Protection method for local scouring of bridge pier
A bridge pier and partial technology, which is applied in the protection field of partial erosion of bridge piers, can solve problems such as service life that has not yet reached the specification, hidden dangers of bridge safe operation, and bridge failure to reach, etc., to achieve good protection effect, improve anti-scouring ability, and long service life Effect
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2020-02-18
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of bridge pier protection, in particular to a protection method for partial scour of bridge piers. Background technique
[0002] There are countless rural road bridges in mountainous areas that have been completed, under construction, and planned in the future. However, the erosion of rivers in mountainous areas is one of the main reasons for the damage of the lower parts of road bridges; The scouring of the river will damage the bridge piers and hollow out the bridge foundation, which will greatly reduce the bearing capacity of the bridge substructure. In severe cases, it will lead to the inclination of the piers or the collapse of the bridge. Therefore, local scour protection of bridges in mountainous areas is particularly necessary.
[0003] The principle of local scour protection for bridge piers includes the following two categories, one is solid anti-scour protection, which refers to placing some soli...
Examples
Embodiment 1
[0046] This embodiment takes a bridge in a mountainous area in Anhui Province as an example. The bridge pier to be reinforced also includes an enlarged foundation 3 arranged under the pier body 2. The central axis of the enlarged foundation 3 coincides with the central axis of the pier body 2, and the enlarged foundation The area of the upper surface of 3 is larger than the area of the pier body 2 and the surface in contact with it; the pier body 2 and the enlarged foundation 3 are both rectangular. Since the bridge is located in a mountainous area, the flood season surges and falls, scouring the river bed surface 1, and the scouring force is extremely strong. After inspection, it was found that the local scouring depth of the bridge was close to the buried depth of the expanded foundation 3. According to a protection method for partial scouring of bridge piers, the specific steps are as follows:
[0047] S1. Determine the reinforcement depth H of the pier to be reinforced ...
Embodiment 2
[0063] This embodiment takes a bridge in a mountainous area of Guangxi Province as an example. The bridge pier to be reinforced also includes an enlarged foundation 3 arranged below the pier body 2. The central axis of the enlarged foundation 3 coincides with the central axis of the pier body 2, and the enlarged foundation The area of the upper surface of 3 is greater than the area of the surface in contact with the pier body 2; wherein the pier body 2 is cylindrical with a diameter of 2.5m, the enlarged foundation 3 is square, and the riverbed is mainly cohesive soil. Affected by the flood, the bridge pier has severe local erosion. According to a protection method for the partial erosion of the bridge pier, the specific steps are as follows:
[0064] S1. Determine the reinforcement depth H of the pier to be reinforced according to the depth h of the scoured pit, such as figure 1 and image 3 As shown, the specific steps are as follows:
[0065] S11, determine the pit ...