A method for forecasting and dispatching capacity of lng multi-point transport ship
A scheduling method and technology of transport ships, applied in the direction of electrical program control, comprehensive factory control, etc., can solve problems such as poor predictability, reduction of downstream gas supply, generalization, etc., and achieve the effect of strong accuracy
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2016-02-10
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The present invention relates to a method for forecasting and dispatching LNG (liquefied natural gas) transport capacity, in particular to an LNG multi-point transport ship coordinated and optimized between multiple LNG long-term supply points (i.e. liquefaction plants) and multiple LNG receiving stations Capacity Forecasting and Scheduling Method. Background technique
[0002] In the LNG industry chain, the basic function of the LNG receiving station is to unload the LNG carrier from the long-term supply point via the ocean, store the LNG material in the LNG storage tank after unloading, and transfer the LNG according to the downstream gas demand. After gasification, it is exported to three types of gaseous users: industrial, civil and gas-fired power plants. At the same time, a small part of LNG is directly transported out in liquid form through LNG tankers. The core of the receiving station's ADP (annual delivery plan) process for long-term supply ...
Examples
Embodiment Construction
[0012] The present invention will be described in detail below in conjunction with the accompanying drawings and embodiments.
[0013] Such as figure 1 , figure 2 Shown, the inventive method comprises the following steps:
[0014] 1) Set up an LNG multi-point carrier capacity forecasting and dispatching system
[0015] In a network structure composed of multiple long-term supply points and multiple receiving stations, an LNG multi-point transport capacity forecasting and dispatching system is set up, which includes DCS1 respectively arranged in each receiving station, and a DCS1 arranged in any receiving station. The simulation system platform 2 of LNG multi-point transport capacity scheduling simulation system and the GMS terminal 3 respectively arranged in each receiving station, the simulation system platform 2 is provided with an initial parameter database 21, a simulation module 22, an index and report display module 23 and an analysis database twenty four. Wherein, ...