Curtain grouting reinforcement method for tunnel group in deep backfill area, and reinforcement effect assessment method
By employing full-section curtain grouting and various testing methods, the problem of insufficient reinforcement of the surrounding rock in tunnels in deep backfill areas was solved, tunnel stability and settlement control were achieved, accurate effect evaluation was provided, and construction safety was ensured.
Patent Information
- Application Number
- PCT/CN2024/103259
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2024-05-15
- Filing Date
- 2024-07-03
- Publication Date
- 2025-11-20
AI Technical Summary
Existing methods cannot adequately reinforce the surrounding rock of tunnels in deep backfill areas, resulting in poor tunnel stability, large surface settlement, and difficulty in accurately evaluating the effect of grouting reinforcement.
The full-section curtain grouting method was adopted, and holes were drilled using a multi-functional hydraulic walking down-the-hole drill rig. Cement grout and dual-liquid grout were used for grouting reinforcement. The grouting effect was comprehensively evaluated by combining drilling inspection hole method, multi-wave multi-component engineering seismograph and high-definition video detection.
It effectively reinforced the surrounding rock of the tunnel, improved the stability of the tunnel and the control of surface settlement, provided a more accurate evaluation of the grouting reinforcement effect, and ensured safe and efficient construction.