BIM-based integrated mechanical and electrical installation construction method and system

Through BIM technology, laser scanning and point cloud data are used to build building models in BIM software, solving the problems of information islands, insufficient accuracy and coordination difficulties in traditional electromechanical installation and construction, realizing intelligent construction management, and improving efficiency and accuracy , reduces costs and error risks.

CN119130388AInactive Publication Date: 2024-12-13GUANGDONG HECHENG ENVIRONMENTAL ENG CO LTD

Patent Information

Application Number
CN202411612439.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-13
Publication Date
2024-12-13
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional electromechanical installation construction methods have information islands, insufficient construction accuracy, conflicts and coordination difficulties, lagging construction drawing updates, and lack of scientific construction planning and collaborative management, resulting in low construction efficiency, high cost and waste of resources.

Method used

Using an integrated electromechanical installation and construction method based on BIM, point cloud data is generated through laser scanning, BIM software is imported to build a building structure model, new electromechanical pipeline layout scheme is determined, conflict detection and optimization are carried out, optimal construction layout scheme is generated, and the model is obtained. Detailed construction drawings are extracted for on-site construction management.

Benefits of technology

It improves the efficiency and accuracy of mechanical and electrical installation construction, optimizes resource allocation, realizes intelligent and refined management of the construction process, reduces error risks and costs, ensures that the construction is consistent with the drawings, and reduces rework and resource waste.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention relates to a BIM (Building Information Modeling)-based integrated mechanical and electrical installation construction method. The method comprises the following steps: performing field scanning by using a laser scanner; importing point cloud data automatically generated by field data acquisition into BIM software; building a building structure model of the construction site in the BIM software; generating a new construction interval of the new electromechanical pipeline and an existing construction interval of the existing electromechanical pipeline in the building structure model; generating a new electromechanical pipeline arrangement scheme based on the new construction interval and the existing construction interval; conflict detection in the BIM software is used, and the compatibility score of the arrangement scheme of the new electromechanical pipeline is evaluated based on a conflict detection result; generating and recording an optimal construction arrangement scheme in the building structure model based on the compatibility score; extracting a detailed construction drawing from the building structure model; carrying out site construction; the system can improve the efficiency and precision of mechanical and electrical installation construction, optimizes resource allocation, and finally realizes intelligent and refined management of the construction process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of BIM construction, and in particular relates to an integrated electromechanical installation construction method and system based on BIM. Background Art

[0002] In modern building construction, electromechanical installation is a key component, and its quality directly affects the overall performance and safety of the building. However, traditional electromechanical installation construction methods have many technical defects and are in urgent need of improvement.

[0003] First, the problem of information silos is widespread. Information in the design, construction, and management stages is often scattered across different teams and systems, resulting in poor data communication. This not only increases the complexity of information transmission, but also increases the probability of errors, ultimately leading to reduced construction efficiency and increased costs.

[0004] Secondly, insufficient construction accuracy is a significant problem. Traditional measurement and modeling methods may cause certain errors due to human factors or technical limitations, affecting the installation accuracy of mechanical and electrical pipelines. This inaccuracy will lead to many problems in the subsequent construction process, increasing the need for modification and adjustment.

[0005] Third, conflicts and coordination difficulties are common problems in mechanical and electrical installation construction. In complex building environments, conflicts between mechanical and electrical pipelines and building structures often occur. Traditional methods usually require multiple modifications on site, which not only wastes time but also increases resource consumption.

[0006] In addition, the delay in updating construction drawings is also a technical defect. Design changes frequently occur during the construction process, but traditional construction drawings often fail to reflect these changes in a timely manner, resulting in the actual situation on the construction site not being consistent with the drawings, increasing the risk of misunderstanding and errors.

[0007] Finally, the lack of scientific construction planning and collaborative management also restricted construction efficiency. The coordination between construction teams was often not close enough, resulting in a waste of resources and time. Traditional management methods made it difficult to achieve real-time progress tracking and dynamic adjustments, which affected the smooth progress of the entire project. Summary of the invention

[0008] In order to overcome the deficiencies and shortcomings of the prior art, the primary purpose of the present invention is to provide an integrated electromechanical installation construction method and system based on BIM. The integrated electromechanical installation construction method and system based on BIM can improve the efficiency and accuracy of electromechanical installation construction, optimize resource allocation, and ultimately realize intelligent and refined management of the construction process.

[0009] The primary purpose of the present invention is achieved through the following technical solutions: An integrated electromechanical installation construction method based on BIM, comprising: Use a laser scanner to scan the site and generate point cloud data; Import the point cloud data automatically generated by field data collection into BIM software; Construct a building structure model of the construction site in BIM software, including models of walls, floors, ceilings, and existing mechanical and electrical pipelines; Determine the quantity, model and connection points of new electromechanical pipelines; Generate new construction intervals for new mechanical and electrical pipelines and existing construction intervals for existing mechanical and electrical pipelines in the building structure model; Generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; Use the conflict detection in the BIM software and evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines based on the conflict detection results; Generate and record the optimal construction layout in the building structure model based on the compatibility score; Extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation details; Carry out on-site construction according to the building structure model and construction drawings.

[0010] As a preferred method, the point cloud data automatically generated by field data collection is imported into the BIM software as follows: Use point cloud processing software to clean and filter the collected data to remove noise; Export the processed point cloud data to a format supported by BIM software; Start the BIM software and import the point cloud file into the software; After setting the imported coordinate system and scale, confirm the import and display the point cloud data in the building structure model.

[0011] As a preferred method, the method of constructing the building structure model of the construction site in the BIM software is: Set the thickness, height and material properties of the wall, and select the wall tool to automatically draw the wall based on the point cloud data; Set the actual height and level of the ground, and select the ground tool to automatically draw the ground at the bottom of the wall based on the point cloud data; Set the height and material of the ceiling and select the ceiling tool to automatically draw the ceiling on top of the wall based on the point cloud data; Set the type, size, and connection points of the pipeline, import existing electromechanical pipeline models, and automatically place electromechanical pipelines based on point cloud data.

[0012] As a preferred method, a new construction section for a new electromechanical pipeline and an existing construction section for an existing electromechanical pipeline are generated in the building structure model as follows: According to the number, model and connection points of the new electromechanical pipelines, select the area tool to generate a new construction section, which includes the connection points of all new electromechanical pipelines; According to the types, sizes and connection points of the existing mechanical and electrical pipelines in the building structure model of the construction site, the area selection tool generates an existing construction section, which includes the connection points of all existing mechanical and electrical pipelines.

[0013] As a preferred method, based on the new construction section and the existing construction section, a method for generating a layout plan for new electromechanical pipelines is: Confirm the scope of the new construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the new construction area, and generate layout plan 1; Confirm the scope of the existing construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the existing construction area, and generate layout plan 2; Confirm the scope of the new construction area in the building structure model and mark the overlap with the existing construction area; Delete the overlapping parts in the new construction section, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the remaining section, and generate layout plan three.

[0014] Preferably, the method of using the conflict detection in the BIM software and evaluating the compatibility score of the layout scheme of the new electromechanical pipelines based on the conflict detection results is as follows: In the BIM software, select the conflict detection tool and set the detection range and type; Enable conflict detection to automatically scan for potential conflicts between new mechanical and electrical pipelines and existing pipelines and building structures; Generate a conflict detection report listing all conflicts found and their location, type and severity; Each conflict is assessed and weighted based on its number, type and impact, including: Minor conflict - low priority, moderate conflict - medium priority, severe conflict - high priority; Based on the evaluation results, the compatibility score is calculated using the following formula; Compatibility score = 100 - \left( \sum \text{(conflict weight)} \right) Compatibility score = 100 − (∑(conflict weight)) Calculate the compatibility scores of layout plan 1, layout plan 2, and layout plan 3.

[0015] Preferably, the method for generating and recording the optimal construction layout scheme in the building structure model based on the compatibility score is: Check the compatibility scores of all layout options and identify the highest scoring option as a preliminary candidate; For candidate solutions, further optimize design parameters, including pipeline directions, connection points and support methods, to improve compatibility; Compare various plans in BIM software and obtain the optimal layout plan based on the compatibility score.

[0016] Another technical problem to be solved by the present invention is to provide an integrated electromechanical installation construction system based on BIM, comprising: A data acquisition module is used to scan the construction site using a laser scanner to generate point cloud data; A data import module, used for importing the point cloud data into BIM software; A modeling module, used to construct a building structure model of the construction site in the BIM software, including models of walls, floors, ceilings and existing electromechanical pipelines; Pipeline planning module, used to determine the number, model and connection points of new electromechanical pipelines; A construction interval management module, used to generate new construction intervals for new electromechanical pipelines and existing construction intervals for existing electromechanical pipelines; A layout plan generation module is used to generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; The conflict detection module is used to evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines using the conflict detection in the BIM software; A scheme optimization module, which is used to generate and record the optimal construction layout scheme based on the compatibility score; A drawing extraction module, used to extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation detail drawings; The construction management module is used to perform on-site construction management according to the building structure model and construction drawings.

[0017] Another technical problem to be solved by the present invention is to provide an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, an integrated electromechanical installation construction method based on BIM as described above is implemented.

[0018] Another technical problem to be solved by the present invention is to provide a computer-readable storage medium on which a computer program is stored, and when the program is executed by a processor, it implements any of the BIM-based integrated electromechanical installation construction methods described above.

[0019] Compared with the prior art, the present invention has the following advantages: Laser scanning and point cloud data are used to ensure high accuracy of on-site models and reduce construction errors. BIM integrates information from all parties, promotes real-time collaboration between design, construction and management teams, and reduces information islands. Automatic conflict detection is performed using BIM software to identify and resolve potential problems in advance, avoiding modifications and delays during the construction phase. The optimal construction layout is generated based on compatibility scores to improve construction efficiency and resource utilization. Construction drawings reflect the latest design in real time to ensure that on-site construction is consistent with the drawings and reduce the risk of errors. Overall project costs and construction periods are reduced by reducing rework and improving efficiency. The building structure model provides a clear visual display to help the construction team better understand the project and improve construction quality. DETAILED DESCRIPTION

[0020] The specific implementation modes of the present invention are further described in detail to make the technical solutions of the present invention easier to understand and grasp. Example

[0021] The integrated mechanical and electrical installation construction method based on BIM includes: Use a laser scanner to scan the site and generate point cloud data; Import the point cloud data automatically generated by field data collection into BIM software; Construct a building structure model of the construction site in BIM software, including models of walls, floors, ceilings, and existing mechanical and electrical pipelines; Determine the quantity, model and connection points of new electromechanical pipelines; Generate new construction intervals for new mechanical and electrical pipelines and existing construction intervals for existing mechanical and electrical pipelines in the building structure model; Generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; Use the conflict detection in the BIM software and evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines based on the conflict detection results; Generate and record the optimal construction layout in the building structure model based on the compatibility score; Extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation details; Carry out on-site construction according to the building structure model and construction drawings.

[0022] On-site scanning phase: Tool application: Use laser scanner to conduct all-round scanning of the construction site.

[0023] Data output: Generate high-precision point cloud data to record in detail the current status of the building and the layout of existing mechanical and electrical pipelines.

[0024] Data Integration: Software selection: Choose appropriate BIM software (such as Revit, Navisworks, etc.).

[0025] Integration process: Import point cloud data into BIM software to build a preliminary 3D model.

[0026] Model building phase: Architectural structure model production: Construct architectural structure models such as walls, floors, ceilings, etc. in BIM software.

[0027] Modeling of existing pipelines: Simultaneously create detailed models of existing mechanical and electrical pipelines, including cables, pipes and ventilation systems.

[0028] Pipeline planning stage: Data analysis: Analyze the demand for new electromechanical pipelines and clarify the quantity, model and connection points.

[0029] Layout Design: Plan the layout of new mechanical and electrical pipelines in the building structure model, taking into account construction space and existing facilities.

[0030] Layout plan output: Division of construction areas: clearly define the construction areas for new and old mechanical and electrical pipelines.

[0031] Solution visualization: Visualize the layout of new and old pipelines in the building structure model to facilitate understanding and adjustment.

[0032] Conflict detection phase: Software application: Use the conflict detection function in BIM software to identify potential conflicts between new and old pipelines.

[0033] Compatibility assessment: Based on the test results, the compatibility of the new electromechanical pipeline layout plan is evaluated to ensure the feasibility of the design.

[0034] Best solution record: Solution Recording: Generate and record the optimal construction layout solution in the building structure model based on the compatibility score.

[0035] Solution optimization: If necessary, make adjustments to ensure maximum construction efficiency and effectiveness.

[0036] Extraction of construction drawings: Drawing generation: Extract detailed construction drawings from the building structure model, including pipeline layout drawings, installation details and material lists.

[0037] Document preparation: Ensure all drawings and documents are clear and complete for the construction team to use.

[0038] On-site construction phase: Construction preparation: Carry out on-site construction preparation according to the building structure model and construction drawings, and coordinate relevant resources and personnel.

[0039] Execute construction: Perform actual installation according to the drawings and monitor construction progress in real time to ensure consistency with the building structure model.

[0040] Use high-precision laser scanning and BIM modeling to reduce errors caused by inconsistent information; use detailed models and plans to rationally allocate materials and human resources to reduce waste; use conflict detection to identify problems in advance to avoid on-site construction conflicts and later rework; share building structure models between different disciplines to strengthen communication and collaboration to ensure the smooth progress of the project; reduce construction uncertainty and reduce the risk of project delays and cost overruns through early planning and simulation.

[0041] The method of importing point cloud data automatically generated by field data collection into BIM software is as follows: Use point cloud processing software to clean and filter the collected data to remove noise; Export the processed point cloud data to a format supported by BIM software; Start the BIM software and import the point cloud file into the software; After setting the imported coordinate system and scale, confirm the import and display the point cloud data in the building structure model.

[0042] Data cleaning and screening: Select appropriate point cloud processing software, such as Cyclone or CloudCompare, to process the data.

[0043] Cleaning operations are performed on the collected data, and filtering technology is used to remove unnecessary noise and redundant points to ensure the accuracy of the data.

[0044] Data output: Select the appropriate output format to export the processed point cloud data into a format compatible with BIM software, such as LAS, E57, PTS, etc.

[0045] Review export parameters and settings to ensure data integrity.

[0046] Start BIM software: Choose appropriate BIM software, such as Revit, Navisworks, etc.

[0047] Execute the "Import" operation in the software to load the previously processed point cloud file.

[0048] Set the coordinate system and scale: Configure the coordinate system according to the actual situation on site to ensure the accuracy of the model.

[0049] Adjust the scale of the point cloud data to ensure that it is consistent with the proportions of existing buildings and other model elements.

[0050] Data presentation: After completing the settings, confirm the import process of the point cloud data and the data will be presented in the building structure model.

[0051] Use the software’s viewing function to check the presentation of the point cloud data to ensure it matches the building structure.

[0052] Point cloud data provides high-precision on-site information, which can accurately reflect the actual situation of the building and help subsequent design and construction work; automatically generated point cloud data can significantly reduce the workload of manual measurement and reduce the risk of human error; through point cloud data, the building structure model can contain more details and information on existing facilities, enhancing the practicality and accuracy of the model; by directly processing point cloud data in the BIM environment, different teams can collaborate on the same platform, improve communication efficiency and reduce design conflicts; through visualized point cloud data, the construction team can have a deeper understanding of site conditions, formulate more reasonable construction plans and reduce risks.

[0053] The method of constructing the building structure model of the construction site in BIM software is: Set the thickness, height and material properties of the wall, and select the wall tool to automatically draw the wall based on the point cloud data; Set the actual height and level of the ground, and select the ground tool to automatically draw the ground at the bottom of the wall based on the point cloud data; Set the height and material of the ceiling and select the ceiling tool to automatically draw the ceiling on top of the wall based on the point cloud data; Set the type, size, and connection points of the pipeline, import existing electromechanical pipeline models, and automatically place electromechanical pipelines based on point cloud data.

[0054] The wall construction process involves setting the thickness, height and material properties of the wall, and using the corresponding wall tools to automatically draw the wall based on the point cloud data. For ground drawing, it is necessary to determine the actual height and flatness of the ground, and use the ground tools to automatically draw the ground at the bottom of the wall based on the point cloud data. As for the setting of the ceiling, it includes setting the height and material properties of the ceiling, selecting the ceiling tool, and automatically drawing the ceiling at the top of the wall based on the point cloud data. In terms of the placement of electromechanical pipelines, it is necessary to clarify the type, size and connection points of the pipelines, import the existing electromechanical pipeline model, and automatically layout the electromechanical pipelines based on the point cloud data.

[0055] The advantage of adopting this solution is its efficient modeling. Automated drawing greatly shortens the time required for manual modeling and quickly generates accurate models. Accurately match the on-site data and build the model directly based on the point cloud data to ensure a high degree of consistency between the model and the actual construction site. In terms of material and performance optimization, by setting material properties, suitable materials can be selected to improve building performance. Enhanced coordination is reflected in the integration of electromechanical pipeline models, which can better coordinate the building and electromechanical design and reduce potential conflicts. Improve construction efficiency. Through visual models, the construction team can understand the design intent more clearly, thereby improving construction efficiency and accuracy.

[0056] The method for generating new construction intervals for new mechanical and electrical pipelines and existing construction intervals for existing mechanical and electrical pipelines in the building structure model is as follows: According to the number, model and connection points of the new electromechanical pipelines, select the area tool to generate a new construction section, which includes the connection points of all new electromechanical pipelines; According to the types, sizes and connection points of the existing mechanical and electrical pipelines in the building structure model of the construction site, the area selection tool generates an existing construction section, which includes the connection points of all existing mechanical and electrical pipelines.

[0057] To create a new construction area: Based on the number, specifications and connection points of the newly added mechanical and electrical pipelines, use the regional tool to delineate a new construction area to ensure that the area fully covers the connection points of all new pipelines.

[0058] Build the existing construction area: According to the types, sizes and connection points of existing mechanical and electrical pipelines, use the area tool to construct the existing construction area to ensure that the area fully includes the connection points of all existing pipelines.

[0059] Clearly mark the construction areas of new and old pipelines to facilitate intuitive understanding and management by the project team; accurately delineate the construction areas to reduce conflicts between new and old pipelines and improve design coordination; through clear area divisions, the construction team can allocate resources and time more efficiently; integrate the information of new and old pipelines to facilitate subsequent maintenance and management; any design changes can be reflected in the model immediately to ensure the consistency and accuracy of information.

[0060] The method for generating the layout plan of new electromechanical pipelines based on the new construction section and the existing construction section is as follows: Confirm the scope of the new construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the new construction area, and generate layout plan 1; Confirm the scope of the existing construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the existing construction area, and generate layout plan 2; Confirm the scope of the new construction area in the building structure model and mark the overlap with the existing construction area; Delete the overlapping parts in the new construction section, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the remaining section, and generate layout plan three.

[0061] Data collection phase: First, collect relevant data on new electromechanical pipelines, including their quantity, model, connection point location and other information.

[0062] Scoping phase: Define the boundaries of the new construction area in the building structural model to ensure that it can contain all new mechanical and electrical pipelines.

[0063] Algorithm application stage: Automatic layout algorithms (such as genetic algorithms, simulated annealing, etc.) are used to automatically layout new electromechanical pipelines within the designated interval to form layout plan 1. The algorithm will optimize the layout based on factors such as the pipeline's spatial requirements, direction, and connection requirements.

[0064] Existing construction section confirmation stage: Existing data assessment phase: Analyze the layout of existing mechanical and electrical pipelines, including their types, sizes and connection points.

[0065] Scope confirmation phase: Confirm the boundaries of the existing construction area in the building structure model to ensure that all existing pipelines are covered.

[0066] Layout plan generation stage: The automatic layout algorithm is also used to layout the new electromechanical pipelines within the existing construction area to form layout plan 2. This plan will take into account the existence of existing pipelines to avoid conflicts.

[0067] Overlapping area marking phase: Conflict detection phase: Use the conflict detection function of the BIM software to identify the overlapping areas between the new construction section and the existing construction section.

[0068] Overlapping area marking stage: Mark these overlapping parts in the model to facilitate subsequent processing and visualization.

[0069] Overlap removal phase: Construction section adjustment phase: Remove the overlapping parts of the marks in the new construction section to avoid laying out new and old pipelines in the same space.

[0070] Area redivision phase: ensure the validity and applicability of the remaining intervals and prepare for subsequent arrangements.

[0071] Arrangement plan three generation stage: Re-arrangement stage: In the remaining available space, the automatic layout algorithm is used again to arrange the new electromechanical pipelines to form layout plan 3. At this time, the algorithm will give priority to the available space and the rationality of the layout to ensure the optimal layout of the new pipelines.

[0072] The automatic layout algorithm can quickly calculate multiple layout plans, significantly improving efficiency and reducing the possibility of human error compared to manual design. By clearly dividing the construction intervals of new and old pipelines, it ensures that the new pipeline does not conflict with the existing pipeline during design, reducing the complexity of subsequent construction and maintenance. During the construction process, if the pipeline layout needs to be adjusted, it only needs to update the data and re-run the layout algorithm to quickly generate a new plan, demonstrating strong adaptability.

[0073] Through the visualization function of the building structure model, the team can intuitively view the relationship between new and old pipelines, ensuring information transparency during the design and construction stages; the precise interval division and the use of automatic layout algorithms can maximize the use of space resources, reduce material waste, and improve construction efficiency; through the building structure model, various professional teams (such as structure, mechanical and electrical, and architecture) can work together on the same platform, facilitating information sharing and communication, and improving the overall project management level.

[0074] The method of using the conflict detection in the BIM software and evaluating the compatibility score of the layout plan of the new mechanical and electrical pipelines based on the conflict detection results is as follows: In the BIM software, select the conflict detection tool and set the detection range and type; Enable conflict detection to automatically scan for potential conflicts between new mechanical and electrical pipelines and existing pipelines and building structures; Generate a conflict detection report listing all conflicts found and their location, type and severity; Each conflict is assessed and weighted based on its number, type and impact, including: Minor conflict - low priority, moderate conflict - medium priority, severe conflict - high priority; Based on the evaluation results, the compatibility score is calculated using the following formula; Compatibility score = 100 - \left( \sum \text{(conflict weight)} \right) Compatibility score = 100 − (∑(conflict weight)) Calculate the compatibility scores of layout plan 1, layout plan 2, and layout plan 3.

[0075] The method for generating and recording the optimal construction layout plan in the building structure model based on the compatibility score is as follows: Check the compatibility scores of all layout options and identify the highest scoring option as a preliminary candidate; For candidate solutions, further optimize design parameters, including pipeline directions, connection points and support methods, to improve compatibility; Compare various plans in BIM software and obtain the optimal layout plan based on the compatibility score.

[0076] Ensure that the compatibility scores of all layout options have been calculated and recorded in the BIM software. Each option should list the conflict type, location and its corresponding score in detail.

[0077] Sort all the proposals according to their scores and select the one with the highest score as the preliminary candidate. Record the detailed information of the proposal, including its design drawings and relevant parameters.

[0078] Conduct in-depth discussions on the design details of the candidate solutions to identify specific parameters that need to be improved, such as: Pipeline layout: Consider adjusting pipeline routes to reduce crossing or overlapping areas.

[0079] Connect nodes: Evaluate connection methods and prioritize simplified designs to reduce potential conflict risks.

[0080] Support structure: Choose a more appropriate support scheme to avoid interference with other structures.

[0081] In the BIM software, the design parameters of the candidate solutions are gradually adjusted. After each adjustment, the conflict detection is re-executed and the changes in the compatibility score are recorded.

[0082] Evaluate the impact of each adjustment to ensure that the optimization direction will help improve the compatibility score.

[0083] Compare all optimized solutions, including preliminary candidate solutions and other solutions. Use the comparison function of BIM software to visualize the compatibility scores of each solution.

[0084] On the basis of the compatibility score, it is also necessary to consider factors such as construction difficulty, cost budget, construction period, etc. to conduct a comprehensive evaluation of the scheme. The weighted average method can be used to comprehensively consider multiple factors to ensure that the final selected scheme performs well in all aspects.

[0085] Based on the comprehensive evaluation results, select the optimal layout solution with the highest compatibility score and meeting other requirements; record all design parameters of the optimal solution in detail in the building structure model, including modification records, optimization process and final compatibility score. Ensure that the solution is archived for future reference; the systematic approach can quickly identify the optimal solution and shorten the time required for the design phase.

[0086] By optimizing the design in advance, possible conflicts and rework rates during the construction process can be reduced; selecting the best solution can effectively reduce material waste and construction workers' time investment, thereby saving project costs; scientifically evaluated and optimized solutions can ensure the feasibility and overall quality of construction; the sharing characteristics of the building structure model enable different professional teams to view the best solution in real time, promoting cross-departmental collaboration and communication.

[0087] An integrated electromechanical installation construction system based on BIM, including: A data acquisition module is used to scan the construction site using a laser scanner to generate point cloud data; A data import module, used for importing the point cloud data into BIM software; A modeling module, used to construct a building structure model of the construction site in the BIM software, including models of walls, floors, ceilings and existing electromechanical pipelines; Pipeline planning module, used to determine the number, model and connection points of new electromechanical pipelines; A construction interval management module, used to generate new construction intervals for new electromechanical pipelines and existing construction intervals for existing electromechanical pipelines; A layout plan generation module is used to generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; The conflict detection module is used to evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines using the conflict detection in the BIM software; A scheme optimization module, which is used to generate and record the optimal construction layout scheme based on the compatibility score; A drawing extraction module, used to extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation detail drawings; The construction management module is used to perform on-site construction management according to the building structure model and construction drawings.

[0088] Laser scanning technology is used to comprehensively scan the construction site and generate high-precision point cloud data to accurately capture the actual size of the site and the location of existing components; the point cloud data is imported into the BIM software to ensure the integrity and accuracy of the data, laying the foundation for subsequent modeling work; the building structure model of the construction site is constructed in the BIM software, covering basic structural elements such as walls, floors, and ceilings. At the same time, a detailed model of the existing electromechanical pipelines is created to ensure coordination with the newly designed pipelines; the number, model, and connection points of the new electromechanical pipelines are automatically analyzed and determined, and the pipeline layout is optimized to reduce intersections and conflicts.

[0089] Based on the layout of new and old pipelines, plan the construction interval of new mechanical and electrical pipelines and the management area of ​​existing pipelines to facilitate segmented construction and rational allocation of resources; based on the new and old construction intervals, automatically generate the layout plan of new mechanical and electrical pipelines to ensure the rationality of the design; use the conflict detection function in the BIM software to evaluate the compatibility score of the new mechanical and electrical pipeline layout plan in real time and identify potential problems; adjust and optimize the layout plan based on the conflict detection results, generate and record the optimal construction layout plan for subsequent use; extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation details drawings, to provide accurate reference materials for the construction team; conduct on-site construction management based on the building structure model and construction drawings, and monitor the construction progress, quality and resource usage in real time.

[0090] Laser scanning provides real data, reduces design errors and improves construction accuracy; automated pipeline planning reduces manual intervention, improves planning efficiency and saves valuable time; real-time conflict detection promptly identifies and solves problems, reduces rework rate and construction costs; the construction management module provides real-time data, helps to dynamically adjust the construction plan and ensure the optimal allocation of resources; the extracted construction drawings are clear and detailed, ensuring that construction personnel accurately understand the design requirements and reduce on-site communication errors.

[0091] This embodiment also provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the integrated electromechanical installation construction method based on BIM as described above is implemented.

[0092] This embodiment also provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the integrated electromechanical installation construction method based on BIM as described above is implemented.

[0093] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).

[0094] Those skilled in the art will clearly understand that for the sake of convenience and brevity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the system can be divided into different functional units or modules to complete all or part of the functions described above.

[0095] Of course, the above are only typical examples of the present invention. In addition to these, the present invention may also have many other specific implementations. Any technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention. Of course, the above are only typical examples of the present invention. In addition to these, the present invention may also have many other specific implementations. Any technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention.

Claims

1. A BIM-based integrated electromechanical installation construction method, characterized in that , including: Use a laser scanner to scan the site and generate point cloud data; Import the point cloud data automatically generated by field data collection into BIM software; Construct a building structure model of the construction site in BIM software, including models of walls, floors, ceilings, and existing mechanical and electrical pipelines; Determine the quantity, model and connection points of new electromechanical pipelines; Generate new construction intervals for new mechanical and electrical pipelines and existing construction intervals for existing mechanical and electrical pipelines in the building structure model; Generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; Use the conflict detection in the BIM software and evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines based on the conflict detection results; Generate and record the optimal construction layout in the building structure model based on the compatibility score; Extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation details; Carry out on-site construction according to the building structure model and construction drawings.

2. The BIM-based integrated electromechanical installation construction method according to claim 1, characterized in that: The method of importing point cloud data automatically generated by field data collection into BIM software is as follows: Use point cloud processing software to clean and filter the collected data to remove noise; Export the processed point cloud data to a format supported by BIM software; Start the BIM software and import the point cloud file into the software; After setting the imported coordinate system and scale, confirm the import and display the point cloud data in the building structure model.

3. The BIM-based integrated electromechanical installation construction method according to claim 2 is characterized in that: The method of constructing the building structure model of the construction site in BIM software is: Determine the building's base surface; Set the thickness, height and material properties of the wall, and select the wall tool to automatically draw the wall based on the point cloud data; Set the actual height and level of the ground, and select the ground tool to automatically draw the ground at the bottom of the wall based on the point cloud data; Set the height and material of the ceiling and select the ceiling tool to automatically draw the ceiling on top of the wall based on the point cloud data; Set the type, size, and connection points of the pipeline, import existing electromechanical pipeline models, and automatically place electromechanical pipelines based on point cloud data.

4. The BIM-based integrated electromechanical installation construction method according to claim 3 is characterized in that: The method for generating new construction intervals for new mechanical and electrical pipelines and existing construction intervals for existing mechanical and electrical pipelines in the building structure model is as follows: According to the number, model and connection points of the new electromechanical pipelines, select the area tool to generate a new construction section, which includes the connection points of all new electromechanical pipelines; According to the types, sizes and connection points of the existing mechanical and electrical pipelines in the building structure model of the construction site, the area selection tool generates an existing construction section, which includes the connection points of all existing mechanical and electrical pipelines.

5. The BIM-based integrated electromechanical installation construction method according to claim 1, characterized in that: The method for generating the layout plan of new electromechanical pipelines based on the new construction section and the existing construction section is as follows: Confirm the scope of the new construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the new construction area, and generate layout plan 1; Confirm the scope of the existing construction area in the building structure model, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the existing construction area, and generate layout plan 2; Confirm the scope of the new construction area in the building structure model and mark the overlap with the existing construction area; Delete the overlapping parts in the new construction section, use the automatic layout algorithm to automatically layout the new mechanical and electrical pipelines in the remaining section, and generate layout plan three.

6. The BIM-based integrated electromechanical installation construction method according to claim 5, characterized in that: The method of using the conflict detection in the BIM software and evaluating the compatibility score of the layout plan of the new mechanical and electrical pipelines based on the conflict detection results is as follows: In the BIM software, select the conflict detection tool and set the detection range and type; Enable conflict detection to automatically scan for potential conflicts between new mechanical and electrical pipelines and existing pipelines and building structures; Generate a conflict detection report listing all conflicts found and their location, type and severity; Each conflict is assessed and weighted based on its number, type and impact, including: Minor conflict - low priority, moderate conflict - medium priority, severe conflict - high priority; Based on the evaluation results, the compatibility score is calculated using the following formula; Compatibility score = 100 − (∑(conflict weight)) Calculate the compatibility scores of layout plan 1, layout plan 2, and layout plan 3.

7. The BIM-based integrated electromechanical installation construction method according to claim 1, characterized in that: The method for generating and recording the optimal construction layout plan in the building structure model based on the compatibility score is as follows: Check the compatibility scores of all layout options and identify the highest scoring option as a preliminary candidate; For candidate solutions, further optimize design parameters, including pipeline directions, connection points and support methods, to improve compatibility; Compare various plans in BIM software and obtain the optimal layout plan based on the compatibility score.

8. The integrated mechanical and electrical installation construction system based on BIM is characterized by: Included are: A data acquisition module is used to scan the construction site using a laser scanner to generate point cloud data; A data import module, used for importing the point cloud data into BIM software; A modeling module, used to construct a building structure model of the construction site in the BIM software, including models of walls, floors, ceilings and existing electromechanical pipelines; Pipeline planning module, used to determine the number, model and connection points of new electromechanical pipelines; A construction interval management module, used to generate new construction intervals for new electromechanical pipelines and existing construction intervals for existing electromechanical pipelines; A layout plan generation module is used to generate a layout plan for new electromechanical pipelines based on the new construction section and the existing construction section; The conflict detection module is used to evaluate the compatibility score of the layout plan of the new mechanical and electrical pipelines using the conflict detection in the BIM software; A scheme optimization module, which is used to generate and record the optimal construction layout scheme based on the compatibility score; A drawing extraction module, used to extract detailed construction drawings from the building structure model, including pipeline layout drawings and installation detail drawings; The construction management module is used to perform on-site construction management according to the building structure model and construction drawings.

9. An electronic device, characterized in that: It includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the integrated electromechanical installation construction method based on BIM as described in any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, an integrated electromechanical installation construction method based on BIM is implemented as described in any one of claims 1 to 7.

Citation Information

Patent Citations

  • Construction method for anti-seismic support post on the basis of BIM (Building Information Modeling)+3D (Three-Dimensional) scanning technology

    CN107633133A

  • Method for surveying and positioning during electromechanical pipeline and equipment mounting

    CN108647384A

  • Electromechanical construction method and system based on BIM technology

    CN114444163A

  • BIM-based building indoor structure rapid detection method

    CN115100348A

  • Electromechanical construction method based on BIM technology

    CN116226988A

Cited By

  • Fabricated building BIM module management device and management method thereof

    CN120410461A

  • A BIM module management device and management method for assembled buildings

    CN120410461B

  • Plant electromechanical pipeline three-dimensional positioning installation system based on BIM (Building Information Modeling) and construction method

    CN121502884A