as additional information. Thereby, the recommendation device 10 can support the user in selecting a maintenance plan adapted to not only handling of a defect but also the operation of the entire plant.

[0155] (System) The processing procedure, the control procedure, the specific names, and the information including various pieces of data and parameters illustrated in the above document and drawings can be arbitrarily changed unless otherwise specified.

[0156] Further, the components of the devices illustrated in the drawings are functionally conceptual ones, and such components do not necessarily need to be physically configured as illustrated in the drawings. That is, specific forms of distribution and integration of the devices are not limited to those illustrated in the drawings. That is, all or some of the devices can be functionally or physically distributed or integrated in arbitrary units according to various loads, usage conditions, etc.

[0157] Further, all or an arbitrary part of each processing function performed in each device can be implemented by a CPU and a program analyzed and executed by the CPU, or can be implemented as hardware based on wired logic.

[0158] (Hardware) Next, a hardware configuration example of the recommendation device 10 is described. Fig. 16 is a diagram describing a hardware configuration example. As illustrated in Fig. 16, the recommendation device 10 includes a communication device 10a, an HDD (hard disk drive) 10b, a memory 10c, and a processor 10d. The units illustrated in Fig. 16 are connected to each other by a bus or the like.

[0159] The communication device 10a is a network interface card or the like, and communicates with other servers. The HDD 10b stores a program that operates the functions illustrated in Fig. 3 and DBs.

[0160] The processor 10d reads out, from the HDD 10b or the like, a program that executes processing similar to the processing of the processing units illustrated in Fig. 3 and develops the program in the memory 10c, and thereby operates a process of executing the functions described in Fig. 2, etc. For example, this process executes functions similar to those of the processing units included in the recommendation device 10. Specifically, the processor 10d reads out, from the HDD 10b or the like, a program having functions similar to those of the display control unit 131, the acquisition unit 132, the specification unit 133, the determination unit 134, etc. Then, the processor 10d executes a process of executing processing similar to the processing of the display control unit 131, the acquisition unit 132, the specification unit 133, the determination unit 134, etc.

[0161] Thus, the recommendation device 10 operates as a recommendation device that executes a recommendation method by reading out and executing a program. Further, the recommendation device 10 can also implement functions similar to those of the above-described embodiment by using a medium-reading device to read out the above program from a recording medium and executing the read-out program. Note that programs referred to in other embodiments are not limited to being executed by the recommendation device 10. For example, the present invention can be similarly applied to cases such as a case where another computer or server executes a program and a case where these execute a program in cooperation.

[0162] This program can be distributed via a network such as the Internet. This program can be executed by being recorded on a computer-readable recording medium such as a hard disk, a flexible disk (FD), a CD-ROM, an MO (magneto-optical disk), or a DVD (digital versatile disc) and being read out from the recording medium by a computer.

[0163] Some examples of combinations of the disclosed technical features are described below.

[0164] (1) A recommendation method comprising a computer's executing: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority. (2) The recommendation method according to (1), wherein in the acquisition processing, the additional information that is a demand inputted by a user or a constraint condition generated on the basis of the demand is acquired. (3) The recommendation method according to (1) or (2), wherein in the acquisition processing, a degree of emphasis on each of a number of personnel, allowable time, and expense associated with a maintenance plan is acquired as the additional information. (4) The recommendation method according to any one of (1) to (3), wherein in the acquisition processing, information regarding danger associated with a maintenance plan is acquired as the additional information. (5) The recommendation method according to any one of (1) to (4), wherein in the acquisition processing, information based on, for each maintenance plan, a number of times that the maintenance plan was chosen in the past and a level of skill of a user who chose the maintenance plan is acquired as the additional information. (6) The recommendation method according to any one of (1) to (5), wherein in the acquisition processing, information regarding weather is acquired as the additional information. (7) The recommendation method according to any one of (1) to (6), wherein in the acquisition processing, an operation plan of the plant is acquired as the additional information. (8) A recommendation program that causes a computer to execute: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority. (9) A recommendation device comprising: an acquisition unit that acquires defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; a specification unit that specifies, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; a determination unit that determines a degree of priority of each of the specified maintenance plans on the basis of the additional information; and a presentation unit that presents the maintenance plans according to the degree of priority.

[0165] 10 Recommendation device 11 Communication unit 12 Storage unit 13 Control unit 61 Defect report screen 62 Maintenance plan search screen 63 Graph display screen 61a, 61b, 61c Pull-down list 61d, 61e, 621b, 621c, 621d Text box 61f, 62h, 62i Button 62e, 62f, 62g Check box 622b, 622c, 622d Seek bar 62j Search result 121 Defect DB 122 Maintenance plan DB 123 Danger information DB 124 Selection history DB 131 Display control unit 132 Acquisition unit 133 Specification unit 134 Determination unit

Claims

1. A recommendation method comprising a computer's executing: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority.

2. The recommendation method according to claim 1, wherein in the acquisition processing, the additional information that is a demand inputted by a user or a constraint condition generated on the basis of the demand is acquired.

3. The recommendation method according to claim 1, wherein in the acquisition processing, a degree of emphasis on each of a number of personnel, allowable time, and expense associated with a maintenance plan is acquired as the additional information.

4. The recommendation method according to claim 1, wherein in the acquisition processing, information regarding danger associated with a maintenance plan is acquired as the additional information.

5. The recommendation method according to claim 1, wherein in the acquisition processing, information based on, for each maintenance plan, a number of times that the maintenance plan was chosen in the past and a level of skill of a user who chose the maintenance plan is acquired as the additional information.

6. The recommendation method according to claim 1, wherein in the acquisition processing, information regarding weather is acquired as the additional information.

7. The recommendation method according to claim 1, wherein in the acquisition processing, an operation plan of the plant is acquired as the additional information.

8. A recommendation program that causes a computer to execute: acquisition processing of acquiring defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; specification processing of specifying, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; determination processing of determining a degree of priority of each of the specified maintenance plans on the basis of the additional information; and presentation processing of presenting the maintenance plans according to the degree of priority.

9. A recommendation device comprising: an acquisition unit that acquires defect information that is information of a defect that has occurred in a plant and additional information different from the defect information; a specification unit that specifies, from information of maintenance plans accumulated in advance in association with defects, maintenance plans associated with defects similar to the defect indicated by the defect information; a determination unit that determines a degree of priority of each of the specified maintenance plans on the basis of the additional information; and a presentation unit that presents the maintenance plans according to the degree of priority.

Citation Information

Patent Citations

  • Maintenance-plan-developing support system, maintenance-plan-developing support method, and maintenance-plan-developing support program

    CA2888334A1

  • Maintenance system

    JP2017097628A