BIM-technology-based system for digital management of entire process of environmentally friendly desilting

The digital management system for the entire process of environmental dredging through BIM technology solves the problems of complex underwater geological environment and high construction difficulty in environmental dredging projects, enables precise operation and data analysis of underwater dredging, and improves construction efficiency. and environmental effects.

WO2024212478A1PCT designated stage expired Publication Date: 2024-10-17CCCC TIANJIN ECO ENVIRONMENTAL PROTECTION DESIGN & RES INST CO LTD

Patent Information

Application Number
PCT/CN2023/127451
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-04-11
Filing Date
2023-10-30
Publication Date
2024-10-17

AI Technical Summary

Technical Problem

In environmental protection dredging projects, the underwater geological environment is complex, dredging depth is difficult to control, and traditional information technology is insufficiently used to meet construction management needs, resulting in high construction difficulty and damage to the underwater ecosystem.

Method used

A digital management system for the whole process of environmental protection dredging based on BIM technology is adopted, including geological model creation, GIS terrain module, dredging process data collection, ship equipment management, real-time dredging sectioning, sediment dewatering management and data analysis modules, through three-dimensional Dynamic display and information-based intelligent management enable precise operation and data analysis of underwater dredging.

Benefits of technology

It achieves unified management of the entire process of environmental protection dredging, improves construction accuracy and efficiency, reduces damage to the underwater ecosystem, and promotes modern management of environmental protection dredging projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023127451_17102024_PF_FP_ABST
    Figure CN2023127451_17102024_PF_FP_ABST
Patent Text Reader

Abstract

Disclosed is a BIM-technology-based system for the digital management of the entire process of environmentally friendly desilting, which belongs to the technical field of environmentally friendly desilting engineering and construction, and comprises: a geological model creation module, a GIS terrain module, a desilting process data acquisition module, a ship device management module, a dredging real-time sectioning module, a sediment water removal management module, a data analysis module, and a collaborative management platform. By using the above technical solution, and by combining reamer position information with a BIM model, the present invention is able to achieve three-dimensional dynamic display of desilting and dredging, solving the problem that presently underwater desilting cannot be operated visually, thereby promoting more-accurate and lower-interference development of environment-friendly desilting, suitable for construction management of environment-friendly desilting engineering. The present invention allows for three-dimensional dynamic display and intelligent information management during the entire process of ship dredging, so as to solve the problems of being unable to see, feel, or accurately operate during underwater desilting; moreover, the invention assists in on-site intelligent decision making, improving quality and efficiency, and achieving modernized lean management.
Need to check novelty before this filing date? Find Prior Art

Description

A digital management system for the entire environmental dredging process based on BIM technology Technical Field

[0001] The present invention belongs to the technical field of environmental protection dredging engineering construction, and specifically relates to a digital management system for the entire environmental protection dredging process based on BIM technology. Background Art

[0002] As we all know, environmental dredging projects have the characteristics of a wide range, complex and changeable underwater geological environment, and high requirements for dredging depth control. Especially in the dredging process, it is necessary to remove the polluted bottom mud in the water body as thoroughly as possible to reduce the release of endogenous pollutants into the water body, while avoiding over-excavation of the original soil under the sludge to prevent damage to the underwater ecosystem.

[0003] In recent years, China has vigorously promoted the informatization of the construction industry, placing higher demands on construction process management. BIM technology has been rapidly adopted in traditional engineering construction, such as the construction of infrastructure such as bridges, roads, and buildings. Environmental dredging projects, primarily targeting areas with complex geology and topography, present different management priorities and challenges compared to traditional industries, making construction management more challenging. Furthermore, the application of information technology is insufficient, and construction guidance is largely based on the experience of on-site managers. Existing methods cannot effectively meet the needs of project construction and management.

[0004] Summary of the Invention

[0005] In order to solve the technical problems existing in the known technology, the present invention provides a digital management system for the entire process of environmental dredging based on BIM technology, which is used to realize three-dimensional dynamic display and information-based intelligent management of the entire process of ship dredging, so as to solve the problems of invisible, intangible and inaccurate operation during underwater dredging, and at the same time assist on-site intelligent decision-making, improve quality and efficiency, and realize modern lean management.

[0006] The purpose of the present invention is to provide a digital management system for the entire process of environmental dredging based on BIM technology, which includes a geological model creation module, a GIS terrain module, a dredging process data acquisition module, a ship equipment management module, a dredging real-time sectioning module, a sediment dewatering management module, a data analysis module, and a collaborative management platform.

[0007] The geological model creation module is used to establish a three-dimensional geological model for the project area based on geological exploration data, and divide the three-dimensional geological model into different soil layer types to distinguish between silt layers and original soil layers;

[0008] The GIS terrain module is used to convert the multi-source geographic coordinates of the project and unify the various coordinate formats involved in the project so that they can be integrated and displayed in the same base map;

[0009] The desilting process data acquisition module is used to collect equipment parameters and engineering data of each link of the construction site through the Internet of Things technology;

[0010] The ship equipment management module is used to monitor the ship status, cutter head latitude and longitude, and depth, and to integrate the ship trajectory with the GIS terrain module;

[0011] The real-time dredging sectioning module is used to couple the spatial position of the cutter head collected by the dredging process data collection module with the data of the geological model creation module, simulate the position relationship of the cutter head in the cross section of the geological model during underwater construction, and dynamically simulate the working state of the cutter head;

[0012] The sediment dewatering management module is used to monitor the mud-water mixture transported to land by suction and to control the dewatering process.

[0013] The data analysis module is used to collect and analyze the data of the ship equipment management module, the dredging real-time sectioning module and the bottom mud dewatering management module;

[0014] The collaborative management platform is used to display complex data in the form of charts, making it easy to view corresponding trends and patterns.

[0015] Furthermore, the geological model creation module establishes an engineering three-dimensional silt body model through Revit or Bentley software.

[0016] Furthermore, the ship equipment management module integrates and displays key parameters such as ship trajectory, cutter head trajectory, cutter head angle, cutter head speed, digging depth, flow rate, concentration, output, and cutter sweep range to avoid missing the construction area;

[0017] Furthermore, the real-time dredging and sectioning module can also modify the thickness of the silt layer in the 3D geological model in real time according to the construction depth of the cutter head, guiding the operator to adjust the position and mechanical parameters of the cutter head in time for precise construction.

[0018] Furthermore, the sediment dewatering management module includes a geotube bag dewatering submodule and a vacuum preloading dewatering submodule;

[0019] The geotube bag dehydration submodule mainly tracks and records data such as filling height, filling times, and moisture content;

[0020] The vacuum preloading dehydration submodule mainly tracks and records data such as the vacuum degree under the membrane, cumulative sedimentation, and moisture content.

[0021] Furthermore, the data analysis module includes a progress comparison module, a tracking analysis module, and a capacity estimation module;

[0022] The progress comparison module generates an actual construction BIM model based on the actual construction situation and compares the differences between the progress plan and the actual model;

[0023] The tracking and analysis module conducts intuitive comparative analysis of the actual progress and planned progress, and issues early warnings for any delays;

[0024] The capacity estimation module predicts the ship dredging capacity and dehydration time based on the completed dredging work volume and the sediment moisture content change curve.

[0025] Furthermore, the collaborative management platform is communicatively connected with the terminal device for integrating and displaying various functional modules; wherein the terminal device includes a computer and a mobile terminal.

[0026] The advantages and positive effects of the present invention are:

[0027] This invention leverages BIM technology to achieve unified management of the entire environmental dredging process. By coupling a three-dimensional geological model with the cutter head's lowering depth, the system displays the underwater construction process of the cutter suction vessel in real time through a visual interface. It also analyzes and manages the progress of vessel equipment construction and sediment dewatering, enabling engineers and technicians to intuitively and immediately understand project progress. This invention promotes more precise environmental dredging, minimizes damage to underwater ecosystems, and improves work efficiency and construction effectiveness. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] FIG1 is a system framework diagram of a preferred embodiment of the present invention;

[0029] FIG2 is a schematic diagram of a simulated geological profile of a cutter suction draught vessel during construction according to a preferred embodiment of the present invention.

[0030] Among them: 1. Cross-section of geological model; 2. Spatial position of cutter head. DETAILED DESCRIPTION

[0031] In order to make the above-mentioned purpose, design control system and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0032] As shown in Figures 1 and 2, the technical solution of the present invention is:

[0033] A digital management system for the entire environmental dredging process based on BIM technology, including a geological model creation module, a GIS terrain module, a dredging process data acquisition module, a ship equipment management module, a dredging real-time sectioning module, a sediment dewatering management module, a data analysis module, and a collaborative management platform; among which:

[0034] The geological model creation module is used to establish a three-dimensional geological model for the project area based on geological exploration data, and divide the three-dimensional geological model into different soil layer types to distinguish between silt layers and original soil layers;

[0035] The GIS terrain module is used to convert the multi-source geographic coordinates of the project and unify the various coordinate formats involved in the project so that they can be integrated and displayed in the same base map;

[0036] The desilting process data acquisition module is used to collect equipment parameters and engineering data of each link of the construction site through the Internet of Things technology;

[0037] The ship equipment management module is used to monitor the ship status, cutter head latitude and longitude, and depth, and to integrate the ship trajectory with the GIS terrain module;

[0038] The dredging real-time sectioning module is used to couple the spatial position 2 of the cutter head collected by the dredging process data collection module with the data of the geological model creation module, simulate the position relationship of the cutter head in the cross section 1 of the geological model during underwater construction, and dynamically simulate the working state of the cutter head;

[0039] The sediment dewatering management module is used to monitor the mud-water mixture transported to land by suction and to control the dewatering process.

[0040] The data analysis module is used to collect and analyze the data of the ship equipment management module, the dredging real-time sectioning module and the bottom mud dewatering management module;

[0041] The collaborative management platform is used to display complex data in the form of charts, making it easy to view corresponding trends and patterns.

[0042] As an implementation method, the geological model creation module establishes an engineering three-dimensional silt body model through Revit or Bentley software.

[0043] As an embodiment, the ship equipment management unit integrates and displays key parameters such as ship trajectory, cutter head trajectory, cutter head angle, cutter head speed, digging depth, flow rate, concentration, output, and cutter sweep range to avoid missing the construction area;

[0044] As an implementation method, the real-time dredging and sectioning module can also modify the thickness of the silt layer in the three-dimensional geological model in real time according to the construction depth of the auger head, guiding the operator to adjust the position and mechanical parameters of the auger head in a timely manner for precise construction.

[0045] As an embodiment, the sediment dewatering management module includes a geotube bag dewatering submodule and a vacuum preloading dewatering submodule;

[0046] The geotube bag dehydration submodule mainly tracks and records data such as filling height, filling times, and moisture content;

[0047] The vacuum preloading dehydration submodule mainly tracks and records data such as the vacuum degree under the membrane, cumulative sedimentation, and moisture content.

[0048] As an implementation method, the data analysis module includes a progress comparison module, a tracking analysis module, and a capacity estimation module;

[0049] The progress comparison module generates an actual construction BIM model based on the actual construction situation and compares the differences between the progress plan and the actual model;

[0050] The tracking and analysis module conducts intuitive comparative analysis of the actual progress and planned progress, and issues early warnings for any delays;

[0051] The capacity estimation module predicts the ship dredging capacity and dehydration time based on the completed dredging work volume and the sediment moisture content change curve.

[0052] As an implementation method, the collaborative management platform is communicatively connected to a terminal device for integrating and displaying various functional modules; wherein the terminal device includes a computer and a mobile terminal.

[0053] The whole process management of environmental dredging using this system includes the following steps:

[0054] (1) In the geological model creation module, a BIM three-dimensional geological model is established using Revit or Bentley software based on construction drawings and geological exploration data, and is divided into silt layers and original soil layers according to different soil layer types, using different colors and materials to distinguish them. To ensure seamless connection of information and effective management of information, model components need to be established according to certain coding rules, and the model components are associated with corresponding planned construction period nodes according to the construction plan;

[0055] (2) In the GIS terrain module, the ship coordinates that meet the NMEA protocol and the engineering coordinates of the three-dimensional geological model are converted into unified longitude and latitude coordinates to facilitate data integration and integration with the BIM model;

[0056] (3) The dredging process data acquisition module also includes acquisition sensors and communication equipment, wherein the acquisition sensors are used to monitor the real-time operating status of the automated equipment of the cutter suction vessel at the construction site and to collect construction parameters and data, including key parameters such as the ship's trajectory, cutter head trajectory, cutter head angle, cutter head speed, digging depth, flow, concentration, and output; the communication equipment is used to transmit the parameters and data collected by the acquisition sensors and establish communication connections with other modules through wireless signals;

[0057] (4) By collecting the position data of the ship and the cutter head in real time, the trajectory can be drawn in the ship equipment management module, and the cutter head trajectory can be visualized to ensure that the entire dredging area of ​​the cutter suction vessel is fully constructed. If there is any omission, the missed area can be quickly tracked by historical query of the construction trajectory. At the same time, the remaining ship construction data can be integrated and displayed in real time, so that staff or management personnel can obtain the operation and production data of the ship equipment;

[0058] (5) In the real-time dredging and sectioning module, the spatial position of the cutter head is coupled with the three-dimensional geological model to simulate the positional relationship of the cutter head in the cross section of the geological model during underwater construction, thereby realizing a three-dimensional display of the cutter head dredging position, dynamically simulating the working state of the cutter, and updating the detailed information of the excavated soil layer in real time according to the construction position of the cutter head;

[0059] (6) The sediment dewatering management module includes a geotube dewatering submodule and a vacuum preloading dewatering submodule. The geotube dewatering submodule mainly tracks and records data such as filling height, filling times, and moisture content. The vacuum preloading dewatering submodule mainly tracks and records data such as sub-membrane vacuum, cumulative settlement, and moisture content. The moisture content and sub-membrane vacuum are collected by acquisition sensors, and the remaining data are filled in by on-site construction personnel by scanning QR codes, and a curve of moisture content changing over time is generated.

[0060] (7) The ship equipment management module, the dredging real-time cutting module, and the bottom mud dewatering management module are connected to the data analysis module, and the data are summarized, analyzed, and processed to form daily output value and monthly output value bar charts, and the actual progress is intuitively compared and analyzed with the planned progress.

[0061] The collaborative management platform interacts with terminal devices for data integration and display of various functional modules. Terminal devices include computers and mobile devices.

[0062] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention are within the scope of the technical solution of the present invention.

Claims

1. A digital management system for the whole process of environmental dredging based on BIM technology, including: The geological model creation module is used to establish a three-dimensional geological model based on geological exploration data, and divide the three-dimensional geological model into a silt layer and an original soil layer according to different soil layer types; it is characterized by also including: GIS terrain module, used to convert multi-source geographic coordinates of the project, unify the various coordinate formats involved in the project, and display them in the same base map; The dredging process data collection module is used to collect equipment parameters and engineering data of each link of the construction site through the Internet of Things; The ship equipment management module is used to monitor the ship status, cutter head latitude and longitude and depth, and to integrate the ship track with the GIS terrain module; the ship equipment management module integrates and displays the ship track, cutter head track, cutter head angle, cutter head speed, digging depth, flow, concentration, production parameters, and cutter sweep range to avoid missing the construction area; The real-time dredging and sectioning module is used to couple the spatial position of the auger head collected by the dredging process data collection module with the data of the geological model creation module, simulate the position relationship of the auger head in the cross section of the geological body model during underwater construction, and dynamically simulate the working state of the auger; the real-time dredging and sectioning module modifies the thickness of the silt layer in the three-dimensional geological model in real time according to the construction depth of the auger head, guides the operator to adjust the position and mechanical parameters of the auger in time, and accurately constructs; realizes the three-dimensional display of the dredging position of the auger head, and updates the detailed information of the excavation layer in real time according to the construction position of the auger head; The sediment dewatering management module is used to monitor the mud-water mixture transported to the land through suction and to control the dewatering process throughout the process; A data analysis module, used to collect and analyze the data of the ship equipment management module, the dredging real-time sectioning module and the bottom mud dewatering management module; The collaborative management platform interacts with the data analysis module and displays the data in the form of charts.

2. The digital management system for the whole process of environmental dredging based on BIM technology according to claim 1 is characterized in that: The geological model creation module establishes an engineering three-dimensional silt body model through Revit or Bentley software.

3. The digital management system for the whole process of environmental dredging based on BIM technology according to claim 1 is characterized in that: The sediment dewatering management module includes a geotube dewatering submodule and a vacuum preloading dewatering submodule; wherein: The geotube dehydration submodule is used to track and record filling height, filling times, and moisture content data; The vacuum preloading dehydration submodule is used to track and record the vacuum degree under the membrane, the accumulated sedimentation, and the moisture content data.

4. The digital management system for the whole process of environmental dredging based on BIM technology according to claim 1 is characterized in that: The data analysis module includes a progress comparison module, a tracking analysis module, and a capacity estimation module; wherein: The progress comparison module generates an actual construction BIM model according to the actual construction situation, and compares the difference between the progress plan and the actual model; The tracking and analysis module conducts intuitive comparative analysis of the actual progress and the planned progress, and issues early warnings for lagging situations; The capacity estimation module predicts the ship dredging capacity and dehydration time based on the completed dredging project volume and the sludge moisture content change curve.

5. The digital management system for the whole process of environmental dredging based on BIM technology according to claim 1 is characterized in that: The collaborative management platform interacts with the terminal device for data integration and display of various functional modules; wherein the terminal device includes a computer and a mobile terminal.

Citation Information

Patent Citations

  • Method for establishing inland waterway dredging graph under single-beam measuring points based on BIM model

    CN108875177A

  • Parameterized three-dimensional geological modeling method and system and information data processing terminal

    CN110689615A

  • Rainwater and sewage pipe network comprehensive disposal method combining BIM with AR technology

    CN112948945A

  • Environment-friendly dredging whole-process digital management system based on BIM (Building Information Modeling) technology

    CN116109282A

  • Method and apparatus for transmitting and receiving hybrid automatic repeat request response in sidelink communication

    KR1020210127100A

Cited By

  • Three-dimensional model construction method of green low-carbon ecological dredging equipment

    CN119939820A

  • Intelligent safety analysis system for construction site

    CN120509744A

  • Sediment deposition prediction and optimized dredging method and system based on AI calculation

    CN122113667A