Railway train approaching early warning protection system and method based on CTC system

By combining the train approach warning system with the CTC system, blocking instructions are dynamically generated, solving the problem of the inability to dynamically set blocking areas in existing technologies, achieving precise control of locomotives, and improving railway construction safety and transportation efficiency.

CN120606877AActive Publication Date: 2025-09-09CASCO SIGNAL LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202510917116.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-03
Publication Date
2025-09-09
Estimated Expiration
2045-07-03

AI Technical Summary

Technical Problem

The existing railway train approach warning system is unable to dynamically set blocking equipment and blocking areas based on the actual operation scope and content of on-site construction, and cannot accurately control locomotive parking, resulting in the inability to prevent collision accidents.

Method used

The train approach warning system obtains the construction operation electronic fence in real time, combines the construction plan information of the CTC system to generate blocking instructions, and uses the computer interlocking system to execute signal equipment blocking and route control to achieve dynamic control of the locomotive.

Benefits of technology

There is no need to add locomotive-mounted positioning equipment, and the on-site operation area and content can be dynamically obtained, achieving precise blocking of the locomotive, preventing collision accidents, and improving the safety of on-site construction operations and transportation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120606877A_ABST
    Figure CN120606877A_ABST
Patent Text Reader

Abstract

The invention discloses a railway train approaching early-warning protection system based on a CTC system, and the system comprises a train approaching early-warning system which is used for obtaining a construction operation electronic fence in real time, and extracting equipment information from the construction operation electronic fence; the CTC system is in communication connection with the train approaching early warning system and is used for generating a blocking instruction according to construction plan information set by the CTC system or equipment information sent by the train approaching early warning system; and the computer interlocking system is in communication connection with the CTC system and is used for executing the blocking instruction to realize construction operation area signal equipment blocking and access control. The locomotive can be controlled not to enter a site construction area, so that collision accidents are prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of early warning and protection technology, and in particular to a railway train approach early warning and protection system and method based on a CTC system. Background Art

[0002] The Centralized Traffic Control (CTC) system is a remote control and telesignaling system used by train dispatchers at a dispatching center to centrally control and monitor signaling equipment at stations within their jurisdiction, and to coordinate and direct train operations. The CTC system typically interfaces with systems such as the TDMS (Traffic Data Management System) and construction management systems to implement equipment locking and unlocking functions based on construction plans.

[0003] Railway train approach warning systems currently typically use high-precision Beidou satellite positioning, electronic maps, construction plans, station approach information, locomotive position information, etc. to provide on-site construction personnel with early warning of incoming trains. This railway train approach warning system provides certain train approach warning and protection functions for on-site construction personnel.

[0004] However, CTC systems typically implement access control by setting equipment blocking and unlocking conditions based on fixed construction plans from systems like TDMS and construction management systems. However, this blocking approach cannot dynamically set blocked equipment and areas based on the actual scope and content of on-site construction work. Furthermore, current railway train approach warning systems are typically non-safety auxiliary warning and protection systems, unable to accurately control locomotive stops. They primarily serve as early warnings, sending only warnings to on-site construction personnel when a train approaches, but unable to prevent locomotives from entering the construction area, thereby preventing collisions. Summary of the Invention

[0005] The purpose of the present invention is to provide a railway train approach warning protection system and method based on the CTC system, which can control locomotives from entering the on-site construction area, thereby preventing collision accidents.

[0006] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0007] A railway train approach warning and protection system based on a CTC system, comprising:

[0008] A train approach warning system for obtaining real-time access to construction operation electronic fences and extracting equipment information from the construction operation electronic fences;

[0009] a CTC system, which is in communication with the train approach warning system and is configured to generate a blocking instruction based on its own construction plan information or the equipment information sent by the train approach warning system;

[0010] A computer interlocking system is connected to the CTC system for executing the blocking instructions to block the signal equipment in the construction area and control the access routes.

[0011] Optionally, the train approach warning system includes: an early warning server and a terminal device; the early warning server is used to receive and send the construction plan information sent by the CTC system to the terminal device, and the terminal device feeds back the construction personnel's satellite positioning position information and the prepare-to-go-on-track operation command to the early warning server;

[0012] The early warning server is further configured to generate a construction operation area and demarcate the construction operation electronic fence based on the construction plan content in the construction plan information in combination with its own electronic map data;

[0013] and displaying the current station equipment status and construction personnel location status in real time on a station vectorized electronic map generated based on the electronic map data according to the construction personnel satellite positioning information;

[0014] The early warning server is further configured to feed back the prepare-to-go-operation command to the CTC system, and the CTC system generates the blocking instruction according to the prepare-to-go-operation command.

[0015] Optionally, the terminal device includes a monitoring terminal and a handheld terminal; the monitoring terminal is used to receive the construction plan information sent by the early warning server; or the monitoring terminal is used to obtain a temporary construction request and generate a temporary construction plan based on the temporary construction request, and generate the construction operation electronic fence on the station vectorized electronic map generated by the monitoring terminal based on the electronic map data according to the temporary construction plan and the actual work area on site, and feedback it to the early warning server; the handheld terminal is used to receive the construction plan information sent by the early warning server, and feedback the construction personnel satellite positioning position information to the early warning server; or the handheld terminal is used to generate the construction operation electronic fence according to a manual dot trigger command, or, when no manual dot trigger command is received, the handheld terminal feedbacks the construction personnel satellite positioning position information to the early warning server, and the early warning server dynamically delineates the construction operation electronic fence according to the construction personnel satellite positioning position information and the preset single-person activity range.

[0016] Optionally, the train approach warning system further includes: a warning interface machine, which is used to communicate with a CTC interface machine in the CTC system.

[0017] Optionally, it further includes: a two-way network gateway, and the early warning interface machine is communicatively connected with the CTC interface machine via the two-way network gateway.

[0018] Optionally, the equipment information includes at least signals, switches and tracks.

[0019] In another aspect, the present invention further provides a railway train approach warning and protection method based on a CTC system, comprising: a fixed construction plan warning and protection process; the fixed construction plan warning and protection process comprising: obtaining construction plan information from the CTC system via a train approach warning system, and automatically generating a construction operation electronic fence on a vectorized electronic map of the station based on the construction plan content in the construction plan information; and generating a blocking instruction based on the construction plan information via the CTC system;

[0020] A computer interlocking system is used to execute the blocking instructions to achieve signal equipment blocking and access control in the construction area.

[0021] Optionally, the fixed construction plan warning protection process also includes: sending the construction operation electronic fence and the construction plan information to the handheld terminal through the warning server in the train approach warning system, and the handheld terminal feedbacks the construction personnel satellite positioning location information and the preparation for going on the road operation command to the warning server, and the warning server displays the current station equipment status and construction personnel location status in real time on the station vectorized electronic map according to the construction personnel satellite positioning location information; and generates the blocking instruction according to the preparation for going on the road operation command through the CTC system.

[0022] Optionally, the system further includes: a temporary construction plan early warning and protection process; the temporary construction plan early warning and protection process includes: generating a construction operation electronic fence of the temporary construction plan through a monitoring terminal or a handheld terminal in the train approach early warning system, and sending the construction operation electronic fence to the CTC system through the early warning server;

[0023] The CTC system pops up a pop-up window to confirm whether the construction operation electronic fence is valid. If the construction operation electronic fence is valid, the warning server is controlled to send the construction operation electronic fence to the handheld terminal and the monitoring terminal in the train approach warning system;

[0024] The handheld terminal feeds back the preparation-on-road operation command and the satellite positioning information of the construction personnel to the early warning server; the early warning server displays the current station yard equipment status and the construction personnel location status in real time on the station vectorized electronic map based on the satellite positioning information of the construction personnel; and the early warning server extracts equipment information from the effective construction operation electronic fence and sends it to the CTC system; the CTC system generates a blocking instruction based on the equipment information; and a computer interlocking system is used to execute the blocking instruction to realize the blocking of signal equipment and access control in the construction operation area.

[0025] Optionally, the method further includes: when the construction operation electronic fence is invalid, controlling the early warning server to send a temporary construction plan creation failure message to the handheld terminal and the monitoring terminal to interrupt the temporary construction plan.

[0026] Optionally, the step of generating a temporary construction plan for the construction operation electronic fence through the monitoring terminal in the train approach warning system includes: generating a temporary construction plan through the monitoring terminal, and generating the construction operation electronic fence on the station vectorized electronic map of the monitoring terminal based on the temporary construction plan and the actual on-site operation area, and feeding back the construction operation electronic fence to the warning server.

[0027] Optionally, the step of generating an electronic fence for construction work of a temporary construction plan through the handheld terminal in the train approach warning system includes: generating the electronic fence for construction work through the handheld terminal according to a manual dot trigger command; or, dynamically demarcating the electronic fence for construction work through the warning server according to the satellite positioning location information of the construction personnel fed back by the handheld terminal and the preset single-person activity range.

[0028] The present invention has the following technical effects:

[0029] 1. The present invention does not require additional locomotive-mounted positioning equipment. By integrating the early warning real-time construction operation area and the construction blocking logic and access control function of the CTC system, it prevents locomotives from entering the construction operation area from the source.

[0030] 2. The present invention can dynamically obtain on-site work areas and work contents by manually setting up electronic fences by on-site construction workers or by automatically calculating the dynamic range of construction workers' activities. This is more accurate and real-time than traditional fixed construction plans in achieving blockades.

[0031] 3. The present invention can achieve automatic equipment and area blockades on railway lines through two methods: construction plans issued by the CTC system and real-time dynamic acquisition of on-site construction areas. At the same time, combined with the manual confirmation method of the CTC station and the actual start time of on-site construction, it ensures the safety of on-site construction operations and accurately implements equipment blockades, thereby improving on-site construction safety and transportation operation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 A structural block diagram of a railway train approach warning and protection system based on a CTC system provided in one embodiment of the present invention;

[0033] Figure 2 A flowchart of a method for early warning and protection without a construction plan provided by an embodiment of the present invention;

[0034] Figure 3 A flowchart of a construction plan early warning and protection method provided by one embodiment of the present invention. DETAILED DESCRIPTION

[0035] The following is a further detailed description of a railway train approach warning protection system and method based on a CTC system proposed by the present invention, in conjunction with the accompanying drawings and specific embodiments. According to the following description, the advantages and features of the present invention will become clearer. It should be noted that the drawings are in a very simplified form and are not in precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, please refer to the drawings. It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the implementation conditions of the present invention. Therefore, they have no technical significance. Any modification of the structure, change in the proportional relationship or adjustment of the size should still fall within the scope of the technical content disclosed by the present invention without affecting the efficacy and purpose that can be achieved by the present invention.

[0036] like Figure 1 As shown, this embodiment provides a railway train approach warning and protection system based on the CTC system, including: a train approach warning system 20, which is used to obtain the construction operation electronic fence in real time and extract equipment information from the construction operation electronic fence; a CTC system 10, which is communicated with the train approach warning system 20 and is used to generate a blocking instruction based on its own construction plan information or the equipment information sent by the train approach warning system 20; a computer interlocking system 30, which is communicated with the CTC system 10 and is used to execute the blocking instruction to realize the blocking of signal equipment and approach control in the construction operation area to prevent locomotives from entering the construction area.

[0037] This embodiment does not require the addition of locomotive-mounted positioning equipment. By using the construction operation electronic fence and the CTC system, that is, integrating the real-time construction operation area of ​​the early warning system and the construction blocking logic and access control function of the CTC system, locomotives are prevented from entering the construction operation area at the source.

[0038] Please continue to refer to Figure 1As shown, the CTC system includes a train operation terminal 101, a CTC server 102 and a CTC interface device 103. The CTC server 102 is in communication with the computer interlocking system 30. The train approach warning system includes an early warning server 202 and terminal equipment.

[0039] When the CTC system 10 issues a fixed construction plan, the warning server 202 is used to receive the construction plan information sent by the CTC system 10; and generate a construction operation area based on the construction plan content in the construction plan information combined with its own electronic map data, and delineate the construction operation electronic fence based on the construction operation area.

[0040] Please continue to refer to Figure 1 As shown, the terminal device may include a handheld terminal 203 and a monitoring terminal 204, each of which communicates with the early warning server 202. The station liaison officer can bind the construction worker information and handheld terminal 203 information for the construction plan to the monitoring terminal 204. After the construction plan is bound to the construction worker's handheld terminal 203, the early warning server 202 automatically transmits the corresponding construction plan information to the corresponding construction worker's handheld terminal 203, allowing the construction worker to view the construction plan content through the handheld terminal 203. At this time, the construction worker enters the work area within the construction work electronic fence at the construction plan start time. The terminal device, specifically the handheld terminal 203, provides the early warning server 202 with the construction worker's satellite positioning location information and a "prepare to go on the road" command. The CTC system 102 automatically generates a blockade command based on the "prepare to go on the road" command and the construction plan information. The blockade command is transmitted via the CTC server 102 to the computer interlocking system 30, which executes the blockade command to block the signal equipment in the work area and control the access route, preventing locomotives from entering the construction area.

[0041] In addition, the early warning server 202 is also used to display the current station equipment status and construction personnel location status in real time on the station vectorized electronic map generated according to the electronic map data through the satellite positioning position information of the construction personnel on site fed back by the handheld terminal 203.

[0042] Please continue to refer to Figure 1 As shown, the train approach warning system 20 further includes a warning interface machine 201 for communicating with the CTC interface machine 103 in the CTC system 10 .

[0043] Please continue to refer to Figure 1 As shown, this embodiment further includes a bidirectional network gatekeeper 31, through which the warning interface machine 201 communicates with the CTC interface machine 103. The bidirectional network gatekeeper 31 implements network security isolation between the train approach warning system 20 and the CTC system 10.

[0044] Please continue to refer to Figure 1 As shown, when on-site construction personnel need to deal with on-site emergency failures and other operations without a fixed construction plan, that is, when there is a temporary construction plan, the station liaison officer can send a temporary construction request to the monitoring terminal 204 based on the actual on-site operation area. The monitoring terminal 204 generates a temporary construction plan based on the temporary construction request, and generates a construction operation electronic fence on the station vectorized electronic map of the monitoring terminal based on the temporary construction plan and the actual on-site operation area; and is also used to feedback the temporary construction plan and the construction operation electronic fence to the early warning server 202.

[0045] After the early warning server 202 receives the temporary construction plan and the construction operation electronic fence issued by the monitoring terminal 204, it extracts the equipment information contained in the construction operation electronic fence after processing (the equipment information includes equipment on the line such as signals, switches and tracks), and sends the extracted equipment information to the CTC server 102 of the CTC system 10 through the early warning interface machine 201 and the CTC interface machine 103. The CTC server 102 generates a blocking instruction, and the computer interlocking system 30 is used to execute the blocking instruction to realize the equipment blocking and access control of the temporary construction operation area to prevent locomotives from entering the construction area.

[0046] Specifically, the CTC server 102 also sends a blocking instruction (the blocking instruction includes information about the equipment to be blocked) to the vehicle service terminal 101, and the vehicle service terminal 101 manually confirms the information about the equipment to be blocked. If the confirmation is passed, the construction operation electronic fence is valid, and the blocking instruction is sent to the computer interlocking system 30; if it is not passed, the early warning server 202 is controlled to send a temporary construction plan creation failure message to the monitoring terminal 204 to interrupt this temporary construction plan.

[0047] Furthermore, the station liaison officer can bind the construction worker information and handheld terminal 203 information of the temporary construction plan on the monitoring terminal 204. After the temporary construction plan is bound to the construction worker's handheld terminal 203, the early warning server 202 is further configured to send the valid construction operation electronic fence and temporary construction plan to the handheld terminal 203. The construction worker can view the temporary construction plan on the handheld terminal 203 and enter the construction area according to the construction operation electronic fence to carry out on-road work. After that, the CTC server 102 sends a blocking instruction to the computer interlocking system 30, which executes the blocking instruction, thereby blocking equipment in the temporary construction area and controlling access to the road, preventing locomotives from entering the construction area.

[0048] Please continue to refer to Figure 1As shown, when there is no fixed construction plan and there is no station liaison officer, and on-site construction personnel need to go on the road to handle work without a fixed construction plan, the handheld terminal 203 is used to generate the construction operation electronic fence according to the manual dot trigger command.

[0049] Specifically, at this time, the on-site construction personnel log in to the handheld terminal 203 with a special work identity. After manually going on the road to the designated work area according to the actual situation, they can use the handheld terminal 203 to manually mark on the station vectorized electronic map to set up temporary construction work electronic fences and temporary construction work tasks. The handheld terminal 203 sends the set construction work electronic fences and temporary construction work tasks to the early warning server 202 via wireless communication.

[0050] After the early warning server 202 receives the temporary construction work task and the construction work electronic fence issued by the handheld terminal 203, it extracts the equipment information contained in the construction work electronic fence after processing (the equipment information includes equipment on the line such as signals, switches and tracks), and sends the extracted equipment information to the CTC server 102 through the early warning interface machine 201 and the CTC interface machine 103. After the CTC server 102 generates a blocking instruction and verifies that the construction work electronic fence is valid through the vehicle service terminal 101, the computer interlocking system 30 is used to execute the blocking instruction to realize the equipment blocking and access control of the temporary construction work area to prevent locomotives from entering the construction area.

[0051] Furthermore, if on-site construction personnel are unable to dynamically set a fixed construction area based on on-site construction requirements, i.e., if they are unable to generate an electronic fence for construction work, the early warning server 202 can dynamically demarcate the electronic fence for construction work based on the satellite positioning information of the construction personnel for the special operation and the set individual activity range (single-person activity radius). The early warning server 202 calculates the equipment information (such as signals, switches, and tracks) contained in the electronic fence based on the automatically generated electronic fence and combined with electronic map data. The early warning server 202 then sends this equipment information and the electronic fence for construction work to the CTC server 102 via the early warning interface 201 and the CTC interface 103. Upon receiving the electronic fence and equipment information, the CTC server 102 prompts a manual confirmation window on the train service terminal 101 to confirm the validity of the electronic fence. After confirmation by the train service personnel at the station, the CTC server 102 generates and sends a blockade command to the computer interlocking system 30. The computer interlocking system 30 executes the blockade command to block the equipment in the temporary construction area and control access to the road, preventing locomotives from entering the construction area.

[0052] In this embodiment, on-site construction workers can manually mark and set up electronic fences for construction operations, or the system can automatically calculate the dynamic activity range of construction workers to dynamically obtain on-site work areas and work contents to generate electronic fences for construction operations. This is more accurate and real-time than traditional fixed construction plans in achieving blockades.

[0053] This embodiment can achieve automatic equipment and area blocking of railway lines through two methods: a fixed construction plan issued by the CTC system and real-time dynamic acquisition of on-site construction areas. At the same time, combined with the manual confirmation method of the train service terminal and the actual start time of on-site construction, it ensures the safety of on-site construction operations and the precise implementation of equipment blocking, thereby improving the safety of on-site construction operations and the efficiency of transportation operations.

[0054] This embodiment also provides a railway train approach warning protection method based on a CTC system, including:

[0055] Fixed construction plan early warning and protection process and temporary construction plan early warning and protection process.

[0056] The fixed construction plan warning protection process is a protection process in which the train approach warning system 20 receives the construction plan sent by the CTC system 10, and the construction personnel go on the track to work according to the construction plan.

[0057] Among them, such as Figure 3 As shown, the fixed construction plan early warning and protection process includes:

[0058] Step S1: The CTC system sends construction plan information to the early warning server and starts equipment pre-lockdown according to the construction plan information.

[0059] Step S2: The early warning server generates a construction area according to the construction plan content in the construction plan information (the construction plan content includes, for example, the name of the work station, the name of the work equipment, and the work time, etc.) combined with its own electronic map data (the electronic map data includes station information, equipment element names, and coordinate information).

[0060] Step S3: The early warning server demarcates an electronic fence based on the generated construction operation area to form a construction operation electronic fence.

[0061] Step S4: The station liaison officer associates the construction plan information with the construction personnel through the monitoring terminal, that is, adds the name of the construction personnel in the personnel option of the construction plan information, and then the construction personnel log in to their respective handheld terminals.

[0062] Step S5: The station liaison officer issues the construction plan information to the construction personnel, and the construction personnel can view their own construction plans on the logged-in handheld terminal.

[0063] Step S6: After receiving the construction plan information through their handheld terminals, when the construction personnel are ready to enter the construction area (within the construction electronic fence) for operation, they manually trigger the prepare-to-go-on-the-road operation command through the handheld terminals. After receiving the prepare-to-go-on-the-road operation command, the early warning server triggers the construction area blockade start command and forwards it to the CTC system. After receiving the construction area blockade start command, the CTC system generates a blockade command according to the construction plan information, and executes the blockade command through the computer interlocking system to control the construction area access blockade and prevent locomotives from entering the construction area.

[0064] In this embodiment, the fixed construction plan early warning and protection process also includes: the construction personnel feedback the construction personnel's satellite positioning location information to the early warning server through the handheld terminal, and the early warning server combines the electronic map data and the construction personnel's satellite positioning location information to display the current station equipment status and construction personnel location status in real time on the station vectorized electronic map.

[0065] like Figure 2 As shown in FIG, when the warning server does not receive the construction plan information sent by the CTC system and the on-site construction personnel receive a temporary construction task (such as emergency handling of on-site equipment failure), they execute the temporary construction plan warning protection process, including:

[0066] Step S2.1: Is there a station liaison officer for the current temporary construction task? If yes, proceed to step S2.2; if not, proceed to step S2.4;

[0067] Step S2.2: The station liaison officer creates a temporary construction plan and construction operation electronic fence on the station monitoring terminal;

[0068] Specifically, a temporary construction plan is generated by the monitoring terminal, and the construction operation electronic fence is generated on the station vectorized electronic map of the monitoring terminal according to the temporary construction plan and combined with the actual operation area on site, and fed back to the early warning server.

[0069] Step S2.3: The on-site liaison associates the temporary construction plan (and the construction operation electronic fence) with the construction personnel and the handheld terminal. The construction personnel log in to the handheld terminal as normal. Then proceed to step S2.6.

[0070] Step S2.6: The monitoring terminal sends the generated construction operation electronic fence to the CTC system via the early warning server. The CTC system prompts a window to manually confirm whether the construction operation electronic fence is valid. If not, the system returns to step S2.1; if valid, the system proceeds to step S2.7.

[0071] Specifically, after receiving the equipment information (also known as line equipment information) contained within the construction electronic fence from the early warning system, the CTC system generates construction blockade equipment information based on the equipment information within the construction electronic fence. A pop-up window appears on the train terminal prompting station train personnel to confirm the construction blockade equipment information. If the train personnel do not confirm or select "Confirm" within the specified manual confirmation timeout, the CTC system initiates the equipment blockade and sends an approach blockade instruction to the computer interlocking system, prohibiting access to the blocked equipment. The CTC system then feeds back the result of the manual "Confirm" selection to the early warning server.

[0072] If the user manually selects "Cancel" within the timeout period, the CTC system will not initiate the blockade of related equipment and will feed back the result of the manual selection of "Cancel" to the early warning server.

[0073] That is, when the construction operation electronic fence is invalid, the early warning server is controlled to send a temporary construction plan creation failure message to the handheld terminal and the monitoring terminal, thereby interrupting the temporary construction plan.

[0074] Step S2.7: The monitoring terminal sends the construction operation electronic fence to the handheld terminal. The construction personnel check the handheld terminal to enter the construction operation electronic fence and start working on the road.

[0075] Specifically, when the construction operation electronic fence is valid, the warning server is controlled to send the construction operation electronic fence to the handheld terminal and the monitoring terminal in the train approach warning system;

[0076] The handheld terminal feeds back a preparation-for-road-operation command and construction worker satellite positioning information to the warning server;

[0077] The early warning server combines the electronic map data and the satellite positioning information of the construction personnel to display the current station equipment status and the construction personnel position status in real time on the station vectorized electronic map.

[0078] Step S2.8: After the construction workers start working on the road, the construction work start instruction in the early warning server is triggered and sent to the CTC system. The CTC system starts the route blockade and performs early warning protection.

[0079] Specifically, the early warning server extracts equipment information from the effective construction electronic fence and sends it to the CTC system; and sends a construction start instruction to the CTC system. After receiving the construction start instruction, the CTC system generates a blocking instruction based on the equipment information; and uses a computer interlocking system to execute the blocking instruction to achieve signal equipment blocking and access control in the construction area.

[0080] Step S2.4: The construction worker logs into the handheld terminal with a special identity and proceeds to step S2.5.

[0081] Step S2.5: The early warning server allows construction workers to use the handheld terminal to mark and set up the construction operation electronic fence in the work area based on the special identity authority of the handheld terminal. If the construction workers do not manually mark and set up the construction operation electronic fence, the early warning server will automatically define the construction workers' construction operation area and generate the construction operation electronic fence based on the construction workers' position and activity range on the track line (the activity radius can be configured, generally the default is 3 meters), and then enter step S2.6.

[0082] In summary, this embodiment can achieve automatic equipment and area blocking of railway lines through two methods: construction plans issued by the CTC system and real-time dynamic acquisition of on-site construction areas. At the same time, combined with the manual confirmation method of the CTC station and the actual start time of on-site construction, it ensures the safety of on-site construction operations and the precise implementation of equipment blocking, thereby improving the safety of on-site construction operations and the efficiency of transportation operations.

[0083] It should be noted that, in this document, the terms "comprises," "includes," or any other variations thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus comprising a series of elements includes not only those elements but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of other identical elements in the process, method, article, or apparatus comprising the element.

[0084] It should be noted that the devices and methods disclosed in the embodiments of this document may also be implemented in other ways. The device embodiments described above are merely illustrative. For example, the flowcharts and block diagrams in the accompanying drawings illustrate the possible architectures, functions, and operations of the devices, methods, and computer program products according to the various embodiments of this document. In this regard, each box in the flowchart or block diagram may represent a module, program, or portion of code, wherein the module, program segment, or portion of code contains one or more executable instructions for implementing a specified logical function, and the module, program segment, or portion of code contains one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions marked in the boxes may also occur in an order different from that marked in the accompanying drawings. For example, two consecutive boxes may actually be executed substantially in parallel, or they may sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or flowchart, and the combination of boxes in the block diagram and / or flowchart, may be implemented by a dedicated hardware-based system for performing the specified function or action, or may be implemented by a combination of dedicated hardware and computer instructions.

[0085] In addition, the functional modules in the various embodiments of this document may be integrated together to form an independent part, or each module may exist independently, or two or more modules may be integrated to form an independent part.

[0086] Although the present invention has been described in detail through the above preferred embodiments, it should be understood that the above description is not intended to limit the present invention. After reading the above description, various modifications and substitutions of the present invention will become apparent to those skilled in the art. Therefore, the scope of protection of the present invention should be defined by the appended claims.

Claims

1. A railway train approach warning and protection system based on a CTC system, characterized in that: include: A train approach warning system for obtaining real-time access to construction operation electronic fences and extracting equipment information from the construction operation electronic fences; a CTC system, which is in communication with the train approach warning system and is configured to generate a blocking instruction based on its own construction plan information or the equipment information sent by the train approach warning system; A computer interlocking system is connected to the CTC system for executing the blocking instructions to block the signal equipment in the construction area and control the access routes.

2. The railway train approach warning and protection system based on the CTC system according to claim 1, characterized in that: The train approach warning system includes: a warning server and a terminal device; The early warning server is used to receive and send the construction plan information sent by the CTC system to the terminal device; the terminal device feeds back the construction personnel's satellite positioning position information and the preparation for going on the road operation command to the early warning server; The early warning server is further configured to generate a construction operation area and demarcate the construction operation electronic fence based on the construction plan content in the construction plan information in combination with its own electronic map data; and displaying the current station equipment status and construction personnel location status in real time on a station vectorized electronic map generated based on the electronic map data according to the construction personnel satellite positioning information; The early warning server is further configured to feed back the prepare-to-go-operation command to the CTC system, and the CTC system generates the blocking instruction according to the prepare-to-go-operation command.

3. The CTC system-based railway train approach warning and protection system according to claim 2, characterized in that: The terminal equipment includes a monitoring terminal and a handheld terminal; The monitoring terminal is used to receive the construction plan information sent by the early warning server; or, The monitoring terminal is used to obtain a temporary construction request and generate a temporary construction plan according to the temporary construction request, and generate, based on the temporary construction plan and the actual work area required on the site, a vectorized electronic map of the station generated by the monitoring terminal based on the electronic map data and feedback the construction operation electronic fence to the early warning server; The handheld terminal is used to receive the construction plan information sent by the early warning server and feed back the satellite positioning information of the construction personnel to the early warning server; or, The handheld terminal is used to generate the construction operation electronic fence according to a manual dot trigger command, or when no manual dot trigger command is received, the handheld terminal feeds back the construction personnel's satellite positioning position information to the early warning server, and the early warning server dynamically delineates the construction operation electronic fence according to the construction personnel's satellite positioning position information and a preset single-person activity range.

4. The railway train approach warning and protection system based on the CTC system as claimed in claim 1, characterized in that: The train approach warning system further includes: a warning interface machine, which is used to communicate with the CTC interface machine in the CTC system.

5. The railway train approach warning and protection system based on the CTC system as claimed in claim 4, characterized in that: Also includes: A two-way network gatekeeper is used to connect the early warning interface machine to the CTC interface machine for communication.

6. The railway train approach warning and protection system based on the CTC system as claimed in claim 1, characterized in that: The equipment information at least includes signals, switches and tracks.

7. A railway train approach warning protection method based on a CTC system, characterized in that: include: Fixed construction plan early warning protection process; The fixed construction plan early warning and protection process includes: Obtaining construction plan information from the CTC system through a train approach warning system, and automatically generating a construction operation electronic fence on a vectorized electronic map of the station according to the construction plan content in the construction plan information; generating a blocking instruction according to the construction plan information through the CTC system; A computer interlocking system is used to execute the blocking instructions to achieve signal equipment blocking and access control in the construction area.

8. The railway train approach warning and protection method based on the CTC system as claimed in claim 7, characterized in that: The fixed construction plan early warning and protection process also includes: The warning server in the train approach warning system sends the construction operation electronic fence and the construction plan information to the handheld terminal, The handheld terminal feeds back the construction worker's satellite positioning location information and the preparation-to-go-on-the-road operation command to the early warning server, and the early warning server displays the current station equipment status and construction worker location status in real time on the station vectorized electronic map based on the construction worker's satellite positioning location information; The blocking instruction is generated by the CTC system according to the prepare-to-go-operation instruction.

9. The railway train approach warning and protection method based on the CTC system as claimed in claim 8, characterized in that: Also includes: Temporary construction plan early warning protection process; The temporary construction plan early warning and protection process includes: Generate a temporary construction plan of the construction operation electronic fence through the monitoring terminal or handheld terminal in the train approach warning system, and send the construction operation electronic fence to the CTC system through the warning server; The CTC system pops up a pop-up window to confirm whether the construction operation electronic fence is valid. If the construction operation electronic fence is valid, the warning server is controlled to send the construction operation electronic fence to the handheld terminal and the monitoring terminal in the train approach warning system; The handheld terminal feeds back a preparation-for-road-operation command and construction worker satellite positioning information to the warning server; The early warning server displays the current station equipment status and construction personnel location status in real time on the station vectorized electronic map based on the construction personnel satellite positioning information; and extracting, through the early warning server, device information from the effective construction operation electronic fence and sending it to the CTC system; The CTC system generates a blocking instruction according to the device information; A computer interlocking system is used to execute the blocking instructions to achieve signal equipment blocking and access control in the construction area.

10. The railway train approach warning protection method based on the CTC system according to claim 9, characterized in that: Also includes: When the construction operation electronic fence is invalid, the early warning server is controlled to send a temporary construction plan creation failure message to the handheld terminal and the monitoring terminal to interrupt the temporary construction plan.

11. The railway train approach warning protection method based on the CTC system according to claim 9, characterized in that: The step of generating an electronic fence for construction work of a temporary construction plan through the monitoring terminal in the train approach warning system includes: generating a temporary construction plan through the monitoring terminal, and generating the electronic fence for construction work on the vectorized electronic map of the station of the monitoring terminal according to the temporary construction plan and the actual operation area on site, and feeding the electronic fence for construction work into the warning server.

12. The railway train approach warning protection method based on the CTC system according to claim 9, characterized in that: The step of generating a construction operation electronic fence of a temporary construction plan by using a handheld terminal in the train approach warning system includes: generating the construction operation electronic fence by using the handheld terminal according to a manual dot triggering command; Alternatively, the early warning server dynamically delineates the construction operation electronic fence based on the satellite positioning position information of the construction personnel fed back by the handheld terminal and a preset single-person activity range.

Citation Information

Patent Citations

  • Railway safety protection early warning system

    CN106541966A

  • Railway operation safety protection method and system

    CN118205597A

  • Construction blocking method and system oriented to bureau-station integration

    CN119796281A

  • Method and system for providing security in a hazardous area in communications when traveling through a hazardous area by a means of transportation

    EP3228520A1

  • Post linkage apparatus and method applied to CTC construction plan

    WO2024000991A1