Cascade water, wind and light storage optimization bidding method based on distribution robust opportunity constraint

Through the method based on distributed robust opportunity constraints, the bidding strategy of the cascade water wind and light energy storage system is optimized, and the impact of uncertainty in wind and light resources in the new power market is solved, the economic and reliability of the system is improved, and more efficient Market participation and resource allocation.

CN119027148APending Publication Date: 2024-11-26CHINA THREE GORGES UNIV
View PDF 0 Cites 8 Cited by

Patent Information

Application Number
CN202410915747.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the new power market environment, short-term optimization scheduling of cascade water and wind and light energy storage systems is difficult to effectively improve economics and market participation flexibility, and the uncertainty of wind and light resources affects system stability.

Method used

The cascaded water wind and light storage optimization bidding method based on distribution robust opportunity constraints is adopted. By collecting historical data, fit the combined probability distribution model of scenery and light output, the maximum return bidding optimization double-layer model is constructed, and the mixed integer linear planning model is used to solve the scenery and light. Constraints on uncertainty in output, optimize bidding strategies in the power-frequency modulation market.

Benefits of technology

It improves the economy and market participation flexibility of the cascade water and wind storage system, enhances the reliability and benefits of the system, balances profit maximization and risk minimization, and provides a model lower limit that is more in line with the actual situation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119027148A_ABST
    Figure CN119027148A_ABST
Patent Text Reader

Abstract

The invention discloses a cascade water, wind and light storage optimization bidding method based on distribution robust opportunity constraint. The method comprises the following steps: S1, collecting historical data of cascade hydropower stations, wind power stations and photovoltaic power stations; fitting and representing the wind-solar output joint probability distribution model of the region and the water level-storage capacity and tail water level-discharge relationship of each hydropower station; s2, describing a bidding output strategy of a cascade water-wind-light-storage system by adopting time parameters according to cascade water-wind-light-storage combined dispatching characteristics and the regulation capability of a cascade hydropower station and stored energy, and setting a strategy of cascade water-wind-light-storage short-term collaborative bidding; s3, constructing a maximum income bidding optimization double-layer bidding model of the cascade water, wind and light storage system in the electric energy-frequency modulation market; s4, on the basis of the step S3, characterizing the distribution robust chance constraint as the constraint of the wind and light output uncertainty, rewriting the equality and inequality containing the wind and light output; s5, performing linearization processing on the constructed model to obtain a mixed integer linear programming model; and S6, solving the mixed integer linear programming model by adopting GUROBI to obtain the optimal bidding mode and bidding strategy of the system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of power systems, and in particular to a cascade hydro-wind-solar-storage optimization bidding method based on distributed robust opportunity constraints. Background Art

[0002] In recent years, solar and wind energy have developed rapidly due to their environmental friendliness, renewable nature, and abundant resources. However, due to their high dependence on climate factors, strong randomness and volatility, direct integration into the power grid may threaten the security and economic operation of the power grid. Hydropower and energy storage systems are ideal for stabilizing the fluctuations in wind and solar output due to their rapid adjustment capabilities. The complementary joint operation of cascade hydropower, wind, solar, and energy storage has become an important factor in achieving high-quality development. China's solar and wind power installed capacity exceeded 200 GW in 2019, but there is a spatial mismatch between electricity demand and supply, with demand in the east higher than in the west. Therefore, studying the complementary joint dispatching method of hydropower, wind, solar, and energy storage is crucial to improving the economy and stability of the system. Under the new power market environment, the short-term optimal dispatching of cascade hydropower systems plays an important role in optimizing market decision-making and resource allocation, helping hydropower companies to participate in market competition and promote high-quality development of the industry. In summary, studying the short-term joint optimal dispatching of hydropower, wind, solar, and energy storage systems is of great theoretical significance and has significant engineering application value in practice. These solutions will not only bring advantages to corporate market decision-making and resource allocation, but will also play an important role in practice, guiding companies to achieve better benefits in the new market environment, while promoting the sustainable development of the power industry. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide an optimized bidding method for cascaded hydro-wind-solar-storage systems based on distributed robust opportunity constraints, which effectively improves the economy of each power generation enterprise and the flexibility of participating in the market, provides technical support for the planning and construction of cascaded hydro-wind-solar complementary systems, and is suitable for promotion and application in the joint complementary scheduling of large-scale power generation systems under the new power market.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a cascade hydropower, wind power, solar power and storage optimization bidding method based on distributed blue opportunity constraints, comprising the following steps: S1. Collect historical data of cascade hydropower stations, wind farms, and photovoltaic power stations; and fit the joint probability distribution model representing the wind and solar power output in the region and the relationship between the water level-reservoir capacity and tailwater level-discharge of each hydropower station; S2. Based on the joint dispatching characteristics of cascade hydropower, wind power, solar power and energy storage, and the regulation capacity of cascade hydropower stations and energy storage, the bidding output strategy of cascade hydropower, wind power, solar power and energy storage systems is described using time parameters, and a short-term coordinated bidding strategy for cascade hydropower, wind power, solar power and energy storage is set; S3. Construct a double-layer bidding model for maximum revenue bidding optimization of cascaded hydro-wind-solar-storage systems in the power-frequency regulation market; S4, based on step S3, the constraint characterized by the blue-robust opportunity constraint as the uncertainty constraint of wind and solar power output is rewritten to include the equations and inequalities of wind and solar power output; S5, linearizing the constructed model to obtain a mixed integer linear programming model; S6. Use GUROBI to solve the mixed integer linear programming model and obtain the optimal bidding model and bidding strategy of the system.

[0005] Preferably, the step S1 is specifically as follows: Firstly, the parameters of water level-reservoir capacity and tailwater level-discharge of each hydropower station were fitted, and the probability density functions of wind power and photovoltaic output samples were obtained based on the non-parametric kernel density estimation method. Then, the Copula theory was used to establish a variety of common joint probability distribution models of wind and photovoltaic output. By comparing the Kendall correlation coefficient, Spearman correlation coefficient and Euclidean distance of these models, the Copula function with the best fitting degree was selected to characterize the complementary characteristics of wind power and photovoltaic output in the region.

[0006] Preferably, the step S3 constructs a double-layer model for maximizing the benefits of the upper cascade hydro-wind-solar-storage system and jointly clearing the power purchase cost of the service market of the lower electric energy-frequency regulation market, which is composed of an objective function, decision variables and constraints: a. Upper objective function The upper objective function is to maximize the benefits of the cascaded hydro-wind-solar-storage system: ; DA means the day-ahead power and frequency regulation joint market stage. is the total revenue of cascaded hydropower, wind power, solar power and storage in the day-ahead market; T is the day-ahead scheduling period, which is 15 minutes; is the revenue of the cascade hydropower plant participating in the day-ahead energy market during period t; The benefits of participating in the day-ahead frequency regulation market for cascaded hydropower companies; The benefits for wind and photovoltaic manufacturers participating in the day-ahead energy market; Profits for energy storage companies participating in the frequency regulation market; Energy storage power stations participate in the day-ahead power-frequency regulation market ; , They are the discharge and charging powers of the energy storage power station in the electricity market; They are the medium volume and winning mileage in the frequency modulation market; , , They are the day-ahead electricity energy market clearing price, the day-ahead auxiliary market frequency regulation capacity clearing price, and the frequency regulation mileage clearing price; The constraints include: (1) Energy storage charging and discharging constraints ; , are the maximum charging power and discharging power of the energy storage station, respectively. , Two are 0 / 1 variables, ensuring that the energy storage station can only be in the charging and discharging states at the same time; (2) Limitation on declared energy storage capacity ; is the frequency regulation capacity declared by the energy storage power station during period t, represents the frequency regulation mileage of the energy storage power station during period t, , They are the maximum frequency regulation capacity and maximum frequency regulation mileage of the energy storage power station; (3) Energy storage quotation constraints ; Where: , , , They are the charging and discharging price, frequency regulation capacity price and frequency regulation mileage price declared by the energy storage power station during period t; , , , They are the upper limits of the charging and discharging prices, frequency regulation capacity prices and frequency regulation mileage prices of energy storage power stations in the electric energy-frequency regulation market; (4) Energy storage state of charge constraints ; ; Where: , , They represent the minimum and maximum capacity allowed by the energy storage station k and its remaining capacity in time period t respectively; , They represent the discharging and charging efficiencies of the energy storage station k respectively; (5) Water balance constraints ; ; ; is the reservoir water storage capacity of power station i at the end of time period t; is the inflow flow of hydropower station i in the period t+1; is the outflow of hydropower station i in period t; is the power generation flow of hydropower station i in period t; is the abandoned water flow of power station i. is the flow rate of power station i-1 at time t after considering the water flow lag; is the interval flow between hydropower station i-1 and hydropower station i in time period t; (6) Reservoir capacity constraints ; , are the minimum and maximum storage capacities of the ith hydropower station respectively; (7) Water level-reservoir capacity relationship ; ; ; Where: is the reservoir water level of hydropower station i at time period t (m), and are the initial water level and the end water level of the period of hydropower station i, respectively, and their values ​​can be determined by the medium-term dispatch of cascade hydropower stations; is the water level-storage capacity relationship curve function of hydropower station i, which can be determined by polynomial fitting method; (8) Tailwater level-discharge relationship curve ; Where: is the tailwater level of hydropower station i at time t, is the relationship function between the discharge flow and tailwater level of hydropower station i, which can be determined by polynomial fitting method; (9) Constraints on downstream flow of hydropower stations ; Where: is the minimum discharge flow of the i-th hydropower station; is the maximum discharge flow of the i-th hydropower station; (10) Calculation process of unit generating head ; Where: is the generating head of the kth unit of the hydropower station i in time t, is the water head loss of the kth unit of the hydropower station i in time t; (11) Head loss function ; Where: and are the head loss coefficient and loss constant of hydropower station i, respectively, which can generally be obtained through hydraulic tests; (12) Unit dynamic characteristics relationship ; Where: is the generating head of the kth unit of the i-th hydropower station in time period t, m; () is the relationship function between output, flow and head of unit k of the i-th hydropower station; (13) Unit vibration zone constraints ; Where: and They are the upper and lower limits of the output of the zth vibration zone of the kth unit of the ith hydropower station; (13) Unit output constraints ; Where: and are the maximum and minimum outputs of the kth unit of the i-th hydropower station within a certain period of time; (14) Wind power day-ahead bidding output constraints ; The output limit of the wind power station; (15) PV day-ahead bidding output constraints ; The output limit of the photovoltaic power station; (16) Hydropower quotation constraints ; Prices declared for hydroelectric power plants; (17) Wind power quotation constraints ; Declare prices for wind power producers; (18) Photovoltaic quotation constraints ; Declare prices for photovoltaics; b. Lower layer objective function In the spot market, the power trading center collects the bidding information of each market participant, and then performs joint clearing of the electric energy and frequency regulation markets; the present invention considers that both energy storage and conventional units can participate in the bidding of the energy and frequency regulation markets. The goal of joint clearing is to minimize the sum of the power purchase cost and the frequency regulation market cost, and determine the winning bid of each power station unit; the lower-level joint clearing model of the electric energy-frequency regulation auxiliary service market is expressed as: ; , , They are the winning bids for cascaded hydro, wind and solar power in the electricity energy market; The constraints include: (1) The clearing of the electricity market needs to follow clearing rules and grid operation constraints ; ; ; ; ; Where: is the load in period t; Declare the output limit for the hydropower unit in time period t; Report the output limit of wind and photovoltaic units for time period t; , , , , , , , , is the dual variable of the corresponding constraint; (2) Frequency regulation market clearing rules and grid constraints ; ; ; ; ; ; Where: , They are frequency regulation capacity demand and frequency regulation mileage demand respectively; , are the frequency modulation capacity and frequency modulation mileage upper limit of frequency modulation machine i respectively; , , , , , , , is the dual variable of the corresponding constraint.

[0007] Preferably, in step S4, the distributed robust chance constraint model includes: a. Fuzzy set construction of wind and solar output: Although the underlying true distribution P is fuzzy, it can be constructed by constructing an empirical distribution To estimate the true distribution P, This is a limited historical sample set of wind and solar power output. When there is enough data, it can meet ; This paper uses Wasserstein distance to measure the similarity between different distributions and constructs an uncertainty set based on this.

[0008] Wasserstein metric is defined as: ; The support is The set of all probability distributions of ; is the joint distribution of w1 and w2 with marginal distributions P1 and P2 respectively; represents an arbitrary norm; The fuzzy set D can be defined as: ; in, For empirical distribution is the radius of the Wasserstein sphere at the center; radius The calculation formula is as follows: ; Where: is the confidence level; where C is a constant that can be obtained by solving the following optimization problem; ; represents the sample mean, N represents the number of sample groups, The minimization of can be determined by bisection; b. Rewrite the constraints: In order to solve the uncertainty of new energy output, the opportunity constraint can be expressed by the following formula: ; The chance constraint means that the power support set of photovoltaic and wind power generation companies must be less than the power generation output of renewable energy. The minimum probability under the worst-case probability distribution EP in the Wasserstein sphere is ; To constrain the risk probability of exceeding the limit, The number of samples to generate the output.

[0009] Preferably, in step S6, the double-layer objective function in step S3 is converted into a single-layer by using KKT and strong duality theorem, and the objective function is obtained by linearization; and at the same time, the distributed robustness chance constraint in step S4 is converted by using a method with support set; The problem of distributing the Robust Opportunity Constraints linearly is as follows: ; ; is the sample set belonging to the sample set at time The mth sample in (N is the number of samples of wind and solar power generation), , , , and is an auxiliary variable; is the radius of the Wasserstein sphere at time t.

[0010] The present invention proposes an optimized bidding method for cascade hydropower, wind power, solar power and energy storage based on distributed robust opportunity constraints. Compared with participating in only a single electricity market, participating in a joint market brings new room for benefit growth for cascade hydropower, wind power and energy storage enterprises. Although the overall revenue may be slightly reduced due to the uncertainty of wind and solar resources, the overall revenue is still higher than the revenue of participating in the electricity market alone, and can provide better reliability for the system. The distributed robust opportunity constraint method proposed in the present invention enables enterprises to adjust the radius and risk factor according to their own preferences to achieve a balance between maximizing revenue and minimizing risk. In addition, the method involving support sets also provides a lower limit for modeling that is more in line with actual conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 is a flow chart of the method of the present invention; Figure 2 This is the unsupported photovoltaic output diagram; Figure 3 It is a supported photovoltaic output diagram; Figure 4 This is the impact diagram of different radius and confidence on system benefits; Figure 5Produce energy distribution maps for each energy entity; Figure 6 Energy market clearing price graph; Figure 7 Market quotation chart of frequency regulation of energy storage power stations. DETAILED DESCRIPTION

[0012] like Figure 1 As shown, a cascade hydropower-wind-solar-storage optimization bidding method based on distributed robust opportunity constraints includes the following steps: S1. Collect historical data of cascade hydropower stations, wind farms, and photovoltaic power stations; and fit the joint probability distribution model representing the wind and solar power output in the region and the relationship between the water level-reservoir capacity and tailwater level-discharge of each hydropower station; S2. Based on the joint dispatching characteristics of cascade hydropower, wind power, solar power and energy storage, and the regulation capacity of cascade hydropower stations and energy storage, the bidding output strategy of cascade hydropower, wind power, solar power and energy storage systems is described using time parameters, and a short-term coordinated bidding strategy for cascade hydropower, wind power, solar power and energy storage is set; S3. Construct a double-layer bidding model for maximum revenue bidding optimization of cascaded hydro-wind-solar-storage systems in the power-frequency regulation market; S4, based on step S3, the constraint characterized by the blue-robust opportunity constraint as the uncertainty constraint of wind and solar power output is rewritten to include the equations and inequalities of wind and solar power output; S5, linearizing the constructed model to obtain a mixed integer linear programming model; S6. Use GUROBI to solve the mixed integer linear programming model and obtain the optimal bidding model and bidding strategy of the system.

[0013] Preferably, the step S1 is specifically as follows: Firstly, the parameters of water level-reservoir capacity and tailwater level-discharge of each hydropower station were fitted, and the probability density functions of wind power and photovoltaic output samples were obtained based on the non-parametric kernel density estimation method. Then, the Copula theory was used to establish a variety of common joint probability distribution models of wind and photovoltaic output. By comparing the Kendall correlation coefficient, Spearman correlation coefficient and Euclidean distance of these models, the Copula function with the best fitting degree was selected to characterize the complementary characteristics of wind power and photovoltaic output in the region.

[0014] Preferably, the step S3 constructs a double-layer model for maximizing the benefits of the upper cascade hydro-wind-solar-storage system and jointly clearing the power purchase cost of the service market of the lower electric energy-frequency regulation market, which is composed of an objective function, decision variables and constraints: a. Upper objective function The upper objective function is to maximize the benefits of the cascaded hydro-wind-solar-storage system: ; DA means the day-ahead power and frequency regulation joint market stage. is the total revenue of cascaded hydropower, wind power, solar power and storage in the day-ahead market; T is the day-ahead scheduling period, which is 15 minutes; is the revenue of the cascade hydropower plant participating in the day-ahead energy market during period t; The benefits of participating in the day-ahead frequency regulation market for cascaded hydropower companies; The benefits for wind and photovoltaic manufacturers participating in the day-ahead energy market; Profits for energy storage companies participating in the frequency regulation market; Energy storage power stations participate in the day-ahead power-frequency regulation market ; , They are the discharge and charging powers of the energy storage power station in the electricity market; They are the medium volume and winning mileage in the frequency modulation market; , , They are the day-ahead electricity energy market clearing price, the day-ahead auxiliary market frequency regulation capacity clearing price, and the frequency regulation mileage clearing price; The constraints include: (1) Energy storage charging and discharging constraints ; , are the maximum charging power and discharging power of the energy storage station, respectively. , Two are 0 / 1 variables, ensuring that the energy storage station can only be in the charging and discharging states at the same time; (2) Limitation on declared energy storage capacity ; is the frequency regulation capacity declared by the energy storage power station during period t, represents the frequency regulation mileage of the energy storage power station during period t, , They are the maximum frequency regulation capacity and maximum frequency regulation mileage of the energy storage power station; (3) Energy storage quotation constraints ; Where: , , , They are the charging and discharging price, frequency regulation capacity price and frequency regulation mileage price declared by the energy storage power station during period t; , , , They are the upper limits of the charging and discharging prices, frequency regulation capacity prices and frequency regulation mileage prices of energy storage power stations in the electric energy-frequency regulation market; (4) Energy storage state of charge constraints ; ; Where: , , They represent the minimum and maximum capacity allowed by energy storage power station k and its remaining capacity in time period t respectively; , They represent the discharging and charging efficiencies of the energy storage station k respectively; (5) Water balance constraints ; ; ; is the reservoir water storage capacity of power station i at the end of time period t; is the inflow flow of hydropower station i in the period t+1; is the outflow of hydropower station i in period t; is the power generation flow of hydropower station i in period t; is the abandoned water flow of power station i. is the flow rate of power station i-1 at time t after considering the water flow lag; is the interval flow between hydropower station i-1 and hydropower station i in time period t; (6) Reservoir capacity constraints ; , are the minimum and maximum storage capacities of the ith hydropower station respectively; (7) Water level-reservoir capacity relationship ; ; ; Where: is the reservoir water level of hydropower station i at time period t (m), and are the initial water level and the end water level of the period of hydropower station i, respectively, and their values ​​can be determined by the medium-term dispatch of cascade hydropower stations; is the water level-storage capacity relationship curve function of hydropower station i, which can be determined by polynomial fitting method; (8) Tailwater level-discharge relationship curve ; Where: is the tailwater level of hydropower station i at time t, is the relationship function between the discharge flow and tailwater level of hydropower station i, which can be determined by polynomial fitting method; (9) Constraints on downstream flow of hydropower stations ; Where: is the minimum discharge flow of the i-th hydropower station; is the maximum discharge flow of the i-th hydropower station; (10) Calculation process of unit generating head ; Where: is the generating head of the kth unit of the hydropower station i in time t, is the water head loss of the kth unit of the hydropower station i in time t; (11) Head loss function ; Where: and are the head loss coefficient and loss constant of hydropower station i, respectively, which can generally be obtained through hydraulic tests; (12) Unit dynamic characteristics relationship ; Where: is the generating head of the kth unit of the i-th hydropower station in time period t, m; () is the relationship function between output, flow and head of unit k of the i-th hydropower station; (13) Unit vibration zone constraints ; Where: and They are the upper and lower limits of the output of the zth vibration zone of the kth unit of the ith hydropower station; (13) Unit output constraints ; Where: and are the maximum and minimum outputs of the kth unit of the i-th hydropower station within a certain period of time; (14) Wind power day-ahead bidding output constraints ; The output limit of the wind power station; (15) PV day-ahead bidding output constraints ; The output limit of the photovoltaic power station; (16) Hydropower quotation constraints ; Prices declared for hydroelectric power plants; (17) Wind power quotation constraints ; Declare prices for wind power producers; (18) Photovoltaic quotation constraints ; Declare prices for photovoltaics; b. Lower layer objective function In the spot market, the power trading center collects the bidding information of each market participant, and then performs joint clearing of the electric energy and frequency regulation markets; the present invention considers that both energy storage and conventional units can participate in the bidding of the energy and frequency regulation markets. The goal of joint clearing is to minimize the sum of the power purchase cost and the frequency regulation market cost, and determine the winning bid of each power station unit; the lower-level joint clearing model of the electric energy-frequency regulation auxiliary service market is expressed as: ; , , They are the winning bids for cascaded hydro, wind and solar power in the electricity energy market; The constraints include: (1) The clearing of the electricity market needs to follow clearing rules and grid operation constraints ; ; ; ; ; Where: is the load in period t; Declare the output limit for the hydropower unit in time period t; Report the output limit of wind and photovoltaic units for time period t; , , , , , , , , is the dual variable of the corresponding constraint; (2) Frequency regulation market clearing rules and grid constraints ; ; ; ; ; ; Where: , They are frequency regulation capacity demand and frequency regulation mileage demand respectively; , are the frequency modulation capacity and frequency modulation mileage upper limit of frequency modulation machine i respectively; , , , , , , , is the dual variable of the corresponding constraint.

[0015] Preferably, in step S4, the distributed robust chance constraint model includes: a. Fuzzy set construction of wind and solar output: Although the underlying true distribution P is fuzzy, it can be constructed by constructing an empirical distribution To estimate the true distribution P, This is a limited historical sample set of wind and solar power output. When there is enough data, it can meet The present invention adopts Wasserstein distance to measure the similarity between different distributions and constructs an uncertainty set based on this.

[0016] Wasserstein metric is defined as: ; The support is The set of all probability distributions of ; is the joint distribution of w1 and w2 with marginal distributions P1 and P2 respectively; represents an arbitrary norm; The fuzzy set D can be defined as: ; in, For empirical distribution is the radius of the Wasserstein sphere at the center; radius The calculation formula is as follows: ; Where: is the confidence level; where C is a constant that can be obtained by solving the following optimization problem; ; represents the sample mean, N represents the number of sample groups, The minimization of can be determined by bisection; b. Rewrite the constraints: In order to solve the uncertainty of new energy output, the opportunity constraint can be expressed by the following formula: ; The chance constraint means that the power support set of photovoltaic and wind power generation companies must be less than the power generation output of renewable energy. The minimum probability under the worst-case probability distribution EP in the Wasserstein sphere is ; To constrain the risk probability of exceeding the limit, The number of samples to generate the output.

[0017] Preferably, in step S6, the double-layer objective function in step S3 is converted into a single-layer by using KKT and strong duality theorem, and the objective function is obtained by linearization; and at the same time, the distributed robustness chance constraint in step S4 is converted by using a method with support set; The problem of distributing the Robust Opportunity Constraints linearly is as follows: ; ; is the sample set belonging to the sample set at time The mth sample in (N is the number of samples of wind and solar power generation), , , , and is an auxiliary variable; is the radius of the Wasserstein sphere at time t.

[0018] In order to verify the superiority of the embodiment of the present invention over the prior art, a specific case is used for verification in this embodiment, which includes four cascade hydropower stations, a wind power station, a photovoltaic power station and an energy storage station. The maximum capacity of the photovoltaic power station is 500MW, and the maximum capacity of the wind power station is 1000MW. The key parameters of the cascade hydropower station and the energy storage station are shown in Table 1 and Table 2: Table 1 Operation parameters of four hydropower stations

[0019] Table 2 Energy storage operation parameters

[0020] Depend on Figure 2 and Figure 3 By contrast, it is noted from these figures that increasing α results in a higher lower limit on the PV power output because the lower limit is allowed to be violated more frequently. Figure 2 It is shown that for α = 0.2 and 0.4, unrealistic lower bounds have negative values ​​due to the absence of support in the distributed robust chance constraint problem. In contrast, Figure 3 It is shown that in the support-integrated distributed robust chance constrained problem, all lower bounds have non-negative values ​​within the support range. This demonstrates the necessity of integrating support into the distributed robust chance constrained problem to avoid unreasonable lower bounds that may lead to highly conservative solutions.

[0021] Depend on Figure 4 It can be seen that this implementation uses 15 minutes as the unit dispatching period of the cascade hydro-wind-solar-storage energy dispatching system. Since the fuzziness set decreases with the increase of historical sample size, it means that with the increase of historical sample size, the unknown distribution gradually approaches the true distribution. Two case studies show that the proposed distributed robust chance constraint model based on Wasserstein distance can provide a choice of fuzziness set size based on Wasserstein metric, so that decision makers can take a risk attitude. At the same time, with the increase of historical data, the understanding of renewable energy uncertainty in the decision-making process is also increasing, which further improves the hedging ability of the distributed robust optimization model based on Wasserstein distance against renewable energy fluctuations.

[0022] Case 1: Participating in the electricity market only Case 2: Participating in both the electricity and frequency regulation ancillary service markets Case 3: Considering the uncertainty of wind and solar power, the system participates in both the power and frequency regulation ancillary service markets Table 3 Comparison of different cases

[0023] As shown in Table 3, although the electricity market is reduced by participating in both the electricity and frequency regulation auxiliary service markets, the total revenue of the hydro-wind-solar-energy storage system can be significantly increased, providing new room for the system to grow in benefits. Although the uncertainty of wind and solar power will slightly reduce the total revenue, it is still more beneficial than participating only in the electricity market, and provides better reliability for the system.

[0024] Depend on Figure 5As can be seen, this figure clearly shows that under the joint operation mode, different types of power resources complement each other and coordinate scheduling to achieve stable operation and optimized management of the power system. The energy storage system charges during the low power load period and discharges during the peak period, which plays a role in peak shaving and valley filling, smoothing the power output curve and reducing the pressure on the power grid. As the main source of power output, hydropower stations maintain a relatively stable output power for most of the time. When the output of new energy is insufficient or the energy storage system needs to be charged, the stable output of the hydropower station ensures the basic power supply needs of the power system.

[0025] Depend on Figure 6 It can be seen that the clearing price of the electricity market fluctuates significantly within a day. During peak hours (such as noon and evening), the price rises significantly, reaching about 300 yuan / MW·h, while during low hours (such as late night and early morning), the price is lower, about 200 yuan / MW·h. Figure 7 It can be seen that the charging quotation of the energy storage system is relatively stable throughout the day, at about 14 yuan / MW·h. The discharge quotation increases significantly in some periods (such as the 12th and 18th hours), indicating that the power demand is higher during these periods. The frequency regulation capacity quotation peaks at the 11th and 18th hours, reaching about 17 yuan / MW·h, reflecting the increased demand for frequency regulation services during these periods. The frequency regulation mileage quotation remains stable for most of the time, at about 14 yuan / MW·h, but rises from the 10th to the 12th hour, and then gradually falls back.

[0026] Overall, Figure 6 and Figure 7 The figure reflects the trend of electricity market prices and energy storage system quotations over time, pointing out the increased demand for electricity and frequency regulation services during peak hours, and the important role of energy storage systems in peak load shaving and valley filling.

[0027] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limiting the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.

Claims

1. A cascade hydropower, wind power, solar power and energy storage optimization bidding method based on distributed robust opportunity constraints, characterized in that: The following steps are involved: S1. Collect historical data of cascade hydropower stations, wind farms, and photovoltaic power stations; and fit the joint probability distribution model representing the wind and solar power output in the region and the relationship between the water level-reservoir capacity and tailwater level-discharge of each hydropower station; S2. Based on the joint dispatching characteristics of cascade hydropower, wind power, solar power and energy storage, and the regulation capacity of cascade hydropower stations and energy storage, the bidding output strategy of cascade hydropower, wind power, solar power and energy storage systems is described using time parameters, and a short-term coordinated bidding strategy for cascade hydropower, wind power, solar power and energy storage is set; S3. Construct a double-layer bidding model for maximum revenue bidding optimization of cascaded hydro-wind-solar-storage systems in the power-frequency regulation market; S4, based on step S3, the constraint characterized by the blue-robust opportunity constraint as the uncertainty constraint of wind and solar power output is rewritten to include the equations and inequalities of wind and solar power output; S5, linearizing the constructed model to obtain a mixed integer linear programming model; S6. Use GUROBI to solve the mixed integer linear programming model and obtain the optimal bidding model and bidding strategy of the system.

2. According to claim 1, a cascade hydropower, wind power, solar power and energy storage optimization bidding method based on distributed robust opportunity constraints is characterized by: The step S1 is specifically as follows: Firstly, the parameters of water level-reservoir capacity and tailwater level-discharge of each hydropower station were fitted, and the probability density functions of wind power and photovoltaic output samples were obtained based on the non-parametric kernel density estimation method. Then, the Copula theory was used to establish a variety of common joint probability distribution models of wind and photovoltaic output. By comparing the Kendall correlation coefficient, Spearman correlation coefficient and Euclidean distance of these models, the Copula function with the best fitting degree was selected to characterize the complementary characteristics of wind power and photovoltaic output in the region.

3. According to claim 1, a cascade hydropower, wind power, solar power and energy storage optimization bidding method based on distributed robust opportunity constraints is characterized by: The step S3 constructs a two-layer model for maximizing the benefits of the upper cascade hydro-wind-solar-storage system and jointly clearing the purchase cost of electricity in the lower layer of the electric energy-frequency regulation market, which is composed of an objective function, decision variables and constraints: a. Upper level objective function The upper objective function is to maximize the benefits of the cascaded hydro-wind-solar-storage system: ; DA means the day-ahead power and frequency regulation joint market stage. The total revenue of cascaded water, wind, solar and storage in the day-ahead market; T is the period of day-ahead scheduling, which is set to 15 minutes; is the revenue of the cascade hydropower plant participating in the day-ahead energy market during period t; The benefits of participating in the day-ahead frequency regulation market for cascaded hydropower companies; The benefits for wind and photovoltaic manufacturers participating in the day-ahead energy market; Profits for energy storage companies participating in the frequency regulation market; Energy storage power stations participate in the day-ahead power-frequency regulation market ; , They are the discharge and charging powers of the energy storage power station in the electricity market; They are the medium volume and winning mileage in the frequency modulation market; , , They are the day-ahead electricity energy market clearing price, the day-ahead auxiliary market frequency regulation capacity clearing price, and the frequency regulation mileage clearing price; The constraints include: (1) Energy storage charging and discharging constraints ; , are the maximum charging power and discharging power of the energy storage station, respectively. , Two are 0 / 1 variables, ensuring that the energy storage station can only be in the charging and discharging states at the same time; (2) Limitation on declared energy storage capacity ; is the frequency regulation capacity declared by the energy storage power station during period t, represents the frequency regulation mileage of the energy storage power station during period t, , They are the maximum frequency regulation capacity and maximum frequency regulation mileage of the energy storage power station; (3) Energy storage quotation constraints ; Where: , , , They are the charging and discharging price, frequency regulation capacity price and frequency regulation mileage price declared by the energy storage power station during period t; , , , They are the upper limits of the charging and discharging prices, frequency regulation capacity prices and frequency regulation mileage prices of energy storage power stations in the electric energy-frequency regulation market; (4) Energy storage state of charge constraints ; ; Where: , , They represent the minimum and maximum capacity allowed by energy storage power station k and its remaining capacity in time period t respectively; , They represent the discharging and charging efficiencies of the energy storage station k respectively; (5) Water balance constraints ; ; ; is the reservoir water storage capacity of power station i at the end of time period t; is the inflow flow of hydropower station i in the period t+1; is the outflow of hydropower station i in period t; is the power generation flow of hydropower station i in period t; is the abandoned water flow of power station i. is the flow rate of power station i-1 at time t after considering the water flow lag; is the interval flow between hydropower station i-1 and hydropower station i in time period t; (6) Reservoir capacity constraints ; , are the minimum and maximum storage capacities of the ith hydropower station respectively; (7) Water level-reservoir capacity relationship ; ; ; Where: is the reservoir water level of hydropower station i at time period t (m), and are the initial water level and the end water level of the period of hydropower station i, respectively, and their values ​​can be determined by the medium-term dispatch of cascade hydropower stations; is the water level-storage capacity relationship curve function of hydropower station i, which can be determined by polynomial fitting method; (8) Tailwater level-discharge relationship curve ; Where: is the tailwater level of hydropower station i at time t, is the relationship function between the discharge flow and tailwater level of hydropower station i, which can be determined by polynomial fitting method; (9) Constraints on downstream flow of hydropower stations ; Where: is the minimum discharge flow of the i-th hydropower station; is the maximum discharge flow of the i-th hydropower station; (10) Calculation process of unit generating head ; Where: is the generating head of the kth unit of the hydropower station i in time t, is the water head loss of the kth unit of the hydropower station i in time t; (11) Head loss function ; Where: and are the head loss coefficient and loss constant of hydropower station i, respectively, which can generally be obtained through hydraulic tests; (12) Relationship between unit power characteristics ; Where: is the generating head of the kth unit of the i-th hydropower station in time period t, m; () is the relationship function between output, flow and head of unit k of the i-th hydropower station; (13) Unit vibration zone constraints ; Where: and They are the upper and lower limits of the output of the zth vibration zone of the kth unit of the ith hydropower station; (13) Unit output constraints ; Where: and are the maximum and minimum outputs of the kth unit of the i-th hydropower station within a certain period of time; (14) Wind power day-ahead bidding output constraints ; The output limit of the wind power station; (15) PV day-ahead bidding output constraints ; The output limit of the photovoltaic power station; (16) Hydropower quotation constraints ; Prices declared for hydroelectric power plants; (17) Wind power quotation constraints ; Declare prices for wind power producers; (18) Photovoltaic quotation constraints ; Declare prices for photovoltaics; b. Lower layer objective function In the spot market, the power trading center collects the bidding information of each market participant, and then performs joint clearing of the electric energy and frequency regulation markets; the goal of joint clearing is to minimize the sum of the power purchase cost and the frequency regulation market cost, and determine the winning bid of each power station unit; the joint clearing model of the lower-level electric energy-frequency regulation auxiliary service market is expressed as: ; , , They are the winning bids for cascaded hydro, wind and solar power in the electricity energy market; The constraints include: (1) The clearing of the electricity market needs to follow clearing rules and grid operation constraints ; ; ; ; ; Where: is the load in period t; Declare the output limit for the hydropower unit in time period t; Report the output limit of wind and photovoltaic units for time period t; , , , , , , , , is the dual variable of the corresponding constraint; (2) Frequency regulation market clearing rules and grid constraints ; ; ; ; ; ; Where: , They are frequency regulation capacity demand and frequency regulation mileage demand respectively; , are the frequency modulation capacity and frequency modulation mileage upper limit of frequency modulation machine i respectively; , , , , , , , is the dual variable of the corresponding constraint.

4. According to claim 1, a cascade hydropower, wind power, solar power and energy storage optimization bidding method based on distributed robust opportunity constraints is characterized by: In step S4, the distributed robust chance constraint model includes: a. Fuzzy set construction of wind and solar output: Although the underlying true distribution P is fuzzy, it can be constructed by constructing an empirical distribution To estimate the true distribution P, This is a limited historical sample set of wind and solar power output. When there is enough data, it can meet ; Wasserstein metric is defined as: ; The support is The set of all probability distributions of ; is the joint distribution of w1 and w2 with marginal distributions P1 and P2 respectively; represents an arbitrary norm; The fuzzy set D can be defined as: ; in, For empirical distribution is the radius of the Wasserstein sphere at the center; radius The calculation formula is as follows: ; Where: is the confidence level; where C is a constant that can be obtained by solving the following optimization problem; ; represents the sample mean, N represents the number of sample groups, The minimization of can be determined by bisection; b. Rewrite the constraints: In order to solve the uncertainty of new energy output, the opportunity constraint can be expressed by the following formula: ; The chance constraint means that the power support set of photovoltaic and wind power generation companies must be less than the power generation output of renewable energy. The minimum probability under the worst-case probability distribution EP in the Wasserstein sphere is ; To constrain the risk probability of exceeding the limit, The number of samples to generate the output.

5. According to claim 1, a cascade hydropower, wind power, solar power and energy storage optimization bidding method based on distributed robust opportunity constraints is characterized by: In step S6, the double-layer objective function in step S3 is converted into a single-layer by using KKT and the strong duality theorem, and the objective function is obtained by linearization; at the same time, the distributed robustness chance constraint in step S4 is converted by using a method with a support set; The problem of distributing the Robust Opportunity Constraints linearly is as follows: ; ; is the sample set belonging to the sample set at time The mth sample in , , , and is an auxiliary variable; is the radius of the Wasserstein sphere at time t.

Citation Information

Cited By

  • Distribution-microgrid collaborative interactive transaction method containing long-term and short-term hybrid energy storage

    CN120725722A

  • Coordinated interactive transaction method of microgrid with long-short period hybrid energy storage

    CN120725722B

  • Double-layer optimization method and system for participation of new storage complex in two-stage electricity market

    CN121707075A

  • Optimization method of water-wind-light combined participation multi-region medium-and-long-term market bidding strategy

    CN121766553A

  • Water, Wind and Light Joint Participation in Multi-Regional Medium- and Long-Term Market Bidding Strategy Optimization Methods

    CN121766553B