Mounting structure of super high-rise high-pressure pipeline

By adopting a multi-stage sealing system and a triangular reinforced locking design in ultra-high-rise high-pressure pipelines, the problems of lax sealing and loose connections during pipeline installation and operation are solved, efficient sealing and stable connections are achieved, and the safety and reliability of the pipeline system are improved.

CN120175925AInactive Publication Date: 2025-06-20SHANXI CONSTR ENG CO LTD

Patent Information

Application Number
CN202510661308.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-05-22
Publication Date
2025-06-20
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the installation and operation of ultra-high-rise high-pressure pipelines, there are problems such as lax sealing, loose connections, and complex installation, resulting in leakage, safety hazards and high maintenance costs.

Method used

A multi-stage sealing system and a triangle reinforced locking design are adopted to build a tight sealing structure through sealing cover, sealing ring and fixing components, and a stable triangle reinforced locking fixing is formed through clamps, reinforcement bolts and locking bolts.

Benefits of technology

It significantly improves sealing performance and connection strength, ensures long-term stable and safe operation of pipelines, reduces leakage risks and maintenance costs, and extends the service life of pipeline systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120175925A_ABST
    Figure CN120175925A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of pipeline installation, and particularly discloses a super high-rise high-pressure pipeline installation structure which comprises a high-pressure pipe set, the high-pressure pipe set is composed of a right-angle bent pipe and two straight pipes connected with the two ends of the right-angle bent pipe respectively, and annular flanges are arranged on the outer sides of the joints of the right-angle bent pipe and the straight pipes. Sealing connecting parts used for connecting the connecting position of the right-angle bent pipe and the straight pipe and conducting multi-stage sealing on the connecting position are arranged at the connecting position of the right-angle bent pipe and the straight pipe, and a triangular reinforcing part used for conducting triangular reinforcing, locking and fixing on the two sealing connecting parts is arranged between the two sealing connecting parts. Different from a traditional mode that only a single sealing ring is arranged in a sleeved mode, a tight multi-stage sealing system is constructed by arranging the sealing connecting part and the triangular reinforcing part in a matched mode, when a high-pressure pipe set is connected, the first sealing ring fills a gap in the connecting position of the straight pipe and the right-angle bent pipe, primary sealing is achieved, and leakage of a high-pressure medium is effectively blocked.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pipeline installation, and more specifically, it relates to an installation structure for ultra-high-rise high-pressure pipelines. Background Art

[0002] Ultra-high-rise high-pressure pipelines refer to special pipeline systems applied in ultra-high-rise buildings (usually with a height exceeding 150 meters) for transporting high-pressure media (such as concrete, gas, water, etc.). Such pipelines need to withstand extremely high pressures, temperature changes, and the impacts brought by building structure deformations. Therefore, there are strict requirements for material selection, structural design, and installation technology.

[0003] Currently, when installing ultra-high-rise high-pressure pipelines, first, a sealing ring with relatively large elasticity needs to be reversely sleeved outside the pipeline. After the reverse sleeving is completed, the pipeline docking operation is carried out. After the pipeline docking is completed, the sealing ring that has been sleeved outside the pipeline needs to be reversed again so that it is sleeved at the pipeline connection. After the installation of the sealing ring is completed, a clamp is sleeved outside the sealing ring. However, this installation method still has certain defects: 1. Currently, under the complex working conditions of ultra-high-rise high-pressure pipelines, a single sealing ring design is difficult to effectively block the leakage of high-pressure media for a long time. Affected by factors such as pressure, temperature changes, and building structure deformations in ultra-high-rise high-pressure pipelines, gaps are likely to appear at the pipeline connections. Once the sealing ring ages, wears, or there are minor deviations during installation, it is easy to cause leakage, increasing the maintenance cost and possibly triggering safety hazards, affecting the long-term stable operation of the pipeline system.

[0004] 2. The strengthening and fixing effect of connecting the pipelines through clamps is limited. When ultra-high-rise high-pressure pipelines are operating, they are affected by huge pressures, vibrations, and stress changes brought by building displacements. Under the long-term external forces, the pipeline connections are prone to loosening and disconnection, reducing the reliability and safety of the pipeline system, shortening the service life of the pipelines, and increasing the frequency of pipeline maintenance and replacement.

[0005] 3. The installation process is relatively cumbersome. It is necessary to first reverse the highly elastic sealing ring and sleeve it outside the pipeline, and then turn it over and sleeve it at the connection after docking the pipelines. During this process, due to the extremely strong elasticity of the sealing ring used for installing high-pressure pipelines, the operation is extremely difficult and time-consuming during this reverse sleeving process. This makes it difficult for construction workers to quickly get started during installation, especially in the special environment of ultra-high-rise construction, where factors such as narrow spaces and high-altitude operations further increase the installation difficulty. Summary of the Invention

[0006] The present invention provides an installation structure for ultra-high-rise high-pressure pipelines to solve the above technical problems.

[0007] The present invention provides an installation structure for a super-high-rise high-pressure pipeline, comprising a high-pressure pipe group, wherein the high-pressure pipe group is composed of a right-angle elbow and two straight pipes respectively connected to the two ends of the right-angle elbow, an annular flange is provided on the outer side of the connection between the right-angle elbow and the straight pipe, and a sealing connection part for connecting the right-angle elbow and the straight pipe and performing multi-stage sealing on the connection is provided at the connection between the right-angle elbow and the straight pipe, and a triangular reinforcement part for triangularly reinforcing and locking the two is provided between the two sealing connections.

[0008] The sealing connection part includes a sealing cover composed of an upper and lower part and butt-mounted on the outside of the connection between the right-angle bend pipe and the straight pipe. A sealing ring is fixedly installed on the inner wall of the sealing cover. When the sealing cover is mounted on the outside of the connection between the right-angle bend pipe and the straight pipe, the inner wall contour of the sealing cover is close to the right-angle bend pipe and the straight pipe and the annular flanges on the outside of the two, and the sealing ring is inserted between the annular flanges on the outside of the right-angle bend pipe and the straight pipe to connect the right-angle bend pipe and the straight pipe and seal the seam.

[0009] The sealing connection part also includes a fixing part which is arranged on the outside of the sealing cover and connects and fixes the upper and lower parts of the sealing cover and reinforces the seal. After the fixing part fixes the upper and lower parts of the sealing cover, the triangular reinforcement part performs triangular reinforcement and locking fixation on the two fixing parts to improve the installation stability.

[0010] Furthermore, the triangular reinforcement part includes two clamping parts respectively sleeved on the outside of the two fixing parts, and a locking plate for cooperating with the reinforcing bolt to fix the clamping part is fixedly installed on the outside of the clamping part. After the clamping part is sleeved on the outside of the fixing part, the reinforcing bolt is inserted into the through hole on the locking plate.

[0011] Furthermore, a connecting frame is fixedly installed at the front end of the left reinforcing bolt, and a connecting sleeve is fixedly installed at the front end of the right reinforcing bolt. After the reinforcing bolt is inserted into the through hole on the locking plate, the connecting sleeve is inserted into the connecting frame, and the center holes of the two are aligned. Then, the connecting sleeve and the connecting frame are fixed by the locking bolt, and the end of the reinforcing bolt away from the locking bolt is fixed by the nut, so as to realize the triangular reinforced locking fixation of the fixed part.

[0012] Furthermore, the fixing part includes a locking sleeve, the inner wall of the locking sleeve is annularly stepped and the inner walls of the two step sections are both provided with external threads, the outer side of the sealing cover is provided with two sections of internal threads matching the corresponding external threads, and the locking sleeve is threadedly installed on the outer side of the sealing cover through the external threads matching the internal threads.

[0013] Furthermore, a sealing ring three and a sealing groove matching with the sealing ring three are fixedly installed on the adjacent sides of the two locking sleeves, and a sealing ring two is fixedly installed on the left inner wall of the locking sleeve. When the locking sleeve is threadedly installed on the outer side of the sealing cover, the sealing ring three is squeezed and inserted into the sealing groove and the sealing ring two is squeezed and pressed against the end face of the sealing cover.

[0014] Furthermore, the clamp member is composed of two clamp half pieces hinged to each other. The plug lock plate is fixedly installed at the top of the end face on the opening side of the clamp half piece. During installation, the two clamp half pieces are closed and sleeved outside the locking sleeve, so that the through holes on the two plug lock plates are aligned with each other.

[0015] Furthermore, an outer shell body composed of upper and lower parts is jointly installed outside the triangular reinforcing part and the two sealing connection parts. During installation, the upper and lower parts of the outer shell body are aligned and installed by means of bolt fixation.

[0016] The beneficial effects of the present invention are as follows: 1. In this application, by setting the sealing connection part and the triangular reinforcing part in cooperation, a strict multi-level sealing system is constructed. When connecting the high-pressure pipe group, the sealing ring I fills the gap at the connection between the straight pipe and the right-angle elbow to achieve primary sealing, effectively blocking the leakage of high-pressure medium. Subsequently, in the sealing cover reinforcement link, the sealing ring II and the sealing ring III work together. The sealing ring II closely adheres to the end face of the sealing cover to prevent the medium from leaking from the joint between the sealing cover and the locking sleeve. The sealing ring III cooperates with the sealing groove to prevent the medium from leaking between the two locking sleeves. This progressive multi-level sealing design greatly improves the sealing performance, ensures the long-term stable and safe operation of the ultra-high-rise high-pressure pipeline under complex working conditions, reduces the leakage risk, and reduces the maintenance cost and potential safety hazards.

[0017] 2. In this application, through the triangular multi-level strengthening and locking design, the connection strength and structural stability are significantly enhanced. During installation, first, the clamp half piece is closed and sleeved outside the locking sleeve and the reinforcing bolt is inserted to achieve preliminary fixation. Subsequently, a stable triangular structure is constructed by using the connecting frame, the connecting sleeve and the locking bolt to further strengthen the locking. The stability of the triangular structure enables the entire high-pressure pipe group installation structure to withstand the huge pressure, vibration generated during the operation of the ultra-high-rise high-pressure pipeline and the stress changes caused by building displacement. This stable connection method effectively prevents the loosening and disconnection of the pipe joints, extends the service life of the pipeline system, and improves the reliability and safety.

[0018] 3. In this application, the sealing cover adopts the form of butt joint of upper and lower parts. Before butt joint, the sealing ring I has been pre-installed in the middle of the inner wall of the sealing cover. During installation, the upper and lower parts of the sealing cover are directly butted and sleeved outside the connection between the straight pipe and the right-angle elbow. The operation is simple and convenient, greatly saving the installation time. At the same time, the threaded connection between the locking sleeve and the sealing cover and the installation of the clamp member and the locking sleeve both have clear positioning and operation procedures. Construction workers can quickly get started and accurately install. In the special environment of ultra-high-rise construction, this efficient installation method not only improves the construction efficiency, but also reduces the construction difficulty, reduces the installation errors caused by complex operation, ensures the installation quality of the pipeline system, effectively shortens the construction period, and improves the overall construction efficiency. Brief Description of the Drawings

[0019] Figure 1 Fig. is a schematic perspective view of the present invention after installation is completed.

[0020] Figure 2 Fig. is a schematic perspective view of the interior of the outer housing of the present invention.

[0021] Figure 3 Fig. is a schematic perspective view of the sealing cover, sealing ring I, clamping member and plug locking plate of the present invention.

[0022] Figure 4 Fig. is a schematic perspective view of the sealing cover, annular flange, locking sleeve and plug locking plate of the present invention.

[0023] Figure 5 Fig. is of the present invention Figure 4 partial enlarged view of part A.

[0024] Figure 6 Fig. is an exploded perspective view of the locking sleeve, internal thread, sealing ring II and sealing groove of the present invention.

[0025] Figure 7 Fig. is a schematic perspective view of the reinforcing bolt, connecting frame, connecting sleeve and locking bolt of the present invention.

[0026] Figure 8 Fig. is a schematic view of the installation process of the present invention.

[0027] In the figures: 1. high-pressure pipe group; 101. right-angle elbow; 102. straight pipe; 103. annular flange; 2. sealed connection part; 201. sealing cover; 202. sealing ring I; 204. fixing part; 2041. locking sleeve; 2042. internal thread; 2043. sealing ring II; 2044. sealing ring III; 2045. sealing groove; 2046. external thread; 3. triangular reinforcing part; 301. clamping member; 302. plug locking plate; 303. reinforcing bolt; 304. connecting frame; 305. connecting sleeve; 306. locking bolt; 4. outer housing. Detailed Embodiments

[0028] Now, the subject matter described herein will be discussed with reference to example embodiments. It should be understood that the discussion of these embodiments is provided so that those skilled in the art can better understand and thereby implement the subject matter described herein. The functions and arrangements of the elements discussed may be changed without departing from the scope of protection of the content of this specification. Each example may omit, substitute or add various processes or components as needed. Additionally, the features described with respect to some examples may be combined in other examples.

[0029] Refer to Figure 1 、Figure 2 , Figure 3 and Figure 4 , in this embodiment, an installation structure of a super-high-rise high-pressure pipeline is proposed, including a high-pressure pipe group 1. The high-pressure pipe group 1 is composed of a right-angle elbow 101 and two straight pipes 102 respectively connected to both ends of the right-angle elbow 101. Annular flanges 103 are provided on the outer sides of the joints between the right-angle elbow 101 and the straight pipes 102. A sealing connection part 2 is provided at the joint between the right-angle elbow 101 and the straight pipe 102 for connecting the joint between the right-angle elbow 101 and the straight pipe 102 and performing multi-stage sealing on the joint. A triangular strengthening part 3 is provided between the two sealing connection parts 2 for triangular strengthening locking and fixing of the two.

[0030] Refer to Figure 1 , Figure 3 , Figure 4 , Figure 5 and Figure 6 , the sealing connection part 2 includes a sealing cover 201 composed of upper and lower parts and sleeved on the outer side of the joint between the right-angle elbow 101 and the straight pipe 102 in a butting manner. A first sealing ring 202 composed of upper and lower parts is fixedly installed on the inner wall of the sealing cover 201. When the sealing cover 201 is sleeved on the outer side of the joint between the right-angle elbow 101 and the straight pipe 102, the inner wall contour of the sealing cover 201 closely adheres to the right-angle elbow 101, the straight pipe 102 and the annular flange 103 on their outer sides, and the first sealing ring 202 is clamped between the annular flanges 103 on the outer sides of the right-angle elbow 101 and the straight pipe 102 to connect the right-angle elbow 101 and the straight pipe 102 and seal the butt joint seam.

[0031] Refer to Figure 5 and Figure 8 , connection and primary sealing of the high-pressure pipe group 1: When installing the straight pipe 102 and the right-angle elbow 101, first butt the end faces of the joints between the straight pipe 102 and the right-angle elbow 101. Then, butt and sleeve the upper and lower parts of the sealing cover 201 on the outer side of the joint between the straight pipe 102 and the right-angle elbow 101. When the sealing cover 201 is sleeved on, its inner wall contour closely adheres to the right-angle elbow 101, the straight pipe 102 and their annular flange 103. At the same time, the first sealing ring 202 is clamped between the two annular flanges 103. At this time, the first sealing ring 202 forms a barrier, filling the gap at the joint between the straight pipe 102 and the right-angle elbow 101 and preventing the leakage of high-pressure medium, realizing the connection and primary sealing of the high-pressure pipe group 1.

[0032] Refer to Figure 3 , Figure 4 , Figure 5 and Figure 6, the sealing connection part 2 further includes a fixing part 204 which is arranged outside the sealing cover 201 and connects, fixes and reinforces the sealing of the upper and lower parts of the sealing cover 201. The fixing part 204 includes two symmetrically arranged locking sleeves 2041. The inner wall of the locking sleeve 2041 is annularly stepped, and external threads 2046 are provided on the inner walls of both stepped sections. Two sections of internal threads 2042 which are matched with the corresponding external threads 2046 are provided on the outside of the sealing cover 201. The locking sleeve 2041 is threadedly installed on the outside of the sealing cover 201 through the cooperation of the external thread 2046 and the internal thread 2042.

[0033] It should be noted that the annular stepped structure of the inner wall of the locking sleeve 2041 increases the contact area and friction force with the sealing cover 201. During installation, the locking sleeve 2041 is connected to the sealing cover 201 by threads. This special inner wall structure makes the connection tighter, can better resist the stress generated by the pressure fluctuation and building vibration of the high-pressure pipe group 1. Compared with the ordinary straight inner wall, it can effectively prevent the locking sleeve 2041 from loosening, stabilize the connection of the high-pressure pipe group 1, avoid sealing failure caused by loosening, and improve the reliability and safety of the high-pressure pipe group 1.

[0034] Refer to Figure 3 , Figure 4 , Figure 5 and Figure 6 , sealing rings three 2044 are respectively fixedly installed on the sides of the two locking sleeves 2041 close to each other, and sealing grooves 2045 which are matched with the sealing rings three 2044 are provided. Sealing rings two 2043 are fixedly installed on the inner walls of the two locking sleeves 2041 on the sides far away from each other. When the locking sleeve 2041 is threadedly installed on the outside of the sealing cover 201, the sealing ring three 2044 is extruded and inserted into the sealing groove 2045, and the sealing ring two 2043 is extruded and tightly attached to the end face of the sealing cover 201.

[0035] Refer to Figure 8 , it should be noted that before installing the sealing cover 201, the two locking sleeves 2041 need to pass through the two annular flanges 103 respectively and be sleeved on the outside of the straight pipe 102 and the right-angle elbow 101.

[0036] Reinforcement and secondary sealing of the sealing cover 201: After the connection and primary sealing of the high-pressure pipe group 1 are completed, the two locking sleeves 2041 are pushed towards the sealing cover 201, and then the two locking sleeves 2041 are rotated so that the internal threads 2042 on the inner wall of the locking sleeves 2041 are thread-fitted with the external threads 2046 on the outside of the sealing cover 201, thereby fixing the sealing cover 201 by screw installation. At the same time, the sealing ring two 2043 on the left inner wall of the locking sleeve 2041 is pressed against the end face of the sealing cover 201 to prevent the medium from leaking from the joint between the sealing cover 201 and the locking sleeve 2041, forming a secondary seal. Moreover, the sealing ring three 2044 on the side where the two locking sleeves 2041 are close to each other cooperates with the sealing groove 2045 to further enhance the sealing effect and prevent the medium from leaking between the two locking sleeves 2041.

[0037] It should be noted that when installing the sealing cover 201 and the locking sleeve 2041 after docking the end faces at the connection between the straight pipe 102 and the right-angle elbow 101, the installation needs to be carried out separately at the connections between the two straight pipes 102 and the right-angle elbow 101. That is to say, after completing the installation of the sealing cover 201 and the locking sleeve 2041 for one side of the straight pipe 102 and the right-angle elbow 101, the installation operation for the other side is carried out.

[0038] Refer to Figure 2 、 Figure 3 、 Figure 6 and Figure 7 As shown in

[0039] Refer to Figure 3 、 Figure 6 and Figure 7 As shown in

[0040] Refer to Figure 3 、 Figure 6 and Figure 7, the clamp member 301 is composed of two half-clamps hinged to each other. The insertion lock plate 302 is fixedly installed at the top of the end face on the opening side of the half-clamp. During installation, the two half-clamps are closed and sleeved on the outside of the locking sleeve 2041, so that the through holes on the two insertion lock plates 302 are aligned with each other.

[0041] Refer to Figure 8 , Preliminary fixing and positioning: After installing the locking sleeve 2041 at the connection between the two straight pipes 102 and the right-angle elbow 101, the two half-clamps are closed and sleeved on the outside of the locking sleeve 2041, so that the through holes on the two insertion lock plates 302 are aligned with each other. Then, the strengthening bolts 303 are inserted into the through holes on the two insertion lock plates 302 (at this time, the above operation needs to be carried out again to synchronously install the connection between another straight pipe 102 and the right-angle elbow 101), thereby circumferentially fixing the two half-clamps. At this time, the half-clamps are in close contact with the locking sleeve 2041, which preliminarily strengthens and fixes the locking sleeve 2041, and at the same time prepares for subsequent locking and strengthening connection.

[0042] Then, control the horizontal movement of the two strengthening bolts 303 to insert the connecting sleeve 305 into the connecting frame 304 (at this time, the horizontal movement of the strengthening bolts 303 will not affect the strengthening and fixing of the clamp member 301), align the central holes of the two, and after alignment, pass the locking bolt 306 through the central holes of the connecting sleeve 305 and the connecting frame 304 and thread-fix the two. At this time, the two clamp members 301 and the locking bolt 306 form a stable triangular strengthening and locking fixing system, which can effectively enhance the connection strength between the straight pipe 102 and the right-angle elbow 101, and greatly improve the stability of the installation structure of the entire high-pressure pipe group 1.

[0043] Explanation of the triangular strengthening and locking fixation: From a mechanical point of view, the triangular strengthening part 3 utilizes the principle of triangle stability. Although in terms of integrity, one side is missing, through the coordinated work of components such as the connecting frame 304, the connecting sleeve 305, the locking bolt 306, and the clamp member 301, a stable triangular force-bearing system is formed. The clamp member 301 is sleeved on the outside of the locking sleeve 2041, the strengthening bolts 303 are inserted into the insertion lock plates 302, and the connecting sleeve 305 and the connecting frame 304 are fixed by the locking bolt 306, so that the force is effectively transmitted and dispersed among these components, similar to a triangular structure that evenly disperses the external force and enhances the overall stability, just like the triangular truss structure in architecture. Although there are complex connections inside, as a whole, it utilizes the triangular principle to withstand huge loads. In ultra-high-rise high-pressure pipelines, it can resist external forces such as pressure fluctuations and building vibrations, and prevent loosening at the pipe joints.

[0044] Refer to Figure 1 , Figure 2 and Figure 3, an outer shell 4 composed of upper and lower parts is jointly installed on the outer sides of the triangular reinforcing part 3 and the two sealing connection parts 2. During installation, the upper and lower parts of the outer shell 4 are aligned and fixed by bolts.

[0045] Refer to Figure 8 , Installation of the outer shell 4: After forming the triangular reinforcing and locking fixing system, the upper and lower parts of the outer shell 4 are aligned and sleeved on the outer side of the right-angle elbow 101 and fixed by bolts, thereby completing the installation of the entire high-pressure pipe group 1. The outer shell 4 can provide a physical barrier for the high-pressure pipe group 1, the sealing connection part 2, and the triangular reinforcing part 3 inside it. While preventing the internal structure from being damaged by the material, it can further enhance the sealing performance of the high-pressure pipe group 1.

[0046] Finally, it should be noted that: Obviously, the above embodiments are merely examples for clearly illustrating the present invention and are not limitations on the implementation manners. For those of ordinary skill in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to enumerate all the implementation manners here. And the obvious changes or modifications derived therefrom are still within the protection scope of the present invention.

Claims

1. An installation structure for ultra-high-rise high-pressure pipelines, comprising: High-pressure pipe group, the high-pressure pipe group is composed of a right-angle elbow and two straight pipes respectively connected to both ends of the right-angle elbow. It is characterized in that annular flanges are provided on the outer sides of the joints between the right-angle elbow and the straight pipes. A sealed connection part is provided at the joint between the right-angle elbow and the straight pipe for connecting the joint between the right-angle elbow and the straight pipe and performing multi-stage sealing on the joint. A triangular strengthening part is provided between the two sealed connection parts for triangular strengthening, locking and fixing them. The sealed connection part includes a sealed cover composed of upper and lower parts and sleeved on the outer side of the joint between the right-angle elbow and the straight pipe in a butt joint manner. A first sealing ring is fixedly installed on the inner wall of the sealed cover. When the sealed cover is sleeved on the outer side of the joint between the right-angle elbow and the straight pipe, the inner wall contour of the sealed cover closely adheres to the right-angle elbow, the straight pipe and the annular flanges on their outer sides, and the first sealing ring is clamped between the annular flanges on the outer sides of the right-angle elbow and the straight pipe to connect the right-angle elbow and the straight pipe and seal the butt joint seam. The sealed connection part further includes a fixing part provided on the outer side of the sealed cover for connecting, fixing and strengthening the seal of the upper and lower parts of the sealed cover. After the fixing part fixes the upper and lower parts of the sealed cover, the triangular strengthening part performs triangular strengthening, locking and fixing on the two fixing parts to improve the installation stability.

2. The installation structure for ultra-high-rise high-pressure pipelines according to claim 1, characterized in that The triangular strengthening part includes two clamp pieces respectively sleeved on the outer sides of the two fixing parts. An insertion lock plate for cooperating with the strengthening bolt to fix the clamp piece is fixedly installed on the outer side of the clamp piece. After the clamp piece is sleeved on the outer side of the fixing part, the strengthening bolt is inserted into the through hole on the insertion lock plate.

3. The installation structure for ultra-high-rise high-pressure pipelines according to claim 2, characterized in that A connecting frame is fixedly installed at the front end of the left strengthening bolt, and a connecting sleeve is fixedly installed at the front end of the right strengthening bolt. After the strengthening bolt is inserted into the through hole on the insertion lock plate, the connecting sleeve is inserted into the connecting frame, and their central holes are aligned. Then, the connecting sleeve and the connecting frame are fixed by a locking bolt, and the end of the strengthening bolt away from the locking bolt is fixed by a nut to realize triangular strengthening, locking and fixing of the fixed part.

4. The installation structure for ultra-high-rise high-pressure pipelines according to claim 2, characterized in that The fixing part includes a locking sleeve. The inner wall of the locking sleeve is in an annular stepped shape, and external threads are provided on the inner walls of both stepped sections. Two internal threads matching the corresponding external threads are provided on the outer side of the sealed cover. The locking sleeve is threadedly installed on the outer side of the sealed cover through the cooperation of the external thread and the internal thread.

5. The installation structure for ultra-high-rise high-pressure pipelines according to claim 4, characterized in that Sealing rings three are respectively fixedly installed on the sides of the two locking sleeves close to each other, and sealing grooves matching the sealing rings three are provided. A sealing ring two is fixedly installed on the left inner wall of the locking sleeve. When the locking sleeve is threadedly installed on the outer side of the sealed cover, the sealing ring three is extruded and inserted into the sealing groove, and the sealing ring two is extruded and closely adheres to the end face of the sealed cover.

6. The installation structure for ultra-high-rise high-pressure pipelines according to claim 4, characterized in that The clamp piece is composed of two clamp half pieces hinged to each other. The insertion lock plate is fixedly installed at the top of the end face of the opening side of the clamp half piece. During installation, the two clamp half pieces are closed and sleeved on the outer side of the locking sleeve, so that the through holes on the two insertion lock plates are aligned.

7. The installation structure for ultra-high-rise high-pressure pipelines according to claim 1, characterized in that An outer shell body composed of upper and lower parts is jointly installed on the outer sides of the triangular strengthening part and the two sealed connection parts. During installation, the upper and lower parts of the outer shell body are aligned and installed by means of bolt fixation.

Citation Information

Patent Citations

  • Hoop fixing device

    CN102606829A

  • Integral insulating joint for pipelines

    CN102865423A

  • Connecting structure of liquid level sensor and connector

    CN112197081A

  • Pipeline connecting structure

    CN112413250A

  • Aluminum alloy convex pipe type joint

    CN116104994A

Cited By

  • Rural sewage transformation pipeline sealing connection mechanism

    CN121067147A

  • A sealing connecting mechanism for rural sewage reconstruction pipeline

    CN121067147B