Task hierarchical management and control method based on project management and application
By refining project management, dividing task nodes, assigning personnel, and collecting and reporting information, the problem of low efficiency in traditional project management has been solved, and the accuracy and efficiency of project management have been improved.
Patent Information
- Application Number
- CN202510733940.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-03
- Publication Date
- 2025-10-17
AI Technical Summary
Traditional project management methods are inefficient and cannot meet the requirements for precise control and orderly progress of large-scale projects, especially in software development and construction projects, where task distribution and progress information collection and analysis are not accurate enough.
By acquiring project information, dividing project nodes, identifying project sub-tasks, assigning task participants and time, collecting task reporting information, and optimizing task execution requirements and problem solutions, we can achieve detailed decomposition and precise management.
It improved the efficiency and accuracy of project management, avoided omissions of important tasks, increased the utilization of project data, enabled the rapid disclosure and circulation of relevant information, and improved the efficiency of project progress.
Smart Images

Figure CN120806404A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of task management, and in particular to a task hierarchical management and control method based on project management and application. BACKGROUND
[0002] With the rapid development of economy, the project scale in various industries is also increasing, such as software development projects in the software industry or construction projects in the construction industry. The content and branch sub-projects of the project are increasing, and therefore, the accurate management of the project becomes more and more important.
[0003] At present, the traditional way of distributing project tasks through meetings and collecting and analyzing project progress information through individual reports of employees is inefficient and cannot meet the accurate management and orderly promotion of large projects. Therefore, it is particularly important to propose a technical solution that can improve the efficiency and accuracy of project management and thus improve the promotion efficiency of the project. SUMMARY
[0004] The present application provides a task hierarchical management and control method based on project management and application, which can improve the efficiency and accuracy of project management and thus improve the promotion efficiency of the project.
[0005] To solve the above technical problems, the first aspect of the present application discloses a task hierarchical management and control method based on project management, which comprises:
[0006] obtaining project information of a target project, and determining a plurality of project nodes of the target project according to the project information, wherein the project information comprises project content information;
[0007] dividing each project node to obtain a plurality of project sub-tasks corresponding to the target project, each project sub-task comprising at least one project node;
[0008] for each project sub-task, determining task information corresponding to the project sub-task, and assigning task participants to the project sub-task according to the task information, limiting the task completion time, wherein the task information comprises task level information;
[0009] collecting task report information fed back by the task participants of each project sub-task, and managing the target project according to each task report information.
[0010] As an optional implementation, in the first aspect of the present application, the task information of each project sub-task further comprises task content information and task execution requirement information of the project sub-task.
[0011] The task information corresponding to each of the project sub-tasks is determined, including:
[0012] The task content information of each of the project sub-tasks is determined according to the node content information of each of the project nodes of the project sub-task;
[0013] The task priority parameter of each of the project sub-tasks is determined according to the task content information of the project sub-task, and the task level information of the project sub-task is determined according to the task priority parameter;
[0014] The hierarchical lowest execution requirement corresponding to the task level information of each of the project sub-tasks is obtained, and the task execution requirement information corresponding to each of the project sub-tasks is determined according to the hierarchical lowest requirement and the task content information of the project sub-task.
[0015] As an optional implementation form, in the first aspect of the present application, the task execution requirement information corresponding to each of the project sub-tasks is determined according to the hierarchical lowest requirement and the task content information of the project sub-task, including:
[0016] For each of the project sub-tasks, at least one stored sub-task matched with the project sub-task and the task completion condition corresponding to each of the stored sub-tasks are screened from a preset task database according to the task content information of the project sub-task, and the task completion condition includes task completion time length and task completion quality.
[0017] For each of the project sub-tasks, the task content information of the project sub-task and the task completion condition corresponding to each of the stored sub-tasks are fused and analyzed to obtain the initial execution requirement information corresponding to the project sub-task.
[0018] For each of the project sub-tasks, it is judged whether the initial execution requirement information corresponding to the project sub-task meets the hierarchical lowest execution requirement, and when the initial execution requirement information does not meet the hierarchical lowest execution requirement, the initial execution requirement information is optimized according to the hierarchical lowest execution requirement to obtain the task execution requirement information corresponding to the project sub-task, and the task execution requirement information includes task execution deadline requirement and task completion quality requirement.
[0019] As an optional implementation form, in the first aspect of the present application, the division of each of the project nodes to obtain the plurality of project sub-tasks corresponding to the target project includes:
[0020] The node content information of each of the project nodes is determined according to the project content information;
[0021] determine a node association relationship between each of the project nodes according to the node content information of each of the project nodes;
[0022] for each of the node association relationships, determine whether the node association relationship satisfies a preset node association condition;
[0023] for each of the node association relationships, when the node association relationship satisfies the node association condition, divide the project node corresponding to the node association relationship into a project subtask, to obtain a plurality of project subtasks corresponding to the target project.
[0024] As an optional implementation, in the first aspect of the present application, the task participant of each of the subtasks includes at least one task responsible person and at least one task performer;
[0025] the task report information fed back by the task participant of each of the project subtasks is collected, and the target project is managed according to each of the task report information, including:
[0026] for each of the project subtasks, the task report information fed back by each of the task performers in the project subtask is collected according to a preset interval length, and the task report information includes task problem information;
[0027] for each of the project subtasks, a task problem set of the project subtask is analyzed according to the task problem information fed back by each of the task performers in the project subtask, and the task problem set includes at least one unsolved task problem;
[0028] for each of the project subtasks, the task problem set of the project subtask is sent to each of the task responsible persons of the project subtask, and a problem solution set fed back by each of the task responsible persons is received;
[0029] for each of the project subtasks, the problem solution set is optimized according to the task content information of the project subtask, and the optimized problem solution set is sent to each of the task performers.
[0030] As an optional implementation, in the first aspect of the present application, the task report information fed back by each of the task performers of each of the project subtasks includes task completion quantity information and task completion quality information;
[0031] the target project is managed according to each of the task report information, including:
[0032] For each of the project sub-tasks, according to the task completion quantity information and the task completion quality information fed back by each of the task performers of the project sub-task, a current completion progress of the project sub-task is determined, and whether the current completion progress meets the task performance requirement information corresponding to the project sub-task is judged;
[0033] For each of the project sub-tasks, when the current completion progress of the project sub-task does not meet the task performance requirement information, a task progress gap of the project sub-task is determined.
[0034] For each of the project sub-tasks, personnel capability information of each of the task performers of the project sub-task is acquired, and according to the personnel capability information of each of the task performers, the task progress gap of the project sub-task and the task level information, a task progress optimization scheme for the project sub-task is determined, the task progress optimization scheme including a task requirement adjustment scheme and / or an execution personnel adjustment scheme.
[0035] As an optional implementation, in the first aspect of the present application, the task participants of each of the project sub-tasks are allocated according to the task information, including:
[0036] For each of the project sub-tasks, according to the task content information and the task level information of the project sub-task, personnel requirement information of the project sub-task is determined, the personnel requirement information including personnel quantity requirement information and personnel level requirement information.
[0037] The personnel level of each of the to-be-assigned personnel is acquired, and for each of the project sub-tasks, according to the personnel requirement information of the project sub-task and the personnel level of each of the to-be-assigned personnel, task participants of the project sub-task are allocated.
[0038] In addition, the method further includes:
[0039] For each of the project sub-tasks, according to the task report information fed back by each of the task performers of the project sub-task, a personnel score of each of the task performers in the project sub-task is calculated, and according to the personnel score of each of the task performers, examination information of each of the task performers is determined.
[0040] The second aspect of the present application discloses a task hierarchical management and control application based on project management, the device includes:
[0041] An acquisition module is configured to acquire project information of a target project, and determine a plurality of project nodes of the target project according to the project information, wherein the project information includes project content information.
[0042] a dividing module, configured to divide each of the project nodes to obtain a plurality of project sub-tasks corresponding to the target project, each of the project sub-tasks comprising at least one of the project nodes;
[0043] a determining module, configured to determine, for each of the project sub-tasks, task information corresponding to the project sub-task, and assign a task participant to the project sub-task, limit a task completion time according to the task information, the task information comprising task level information;
[0044] a collecting module, configured to collect task report information fed back by the task participant of each of the project sub-tasks, and manage the target project according to each of the task report information.
[0045] As an optional implementation form, in the second aspect of the present application, the task information of each of the project sub-tasks further comprises task content information and task execution requirement information of the project sub-task;
[0046] The manner in which the determining module determines, for each of the project sub-tasks, the task information corresponding to the project sub-task specifically comprises:
[0047] For each of the project sub-tasks, the task content information of the project sub-task is determined according to the node content information of each of the project nodes of the project sub-task;
[0048] For each of the project sub-tasks, the task priority parameter of the project sub-task is determined according to the task content information of the project sub-task, and the task level information of the project sub-task is determined according to the task priority parameter;
[0049] For each of the project sub-tasks, a preset lowest level execution requirement corresponding to the task level information of the project sub-task is obtained, and the task execution requirement information corresponding to the project sub-task is determined according to the lowest level requirement and the task content information of the project sub-task.
[0050] As an optional implementation form, in the second aspect of the present application, the manner in which the determining module determines, for each of the project sub-tasks, the task execution requirement information corresponding to the project sub-task according to the lowest level requirement and the task content information of the project sub-task specifically comprises:
[0051] For each of the project sub-tasks, at least one stored sub-task matching the project sub-task and task completion condition corresponding to each of the stored sub-tasks are screened from a preset task database according to the task content information of the project sub-task, the task completion condition comprising task completion time length and task completion quality;
[0052] For each of the project subtasks, the task content information of the project subtask and the task completion condition corresponding to each of the storage subtasks are fused and analyzed to obtain initial execution requirement information corresponding to the project subtask;
[0053] For each of the project subtasks, it is judged whether the initial execution requirement information corresponding to the project subtask meets the hierarchical lowest execution requirement corresponding to the project subtask. When the initial execution requirement information does not meet the hierarchical lowest execution requirement, the initial execution requirement information is optimized according to the hierarchical lowest execution requirement to obtain task execution requirement information corresponding to the project subtask. The task execution requirement information includes task execution deadline requirement and task completion quality requirement.
[0054] As an optional implementation, in the second aspect of the present application, the manner in which the division module divides each of the project nodes to obtain the plurality of project subtasks corresponding to the target project specifically includes:
[0055] According to the project content information, the node content information of each of the project nodes is determined;
[0056] According to the node content information of each of the project nodes, the node association relationship between each of the project nodes is determined;
[0057] For each of the node association relationships, it is judged whether the node association relationship meets a preset node association condition;
[0058] For each of the node association relationships, when the node association relationship meets the node association condition, the project node corresponding to the node association relationship is divided into a project subtask to obtain the plurality of project subtasks corresponding to the target project.
[0059] As an optional implementation, in the second aspect of the present application, the task participants of each of the subtasks include at least one task responsible person and at least one task performer;
[0060] The manner in which the collection module collects the task report information fed back by the task participants of each of the project subtasks and manages the target project according to each of the task report information specifically includes:
[0061] For each of the project subtasks, the task report information fed back by each of the task performers in the project subtask is collected according to a preset interval length. The task report information includes task problem information;
[0062] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0063] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0064] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0065] As an optional implementation form, in the second aspect of the present application, the task report information fed back by each of the task performers of each of the project sub-tasks includes task completion quantity information and task completion quality information;
[0066] The collection module manages the target project according to each of the task report information in the following manner:
[0067] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0068] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0069] For each of the project sub-tasks, a task problem set of the project sub-task is analyzed according to the task problem information fed back by each of the task performers in the project sub-task, and the task problem set includes at least one unsolved task problem;
[0070] As an optional implementation form, in the second aspect of the present application, the manner in which the determination module allocates task performers to each of the project sub-tasks according to the task information specifically includes:
[0071] For each of the project sub-tasks, personnel requirement information of the project sub-task is determined according to the task content information and the task level information of the project sub-task, and the personnel requirement information includes personnel quantity requirement information and personnel level requirement information;
[0072] The personnel level of each to-be-assigned personnel is acquired, for each of the project sub-tasks, task participant personnel of the project sub-task is assigned according to the personnel requirement information of the project sub-task and the personnel level of each of the to-be-assigned personnel;
[0073] And the application further includes:
[0074] A calculating module is configured to, for each of the project sub-tasks, calculate personnel scores of each of the task performers in the project sub-task according to task report information fed back by each of the task performers of the project sub-task, and determine examination information of each of the task performers according to the personnel scores of each of the task performers.
[0075] The third aspect of the present application discloses a task hierarchical management and control device based on project management, and the device includes:
[0076] A memory in which executable program codes are stored;
[0077] A processor coupled with the memory;
[0078] The processor invokes the executable program codes stored in the memory to execute the task hierarchical management and control method based on project management disclosed in the first aspect of the present application.
[0079] The fourth aspect of the present application discloses a computer storage medium, and the computer storage medium stores computer instructions, and the computer instructions are used to execute the task hierarchical management and control method based on project management disclosed in the first aspect of the present application when being invoked.
[0080] Compared with the prior art, the embodiments of the present application have the following beneficial effects:
[0081] In the embodiment of the present application, the project information of the target project is acquired, and a plurality of project nodes of the target project are determined according to the project information. Each project node is divided to obtain a plurality of project sub-tasks corresponding to the target project. For each project sub-task, the task information corresponding to the project sub-task is determined, and the task participants of the project sub-task are allocated according to the task information. The task report information fed back by the task participants of each project sub-task is collected, and the target project is managed according to each task report information. It can be seen that the present application can refine and control the project tasks, improve the efficiency and accuracy of project management, avoid important task omissions, improve the utilization degree of project data, make relevant information quickly disclosed and circulated, and further improve the efficiency of project promotion. BRIEF DESCRIPTION OF DRAWINGS
[0082] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed in the embodiment description will be briefly introduced. Obviously, the drawings in the following description are only some embodiments of the present application, and other drawings can be obtained by those skilled in the art without creative labor.
[0083] Figure 1 is a flow diagram of a task hierarchical control method based on project management disclosed by the embodiment of the present application;
[0084] Figure 2 is a flow diagram of another task hierarchical control method based on project management disclosed by the embodiment of the present application;
[0085] Figure 3 is a structure diagram of a task hierarchical control application based on project management disclosed by the embodiment of the present application;
[0086] Figure 4 is a structure diagram of another task hierarchical control application based on project management disclosed by the embodiment of the present application;
[0087] Figure 5 is a structure diagram of a task hierarchical control device based on project management disclosed by the embodiment of the present application. DETAILED DESCRIPTION
[0088] In order to make those skilled in the art better understand the present application, the technical solutions in the embodiments of the present application will be described clearly and completely with reference to the drawings of the embodiments of the present application. Obviously, the described embodiments are only some embodiments of the present application, not all embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor are within the scope of protection of the present application.
[0089] The terms "first", "second", and the like in the description and claims of the present application and above drawings are used for distinguishing between similar objects, not necessarily described in a particular order. Also, the terms "comprise", "comprising", and the like are intended to encompass non-exclusive inclusions. For example, processes, methods, articles, or apparatuses that comprise a list of steps or elements are not limited to the listed steps or elements, but can also comprise additional steps or elements not expressly listed, or can also comprise steps or elements inherent in such processes, methods, articles, or apparatuses.
[0090] Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment is included in at least one embodiment of the application. The appearances of the phrase in various places in the specification are not necessarily all referring to the same embodiment, nor are they necessarily mutually exclusive of one another. It is expressly understood that the embodiments described herein are merely examples from a potentially infinite number of embodiments that serve the same or similar purpose or functions. Accordingly, the phrase "an embodiment" is not used herein to refer to one particular embodiment or to exclude some embodiments.
[0091] The application discloses a project management-based task hierarchical management and control method and application, which can refine and decompose project tasks for control, improve the efficiency and accuracy of project management, avoid important task omissions, improve the utilization degree of project data, quickly disclose and circulate relevant information, and further improve the promotion efficiency of the project. The following will be described in detail.
[0092] Embodiment one
[0093] Please refer to Figure 1 , Figure 1 is a flowchart of a project management-based task hierarchical management and control method disclosed by the embodiments of the application. Wherein, Figure 1 The project management-based task hierarchical management and control method described can be applied to a project management-based task hierarchical management and control application, wherein the project management-based task hierarchical management and control application can include an intelligent server or an intelligent platform, and the intelligent server includes a local server or a cloud server, and the embodiments of the application are not limited. As shown in Figure 1 The project management-based task hierarchical management and control method can include the following operations:
[0094] 101, obtaining project information of a target project, and determining a plurality of project nodes of the target project according to the project information.
[0095] In the embodiment of the present application, optionally, the target project can include one of a software development project, an engineering construction project, a performance process project, etc., and the target project information can include target project content information, which can include one or a combination of project content, project process, project target, project description, etc.
[0096] In the embodiment of the present application, optionally, the multiple project nodes of the target project can include multiple key components in the target project, for example, the multiple project nodes of the target project can include one or a combination of project preparation, project requirement analysis, project technology selection, project architecture design, each development module of the project development part, and module testing of each development module, etc.
[0097] 102. Dividing each project node to obtain multiple project sub-tasks corresponding to the target project, each project sub-task including at least one project node.
[0098] In the embodiment of the present application, optionally, each project node can be divided to obtain multiple project sub-tasks corresponding to the target project, specifically, one single project node can be divided into one project sub-task, for example, the development and implementation task of a module in the software development project can be divided into one project sub-task, or two or more project nodes can be divided into one project sub-task, for example, the project technology selection and the project architecture design in the software development project can be divided into one project sub-task, each project sub-task can include at least one project node, and the present application is not limited in this regard.
[0099] 103. For each project sub-task, determining task information corresponding to the project sub-task, and assigning task participants to the project sub-task according to the task information and limiting the task completion time.
[0100] In the embodiment of the present application, optionally, the task information of each project sub-task can include task level information of the project sub-task, and can also include task content information and task execution requirement information of the project sub-task, the task level information can be used to indicate the task priority of the project sub-task, and can also be used to indicate the hierarchical position of the project sub-task in the project architecture of the entire target project, for example, the task level information can be divided into a first-level task, a second-level task, a third-level task, etc., and the present application is not limited in this regard.
[0101] In the embodiment of the present application, optionally, the task participants can be assigned to the project subtask according to the task information, and the task completion time is limited. Specifically, the task participants can be assigned to the project subtask according to the task level information of the project subtask. The task participants can include at least one task responsible person and at least one task performer. The task responsible person can adjust the work content of each task performer in the project subtask. The task responsible person is responsible for the overall task progress and quality of the project subtask. After the task participants are assigned, the task completion time is limited. The task completion time can be limited by the task responsible person of the project subtask, or can be uniformly limited by a higher-level manager. The present application does not make any limitation.
[0102] 104. Collecting the task report information fed back by the task participants of each project subtask, and managing the target project according to each task report information.
[0103] In the embodiment of the present application, optionally, the task report information fed back by the task participants of each project subtask can be collected. The task report information can include task completion quantity information and task completion quality information. Then, the target project can be managed according to each task report information. The present application does not make any limitation.
[0104] In an embodiment of the present invention, optionally, the overall management and control process of the target project can be completed on the project management and control system. The project management and control system can adopt a multi-layer technical architecture, integrate mobile APP and B / S technologies, and combine intelligent communication + GIS + Internet of Things + big data technology; the system can provide an open data interface and have the ability to connect various types of data with other business systems. The system can adopt MySQL database, and support massive data storage through database and table partitioning technology, Tablestore big data storage and NOSQL mongodb cache, Redis high-speed cache and other technologies; enable users to quickly and accurately obtain the required data resources; the system fully considers redundancy and backup in design to ensure the security, reliability and service quality of system data and data transmission; the system can support Https access; the system strictly follows the specifications of Web security, front-end and back-end double verification, parameter encoding transmission, password asymmetric encryption storage, permission verification, SQL parameterization, fundamentally reducing common web attack methods such as SQL injection, XSS attack, CSRF attack, etc., to ensure data efficiency and security; the system software layer is divided into two parts: basic support and platform application, and the basic support digital tasks, progress information, and construction log information system are two parts; through The integration of basic data and standard specifications jointly provides data and business support for the platform; the system platform application is based on the organizational structure, project log, conference system, task target management and control, and data collection of the construction site to realize the data association and statistical analysis of smart construction digital information, and provide users with multi-dimensional digital resources and analysis management; system user interface: the presentation layer is divided into two parts: access users and front-end display methods. Users cover all stakeholders in the construction process, including owners, project management personnel, on-site technicians, construction, supervision and construction design personnel, etc.; users can access the system through different methods such as browsers and mobile APPs to manage or view the entire project management situation, and realize data interoperability, supervision, statistical analysis, reporting and other functions within the scope of project management.
[0105] It can be seen that implementation Figure 1 The described task hierarchical control method based on project management can obtain the project information of the target project, and determine multiple project nodes of the target project based on the project information, divide each project node to obtain multiple project subtasks corresponding to the target project, and for each project subtask, determine the task information corresponding to the project subtask, and assign task participants to the project subtask based on the task information, collect task report information feedback from the task participants of each project subtask, and manage the target project based on each task report information. It can carry out detailed decomposition and control of project tasks, improve the efficiency and accuracy of project management, avoid omissions of important tasks, improve the utilization of project data, and enable the rapid disclosure and circulation of relevant information, thereby improving the efficiency of project promotion.
[0106] In an optional embodiment, dividing each project node to obtain the plurality of project sub-tasks corresponding to the target project can include the following operations:
[0107] According to the project content information, determining the node content information of each project node;
[0108] According to the node content information of each project node, determining the node association relationship between each project node;
[0109] For each node association relationship, determining whether the node association relationship satisfies a preset node association condition;
[0110] For each node association relationship, when the node association relationship satisfies the node association condition, dividing the project nodes corresponding to the node association relationship into a project sub-task to obtain the plurality of project sub-tasks corresponding to the target project.
[0111] In the optional embodiment, the node content information of each project node can be determined according to the project content information. Specifically, the node content information of each project node can be determined by performing content splitting on the specific content of the target project. In addition, one or more of the project outline, project abstract, project description, and other information in the project content information of the target project can be analyzed to determine the node content information of each project node. The present embodiment is not limited in this regard.
[0112] In the optional embodiment, the node association relationship between each project node can be determined according to the node content information of each project node. The node association relationship between each project node can include one or more combinations of the association relationship between the specific content of the project nodes, the association relationship between the execution order of the project nodes, the association relationship between the execution priority of the project nodes, and the like. The present embodiment is not limited in this regard.
[0113] In the optional embodiment, the node association condition can be determined. The node association condition can include a node association degree threshold. Specifically, it can be determined whether the node association degree corresponding to the node association relationship is greater than the node association degree threshold. When the node association relationship satisfies the node association condition, the project nodes corresponding to the node association relationship can be divided into a project sub-task. One node association relationship can correspond to at least two project nodes. The present embodiment is not limited in this regard.
[0114] It can be seen that the optional embodiment can determine the node content information of each project node according to the project content information, determine the node association relationship between each project node according to the node content information of each project node, divide the project nodes corresponding to the node association relationship into a project subtask when the node association relationship meets the node association condition, and obtain the multiple project subtasks corresponding to the target project. The rationality and accuracy of determining the project subtask can be improved, the consistency of the overall content in the project subtask can be improved, and the promotion and execution efficiency of the project execution personnel on the project subtask can be improved.
[0115] In another optional embodiment, the task participants of each subtask include at least one task responsible person and at least one task execution person;
[0116] Collecting the task report information fed back by the task participants of each project subtask and managing the target project according to each task report information can include the following operations:
[0117] For each project subtask, the task report information fed back by each task execution person in the project subtask is collected at a preset interval, and the task report information includes task problem information;
[0118] For each project subtask, the task problem set of the project subtask is analyzed according to the task problem information fed back by each task execution person in the project subtask, and the task problem set includes at least one unsolved task problem;
[0119] For each project subtask, the task problem set of the project subtask is sent to each task responsible person of the project subtask, and a problem solution set fed back by the task responsible person is received;
[0120] For each project subtask, the problem solution set is optimized according to the task content information of the project subtask, and the optimized problem solution set is sent to each task execution person.
[0121] In the optional embodiment, optionally, the task participants of each subtask can include at least one task responsible person and at least one task execution person. When multiple task responsible persons are included, a main responsible person and multiple secondary responsible persons can be included. The task responsible person can adjust the work content of each task execution person in the project subtask, and the task responsible person is responsible for the overall task progress and quality of the project subtask. This embodiment is not limited.
[0122] In the optional embodiment, the task report information fed back by each task performer in the project subtask can be collected at a preset interval, which can be set by the overall project manager or the main responsible person of the project subtask. The preset interval can be one day, three days, one week, or one month. The task report information can include task problem information, and can also include task completion quantity information and task completion quality information. The embodiment is not limited in this regard.
[0123] In the optional embodiment, the task problem set of the project subtask can be analyzed according to the task problem information fed back by each task performer in the project subtask. The task problem set can include at least one unsolved task problem, i.e., a problem that the task performer cannot solve, and / or a problem that the task performer cannot solve in a short time, and / or a problem that the task performer cannot solve under the current authority. The embodiment is not limited in this regard.
[0124] In the optional embodiment, the task problem set of the project subtask can be sent to each task responsible person of the project subtask, and the task responsible person can provide a problem solution for the task problem set, or the task responsible person can obtain a problem solution for the task problem set from a higher-level responsible person. When the set of problem solutions fed back by the task responsible person is received, the set of problem solutions can be optimized according to the task content information of the project subtask, i.e., the set of problem solutions can be optimized according to the actual situation of the project subtask. For example, the optimal solution is selected, and the optimized set of problem solutions is sent to each task performer. The embodiment is not limited in this regard.
[0125] It can be seen that the optional embodiment can collect the task report information fed back by each task performer in the project subtask at a preset interval, analyze the task problem set of the project subtask according to the task problem information fed back by each task performer in the project subtask, send the task problem set of the project subtask to each task responsible person of the project subtask, receive the set of problem solutions fed back by the task responsible person, optimize the set of problem solutions according to the task content information of the project subtask, and send the optimized set of problem solutions to each task performer. The overall project manager can assist in solving sudden problems or task difficulties in the project, improve the overall smoothness and efficiency of the project, and improve the overall management efficiency of the project.
[0126] Embodiment Two
[0127] Please refer to Figure 2 , Figure 2is a flow diagram of a project management-based task hierarchical management and control method disclosed by an embodiment of the present application. Among them, Figure 2 The project management-based task hierarchical management and control method described can be applied to a project management-based task hierarchical management and control application, wherein the project management-based task hierarchical management and control application can include an intelligent server or an intelligent platform, and the intelligent server includes a local server or a cloud server, and the embodiments of the present application are not limited. As shown in Figure 2 The project management-based task hierarchical management and control method can include the following operations:
[0128] 201, obtaining project information of a target project, and determining a plurality of project nodes of the target project according to the project information.
[0129] 202, dividing each project node to obtain a plurality of project sub-tasks corresponding to the target project, and each project sub-task includes at least one project node.
[0130] 203, for each project sub-task, determining task content information of the project sub-task according to node content information of each project node of the project sub-task.
[0131] In the embodiments of the present application, optionally, the task content information of each project sub-task can be determined according to the node content information of each project node of the project sub-task, for example, the specific development content of the project sub-task, and the task information of each project sub-task can include the task content information of the project sub-task, and the present application is not limited.
[0132] 204, for each project sub-task, determining a task priority parameter of the project sub-task according to the task content information of the project sub-task, and determining task level information of the project sub-task according to the task priority parameter.
[0133] In the embodiments of the present application, optionally, the task priority parameter of each project sub-task can be determined according to the task content information of the project sub-task, and the task priority parameter can represent the task processing priority or the task processing urgency of the project sub-task, the greater the task priority parameter, the higher the task processing priority or the higher the task processing urgency of the project sub-task, and the task level information of the project sub-task is determined according to the task priority parameter.
[0134] 205, for each project sub-task, obtaining a preset lowest level execution requirement corresponding to the task level information of the project sub-task, and determining task execution requirement information corresponding to the project sub-task according to the lowest level requirement and the task content information of the project sub-task.
[0135] In an embodiment of the present invention, optionally, each task level information corresponds to a preset level minimum execution requirement, and the level minimum execution requirement may include a minimum execution deadline requirement and a minimum completion quality requirement. The level minimum execution requirement corresponding to the task level information of the project subtask may be obtained, and the task execution requirement information corresponding to the project subtask may be determined based on the level minimum requirement and the task content information of the project subtask. The task execution requirement information corresponding to the project subtask may include a task execution deadline requirement and a task completion quality requirement, which is not limited by the present invention.
[0136] 206. Assign task participants to the project subtasks based on the task information and set a time limit for task completion.
[0137] 207. Collect the task report information feedback from the task participants of each project subtask, and manage the target project based on each task report information.
[0138] In the embodiment of the present invention, for other descriptions of step 201, step 202, step 206 and step 207, please refer to the detailed description of step 101 to step 104 in the first embodiment of the present invention, and the embodiment of the present invention will not be repeated.
[0139] It can be seen that implementation Figure 2 The described task hierarchical control method based on project management can obtain the project information of the target project, and determine multiple project nodes of the target project according to the project information, divide each project node, and obtain multiple project subtasks corresponding to the target project. For each project subtask, the task content information of the project subtask is determined according to the node content information of each project node of the project subtask. For each project subtask, the task priority parameter of the project subtask is determined according to the task content information of the project subtask, and the task level information of the project subtask is determined according to the task priority parameter. For each project subtask, the minimum level execution requirement corresponding to the preset task level information of the project subtask is obtained, and the level information is determined according to the level information. The minimum requirements of the project level and the task content information of the project subtasks can be used to determine the task execution requirement information corresponding to the project subtasks, which can improve the accuracy and reliability of information such as the content, level and requirements of the project subtasks, thereby improving the accuracy and efficiency of the management and control of each project subtask. Task participants are assigned to the project subtasks according to the task information, and task report information feedback from the task participants of each project subtask is collected. The target project is managed according to the information of each task report, which can carry out detailed decomposition and control of project tasks, improve the efficiency and accuracy of project management, avoid omissions of important tasks, improve the utilization of project data, and enable the rapid disclosure and circulation of relevant information, thereby improving the efficiency of project promotion.
[0140] In an optional embodiment, for each project subtask, determining the task execution requirement information corresponding to the project subtask according to the hierarchical minimum requirement and the task content information of the project subtask can include the following operations:
[0141] For each project subtask, according to the task content information of the project subtask, at least one stored subtask matching the project subtask and the task completion condition corresponding to each stored subtask are screened from the preset task database, and the task completion condition includes the task completion duration and the task completion quality.
[0142] For each project subtask, the task content information of the project subtask and the task completion condition corresponding to each stored subtask are fused and analyzed to obtain the initial execution requirement information corresponding to the project subtask.
[0143] For each project subtask, it is judged whether the initial execution requirement information corresponding to the project subtask meets the hierarchical minimum execution requirement corresponding to the project subtask. When the initial execution requirement information does not meet the hierarchical minimum execution requirement, the initial execution requirement information is optimized according to the hierarchical minimum execution requirement to obtain the task execution requirement information corresponding to the project subtask, and the task execution requirement information includes the task execution deadline requirement and the task completion quality requirement.
[0144] In the optional embodiment, after each project task is executed, the task information of the project task and the control information of the project task can be stored in the task database. At least one stored subtask matching each project subtask can be screened from the task database according to the task content information of the project subtask. Specifically, at least one stored subtask matching the task content, the task type, the task level and the like of the project subtask can be screened from the task database. The task completion condition of each stored subtask can include the task completion duration and the task completion quality, which is not limited in the embodiment.
[0145] In the optional embodiment, the task content information of each project subtask and the task completion condition of each stored subtask can be fused and analyzed to obtain the initial execution requirement information corresponding to the project subtask. The initial execution requirement information can include the initial task execution deadline requirement and the initial task completion quality requirement, which is not limited in the embodiment.
[0146] In the optional embodiment, optionally, it can be judged whether the initial execution requirement information corresponding to each project subtask meets the hierarchical minimum execution requirement corresponding to the project subtask. Specifically, it can be judged whether the initial task execution deadline requirement of each project subtask meets the execution deadline minimum requirement of the project subtask, and / or whether the initial task completion quality requirement of each project subtask meets the completion quality minimum requirement of the project subtask. When the initial task execution deadline requirement of the project subtask does not meet the execution deadline minimum requirement of the project subtask, the initial task execution deadline requirement can be optimized according to the execution deadline minimum requirement to obtain the task execution deadline requirement of the project subtask, and / or when the initial task completion quality requirement of the project subtask does not meet the completion quality minimum requirement of the project subtask, the initial task completion quality requirement can be optimized according to the completion quality minimum requirement to obtain the task completion quality requirement of the project subtask. This embodiment is not limited.
[0147] It can be seen that by implementing the optional embodiment, the initial execution requirement information corresponding to the project subtask can be obtained according to the task content information of the project subtask, by screening at least one stored subtask matching the project subtask and the task completion condition corresponding to each stored subtask from the preset task database, and by performing fusion analysis on the task content information of the project subtask and the task completion condition corresponding to each stored subtask. When the initial execution requirement information does not meet the hierarchical minimum execution requirement, the initial execution requirement information is optimized according to the hierarchical minimum execution requirement to obtain the task execution requirement information corresponding to the project subtask. The accuracy and reliability of determining the task execution requirement information corresponding to the project subtask can be improved based on the historical information stored in the database and the content information of the project subtask, thereby improving the overall requirement level of each project subtask, improving the overall management efficiency of the target project, and improving the overall promotion efficiency of the target project.
[0148] In another optional embodiment, the task report information fed back by each task performer of each project subtask includes task completion quantity information and task completion quality information.
[0149] The management of the target project according to each task report information can include the following operations:
[0150] For each project subtask, the current completion progress of the project subtask is determined according to the task completion quantity information and the task completion quality information fed back by each task performer of the project subtask, and it is judged whether the current completion progress meets the task execution requirement information corresponding to the project subtask.
[0151] For each project subtask, when the current completion progress of the project subtask does not meet the task execution requirement information, the task progress gap of the project subtask is determined.
[0152] For each project subtask, personnel capability information of each task performer of the project subtask is acquired, and a task progress optimization scheme for the project subtask is determined according to the personnel capability information of each task performer, the task progress gap of the project subtask, and the task level information, the task progress optimization scheme including a task requirement adjustment scheme and / or an execution personnel adjustment scheme.
[0153] In the optional embodiment, the task report information fed back by each task performer of each project subtask can include task completion quantity information and task completion quality information, and can also include task problem information, the current completion progress of the project subtask can be determined according to the task completion quantity information and the task completion quality information fed back by each task performer of the project subtask, the current completion progress can include current completion time progress, current completion content progress, and current completion quality progress, and the current completion progress can be in the form of percentage, which is not limited in the embodiment.
[0154] In the optional embodiment, it can be judged whether the current completion progress meets the task execution requirement information corresponding to the project subtask, and when the current completion progress of the project subtask does not meet the task execution requirement information, the task progress gap of the project subtask can be determined, the task progress gap including task time progress gap, task content progress gap, and task quality progress gap, which is not limited in the embodiment.
[0155] In the optional embodiment, the personnel capability information of each task performer of the project subtask can be acquired, and the task progress optimization scheme for the project subtask can be determined according to the personnel capability information of each task performer, the task progress gap of the project subtask, and the task level information, specifically, whether the task performer can optimize the task progress gap can be analyzed according to the personnel capability information of each task performer, when the personnel capability of one or more task performers cannot meet the optimization of the task progress gap, other task performers who can meet the optimization of the task progress gap are screened to replace the one or more task performers, to obtain an execution personnel adjustment scheme, and / or the task level information is analyzed to determine whether the task requirement of the project subtask can be adjusted based on the task progress gap, i.e. the task requirement is reduced, to obtain a task requirement adjustment scheme, which is not limited in the embodiment.
[0156] It can be seen that the optional embodiment can determine the current completion progress of the project subtask according to the task completion quantity information and the task completion quality information fed back by each task performer of the project subtask, and when the current completion progress of the project subtask does not meet the task performance requirement information, determine the task progress gap of the project subtask, and according to the personnel capability information of each task performer, the task progress gap of the project subtask, and the task level information, determine the task progress optimization scheme for the project subtask. The progress optimization scheme can be given by adjusting the personnel or adjusting the project requirements in the case of the overall progress of the project subtask, so as to ensure the overall progress of the project and improve the promotion efficiency of the project.
[0157] In yet another optional embodiment, for each project subtask, the operation of assigning task participants to the project subtask according to the task information can include the following operations:
[0158] For each project subtask, the personnel requirement information of the project subtask is determined according to the task content information and the task level information of the project subtask, and the personnel requirement information includes personnel quantity requirement information and personnel level requirement information.
[0159] The personnel level of each to-be-assigned personnel is obtained, and for each project subtask, the task participants are assigned to the project subtask according to the personnel requirement information of the project subtask and the personnel level of each to-be-assigned personnel.
[0160] In addition, the task hierarchical management and control method based on project management can further include the following operations:
[0161] For each project subtask, the personnel score of each task performer in the project subtask is calculated according to the task report information fed back by each task performer of the project subtask, and the assessment information of each task performer is determined according to the personnel score of each task performer.
[0162] In the optional embodiment, the personnel requirement information of the project subtask can be determined according to the task content information and the task level information of the project subtask, and the personnel requirement information includes personnel quantity requirement information and personnel level requirement information. Specifically, a plurality of personnel levels and the personnel quantity corresponding to each personnel level can be included, the personnel level of each to-be-assigned personnel is obtained, and the task participants matching the personnel requirement information are selected from the to-be-assigned personnel. This embodiment is not limited.
[0163] In the optional embodiment, the personnel score of each task performer in the project subtask can be calculated according to the task report information fed back by each task performer of the project subtask, and the personnel score can specifically include a time progress score, a content progress score and a quality progress score. Then, the assessment information of each task performer can be determined according to the personnel score of each task performer, and the assessment information can include an assessment score or an assessment level. Specifically, the assessment score of each task performer can be calculated according to the score of each personnel score and a preset weight ratio, and the embodiment is not limited.
[0164] It can be seen that the optional embodiment can determine the personnel requirement information of the project subtask according to the task content information and the task level information of the project subtask, allocate the task participants for the project subtask according to the personnel requirement information of the project subtask and the personnel level of each to-be-assigned personnel, can screen the level-matched participants for the project subtask, ensure the overall promotion efficiency and control efficiency of the project while reducing the waste of personnel resources, calculate the personnel score of each task performer in the project subtask according to the task report information fed back by each task performer of the project subtask, and determine the assessment information of each task performer according to the personnel score of each task performer, which can improve the accuracy and fairness of the assessment of the project performers, and then improve the overall promotion efficiency of the project.
[0165] Embodiment three
[0166] Please refer to Figure 3 , Figure 3 is a structure schematic diagram of a task hierarchical control application based on project management disclosed by the embodiment of the application. Wherein, Figure 3 The task hierarchical control application based on project management described above can include an intelligent server or an intelligent platform, and the intelligent server includes a local server or a cloud server, and the embodiment of the application is not limited. As shown in Figure 3 The task hierarchical control application based on project management can include:
[0167] The acquisition module 301 is configured to acquire the project information of the target project, and determine a plurality of project nodes of the target project according to the project information, wherein the project information includes project content information.
[0168] The division module 302 is configured to divide each project node to obtain a plurality of project subtasks corresponding to the target project, and each project subtask includes at least one project node.
[0169] The determination module 303 is configured to determine the task information corresponding to each project subtask, and allocate the task participants for the project subtask according to the task information, and limit the task completion time, wherein the task information includes the task level information.
[0170] The collection module 304 is configured to collect task report information of task participant feedback of each project subtask, and manage the target project according to each task report information.
[0171] It can be seen that the implementation Figure 3 The project management-based task hierarchical control application described herein can obtain project information of a target project, determine a plurality of project nodes of the target project according to the project information, divide each project node to obtain a plurality of project subtasks corresponding to the target project, determine task information corresponding to each project subtask, assign task participants to each project subtask according to the task information, collect task report information of task participant feedback of each project subtask, and manage the target project according to each task report information. The project management-based task hierarchical control application can refine and control project tasks, improve the efficiency and accuracy of project management, avoid missing important tasks, improve the utilization degree of project data, make relevant information quickly disclosed and circulated, and further improve the efficiency of project promotion.
[0172] In an optional embodiment, as Figure 4 shown, the task information of each project subtask further includes task content information and task execution requirement information of the project subtask;
[0173] The determination module 303 is configured to determine, for each project subtask, the task information corresponding to the project subtask in the following manner:
[0174] For each project subtask, the task content information of the project subtask is determined according to the node content information of each project node of the project subtask;
[0175] For each project subtask, the task priority parameter of the project subtask is determined according to the task content information of the project subtask, and the task level information of the project subtask is determined according to the task priority parameter;
[0176] For each project subtask, the hierarchical lowest execution requirement corresponding to the task level information of the project subtask is obtained, and the task execution requirement information corresponding to the project subtask is determined according to the hierarchical lowest requirement and the task content information of the project subtask.
[0177] It can be seen that the implementation Figure 4The described project management-based task hierarchical management and control application can obtain project information of a target project, determine a plurality of project nodes of the target project according to the project information, divide each project node to obtain a plurality of project sub-tasks corresponding to the target project, for each project sub-task, determine task content information of the project sub-task according to node content information of each project node of the project sub-task, for each project sub-task, determine a task priority parameter of the project sub-task according to the task content information of the project sub-task, and determine task hierarchical information of the project sub-task according to the task priority parameter, for each project sub-task, obtain a preset lowest hierarchical execution requirement corresponding to the task hierarchical information of the project sub-task, and determine task execution requirement information corresponding to the project sub-task according to the lowest hierarchical requirement and the task content information of the project sub-task, which can improve the accuracy and reliability of determining the content, hierarchy and requirements of the project sub-task, and further improve the management and control accuracy and efficiency of each project sub-task, assign task participants to the project sub-task according to the task information, collect task report information fed back by the task participants of each project sub-task, and manage the target project according to each task report information, which can refine and control the project task, improve the efficiency and accuracy of managing the project, avoid missing important tasks, improve the utilization degree of project data, make relevant information quickly disclosed and circulated, and further improve the efficiency of promoting the project.
[0178] In another optional embodiment, as shown in Figure 4 The specific manner in which the determining module 303 determines, for each project sub-task, the task execution requirement information corresponding to the project sub-task according to the lowest hierarchical requirement and the task content information of the project sub-task includes:
[0179] For each project sub-task, according to the task content information of the project sub-task, at least one stored sub-task matching the project sub-task and task completion information corresponding to each stored sub-task are screened from a preset task database, and the task completion information includes task completion time length and task completion quality.
[0180] For each project sub-task, the task content information of the project sub-task and the task completion information corresponding to each stored sub-task are fused and analyzed to obtain initial execution requirement information corresponding to the project sub-task.
[0181] For each project subtask, it is judged whether the initial execution requirement information corresponding to the project subtask meets the hierarchical minimum execution requirement corresponding to the project subtask. When the initial execution requirement information does not meet the hierarchical minimum execution requirement, the initial execution requirement information is optimized according to the hierarchical minimum execution requirement to obtain task execution requirement information corresponding to the project subtask. The task execution requirement information includes task execution deadline requirement and task completion quality requirement.
[0182] It can be seen that the implementation Figure 4 The project management-based task hierarchical management and control application described herein can filter at least one stored subtask matching a project subtask and task completion information corresponding to each stored subtask from a preset task database according to task content information of the project subtask, perform fusion analysis on the task content information of the project subtask and the task completion information corresponding to each stored subtask, obtain initial execution requirement information corresponding to the project subtask, optimize the initial execution requirement information according to the hierarchical minimum execution requirement when the initial execution requirement information does not meet the hierarchical minimum execution requirement, and obtain task execution requirement information corresponding to the project subtask. The application can improve the accuracy and reliability of determining the task execution requirement information corresponding to the project subtask based on the historical information stored in the database and the content information of the project subtask, thereby improving the overall requirement level of each project subtask, improving the overall management and control efficiency of the target project, and improving the overall promotion efficiency of the target project.
[0183] In yet another optional embodiment, as Figure 4 shown, the division module 302 divides each project node to obtain the specific manner of the target project corresponding to a plurality of project subtasks, which includes:
[0184] According to the project content information, the node content information of each project node is determined;
[0185] According to the node content information of each project node, the node association relationship between each project node is determined;
[0186] For each node association relationship, it is judged whether the node association relationship meets the preset node association condition;
[0187] For each node association relationship, when the node association relationship meets the node association condition, the project node corresponding to the node association relationship is divided into a project subtask to obtain a plurality of project subtasks corresponding to the target project.
[0188] It can be seen that the implementation Figure 4The described project management-based task hierarchical management and control application can determine node content information of each project node according to project content information, determine node association relationships between each project node according to the node content information of each project node, divide the project nodes corresponding to the node association relationships into a project subtask when the node association relationships meet node association conditions, and obtain multiple project subtasks corresponding to the target project, which can improve the rationality and accuracy of determining the project subtask, improve the consistency of the overall content in the project subtask, and further improve the promotion and execution efficiency of the project execution personnel on the project subtask.
[0189] In yet another optional embodiment, as shown in Figure 4 The task participants of each subtask include at least one task responsible person and at least one task execution person;
[0190] The collection module 304 collects task report information fed back by the task participants of each project subtask, and the specific way of managing the target project according to each task report information includes:
[0191] For each project subtask, task report information fed back by each task execution person in the project subtask is collected at a preset interval, and the task report information includes task problem information;
[0192] For each project subtask, a task problem set of the project subtask is analyzed according to the task problem information fed back by each task execution person in the project subtask, and the task problem set includes at least one unsolved task problem;
[0193] For each project subtask, the task problem set of the project subtask is sent to each task responsible person of the project subtask, and a problem solution set fed back by the task responsible person is received;
[0194] For each project subtask, the problem solution set is optimized according to the task content information of the project subtask, and the optimized problem solution set is sent to each task execution person.
[0195] It can be seen that the implementation Figure 4The described project management-based task hierarchical management and control application can collect task report information fed back by each task performer in a project subtask according to a preset interval, analyze a task problem set of the project subtask according to the task problem information fed back by each task performer in the project subtask, send the task problem set of the project subtask to each task performer of the project subtask, receive a problem solution set fed back by the task performer, optimize the problem solution set according to the task content information of the project subtask, and send the optimized problem solution set to each task performer. The application can assist in solving sudden problems or task difficulties in the project based on a project manager, improve the overall smoothness and efficiency of the project, and improve the overall management efficiency of the project.
[0196] In yet another optional embodiment, as shown in Figure 4 The task report information fed back by each task performer of each project subtask includes task completion quantity information and task completion quality information.
[0197] The specific manner in which the collection module 304 manages the target project according to each task report information includes:
[0198] For each project subtask, the current completion progress of the project subtask is determined according to the task completion quantity information and the task completion quality information fed back by each task performer of the project subtask, and it is determined whether the current completion progress meets the task execution requirement information corresponding to the project subtask.
[0199] For each project subtask, when the current completion progress of the project subtask does not meet the task execution requirement information, the task progress gap of the project subtask is determined.
[0200] For each project subtask, the personnel capability information of each task performer of the project subtask is obtained, and a task progress optimization scheme for the project subtask is determined according to the personnel capability information of each task performer, the task progress gap of the project subtask, and the task hierarchical information. The task progress optimization scheme includes a task requirement adjustment scheme and / or an execution personnel adjustment scheme.
[0201] It can be seen that the implementation Figure 4The described project management-based task hierarchical management and control application can determine the current completion progress of a project subtask according to the task completion quantity information and the task completion quality information fed back by each task performer of the project subtask, and when the current completion progress of the project subtask does not meet the task performance requirement information, determine the task progress gap of the project subtask, determine the task progress optimization scheme for the project subtask according to the personnel capability information of each task performer, the task progress gap of the project subtask, and the task level information, and can give a progress optimization scheme by adjusting personnel or adjusting project requirements in the case that the overall progress of the project subtask is lagging behind, so as to ensure the overall progress of the project and improve the promotion efficiency of the project.
[0202] In yet another optional embodiment, as shown in Figure 4 The determining module 303 determines the specific manner of assigning the task performers to each project subtask according to the task information, which includes:
[0203] For each project subtask, the personnel requirement information of the project subtask is determined according to the task content information and the task level information of the project subtask, and the personnel requirement information includes the personnel quantity requirement information and the personnel level requirement information.
[0204] The personnel level of each to-be-assigned personnel is obtained, and for each project subtask, the task performers are assigned to the project subtask according to the personnel requirement information of the project subtask and the personnel level of each to-be-assigned personnel.
[0205] In addition, the project management-based task hierarchical management and control application can further include:
[0206] The calculating module 305 is configured to calculate the personnel score of each task performer in the project subtask according to the task report information fed back by each task performer of the project subtask, and determine the assessment information of each task performer according to the personnel score of each task performer.
[0207] It can be seen that the implementation Figure 5The described project management-based task hierarchical management and control application can determine personnel requirement information of a project subtask according to task content information and task level information of the project subtask, allocate a task participant to the project subtask according to the personnel requirement information of the project subtask and a personnel level of each to-be-assigned personnel, can filter a level-matched participant for the project subtask, ensure the overall promotion efficiency and control efficiency of the project while reducing the waste of personnel resources, calculate a personnel score of each task performer in the project subtask according to task report information fed back by each task performer of the project subtask, and determine assessment information of each task performer according to the personnel score of each task performer, which can improve the accuracy and fairness of assessment on the project performer, and further improve the overall promotion efficiency of the project.
[0208] Embodiment four
[0209] Please refer to Figure 5 , Figure 5 is a structural schematic diagram of a project management-based task hierarchical management and control device disclosed by an embodiment of the application. As shown in the figure, The project management-based task hierarchical management and control device can include:
[0210] a memory 401 storing executable program codes;
[0211] a processor 402 coupled with the memory 401;
[0212] The processor 402 invokes the executable program codes stored in the memory 401 to execute the steps in the project management-based task hierarchical management and control method described in the embodiment one or the embodiment two of the application.
[0213] Embodiment five
[0214] The embodiment of the application discloses a computer storage medium storing computer instructions, which, when invoked, are used to execute the steps in the project management-based task hierarchical management and control method described in the embodiment one or the embodiment two of the application.
[0215] Embodiment six
[0216] The embodiment of the application discloses a computer program product including a non-transitory computer readable storage medium storing a computer program, and the computer program is operable to make a computer execute the steps in the project management-based task hierarchical management and control method described in the embodiment one or the embodiment two.
[0217] The apparatus embodiments described above are only illustrative, wherein the modules described as separate components can or can not be physically separated, and the components displayed as modules can or can not be physical modules, i.e., can be located in one place or distributed to multiple network modules. Part or all of the modules can be selected to achieve the purposes of the embodiments according to actual needs. Those skilled in the art can understand and implement without creative labor.
[0218] Through the specific description of the above embodiments, those skilled in the art can clearly understand that each embodiment can be realized by means of software and necessary general hardware platform, and of course can also be realized by hardware. Based on such understanding, the above technical solutions can be embodied in the form of software products, and the computer software products can be stored in a computer readable storage medium, including a read-only memory (ROM), a random access memory (RAM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), a one-time programmable read-only memory (OTPROM), an electrically erasable programmable read-only memory (EEPROM), a compact disc read-only memory (CD-ROM) or other optical disk storage, a magnetic disk storage, a magnetic tape storage, or any other computer readable medium that can be used to carry or store data.
[0219] Finally, it should be noted that: the project management-based task hierarchical management and control method and the application disclosed by the embodiments of the present application are only the preferred embodiments of the present application, and are only used to illustrate the technical solutions of the present application, but not to limit them; although the present application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that; the technical solutions recorded in the foregoing embodiments can be modified, or some technical features can be replaced by equivalents; and these modifications or replacements do not make the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A task hierarchical control method based on project management, characterized in that: The method comprises: Acquire project information of a target project, and determine multiple project nodes of the target project based on the project information, wherein the project information includes project content information; Dividing each of the project nodes to obtain a plurality of project subtasks corresponding to the target project, each of the project subtasks including at least one of the project nodes; For each of the project subtasks, determine the task information corresponding to the project subtask, assign task participants to the project subtask based on the task information, and limit the task completion time, wherein the task information includes task level information; The task report information fed back by the task participants of each of the project subtasks is collected, and the target project is managed according to each of the task report information.
2. The task hierarchical control method based on project management according to claim 1 is characterized in that: The task information of each project subtask also includes task content information and task execution requirement information of the project subtask; For each of the project subtasks, determining the task information corresponding to the project subtask includes: For each of the project subtasks, determining the task content information of the project subtask according to the node content information of each of the project nodes of the project subtask; For each of the project subtasks, determining a task priority parameter of the project subtask according to the task content information of the project subtask, and determining task level information of the project subtask according to the task priority parameter; For each of the project subtasks, the minimum level execution requirements corresponding to the preset task level information of the project subtask are obtained, and the task execution requirement information corresponding to the project subtask is determined based on the minimum level requirements and the task content information of the project subtask.
3. The task hierarchical control method based on project management according to claim 2 is characterized in that: For each of the project subtasks, determining the task execution requirement information corresponding to the project subtask based on the minimum level requirement and the task content information of the project subtask includes: For each of the project subtasks, based on the task content information of the project subtask, at least one stored subtask matching the project subtask and the task completion status corresponding to each of the stored subtasks are screened from a preset task database, the task completion status including the task completion time and task completion quality; For each of the project subtasks, performing a fusion analysis on the task content information of the project subtask and the task completion status corresponding to each of the stored subtasks to obtain the initial execution requirement information corresponding to the project subtask; For each of the project subtasks, determine whether the initial execution requirement information corresponding to the project subtask meets the minimum execution requirements of the level corresponding to the project subtask. When the initial execution requirement information does not meet the minimum execution requirements of the level, optimize the initial execution requirement information according to the minimum execution requirements of the level to obtain the task execution requirement information corresponding to the project subtask. The task execution requirement information includes the task execution deadline requirements and the task completion quality requirements.
4. The task hierarchical control method based on project management according to any one of claims 1 to 3, characterized in that: The step of dividing each of the project nodes to obtain a plurality of project subtasks corresponding to the target project includes: Determining node content information of each of the project nodes according to the project content information; Determining the node association relationship between each of the project nodes based on the node content information of each of the project nodes; For each of the node association relationships, determining whether the node association relationship satisfies a preset node association condition; For each of the node association relationships, when the node association relationship satisfies the node association condition, the project node corresponding to the node association relationship is divided into a project subtask, thereby obtaining a plurality of project subtasks corresponding to the target project.
5. The task hierarchical control method based on project management according to any one of claims 1 to 3, characterized in that: The task participants of each subtask include at least one task responsible person and at least one task executor; The collecting of task report information fed back by task participants of each project subtask and managing the target project according to each task report information includes: For each of the project subtasks, task report information fed back by each of the task executors in the project subtask is collected at preset intervals, wherein the task report information includes task problem information; For each of the project subtasks, analyzing a task problem set of the project subtask based on the task problem information fed back by each of the task executors in the project subtask, wherein the task problem set includes at least one unresolved task problem; For each of the project subtasks, the task problem set of the project subtask is sent to each of the task responsible persons of the project subtask, and a problem solution set fed back by each of the task responsible persons is received; For each of the project subtasks, the problem solution set is optimized according to the task content information of the project subtask, and the optimized problem solution set is sent to each of the task executors.
6. The task hierarchical control method based on project management according to claim 2 or 3, characterized in that: The task report information fed back by each task executor of each project subtask includes task completion amount information and task completion quality information; Managing the target project according to each task report information includes: For each of the project subtasks, based on the task completion amount information and task completion quality information fed back by each of the task executors of the project subtask, determine the current completion progress of the project subtask, and judge whether the current completion progress meets the task execution requirement information corresponding to the project subtask; For each of the project subtasks, when the current completion progress of the project subtask does not meet the task execution requirement information, determining the task progress gap of the project subtask; For each of the project subtasks, the personnel capability information of each of the task executors of the project subtask is obtained, and based on the personnel capability information of each of the task executors, the task progress gap of the project subtask and the task level information, a task progress optimization plan for the project subtask is determined, wherein the task progress optimization plan includes a task requirement adjustment plan and / or an executor adjustment plan.
7. The task hierarchical control method based on project management according to claim 6 is characterized in that: For each of the project subtasks, assigning task participants to the project subtask according to the task information includes: For each of the project subtasks, determining the personnel requirement information of the project subtask based on the task content information and the task level information of the project subtask, wherein the personnel requirement information includes personnel quantity requirement information and personnel level requirement information; Obtaining the personnel level of each to-be-assigned person, and for each of the project subtasks, assigning task participants to the project subtasks based on the personnel requirement information of the project subtasks and the personnel level of each to-be-assigned person; And, the method further comprises: For each of the project subtasks, the personnel score of each of the task executors in the project subtask is calculated based on the task report information fed back by each of the task executors in the project subtask, and the assessment information of each of the task executors is determined based on the personnel score of each of the task executors.
8. A task hierarchical control application based on project management, characterized in that: The applications include: an acquisition module, configured to acquire project information of a target project and determine a plurality of project nodes of the target project according to the project information, wherein the project information includes project content information; a division module, configured to divide each of the project nodes to obtain a plurality of project subtasks corresponding to the target project, each of the project subtasks including at least one of the project nodes; a determination module, configured to determine, for each of the project subtasks, the task information corresponding to the project subtask, assign task participants to the project subtask based on the task information, and limit the task completion time, wherein the task information includes task level information; The collection module is used to collect task report information fed back by task participants of each project subtask, and manage the target project according to each task report information.
9. A task hierarchical control device based on project management, characterized in that: The device comprises: a memory storing executable program code; a processor coupled to the memory; The processor calls the executable program code stored in the memory to execute the task hierarchical control method based on project management as described in any one of claims 1 to 7.
10. A computer storage medium, characterized in that The computer storage medium stores computer instructions, and when the computer instructions are called, they are used to execute the task hierarchical control method based on project management according to any one of claims 1 to 7.
Citation Information
Patent Citations
Task management method and device, electronic device and storage medium
CN109559088A
Project collaborative management method and system based on task nodes and storage medium
CN112215586A
Task full-life-cycle management method and device and electronic equipment
CN112488476A
Progress management method and system for information system supervision project
CN115860430A
Task processing method and device for product research and development and computer equipment
CN116703125A