Three-chamber application pump operating method for powder paint coating

The three-chamber application pump with phase-shifted suction-transfer chambers and externally piloted directional control valves ensures continuous and precise powder paint flow, overcoming irregularities and achieving high flow rates and self-cleaning in powder coating processes.

WO2026235649A1PCT designated stage Publication Date: 2026-11-12SISTEM TEKNIK MAKINA SANAYI VE TICARET ANONIM SIRKETI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/TR2025/051288
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2025-10-14
Publication Date
2026-11-12

AI Technical Summary

Technical Problem

Existing powder paint application technologies face issues with irregular flow, low flow rates, and difficulty in achieving high flow rates, air consumption, self-cleaning, and paint/air control, particularly in the context of powder coating processes.

Method used

A three-chamber application pump with phase-shifted suction-transfer chambers and externally piloted directional control valves, ensuring continuous and precise control of powder paint flow by using three suction-transfer chambers operating in phase-shifted harmony, combined with a specialized pneumatic diagram for high flow rates and precise operation.

Benefits of technology

The solution provides a regular and uninterrupted powder paint flow with precise control, enabling high flow rates and self-cleaning capabilities, addressing the limitations of existing technologies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure TR2025051288_12112026_PF_FP_ABST
    Figure TR2025051288_12112026_PF_FP_ABST
Patent Text Reader

Abstract

The invention relates to a powder paint application pump comprising three suction transfer chambers (EB1, EB2, EB3) to be used in the thermoset / thermoplastic / enamel powder paint coating process. In addition to having a regular paint flow, the invention also allows precise control of the powder paint. Although the three suction-transfer chambers (EB1, EB2 and EB3) in the invention operate with the same working period (WT), the beginnings of these periods are different from each other. When the first suction-transfer chamber (EB1) starts operating at time T=0, the second suction-transfer chamber (EB2) starts operating after one-third of the operating time (WT) (T=WT / 3), and the third suction-transfer chamber (EB3) starts operating after two-thirds of the operating time (WT) (T=2*WT / 3). In the invention, an operating system is created in which two of the transfer valves (VT1, VT2 and VT3) remain open at all times during continuous operation. In this way, it enables the air (and therefore the powder paint contained in it) to be delivered to the powder coating gun (TB) in a regular manner.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] THREE-CHAMBER APPLICATION PUMP OPERATING METHOD FOR POWDER PAINT COATING

[0002] Technical Field

[0003] The invention relates to the operating method of a powder paint pump comprising three suction-transfer chambers to be used in the thermoset / thermoplastic / enamel powder paint coating process.

[0004] State of Art

[0005] When the studies in the sector are examined, powder coating injectors, generally based on the venturi principle, and powder coating pumps, based on the suction and transfer principle, ensure that the powder coating is sucked from a reservoir and sent to the powder coating gun, thus applying powder coating to the workpiece.

[0006] Injectors based on the Venturi principle provide a more regular paint flow compared to pumps based on the suction and transfer principle and are frequently used in the industry due to their affordable cost. Although pumps based on the suction and transfer principle do not form as regular a flow as powder paint injectors due to the phase-by-phase delivery of the powder paint, the inadequacy of powder paint injectors at high flow rates has opened up the use of powder paint pumps.

[0007] The traditional method for spraying powder paint from a gun is the injector structures operating on the venturi principle. The function of sending powder paint from a reservoir to a powder coating gun is achieved through a component called an injector, which operates on this principle. The publication numbered EP0178120 (B1) concerns these injectors. These structures, which are used to send the paint from a reservoir to the powder coating gun and operate with the venturi principle, have disadvantages such as not being able to provide a solution for sending paint at high flow rates to the powder coating gun, consuming too much air, not being self-cleaning, and difficulty in paint / air control.

[0008] In the publication numbered EP1551558A1, which was encountered in the literature research, there are two dust carrying chambers, these chambers are positioned parallel to each other, and the pinch valves are arranged in a mechanically operating structure.Directional control is achieved by mechanically crushing or opening the structure. This technique includes a filter pipe. This pipe is a structure that is permeable only to air. The structure is planned to operate by filling the filter volume with powder paint and delivering it as desired. Publications US2001 / 0003568 A1 and EP1752399A1 are also known related to the art.

[0009] The publication numbered EP2311573B1, which was encountered in the literature research, has two dust transport chambers, and these chambers are positioned parallel to each other and arranged with air-controlled pinch valves. According to the operating method described in the publication, it is formed sequentially in a way that one chamber is suctioning while the other chamber is pressing. Since this method does not contain an intermediate phase, it causes paint pulsation that disrupts continuity in low flow paint application demands.

[0010] The publication numbered US10604360B2, encountered in the literature research, is about a powder paint pump in which a single chamber performs suction and discharge(transfer), and the second chamber connected in series to this chamber does not perform suction. In the operating method shown in this publication, the paint is sent phase by phase, one full and one empty. This method not only results in low powder coating flow rates but also results in uneven paint output from the gun tip due to the presence of empty phases. Publications EP3302819 and EP3585522 are also known related to the art.

[0011] As a result, there is a need for a new application pump and a suitable operating method that surpasses the known state of the art and eliminates its disadvantages for use in the powder coating process.

[0012] Object of the Invention

[0013] The invention is an operating method of an application pump that surpasses the known state of the art, eliminates its disadvantages, and provides additional advantages for use in the powder paint coating process.

[0014] The invention relates to the operating method of a pump used to send thermoset / thermoplastic / enamel powder paint from a reservoir to a powder coating gun or another reservoir. It operates precisely and quickly to ensure that the thermoset / thermoplastic / enamel powder paint is sprayed evenly from the powder coatinggun. Here, the powder coating gun can be a hand-held structure that sprays thermoset / thermoplastic / enamel powder paint to powder coat a workpiece, or a structure capable of automatic painting.

[0015] The invention uses a powder paint pump with three suction-transfer chambers; each suction-transfer chamber being operated in a specific phase order. In this way, it provides a solution to the irregular flow (pulsation) problem caused by the phase-phase operation of powder paint pumps, as it has a structure that provides continuity in the suction and transfer process. In addition to having a regular paint flow, the invention also allows precise control of the powder paint.

[0016] Figures to Help Understand the Invention

[0017] Figure-1. View showing the powder transfer unit with three suction-transfer chambers included in the invention, the powder coating device that provides the air and electrical power required for this pump, the powder coating chamber, the powder coating gun and the workpiece on which the application is made.

[0018] Figure-2 Graphic view showing the operation of the suction-transfer chambers of the powder paint pump, which is the subject of the invention, in a phase-shifted manner relative to each other.

[0019] Figure 3: Graphical view showing the positions of the valves during the WT time in the invention. (Figure VT1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5 and VP6, where "0" means that the relevant elements are not triggered, "1" means that they are triggered.)

[0020] Figure-4 Detailed cross-sectional view of the powder transfer unit in the pump which is the subject of the invention.

[0021] Description of Piece References

[0022] I . Powder transfer unit

[0023] I I . Three-chamber connecting piece

[0024] I I I . Three-chamber connecting piece path

[0025] 12. Pinch valve chamber

[0026] 13. Tube filter chamber

[0027] 131 . First tube filter

[0028] 132. Second tube filter133. Third tube filter

[0029] 2. Pump body

[0030] T. Time

[0031] VA. Vacuum open time

[0032] WT. Operating period

[0033] HR. Air regulator

[0034] EB1. First suction-transfer chamber EB2. Second suction-transfer chamber EB3. Third suction-transfer chamber VT 1. First transfer valve

[0035] VT2. Second transfer valve

[0036] VT3. Third transfer valve

[0037] VV1. First vacuum valve

[0038] VV2. Second vacuum valve

[0039] VV3. Third vacuum valve

[0040] VP1. First pinch valve actuator VP2. Second pinch valve actuator VP3. Third pinch valve actuator VP4. Fourth pinch valve actuator VP5. Fifth pinch valve actuator VP6. Sixth pinch valve actuator VPUR. Cleaning valve

[0041] VAC1. First vacuum generator VAC2. Second vacuum generator VAC3. Third vacuum generator

[0042] P1. First pinch valve

[0043] P2. Second pinch valve

[0044] P3. Third pinch valve

[0045] P4. Fourth pinch valve

[0046] P5. Fifth pinch valve

[0047] P6. Sixth pinch valve

[0048] A1. Main air

[0049] A2. Pinch valve air

[0050] A3. Transmission air

[0051] A4. Mixer airA5. Gun needle air

[0052] A6. Under-reservoir pneumatic line

[0053] IP. Workpiece

[0054] H. Reservoir

[0055] H1 . Powder paint

[0056] H2. Fluidization base

[0057] H3. Non-permeable section

[0058] H4. Suction pipe

[0059] H5. Transfer pipe

[0060] TB. Powder coating gun

[0061] TB1. Powder coating gun trigger

[0062] 5. Gun signal connection

[0063] 65. Mixer part

[0064] K. Control unit

[0065] K1. Main control board

[0066] K2. Pump driver board

[0067] K3. Pressure balancing tank

[0068] K11 . First proportional pressure control valve

[0069] K12. Second proportional pressure control valve

[0070] K13. Third proportional pressure control valve

[0071] VD. Filling valve

[0072] BS. Pressure sensor

[0073] Detailed Description of the Invention

[0074] In this detailed description, the powder paint application pump which is the subject of the invention is described with examples which will not form any limiting effect, only for the purpose of a better understanding of the subject.

[0075] In Figure 1 , the view of the pump, which is the subject of the invention, shows the powder transfer unit (1), pump body (2), powder paint (H1), reservoir (H), powder coating gun (TB), workpiece (IP) and control unit (K). A cross-sectional detail view of the powder transfer unit (1) is given in Figure 2. Accordingly, the powder transfer unit (1) included in the invention is used to take powder paint (H1) from the reservoir (H) and transfer it to the powder coating gun (TB) or another reservoir. The pump body (2) included in the invention provides the transmission of main air (A1), pinch valve air (A2) andtransmission air (A3) to the powder transfer unit (1) and the electrical power of the powder transfer unit (1). The reservoir (H) is the section that supplies the powder paint (H1), while the powder coating gun (TB) applies the powder paint (H1) to the workpiece (IP). In the invention, the control unit (K) controls the valves and electronic equipment.

[0076] In the powder transfer unit (1 ) of the pump which is the subject of the invention, there are three suction-transfer chambers (EB1, EB2, EB3), namely the first suction-transfer chamber (EB1), the second suction-transfer chamber (EB2), and the third suctiontransfer chamber (EB3). Suction-transfer chambers (EB1 , EB2, EB3) perform the suction and transfer function and ensure that the powder paint (H1) in the reservoir (H) is transferred to the powder coating gun (TB). In this way, the invention not only has a regular paint flow but also allows precise control of the powder paint (H1).

[0077] In the invention, the suction-transfer chambers (EB1, EB2, EB3) are placed inside the tube filters (131, 132, 133) in the tube filter chamber (13). The tube filters (131 , 132, 133) in the tube filter chamber (13) are preferably connected to each other with a mechanical element (e.g. a bolt) and formed into a whole. The tube filter chamber (13) is a structure comprising a first tube filter (131), a second tube filter (132) and a third tube filter (133) in a porous structure that is impermeable to dust and permeable to air. This allows main air (A1) or transmission air (A3) to be delivered into suction-transfer chambers (EB1, EB2, EB3) without the need for powder coating (H1). The tube filters (131, 132, 133) are arranged in a geometrical structure, preferably with the shortest and equal distances between them. Tube filters (131, 132 133) are tube-shaped structures made of a special porous material that is permeable only to air but not to thermoset / thermoplastic / enamel powder paint. Filters keep the thermoset / thermoplastic / enamel powder paint in their internal volumes and do not let it pass to their external volumes. These tube filters (131 , 132, 133) may be a circular cross-section tube or pipe-like structure as shown in the invention (Figure 2), or they may also be in square, rectangular or elliptical cross-section shapes.

[0078] In the invention, each suction-transfer chamber (EB1, EB2, EB3) performs a cycle by performing its functions during suction and transfer. This is called the operating period (WT) in milliseconds. The operating period (WT) is repeated repeatedly to ensure regular operation of the pump. Although the three suction-transfer chambers (EB1, EB2 and EB3) in the invention operate with the same operating period (WT), the beginnings of these periods are different from each other. As shown in Figure 2, when the first suction-transfer chamber (EB1) starts operating at time T=0, the second suction-transfer chamber (EB2) starts operating after one-third of the operating time (WT) (T=WT / 3), and the third suction-transfer chamber (EB3) starts operating after two-thirds of the operating time (WT) (T=2*WT / 3). This results in phase-shifted times relative to each other. These three sections operate in phase-shifted harmony. Thanks to the phase shifted operating method, the pump's operating continuity is ensured due to the suction-transfer chambers (EB1, EB2, EB3).

[0079] In the invention, a special pneumatic diagram (Figure - 1) prepared inside the pump body (2) is envisaged for increasing the paint flow rate and for precise operation. As will be described in detail in the claims, selecting directional control valves with external pilots has shortened the reaction times of the directional control valves, enabled them to operate with air from the vacuum generator, and enabled them to operate with variable air pressure and / or negative pressure coming to the valves. This pneumatic diagram is an essential feature for the operation of the application pump for thermoset / thermoplastic / enamel powder coatings, and the precise and rapid operation of the directional control valves ensures high flow and uniform output during powder coating spraying (H1) from the powder coating gun (TB).

[0080] The application pump for thermoset / thermoplastic / enamel powder coatings operates in the two modes described below. The specifications for which these modes are to be used and the differences between them are specified in the claims. It is advantageous because it is equipped to operate in different situations and allows the application of different types of powder paint with other features specified in the claims. In addition to these operating states, there is a cleaning state that enables the application pump to clean itself for thermoset / thermoplastic / enamel powder coatings.

[0081] The three-chamber application pump starts operating when the gun trigger (TB1) is pressed or the powder control box (K) is set to self-start.

[0082] The pneumatic diagram shown in Figure 1 shows the initial positions of the directional control valves (VT1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1 , VV2, VV3, VPUR). Directional changes are achieved by providing electrical signals to the valves.

[0083] In the invention, pinch valve actuators (VP1, VP2, VP3, VP4, VP5, VP6) are elements that are triggered to open and close the pinch valves (P1 , P2, P3, P4, P5, P6). For example, by triggering the first pinch valve actuator (VP1), the first pinch valve (P1)closes. When not triggered, the path to the first pinch valve (P1 ) is open. In the invention, the pinch valve actuators (VP1, VP2, VP3, VP4, VP5, VP6) and the pinch valves (P1, P2, P3, P4, P5, P6) are arranged to match each other as VP2-P2, VP3-P3, VP4-P4, VP5-P5, VP6-P6.

[0084] In the invention, the vacuum valves (VV1, VV2, VV3) are connected to the vacuum generators (VAC1 , VAC2, VAC3) with the air regulator (HR) in front of them. When the first vacuum valve (VV1) is not triggered, it does not pass air, so no air is supplied to the first vacuum generator (VAC1). When triggered, the air passing through it reaches the first vacuum generator (VAC1). This generates vacuum power on the pneumatic line to which the first vacuum generator (VAC1 ) is connected. This is similar for VV2-VAC2 and VV3-VAC3.

[0085] In the invention, the transfer valves (VT 1 , VT2, VT3) are arranged in a way that they are connected to the vacuum generators (VAC1) when they are not triggered. For example, when the first transfer valve (VT1) is not triggered but the first vacuum valve (VV1) is triggered, the vacuum power created by the first vacuum generator (VAC1 ) is transferred to the first suction-transfer chamber (EB1 ) through the line to which the first transfer valve (VT1) is connected. Since the first tube filter (131) in the first suction-transfer chamber (EB1 ) is only permeable to air and not to paint, the powder paint (H1 ) can be sucked into the first suction-transfer chamber (EB1) with the vacuum power transferred here.

[0086] This event is carried out when the first pinch valve (P1) path is closed, and the fourth pinch valve (P4) path is open. When the path of the fourth pinch valve (P4) is closed and the path of the first pinch valve (P1) is open, the powder paint (H1) is transferred from the first suction-transfer chamber (EB1) in the direction of the powder coating gun (TB). At this moment, the first transfer valve (VT 1 ) is triggered and the powder paint (H1 ) which was sucked into the first suction-transfer chamber (EB1) in the previous phase with the air coming from the delivery air (A3) to which the other end of the valve is connected is sent towards the powder coating gun (TB).

[0087] In the invention, the second transfer valve (VT2) is arranged in such a way that when it is not triggered, it is connected to the second vacuum generator (VAC2). When the second transfer valve (VT2) is not triggered but the second vacuum valve (VV2) is triggered, the vacuum power created by the second vacuum generator (VAC2) is transferred to the second suction-transfer chamber (EB2) through the line to which the second transfer valve (VT2) is connected. Since the second tube filter (132) in thesecond suction-transfer chamber (EB2) is only permeable to air and not to paint, the powder paint (H1) can be sucked into the second suction-transfer chamber (EB2) with the vacuum power transferred here. This event is performed at the moment when the path of the second pinch valve (P2) is closed, and the path of the fifth pinch valve (P5) is open. When the fifth pinch valve (P5) is closed and the second pinch valve (P2) is open, the powder paint (H1) is transferred towards the powder coating gun (TB). At this moment, the second transfer valve (VT2) is triggered and the powder paint (H1), which was sucked into the second suction-transfer chamber (EB2) in the previous phase, is sent towards the powder coating gun with the air coming from the transmission air (A3) to which the other end of the valve is connected.

[0088] In the invention, the path is arranged to be connected to the third vacuum generator (VAC3) when the third transfer valve (VT3) is not triggered. When the third transfer valve (VT3) is not triggered but the third vacuum valve (VV3) is triggered, the vacuum power created by the third vacuum generator (VAC3) is transferred to the third suction-transfer chamber (EB3) through the line to which the third transfer valve (VT3) is connected. Since the third tube filter (133) in the third suction-transfer chamber (EB3) is only permeable to air and not to paint, the powder paint (H1) can be sucked into the third suction-transfer chamber (EB3) with the vacuum power transferred here. This event is performed at the moment when the path of the third pinch valve (P3) is closed, and the path of the sixth pinch valve (P6) is open. When the sixth pinch valve (P6) is closed and the third pinch valve (P3) is open, the powder paint (H1) is transferred to the powder coating gun (TB). At this moment, the third transfer valve (VT3) is triggered and the powder paint (H1) which was sucked into the third suction-transfer chamber (EB3) in the previous phase with the air coming from the transmission air (A3) to which the other end of the valve is connected is sent towards the powder coating gun (TB).

[0089] In the invention, the opening times of the first vacuum valve (VV1), the second vacuum valve (VV2) and the third vacuum valve (VV3) determine the amount of paint absorbed (filled) into the suction-transfer chambers (EB1 , EB2, EB3). The vacuum on time (VA) is an expression in milliseconds, set via the control unit (K). In the invention, the vacuum on time (VA) is arranged so that it cannot exceed WT / 3 time.

[0090] In the invention, pressing the powder coating gun trigger (TB1) on the powder coating gun (TB) or setting the control unit (K) for automatic operation ensures that the T=0 time operating conditions shown in Figure-2 and Figure-3 are achieved. Releasing the powdercoating gun trigger (TB1) on the powder coating gun (TB) or stopping it via the control unit (K) means that time T = 0 (initial state). Restarting occurs with the T = 0 condition.

[0091] In the invention, the operation of the second suction-transfer chamber (EB2) with a WT / 3 phase shift relative to the first suction-transfer chamber (EB1), and the third suctiontransfer chamber (EB3) with a 2*WT / 3 phase shift relative to the first suction-transfer chamber (EB1), will ensure continuous paint suction and transfer. Phase shifting is performed once during the WT period, when the system starts operating. The WT period then repeats in all suction-transfer chambers (EB1 , EB2, EB3), as shown in Figure 2.

[0092] Pump operation will be described in two main sections: normal operation and cleaning. Normal operation is examined in three sections.

[0093] Normal operation:

[0094] FIRST SUCTION-TRANSFER CHAMBER (EB1):

[0095] From time T=0 to time T=WT / 3 the first transfer valve (VT1) and the fourth pinch valve actuator (VP4) are not triggered, the first pinch valve actuator (VP1) is triggered. Since the fourth pinch valve actuator (VP4) is not triggered and the first pinch valve actuator (VP1) is triggered, the first pinch valve (P1) is closed, and the fourth pinch valve (P4) is open. At time T=0, the first vacuum valve (VV1) is triggered. The first vacuum valve (VV1) will remain open for the vacuum on time (VA) and then close. Meanwhile, the powder paint (H1 ) in the suction pipe (H4) is filled into the first suction-transfer chamber (EB1 ).

[0096] From time T=WT / 3 to time T=WT, the first transfer valve (VT1) and the fourth pinch valve actuator (VP4) are triggered. The first pinch valve actuator (VP1) is not triggered. Since the fourth pinch valve actuator (VP4) is triggered and the first pinch valve actuator (VP1 ) is not triggered, the first pinch valve (P1) is open, and the fourth pinch valve (P4) is closed. Meanwhile, at T=0 and T=WT / 3, the powder paint (H1) filled in the first suctiontransfer chamber (EB1) is transferred towards the powder coating gun (TB). Details are shown in Figure 3. The pump then returns to its T=0 state and operates in successive cycles. This creates a periodic operating cycle, as shown in Figure 2.

[0097] SECOND SUCTION-TRANSFER CHAMBER (EB2):

[0098] As seen in the graph in Figure 2, the operation of the second suction-transfer chamber (EB2) is shifted by T=WT / 3 compared to the first suction-transfer chamber (EB1). As canbe seen in Figure 2, the time shift is performed once. As shown in Figure 3, from the moment T=0 to the moment T=WT / 3, the second pinch valve actuator (VP2) is not triggered, the fifth pinch valve actuator (VP5) and the second transfer valve (VT2) are triggered. Since the second pinch valve actuator (VP2) is not triggered and the fifth pinch valve actuator (VP5) is triggered, the second pinch valve (P2) is open, and the fifth pinch valve (P5) is closed.

[0099] After T=WT / 3, the second suction-transfer chamber (EB2) operates in a sequential cycle as described below: For a time period of WT / 3, the second transfer valve (VT2) and the fifth pinch valve actuator (VP5) are not triggered, while the second pinch valve actuator (VP2) is triggered. Because the second pinch valve actuator (VP2) is triggered but the fifth pinch valve actuator (VP5) is not, the second pinch valve (P2) is closed, and the fifth pinch valve (P5) is open. The second vacuum valve (VV2) is triggered. The second vacuum valve (VV2) is triggered for the vacuum open time (VA). At this time, the powder paint (H1) in the suction pipe (H4) is filled into the second suction-transfer chamber (EB2).

[0100] Subsequently, for a period of 2*WT / 3, the second transfer valve (VT2) and the fifth pinch valve actuator (VP5) are triggered, and the second pinch valve actuator (VP2) is not triggered. Since the second pinch valve actuator (VP2) is not triggered and the fifth pinch valve actuator (VP5) is triggered, the second pinch valve (P2) is open, and the fifth pinch valve (P5) is closed. As shown in Figure-2 and Figure-3, WT continues to operate with its total time remaining constant. Meanwhile, the powder paint (H1) filled in the second suction-transfer chamber (EB2) in the previous phase (WT / 3 time ago) is transferred towards the powder coating gun (TB).

[0101] THIRD SUCTION-TRANSFER CHAMBER (EB3):

[0102] As shown in Figure 3, from the moment T= 0 to the moment T=2*WT / 3, the third transfer valve (VT3) and the sixth pinch valve actuator (VP6) are triggered, the third pinch valve actuator (VP3) is not triggered.

[0103] As seen in the graph in Figure 2, the operation of the third suction-transfer chamber (EB3) is shifted by T=2*WT / 3 compared to the first suction-transfer chamber (EB1). As can be seen in Figure 2, the time shift is performed once.After T=2*WT / 3, the operation of the third suction-transfer chamber occurs sequentially as described below; for a period of WT / 3; the third transfer valve (VT3) and the sixth pinch valve actuator (VP6) are not triggered, the third pinch valve actuator (VP3) is triggered. Since the sixth pinch valve actuator (VP6) is not triggered and the third pinch valve actuator (VP3) is triggered, the sixth pinch valve (P6) is open, and the third pinch valve (P3) is closed. The third vacuum valve (VV3) is triggered. The third vacuum valve (VV3) will be triggered for the vacuum on time (VA). Meanwhile, the powder paint (H1) in the suction pipe (H4) is filled into the third suction-transfer chamber (EB3).

[0104] Up to 2*WT / 3 time, the third transfer valve (VT3) and the sixth pinch valve actuator (VP6) are triggered, the third pinch valve actuator (VP3) is not triggered. Since the sixth pinch valve actuator (VP6) is triggered and the third pinch valve actuator (VP3) is not triggered, the sixth pinch valve (P6) is closed, and the third pinch valve (P3) is open. Meanwhile, the powder paint (H1) filled in the third suction-transfer chamber (EB3) in the previous phase (WT / 3 time ago) is transferred towards the powder coating gun (TB). As shown in Figure-2 and Figure-3, WT continues to operate with its total time remaining constant.

[0105] As can be seen in Figure 2 and Figure 3, an operating order is created in which two of the transfer valves (VT1, VT2 and VT3) remain open at all times during continuous operation. In this way, it enables the air (and therefore the powder paint contained in it) to be delivered to the powder coating gun (TB) in a regular manner.

[0106] Cleanliness status:

[0107] The invention allows cleaning from the pump to the paint reservoir (H), from the pump to the powder coating gun (TB), and / or both simultaneously. The powder paint pump, which has three-chamber, can be cleaned when powder paint is desired to be removed. During this process, a different operation will be performed than normal. When the cleaning operation is activated via the control unit (K) or the powder coating gun (TB), it operates as follows. In cleaning mode, the first vacuum valve (VV1), the second vacuum valve (VV2) and the third vacuum valve (VV3) do not operate (are not triggered).

[0108] Cleaning is carried out from the pump to the reservoir by triggering the cleaning valve (VPUR), the first pinch valve actuator (VP1), the second pinch valve actuator (VP2), the third pinch valve actuator (VP3), the first transfer valve (VT1), the second transfer valve (VT2) and the third transfer valve (VT3). At this time, the first pinch valve (P1 ), the secondpinch valve (P2), the third pinch valve (P3) are closed, the fourth pinch valve (P4), the fifth pinch valve (P5), and the sixth pinch valve (P6) are open.

[0109] The cleaning process is carried out from the pump to the powder coating gun (TB) by triggering the cleaning valve (VPUR), the fourth pinch valve actuator (VP4), the fifth pinch valve actuator (VP5) and the sixth pinch valve actuator (VP6), the first transfer valve (VT1), the second transfer valve (VT2) and the third transfer valve (VT3). At this time, the first pinch valve (P1), the second pinch valve (P2), the third pinch valve (P3) are open, the fourth pinch valve (P4), the fifth pinch valve (P5), and the sixth pinch valve (P6) are closed. These operations can be performed consecutively and / or several times as needed.

[0110] The pump body (2) comprises the pneumatic valves (VT1, VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1, VV2, VV3, VPUR), vacuum generators (VAC1, VAC2, VAC3), a valve island where the valves are located and the air regulator (HR). The air regulator (HR) is used to regulate the air required by the vacuum generators (VAC1 , VAC2, VAC3).

[0111] Transfer valves (VT1, VT2, VT3) are externally piloted, three-way, two-position (3 / 2) valves. The pneumatic diagram becomes more meaningful with the use of these valves. If instead of the externally piloted directional control valves shown in Figure 1, internally piloted directional control valves, that is, valves in which the movement of the valve core is actuated by the inlet air pressure, had been used, the application pump for thermoset, thermoplastic, or enamel powder paint would not have operated properly and its operation would in fact have been impossible. Because in internally piloted directional control valves, a portion of the compressed air entering the directional control valve is used for the movement of the valve core. This phenomenon will cause the directional control valves to react differently at different pressures, to be delayed and / or not to operate at all if the air pressure is variable. By using externally piloted valves, rapid and regular operation of directional control valves is achieved, providing a great advantage over other structures known in the art. Thanks to these externally piloted directional control valves, the increase in paint flow rate as well as the control of the powder paint is particularly advantageous, with the powder paint being sprayed in a regular, uninterrupted manner from the powder paint coating gun (TB).

[0112] In the invention, the control of the transmission air (A3), the mixer part pneumatic line (A4), the gun signal connection (5) is performed from the screen on the control unit (K). The control unit (K) consists of a main control board (K1), a pump driver board (K2),proportional pressure control valves (K11 , K12, K13), a pressure compensation tank (K3) and a filling valve (VD). In the invention, directional control valves (VT 1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1 , VV2, VV3, VPUR) are controlled by the signals created by the pump driver board (K2).

[0113] In the invention, the main control board (K1) controls the proportional pressure control valves (K11 , K12, K13) and ensures that the general air from the main air line (A1 ), the transmission air (A3), the gun needle air (A5), the mixer air (A4) are regulated as desired and their pressures are adjusted.

[0114] In the invention, the transmission air (A3) ensures that the thermoset / thermoplastic / enamel powder paint absorbed into the suction-transfer chambers (EB1, EB2, EB3) in the previous phase is conveyed towards the powder coating gun (TB) direction by triggering the transfer valves (VT 1 , VT2, VT3).

[0115] In the invention, pneumatic air (A4) is connected to the mixer part (65). When not in use, the mixer part (65) is connected directly to the powder coating gun (TB) or, if not used, can be turned off by adjusting it from the control unit (K).

[0116] In the invention, the gun signal connection (5) sends an electrical signal to the powder coating gun (TB) via the main control board (K1) in the control unit (K). In addition, the trigger (TB1), cleaning and / or other electrical signals coming from the powder coating gun (TB) are transferred to the main control card (K1) in the control unit (K) via the gun signal connection (5).

[0117] In the invention, there is a pressure sensor (BS) integrated into the pump driver board (K2) located within the control unit (K). Here, the pressure sensor (BS) is a sensor that converts the analog pressure information it reads into an electrical signal and / or is used for this purpose. The pressure sensor (BS) measures the pressure of the air in the pressure compensation tank (K3) and transfers this pressure value as electrical information to the pump driver board (K2). If this air pressure is lower than the value set in the control unit (K), the filling valve (VD) opens when the pump driver board (K2) generates a trigger signal and remains open until the pressure reaches the preset value measured by the pressure sensor (BS). The filling valve (VD) closes when the desired pressure is reached. This maintains the air in the pressure compensation tank (K3) at the desired pressure. The air held at the desired pressure in the pressure compensationtank (K3) is used to close the pinch valves (P1, P2, P3, P4, P5, P6) by triggering the pinch valve actuators (VP1 , VP2, VP3, VP4, VP5, VP6) of the pump driver board (K2).

[0118] The invention has two pinch valve chambers (12). The first of these is located above the tube filter chamber (13) (in the inlet section) and the second is located below the tube filter chamber (13) (in the outlet section). The lower pinch valve chamber (12) comprises the first pinch valve (P1), the second pinch valve (P2), and the third pinch valve (P3), while the upper pinch valve chamber (12) comprises the fourth pinch valve (P4), the fifth pinch valve (P5), and the sixth pinch valve (P6). Pinch valves (P1, P2, P3, P4, P5, P6) are responsible for opening and closing the relevant path required for suction and transfer actions to be taken within the suction-transfer chambers (EB1, EB2, EB3). The pinch valve chambers (12) are arranged so that the pinch valves (P1 , P2, P3) and (P4, P5, P6) can be installed therein. The chamber (12) containing three pinch valves is arranged in a geometric structure so that the distance between the pinch valves (P1 , P2, P3, P4, P5, P6) is the shortest and equal. The pinch valves (P1, P2, P3, P4, P5, P6) have a flexible structure, similar to a hose, which closes when pressurized air is applied and returns to its initial position when this air is released. The pinch valves (P1, P2, P3, P4, P5, P6) can be made of a flexible material such as silicone, EPDM or a special formula of their alloy.

[0119] The pinch valve chambers (12), and the tube filter chamber (13) are preferably connected to each other by a mechanical element (e.g. a bolt) and formed into a single unit. The three chamber connecting piece (11), the pinch valve chamber (12) and the tube filter chamber (13) are preferably made of metal and / or hard plastic material. In the invention, there are two three-chamber connecting pieces (11). The first of these is at the entrance of the powder transfer unit (1 ), and the other at its exit. In the invention, the powder paint (H1) coming from the reservoir (H) is taken from a suction pipe (H4) to the three chamber connection piece (11), and to the pinch valves (P1 , P2, P3) in the pinch valve chambers (12) via the three chamber connection piece paths (111).

[0120] The three-chamber connecting piece path (111), which enable the three paint paths in the three-chamber connecting piece (11) to become a single path, are preferably arranged in a geometric structure in the shortest and equal distance. When the pinch valves (P1, P2, P3) are compressed by the pinch valve air (A2), the powder paint (H1) is transferred to the suction-transfer chambers (EB1 , EB2, EB3) in the tube filter chamber (13). In the suction-transfer chambers (EB1 , EB2, EB3), powder paint (H1) is supplied tothe three chamber connection piece paths (111) in the lower three chamber connection piece (11) with the help of the main air (A1) and the pinch valves (P4, P5, P6) in the lower pinch valve chamber (12) and from there it is transferred to the transfer pipe (H5). In the invention, the pinch valves (P1 , P2, P3, P4, P5, P6) are made of flexible material and when air is given, they are in a position to compress and close the path, and when the air is released, they expand and open the path. In this way, the suction-transfer chambers (EB1, EB2, EB3) can perform the suction and thrust (pressure) functions. Thanks to the 3 suction-transfer chambers (EB1 , EB2, EB3) and 6 pinch valves (P1 , P2, P3, P4, P5, P6) in the invention, the said pump has a regular paint flow and allows precise control of the powder paint (H1). Suction-transfer chambers (EB1, EB2, EB3) provide powder paint (H1) flow in a way that allows continuity by performing suction and transfer processes at different time intervals.

[0121] In the invention, powder paint (H1) is located in the reservoir (H). Beneath the powder paint (H1 ) in the reservoir (H), there is a fluidization base (H2). The fluidization base (H2) is air permeable, but not the powder paint (H1). In this way, a non-permeable section (H3) is created at the bottom of the reservoir (H). In the invention, the powder paint (H1) is transferred to the suction pipe (H4) by the air coming from the pneumatic line (A6) under the chamber in the non-permeable section (H3). When pressurized air is supplied to the section of the reservoir (H) that is impermeable to powder paint - non-permeable section - (H3) from the pneumatic line (A6) under the chamber, the thermoset / thermoplastic / enamel powder (H1) begins to bubble and behave like a fluid. Thermoset / thermoplastic / enamel powder paint (H1), which is supplied with air from below and starts to behave like a fluid, can be absorbed through the suction pipe (H4). The powder paint (H1), picked up by the suction pipe (H4), passes through the powder transfer unit (1) and is transferred to the transfer pipe (H5). It is then transferred to the powder coating gun (TB) via the transfer pipe (H5).

[0122] In the invention, the powder coating gun (TB) comprises a powder coating trigger (TB1) that sprays powder paint (H1) when pressed. The powder paint (H1), pressurized with air coming from the gun needle air (A5) line, is sprayed at the tip of the powder coating gun (TB) and applied to the workpiece (IP). In the invention, the powder coating gun (TB) is integrated into the control unit (K) via the gun signal connection (5). In the invention, there is a mixer part (65) in a section of the powder coating gun (TB). The function of the mixer part (65) is to ensure that the powder paint (H1) taken from the transfer pipe (H5) is mixed with the air coming from the mixer air (A4) line and made homogeneous. Themixer part (65) is connected directly to the powder coating gun (TB) when not in use, or it can be turned off by adjusting it from the control unit (K) if it is not used.

[0123] In the invention, the main air (A1) is constant pressure air produced in a compressor or generator and regulated as desired in a regulator. The transmission air (A3) ensures that the thermoset / thermoplastic / enamel powder paint absorbed into the internal volume of the tube filters (131 , 132, 133) is conveyed towards the powder coating gun (TB). Pinch valve air (A2) is used to compress or loosen the pinch valves (P1 , P2, P3, P4, P5, P6).

[0124] In the invention, the control of the main air (A1), pinch valve air (A2), transmission air (A3), mixer air (A4), gun needle air (A5), under-chamber pneumatic line (A6) air and gun signal connection (5) is performed via the screen or computer in the control unit (K).

Claims

CLAIMS1. A method for operating a powder paint pump that takes the powder paint (H1) in a reservoir (H) through a suction pipe (H4) and transfers it to a powder coating gun (TB) or a reservoir (H) via a transfer pipe (H5), having the following:• at least one powder transfer unit (1 ),• three suction-transfer chambers (EB1 , EB2, EB3),• a pinch valve chamber (12) located at the inlet section of the aforementioned powder transfer unit (1), comprising a fourth pinch valve (P4), a fifth pinch valve (P5), and a sixth pinch valve (P6), all made of flexible material,• a pinch valve chamber (12) located at the outlet section of the powder transfer unit (1 ), comprising a first pinch valve (P1 ), a second pinch valve (P2), and a third pinch valve (P3), all made of flexible material,• a tube filter chamber (13) comprising the first suction-transfer chamber (EB1 ), the second suction-transfer chamber (EB2) and the third suction-transfer chamber (EB3) which takes the powder paint (H1) from the direction of the suction pipe (H4) and transfers it to the direction of the transfer pipe (H5) and is formed between the pinch valve chambers (12) in the inlet and outlet sections, the first tube filter (131), the second tube filter (132) and the third tube filter (133),• at least one pump body (2) that supplies pinch valve air (A2) for the compression and loosening of the pinch valves (P1, P2, P3, P4, P5, P6) through the main air (A1 ) it has, and transmission air (A3) for the transmission of the powder paint (H1) to the suction-transfer chambers (EB1, EB2, EB3) in the tube filter chamber (13) to the pinch valve chamber (12) at the outlet, • at least one control unit (K) controlling the air lines (A2, A3, A4, A5) gun signal connection (5) and electronic equipment required for the operation of the powder coating gun (TB),characterized in thato the operating period (WT) of the second suction-transfer chamber (EB2) is arranged so that it begins T = WT / 3 time after the first suctiontransfer chamber (EB1 ) begins operating,o the operation period (WT) of the third suction-transfer chamber (EB3) is arranged so that it begins T= 2WT / 3 time after the operation of the first suction-transfer chamber (EB1 ),o the first suction-transfer chamber (EB1), the second suction-transfer chamber (EB2) and the third suction-transfer chamber (EB3) continue to operate in repetitive cycles to maintain the phase shift at the specified T= WT / 3 and T= 2WT / 3 time (T) values, o the directional control valves (VT1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1 , VV2, VV3, VPUR) that provide the mentioned cycle and the cleaning actions of the pump are triggered at the appropriate times and direct the air and pressure in the pump, o in order to ensure the regular transmission of air and powder paint to the powder coating gun (TB), any two of the transfer valves (VT 1 , VT2, VT3) remain open during continuous operation.

2. The method according to claim 1, characterized in that• From T=0 to T=WT / 3 the first pinch valve actuator (VP1 ) is triggered,• At T=0, the first vacuum valve (VV1) is triggered and remains open for the vacuum open time (VA),• Meanwhile, the powder paint (H1 ) in the suction pipe (H4) is filled into the first suction-transfer chamber (EB1),• From the moment T = WT / 3 to the moment T =WT, the first transfer valve (VT 1 ) and the fourth pinch valve actuator (VP4) are triggered,• The powder paint (H1) filled into the first suction-transfer chamber (EB1) between T=0 and T= WT / 3 is transferred towards the powder coating gun (TB).

3. The method according to claim 1, characterized in that• From T=0 to T=WT / 3, the fifth pinch valve actuator (VP5) is triggered,• After T=WT / 3, the second pinch valve actuator (VP2) is triggered for WT / 3 time,• The second vacuum valve (VV2) is triggered for the vacuum open time (VA), • Meanwhile, the powder paint (H1) in the suction pipe (H4) is filled into the second suction-transfer chamber (EB2),• Then, for a period of 2*WT / 3, the second transfer valve (VT2) and the fifth pinch valve actuator (VP5) are triggered,T= WT / 3 time ago, the powder paint (H1) filled into the second suctiontransfer chamber (EB2) is transferred towards the powder coating gun (TB).

4. The method according to claim 1, characterized in that• From the moment T= 0 to the moment T=2*WT / 3 the third transfer valve (VT3) and the sixth pinch valve actuator (VP6) are triggered,• The third pinch valve actuator (VP3) is triggered for WT / 3 time,• The third vacuum valve (VV3) is triggered for the vacuum open time (VA), • Meanwhile, the powder paint (H1) in the suction pipe (H4) is filled into the third suction-transfer chamber (EB3),• Then, for a period of 2*WT / 3 time, the third transfer valve (VT3) and the sixth pinch valve actuator (VP6) are triggered,• T= WT / 3 time ago, the powder paint (H1) filled in the third suction-transfer chamber (EB3) is transferred towards the powder coating gun (TB).

5. The method according to claim 1 , characterized in that cleaning is carried out from the pump to the reservoir (H) or from the pump to the powder coating gun (TB) or both together by triggering the cleaning valve (VPUR) and the pinch valve actuators (VP1, VP2, VP3, VP4, VP5, VP6).

6. The method according to claim 5, characterized in that the cleaning valve (VPUR) performs the cleaning process from the pump to the reservoir (H) by triggering the first pinch valve actuator (VP1 ), the second pinch valve actuator (VP2), the third pinch valve actuator (VP3), the first transfer valve (VT1), the second transfer valve (VT2) and the third transfer valve (VT3).

7. The method according to claim 5, characterized in that the cleaning valve (VPUR) performs the cleaning process from the pump to the powder coating gun (TB) by triggering the fourth pinch valve actuator (VP4), the fifth pinch valve actuator (VP5), the sixth pinch valve actuator (VP6), the first transfer valve (VT 1 ), the second transfer valve (VT2) and the third transfer valve (VT3).

8. A powder paint pump that takes the powder paint (H1 ) from a reservoir (H) through a suction pipe (H4) and transfers it to a powder coating gun (TB) or a reservoir (H) through a transfer pipe (H5), having the following:at least one powder transfer unit (1),• three suction-transfer chambers (EB1 , EB2, EB3),• a pinch valve chamber (12) located at the inlet section of the aforementioned powder transfer unit (1), comprising a fourth pinch valve (P4), a fifth pinch valve (P5), and a sixth pinch valve (P6), all made of flexible material,• a pinch valve chamber (12) located at the outlet section of the powder transfer unit (1 ), comprising a first pinch valve (P1 ), a second pinch valve (P2), and a third pinch valve (P3), all made of flexible material,• a tube filter chamber (13) comprising the first suction-transfer chamber (EB1 ), the second suction-transfer chamber (EB2) and the third suction-transfer chamber (EB3) which takes the powder paint (H1) from the direction of the suction pipe (H4) and transfers it to the direction of the transfer pipe (H5) and is formed between the pinch valve chambers (12) in the inlet and outlet sections, the first tube filter (131), the second tube filter (132) and the third tube filter (133),• at least one pump body (2) that supplies pinch valve air (A2) for the compression and loosening of the pinch valves (P1, P2, P3, P4, P5, P6) through the main air (A1 ) it has, and transmission air (A3) for the transmission of the powder paint (H1) to the suction-transfer chambers (EB1, EB2, EB3) in the tube filter chamber (13) to the pinch valve chamber (12) at the outlet, • at least one control unit (K) controlling the air lines (A2, A3, A4, A5), the gun signal connection (5), and the electronic equipment required for operation of the powder coating gun (TB),characterized by comprising:o transfer valves (VT1, VT2, VT3) on the said pump body (2), which transfer the vacuum power produced by the vacuum generators (VAC1, VAC2, VAC3) to the suction-transfer chambers (EB1, EB2, EB3),o vacuum valves (VV1, VV2, VV3) that produce vacuum in vacuum generators (VAC1, VAC2, VAC3) with air supplied from an air regulator (HR),o pinch valve actuators (VP1 , VP2, VP3, VP4, VP5, VP6), which are triggered to open and close the pinch valves (P1 , P2, P3, P4, P5, P6), o the first suction-transfer chamber (EB1 ) which starts to operate at T=0 by triggering the mentioned directional control valves (VT 1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1 , VV2, VV3, VPUR); the secondsuction-transfer chamber (EB2) which starts to operate WT / 3 time after the first suction-transfer chamber (EB1); the third suctiontransfer chamber (EB3) which starts to operate 2WT / 3 time after the first suction-transfer chamber (EB1 );9. The pump according to claim 8, characterized by comprising at least one cleaning valve (VPUR) in the pump body (2), which performs cleaning from the pump to the reservoir (H) or from the pump to the powder coating gun (TB) or both together by triggering the pinch valve actuators (VP1, VP2, VP3, VP4, VP5, VP6).

10. The pump according to claim 8, characterized by comprising:• the main control board (K1) that controls the proportional pressure control valves (K11, K12, K13) in the control unit (K) and allows the general air from the main air line (A1 ) to be regulated as desired for the transmission air (A3), gun needle air (A5), mixer air (A4) and their pressures to be adjusted,• pump driver board (K2) that controls directional control valves (VT1 , VT2, VT3, VP1 , VP2, VP3, VP4, VP5, VP6, VV1 , VV2, VV3, VPUR), • proportional control valves (K11, K12, K13) that provide pressurization of general air, transmission air (A3), gun needle air (A5), mixer air (A4) from the main air line (A1),• pressure compensation tank (K3), which supplies the pressure required to close the pinch valves (P1, P2, P3, P4, P5, P6) by triggering the pinch valve actuators (VP1 , VP2, VP3, VP4, VP5, VP6),• pressure sensor (BS) which measures the pressure of the air in the pressure compensation tank (K3) and transfers this pressure value as electrical information to the pump driver board (K2),• a filling valve (VD) that keeps the air in the pressure compensation tank (K3) at the desired pressure.

11. The pump according to claim 8, characterized in that the transfer valves (VT 1 , VT2, VT3) are made up of three-way two-position (3 / 2) valves and are externally piloted valves.