Water supply system risk evaluation method based on complex network and combined weighting method
By constructing complex network models and combination empowerment methods, combined with gray fuzzy comprehensive evaluation, the problem of insensitive to extreme data in the existing technology of water supply pipeline safety evaluation methods is solved, and real-time and accurate safety assessment of water supply pipelines is achieved. , improves the accuracy of risk assessment.
Patent Information
- Application Number
- CN202411151900.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing water supply pipeline safety evaluation methods cannot fully consider the differences in the role and nature of each indicator, which leads to insensitive to abnormal data when facing extreme data and cannot meet the needs of real-time monitoring and accurate assessment of the safety of water supply pipelines.
Using a risk evaluation method based on complex network and combination empowerment method, the evaluation index system is determined by building a complex network model of the water supply network, the G1 method and COWA operator are used to allocate weights, combined with gray fuzzy comprehensive evaluation, the weights are dynamically adjusted and calculated Comprehensive risk values to achieve real-time risk assessment and emergency response.
This method can fully capture the complexity of the water supply system, improve the accuracy of risk assessment, effectively deal with uncertainty and ambiguity in the evaluation process, and monitor and accurately evaluate the safety of the water supply pipeline network in real time.
Smart Images

Figure CN119026912A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of municipal water supply safety, and specifically is a water supply system risk assessment method based on complex network and combined weighting method. Background Art
[0002] With the acceleration of urbanization, water supply safety issues have become increasingly prominent, and higher requirements have been placed on the safety management of water supply networks. As a complex system, the safety evaluation of water supply networks not only needs to consider static structural characteristics, but also pay attention to dynamic operating conditions and potential risk changes. Therefore, it is necessary to develop a technology that can accurately evaluate the safety status of water supply networks in real time, so as to carry out emergency warnings in a timely manner, formulate effective risk management plans and risk spread blocking strategies, and achieve the purpose of chain-breaking disaster reduction.
[0003] At present, the traditional weighted index evaluation methods are mainly used to evaluate the safety of urban water supply, including simple quantitative evaluation and judgment based on experience. At the same time, these common methods have some significant problems, such as not fully considering the differences in the role and nature of each indicator, and being insensitive to abnormal data when facing extreme data. In addition, the existing evaluation process often does not take into account the different roles of each water supply point in the water supply network, which makes them unable to meet the actual needs of real-time monitoring and accurate evaluation of the safety of the water supply network. Summary of the invention
[0004] In view of the above problems, the present invention is proposed to provide a water supply system risk assessment method based on complex network and combined weighting method to overcome the above problems or at least partially solve the above problems.
[0005] To achieve the above object, the present invention adopts the following technical solutions:
[0006] A water supply system risk assessment method based on complex network and combined weighting method, the method comprising:
[0007] Construct a complex network model of the water supply network;
[0008] Determine the evaluation indicator system;
[0009] Apply the combined weighting method to assign weights;
[0010] Apply variable weight theory to determine variable weight vector;
[0011] Grey fuzzy comprehensive evaluation;
[0012] Calculate the comprehensive risk value;
[0013] Dynamic risk assessment and emergency response.
[0014] Optionally, it is characterized in that constructing a complex network model of the water supply network requires collecting geographic information system data, pipeline attributes and node types of the water supply network.
[0015] Optionally, it is characterized in that the water supply network is expressed as G=(N,E), where N is a node set and E is a pipeline connection set.
[0016] Optionally, it is characterized in that the evaluation indicators include pipeline material, pipe diameter, service life, water pressure, flow rate, water quality and node chlorine content.
[0017] Optionally, it is characterized in that the G1 method and COWA operator tool are used to assign weights to the evaluation indicators, specifically including:
[0018] The importance ranking of each indicator is determined by expert scoring, and the importance ratio of adjacent indicators is calculated:
[0019] r k =w k-1 / w k (k=n, n-1, ..., 3, 2)
[0020] Then determine the subjective weight of each indicator:
[0021]
[0022] In the formula, w k is the weight of the indicator factor, r k is the importance of the k-1th index factor to the kth index factor in the order relationship, π i is the importance ratio of the i-th indicator to the previous indicator r k ;
[0023] Using the COWA method, based on expert scoring, the objective weight of each indicator is determined by calculating the weighted vector and absolute weight:
[0024]
[0025] In the formula, w j is the objective weight, is the number of combinations, b i The data is sorted after being scored by experts;
[0026] Combining the results of the G1 method and the COWA operator, the final weight is determined by linear combination:
[0027] W=αW G1 +(1-α)W COWA
[0028] In the formula, W is a fixed weight vector, W G 1 and WCOWA are the weight vectors determined by the G1 method and the COWA operator respectively, and α is the adjustment parameter.
[0029] Optionally, it is characterized in that, according to the importance and sensitivity of the indicator, the fixed weight vector is adjusted to obtain a variable weight vector S(x)={S1(x), S2(x), ..., S n (x), and set the sensitivity threshold and weight adjustment coefficient of the indicator.
[0030] Optionally, it is characterized in that the grey fuzzy comprehensive evaluation includes:
[0031] Perform membership analysis on each indicator and construct membership function The grey model GM1 is used to predict the membership degree, and the formula is:
[0032]
[0033] In the formula, x is the actual measured value of the indicator, and β is the model parameter.
[0034] Optionally, the method is characterized in that calculating the comprehensive risk value comprises:
[0035] Calculate the comprehensive score of each indicator B i ;
[0036]
[0037] In the formula, w fi is the weight after fusion, s i (x) is the variable weight, is the degree of membership;
[0038] The comprehensive scores of all indicators are weighted and summed to obtain the comprehensive risk value of the water supply network;
[0039]
[0040] In the formula, R is the comprehensive risk value, B i It is the comprehensive score of each indicator.
[0041] Optionally, it is characterized in that risk levels are divided according to the comprehensive risk value R, and emergency warning and risk management measures are formulated.
[0042] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0043] 1. The present invention constructs a complex network model of the water supply network, which not only takes into account the structural characteristics of the network, but also integrates the importance of each node and pipeline, thereby solving the problem in the prior art that a single evaluation method cannot fully capture the complexity of the water supply system.
[0044] 2. The present invention adopts a combined weighting method, including the G1 method and the COWA operator, to dynamically adjust the weight of each indicator, solving the problem that the traditional fixed weight method is insensitive to abnormal data when facing extreme data. Combined with the gray fuzzy comprehensive evaluation method, it can monitor and accurately evaluate the safety of the water supply network in real time, and can effectively deal with the uncertainty and ambiguity in the evaluation process, thereby improving the accuracy of risk assessment. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 It is a flow chart of a water supply system risk assessment method based on complex network and combined weighting method provided in an embodiment of the present application;
[0046] Figure 2 Pipeline network topology diagram of the embodiment of the present application;
[0047] Figure 3 It is the weight allocation flow chart of the combined weighting method;
[0048] Figure 4 It is a grey fuzzy comprehensive evaluation flow chart. DETAILED DESCRIPTION
[0049] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0050] See also Figure 1 This embodiment provides a water supply system risk assessment method based on complex network and combined weighting method, including:
[0051] S1. Construct a complex network model of the water supply network.
[0052] The water supply network of a certain city was selected as the research object. To construct a complex network model of the water supply network, it was necessary to collect information such as geographic information system data, pipeline attributes, and node types of the water supply network.
[0053] The water supply network is represented by G = (N, E), where N is the node set and E is the pipeline connection set. The pipeline topology of this embodiment is as follows Figure 2 As shown, the physical layout of the network is provided for evaluation.
[0054] S2. Determine the evaluation index system.
[0055] According to the characteristics of the water supply network, the evaluation indicators include pipe material, pipe diameter, service life, water pressure, flow, water quality and node chlorine content. Set the indicator set A = {a1, a2, a3, a4, a5, a6, a7}, where a n It corresponds to a specific aspect in the safety assessment of water supply networks.
[0056] S3. Apply the combined weighting method to assign weights.
[0057] Combining expert experience and objective data analysis, the G1 method and COWA operator tool are used to assign weights to the evaluation indicators, such as Figure 3 As shown, specifically including:
[0058] The importance ranking of each indicator is determined by expert scoring, and the importance ratio of adjacent indicators is calculated:
[0059] r k =w k-1 / w k (k=n, n-1, ..., 3, 2)
[0060] Then determine the subjective weight of each indicator:
[0061]
[0062] In the formula, w k is the weight of the indicator factor, r k is the importance of the k-1th index factor to the kth index factor in the order relationship, π i is the importance ratio of the i-th indicator to the previous indicator r k ;
[0063] Using the COWA method, based on expert scoring, the objective weight of each indicator is determined by calculating the weighted vector and absolute weight:
[0064]
[0065] In the formula, w j is the objective weight, is the number of combinations, b i The data is sorted after the experts score; the calculated w k and w j They are:
[0066] 0.15, 0.20, 0.10, 0.25, 0.15, 0.10, 0.05 and 0.12, 0.18, 0.08, 0.30, 0.15, 0.07, 0.10.
[0067] Combining the results of the G1 method and the COWA operator, the final weight is determined by linear combination:
[0068] W=αW G1 +(1-α)W COWA
[0069] In the formula, W is a fixed weight vector, W G 1 and W COWA are the weight vectors determined by the G1 method and the COWA operator respectively, and α is the adjustment parameter.
[0070] When the objective function is minimum, α=0.5, W=0.5W1+0.5W2.
[0071] It can be obtained that W1=0.135, W2=0.190, W3=0.090, W4=0.275, W5=0.150, W6=0.085, W7=0.075.
[0072] S4, applying variable weight theory to determine variable weight vector;
[0073] Determine the sensitivity level of each indicator, divide the indicators into three categories: strongly sensitive, medium sensitive and weakly sensitive, and assign different adjustment coefficients to each type of indicator: Strongly sensitive indicators: the adjustment coefficient may be 1.2 or higher, indicating that more weight is given to small changes in these indicators; Medium sensitive indicators: the adjustment coefficient may be 1.0, indicating that no adjustment is made; Weakly sensitive indicators: the adjustment coefficient may be 0.8 or lower, indicating that less weight is given to changes in these indicators.
[0074] According to the importance and sensitivity of the indicator, the fixed weight vector W is adjusted to obtain the variable weight vector S(x)={S1(x), S2(x),..., S n (x), and set the sensitivity threshold and weight adjustment coefficient of the indicator.
[0075] We can get W = [0.15, 0.20, 0.10, 0.25, 0.15, 0.10, 0.05], indicators 1 and 2 are highly sensitive, the adjustment coefficient is 1.2, indicators 3 and 4 are moderately sensitive, the adjustment coefficient is 1.0, indicators 5 and 6 are weakly sensitive, the adjustment coefficient is 0.8. The variable weight vector S(x) is calculated as follows:
[0076] S(x)1=1.2·0.15=0.18
[0077] S(x)2=1.2·0.20=0.24
[0078] S(x)3=1.0·0.10=0.10
[0079] S(x)4=1.0·0.25=0.25
[0080] S(x)5=0.8·0.15=0.12
[0081] S(x)6=0.8·0.10=0.08
[0082] S(x)7=0.8·0.05=0.04
[0083] S5. Grey fuzzy comprehensive evaluation. Figure 4 As shown, Figure 4 This is a grey fuzzy comprehensive evaluation flow chart.
[0084] Perform membership analysis on each indicator and construct membership function The grey model GM1 is used to predict the membership degree, and the formula is:
[0085]
[0086] In the formula, x is the actual measured value of the indicator, and β is the model parameter.
[0087] The calculation can be obtained:
[0088] μ 12 =0.2, μ 13 =0
[0089] μ 21 =0.6, μ 22 =0.4,μ 23 =0
[0090] μ 31 =0.3,μ 32 =0.6, μ 33 =0.1
[0091] μ 41 =0.1,μ 42 =0.7, μ 43 =0.2
[0092] μ 51 =0.4,μ 52 =0.5, μ 53 =0.1
[0093] μ 61 =0.2, μ 62 =0.6, μ 63 =0.2
[0094] μ 71 =0.1,μ 72 =0.8,μ 73 =0.1
[0095] Substituting the given values into the formula, we obtain μ = 1.0.
[0096] S6. Calculate the comprehensive risk value.
[0097] Calculate the comprehensive score of each indicator B i ;
[0098]
[0099] In the formula, w fi is the weight after fusion, s i (x) is the variable weight, is the degree of membership;
[0100] The comprehensive scores of all indicators are weighted and summed to obtain the comprehensive risk value of the water supply network;
[0101]
[0102] In the formula, R is the comprehensive risk value, B i It is the comprehensive score of each indicator.
[0103] Calculation shows that R=0.12+0.14+0.06+0.125+0.06+0.03+0.01=0.52.
[0104] The comprehensive risk value is 0.52, which represents the overall risk level of the water supply network based on the current weights and membership values. In practical applications, the membership value needs to be determined based on the specific membership function and the actual measured indicator data, and more evaluation levels and membership values may need to be considered.
[0105] S7. Dynamic risk assessment and emergency response.
[0106] Risk levels are divided according to the comprehensive risk value R, and emergency warning and risk management measures are formulated. The comprehensive risk value of this embodiment is 0.52, which is a moderate risk. It should be taken seriously and corresponding emergency warning and risk management measures should be formulated.
[0107] This embodiment constructs a complex network model of the water supply network, which not only takes into account the structural characteristics of the network, but also integrates the importance of each node and pipeline, thereby solving the problem in the prior art that a single evaluation method cannot fully capture the complexity of the water supply system.
[0108] This embodiment adopts a combined weighting method, including the G1 method and the COWA operator, to dynamically adjust the weight of each indicator, solving the problem that the traditional fixed weight method is insensitive to abnormal data when facing extreme data. Combined with the gray fuzzy comprehensive evaluation method, it can monitor and accurately evaluate the safety of the water supply network in real time, effectively deal with the uncertainty and ambiguity in the evaluation process, and improve the accuracy of risk assessment.
[0109] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, and it cannot be determined that the specific implementation of the present invention is limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as falling within the protection scope of the present invention.
Claims
1. A water supply system risk assessment method based on complex network and combined weighting method, characterized in that: The method comprises: Construct a complex network model of the water supply network; Determine the evaluation indicator system; Apply the combined weighting method to assign weights; Apply variable weight theory to determine variable weight vector; Grey fuzzy comprehensive evaluation; Calculate the comprehensive risk value; Dynamic risk assessment and emergency response.
2. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: Constructing a complex network model of the water supply network requires collecting geographic information system data, pipeline attributes, and node types of the water supply network.
3. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: The water supply network is represented by G=(N,E), where N is a node set and E is a pipeline connection set.
4. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: The evaluation indicators include pipeline material, pipe diameter, service life, water pressure, flow, water quality and node chlorine content.
5. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: Use the G1 method and COWA operator tool to assign weights to the evaluation indicators, including: The importance ranking of each indicator is determined by expert scoring, and the importance ratio of adjacent indicators is calculated: r k =w k-1 / w k (k=n,n-1,…,3,2) Then determine the subjective weight of each indicator: In the formula, w k is the weight of the indicator factor, r k is the importance of the k-1th index factor to the kth index factor in the order relationship, π i is the importance ratio of the i-th indicator to the previous indicator r k ; Using the COWA method, based on expert scoring, the objective weight of each indicator is determined by calculating the weighted vector and absolute weight: In the formula, w j is the objective weight, is the number of combinations, b i The data is sorted after being scored by experts; Combining the results of the G1 method and the COWA operator, the final weight is determined by linear combination: W=αW G1 +(1-α)W COWA In the formula, W is a fixed weight vector, W G 1 and W COWA are the weight vectors determined by the G1 method and the COWA operator respectively, and α is the adjustment parameter.
6. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: According to the importance and sensitivity of the indicator, the fixed weight vector is adjusted to obtain the variable weight vector S(x)={S1(x), S2(x),..., S n (x), and set the sensitivity threshold and weight adjustment coefficient of the indicator.
7. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: Grey fuzzy comprehensive evaluation includes: Perform membership analysis on each indicator and construct membership function The grey model GM1 is used to predict the membership degree, and the formula is: In the formula, x is the actual measured value of the indicator, and β is the model parameter.
8. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 1, characterized in that: Calculation of comprehensive risk value includes: Calculate the comprehensive score of each indicator B i ; In the formula, w fi is the weight after fusion, s i (x) is the variable weight, is the degree of membership; The comprehensive scores of all indicators are weighted and summed to obtain the comprehensive risk value of the water supply network; In the formula, R is the comprehensive risk value, B i It is the comprehensive score of each indicator.
9. A water supply system risk assessment method based on complex network and combined weighting method as claimed in claim 8, characterized in that: Risk levels are divided according to the comprehensive risk value R, and emergency warning and risk management measures are formulated.
Citation Information
Patent Citations
Pipeline water quality risk evaluation method based on water supply network dynamic model
CN106600094A
State evaluation and life prediction method of power transformer
CN115544793A
Underground cavern surrounding rock stability fuzzy comprehensive evaluation method based on AHP-variable weight
CN117350577A
Safety evaluation method for buildings and safety evaluation apparatus for buildings
KR101880054B1