Mounting and construction method of U-shaped tunnel pipelines
A technology of pipeline installation and construction method, applied in the direction of pipeline laying and maintenance, pipes/pipe joints/fittings, machinery and equipment, etc., can solve the problems of high safety hazard, difficult to guarantee installation quality, long construction period, etc., to improve work efficiency and reduce The effect of working time and shortening construction period
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2011-09-07
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to an installation and construction method of a large-diameter pipeline, in particular to a U-shaped tunnel pipeline installation and construction method with a long inclined shaft section. Background technique
[0002] At present, for the installation of pipelines in U-shaped tunnels, the construction method of installing them from bottom to top is usually adopted in the tunnel. Disadvantages: (1) The construction personnel will install the pipeline in the tunnel throughout the whole process, which has a great potential safety hazard. Once there is poor ventilation, foreign objects or landslides, safety accidents will occur. The construction safety problems of the bare tunnel section and the initial branch section are particularly prominent. ; (2) The humidity in the tunnel is relatively high, which greatly affects the quality of welding and patching; (3) Due to space constraints in the tunnel, mechanical equipment cannot be used...
Examples
Embodiment Construction
[0012] The U-shaped tunnel includes left inclined shaft section, level road section and right inclined shaft section. like figure 1 , figure 2 As shown in the figure, the U-shaped tunnel pipeline installation and construction method of the present invention includes the following steps: firstly, the pipeline installation of the left-inclined well section is carried out, and at the same time, the pipeline transportation and distribution of the roadway section is carried out. The pipelines in the right inclined well section are installed and finally connected at the level road section.
[0013] The pipeline installation steps of the inclined shaft section are as follows: (1) Lay a light rail at the bottom of the tunnel inclined shaft 4 as a guide device for the pipeline to slide down; (2) bury a ground anchor 1 capable of carrying the pipeline slide load in front of the tunnel mouth 4a, and at the bottom of the tunnel 4a. Fix the hoist in a proper position; (3) excavate the w...